CN109024569A - A kind of beading solution cavity pretreatment construction method - Google Patents
A kind of beading solution cavity pretreatment construction method Download PDFInfo
- Publication number
- CN109024569A CN109024569A CN201810961595.5A CN201810961595A CN109024569A CN 109024569 A CN109024569 A CN 109024569A CN 201810961595 A CN201810961595 A CN 201810961595A CN 109024569 A CN109024569 A CN 109024569A
- Authority
- CN
- China
- Prior art keywords
- solution cavity
- beading
- drilling
- tube
- beading solution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The present invention provides a kind of beading solution cavity pretreatment construction method, and the size and location of beading solution cavity are verified using the method that Advance Drilling method and tube detecting method combine.For the slurries of the size configuration different mixture ratio of beading solution cavity, guarantee the filling degree of beading solution cavity.Material is efficient relative to original simple process, effectively solve the problems, such as to handle when beading solution cavity is unevenly distributed, reach design requirement intensity to karst cave treatment slurries, the processing result of beading solution cavity is checked and accepted using tube detecting method, treated, and ground meets the requirement for bearing capacity of pile foundation, strongly avoid quality accident caused by beading solution cavity occur, make subsequent construction and come into operation to obtain effective safety assurance in the future.Belong to ground and foundation construction technical field.
Description
Technical field
The present invention relates to a kind of unfavorable foundations to handle construction technology, belongs to ground and basis in Industrial and Civil Engineering
The technical field of construction of processing.
Background technique
The pretreatment of beading solution cavity is a great problem of unfavorable foundation processing, and traditional beading karst cave treatment method compares office
Limit includes the following: 1, detection can not specifically detect the plane sizes and development feelings of beading solution cavity only with advance drilling method
Condition.2, it is handled frequently with double steel pipe method, with high costs, construction is inconvenient, and material can not carry out recycling and reusing.3, it passes
Not specified corresponding check mesures after the beading solution cavity scheme processing of system, cause quality uncontrollable.
Summary of the invention
It is an object of the invention to: a kind of beading solution cavity pretreatment construction method is provided, the detection, construction from beading solution cavity
And check and accept links and set about, solve the defect of traditional handicraft.
To solve the above problems, such a beading solution cavity of proposed adoption pre-processes construction method, the specific method is as follows:
Step 1: carrying out advance drilling to corresponding stake position, tube wave detecting verifies geological condition;
Step 2: drawing histogram, tube wave detecting figure: drawing histogram, the pipe of corresponding absolute altitude according to the rock sample that advance drilling takes out
Wave figure, and determine according to histogram, tube wave figure position, absolute altitude and the developmental state of solution cavity;
Step 3: advanced drilling machine drills by design requirement: the position of the stake position according to provided by histogram carries out aperture, aperture
Quantity meets the requirement of karst cave treatment, has section existing for beading solution cavity to advance drilling announcement, every has disclosed the stake of solution cavity
Tentative 3 drilling for detecting, slip casting and exhaust, the absolute altitude of drilling is in solution cavity lowest bid eminence;
Step 4: embedment mini-valve tube, steel pipe: the hole drilled out according to advance drilling is embedded to mini-valve tube, and in mini-valve tube and ground
Intersection is blocked, and the end of Grouting Pipe connects coating steel pipe;
Step 5: beading solution cavity slip casting: lower layer is first perfused to multilayer karst cave in the treatment principle to get on, get off according to beading solution cavity
Solution cavity, Reperfu- sion upper layer solution cavity, Grouting Pipe press the vertical distribution situation of solution cavity from bottom to top, are successively promoted, pass through the molten of cementing tank
Hole processing backstage carries out manufacture cement grout, and cement grout is by force (forcing) pump and Grouting Pipe pressurization injection solution cavity, to minimum absolute altitude
The solution cavity at place first carries out injecting treatment, when reaching certain pressure value can not be pressed into, then hoisting grouting pipe, slip casting is pulled out after the completion of slip casting
Pipe, and coating steel pipe is extracted and cleaned up;
Step 6: beading karst cave treatment is checked and accepted.
In step 1, drilled according to drawing requirement to corresponding hole location, for support pile, continuous three stakes one brill
Hole, if there is solution cavity, counter septum stake position drills again;For one hole of engineering pile, the geology feelings of its bored concrete pile position are verified
Condition, drilling depth must satisfy Design Requirement Drawing;
In step 4, the hole drilled out according to advance drilling is embedded to the mini-valve tube of 48mm*3mm, and intersects in mini-valve tube with ground
The cement slurry that place carries out 500mm high is blocked, and guarantees the leakproofness of solution cavity grouting pipe, and the end of Grouting Pipe connects a 4m
Long DN20 coating steel pipe;
In step 6, the beading solution cavity of design strength is reached to slip casting, the effect of its slip casting is carried out using tube detecting method
Detection, through detecting, karst cave treatment works well, and slurries are full, and intensity meet the requirements can by check and accept, otherwise be answered again
It fills.
Traditional shaped corroded cave model preconditioning technique is handled during slip casting frequently with double steel pipe method, construction cost mistake
High and process is complex, and construction material not can be carried out reasonable recycling and reuse.The beading that this technology is reconnoitred according to early period
The size of shape solution cavity combines the slurries of live practice of construction condition configuration different mixture ratio, it is ensured that the fullness coefficient in solution cavity meets
Design requirement.It is improved simultaneously for deficiency existing for conventional pretreatment technology, the note combined using mini-valve tube with steel pipe
Starch equipment.According to advance drilling bore position bury 48mm(outer diameter) * 3mm(wall thickness) and mini-valve tube, while in order to guarantee solution cavity infuse
The leakproofness for starching pipeline connects the DN20 coating steel pipe of 1 4m long in the end of Grouting Pipe, makes in mini-valve tube and ground intersection
It is blocked with cement slurry.
Compared with prior art, the present invention has the further advantage that mutually is tied using Advance Drilling method and tube detecting method
The method of conjunction verifies the size and location of beading solution cavity, for the slurries of the size configuration different mixture ratio of beading solution cavity, guarantees
The filling degree of beading solution cavity, material is efficient relative to original simple process, effectively solves at when beading solution cavity is unevenly distributed
The problem of reason reaches design requirement intensity to karst cave treatment slurries, and the processing result of beading solution cavity is checked and accepted using tube detecting method,
Treated, and ground meets the requirement for bearing capacity of pile foundation, strongly avoid quality accident caused by beading solution cavity occur, after making
It is continuous to construct and come into operation to obtain effective safety assurance in the future.
Detailed description of the invention
Fig. 1 is the schematic diagram of tube detecting method;
Fig. 2 is the schematic diagram of beading solution cavity injecting treatment method;
In figure, 1 is transmitter;2 be transmitting pulse signal;3 be transmitting transducer;4 be reception transducer;5 believe for vibrational waveform
Number;6 be recorder;7 be synchronous triggering signal;8 be advance borehole;9 be grouting pump;10 be Grouting Pipe;11 be DN20 galvanized steel
Pipe;12 be mini-valve tube;13 seal for cement mortar;14 drill for advance drilling;15 be solution cavity I;16 be solution cavity II;17 be solution cavity
Ⅲ。
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention is made into one below in conjunction with attached drawing
The detailed description of step.
Embodiment:
Referring to Figures 1 and 2, the present embodiment provides a kind of beading solution cavities to pre-process construction method, and the specific method is as follows:
Beading solution cavity is detected using Advance Drilling method and tube detecting method, using advanced drilling machine to having verified solution cavity
The stake position in region drills, and forms advance drilling drilling 14, fix tentatively 3 drillings for detecting, slip casting and exhaust;Pre-buried 48*3 is thick
Mini-valve tube 12,12 material of mini-valve tube be PVC, open one group of 4 Φ 8mm every 330mm on the mini-valve tube 12 of solution cavity slip casting section
Slurry hole is penetrated, every group of hole longitudinal length 60mm is penetrated outside slurry hole for every group and wrapped up one layer of rubber sleeve, long 80mm, when transferring mini-valve tube 12
It wraps, it is ensured that penetrate slurry hole just at corresponding beading solution cavity absolute altitude;Mini-valve tube 12 and the earth horizontal plane intersection use
The cement mortar sealing 13 of 50cm thickness water, guarantees grouting pressure;In double plugs sealing DN20 plating of the top of mini-valve tube 12 insertion 4m long
Zinc steel pipe 11,11 end of coating steel pipe connect Grouting Pipe 10, and beading karst cave treatment slurries pass through the cement slurry slip casting of KZY50/70 type
Pump 9 is that solution cavity slip casting section is pressurizeed through Grouting Pipe 10, drills 14 calibers using advance drilling as 110mm, and 12 caliber of mini-valve tube
Gap between 50mm first fills solution cavity III 17, is filled out using the mobility of cement grout to solution cavity II 16 after filling
Fill, and so on solution cavity I 15 is filled up again, using interval grouting mode, add accelerator (the 3% of cement consumption), make slurries
Cementing in advance, the intermittent time controlled at 10-20 minutes.
It carries out an acceptance inspection to the beading karst cave treatment carried out, is carried out using advanced drill hole of drilling machine, and using tube wave detecting instrument
The filling degree for detecting solution cavity, draws out corresponding tube wave figure.
Tube detecting method principle: according to the test environment in the propagation characteristic of tube wave and hole, the detection of tube detecting method is filled
It sets as shown in Figure 1, the transmitting pulse signal that emitting device generates in Fig. 1 is converted into vibratory impulse by transmitting transducer, in hole
Tube wave is generated around wall, tube wave is axially upwardly or downwardly propagated along drilling, is received energy converter and is firstly received direct tube wave, edge is bored
The tube wave of hole Propagation is at wave impedance differential boundary (at varying aperture, at liquid level, bottom hole, hole wall wave impedance differential boundary)
Reflection and transmission occurs, reflection tube wave is received by reception energy converter.
The above embodiments are only used to illustrate and not limit the technical solutions of the present invention, although referring to above-described embodiment to this hair
It is bright to be described in detail, it will be apparent to an ordinarily skilled person in the art that: still the present invention can be modified or be waited
With replacement, without departing from the spirit or scope of the invention, or any substitutions, should all cover in power of the invention
In sharp claimed range.
Claims (4)
1. a kind of beading solution cavity pre-processes construction method, which is characterized in that the specific method is as follows:
Step 1: carrying out advance drilling to corresponding stake position, tube wave detecting verifies geological condition;
Step 2: drawing histogram, tube wave detecting figure: drawing histogram, the pipe of corresponding absolute altitude according to the rock sample that advance drilling takes out
Wave figure, and determine according to histogram, tube wave figure position, absolute altitude and the developmental state of solution cavity;
Step 3: advanced drilling machine drills by design requirement: the position of the stake position according to provided by histogram carries out aperture, aperture
Quantity meets the requirement of karst cave treatment, has section existing for beading solution cavity to advance drilling announcement, every has disclosed the stake of solution cavity
Tentative 3 drilling for detecting, slip casting and exhaust, the absolute altitude of drilling is in solution cavity lowest bid eminence;
Step 4: embedment mini-valve tube, steel pipe: the hole drilled out according to advance drilling is embedded to mini-valve tube, and in mini-valve tube and ground
Intersection is blocked, and the end of Grouting Pipe connects coating steel pipe;
Step 5: beading solution cavity slip casting: lower layer is first perfused to multilayer karst cave in the treatment principle to get on, get off according to beading solution cavity
Solution cavity, Reperfu- sion upper layer solution cavity, Grouting Pipe press the vertical distribution situation of solution cavity from bottom to top, are successively promoted, pass through the molten of cementing tank
Hole processing backstage carries out manufacture cement grout, and cement grout is by force (forcing) pump and Grouting Pipe pressurization injection solution cavity, to minimum absolute altitude
The solution cavity at place first carries out injecting treatment, when reaching certain pressure value can not be pressed into, then hoisting grouting pipe, slip casting is pulled out after the completion of slip casting
Pipe, and coating steel pipe is extracted and cleaned up;
Step 6: beading karst cave treatment is checked and accepted.
2. a kind of beading solution cavity pre-processes construction method according to claim 1, it is characterised in that: in step 1, according to figure
Paper requires to drill to corresponding hole location, for support pile, continuous three stakes one drilling, if there is solution cavity counter septum stake position again
It drills;For one hole of engineering pile, the geological condition of its bored concrete pile position is verified, drilling depth must satisfy drawing and set
Meter requires.
3. a kind of beading solution cavity pre-processes construction method according to claim 1, it is characterised in that: in step 4, according to super
It is preceding to bore drilled out hole, it is embedded to the mini-valve tube of 48mm*3mm, and carry out the cement of 500mm high in mini-valve tube and ground intersection
Slurry is blocked, and guarantees the leakproofness of solution cavity grouting pipe, and the end of Grouting Pipe connects the DN20 coating steel pipe of a 4m long.
4. a kind of beading solution cavity pre-processes construction method according to claim 1, it is characterised in that: in step 6, to having infused
Slurry reaches the beading solution cavity of design strength, is detected to the effect of its slip casting using tube detecting method, through detecting, karst cave treatment
Work well, slurries are full, and intensity meet the requirements otherwise can carry out again multiple filling by checking and accepting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810961595.5A CN109024569A (en) | 2018-08-22 | 2018-08-22 | A kind of beading solution cavity pretreatment construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810961595.5A CN109024569A (en) | 2018-08-22 | 2018-08-22 | A kind of beading solution cavity pretreatment construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109024569A true CN109024569A (en) | 2018-12-18 |
Family
ID=64628012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810961595.5A Pending CN109024569A (en) | 2018-08-22 | 2018-08-22 | A kind of beading solution cavity pretreatment construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109024569A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110056326A (en) * | 2019-04-29 | 2019-07-26 | 中铁第四勘察设计院集团有限公司 | Hole sealing structure and implementation method for drilling with bead type solution cavity |
CN110258495A (en) * | 2019-06-12 | 2019-09-20 | 中国能源建设集团广东省电力设计研究院有限公司 | A kind of Pile Foundations Design and construction method of karst area |
CN110889249A (en) * | 2019-11-07 | 2020-03-17 | 中国建筑第四工程局有限公司 | Resistivity karst cave identification method based on population evolution algorithm |
CN111254933A (en) * | 2020-01-20 | 2020-06-09 | 武汉正洪岩土工程有限公司 | Karst grouting construction method for sleeve valve pipe |
CN112030647A (en) * | 2020-03-04 | 2020-12-04 | 河北鸿森公路工程技术有限公司 | Repairing construction process for road of filling and digging boundary roadbed road section |
CN112813981A (en) * | 2021-02-05 | 2021-05-18 | 云南建投基础工程有限责任公司 | Karst geological cast-in-place pile quality defect repairing grouting assembly and construction method |
CN113417644A (en) * | 2021-05-31 | 2021-09-21 | 中铁十六局集团北京轨道交通工程建设有限公司 | Karst cave detection method in shield construction process |
CN115262563A (en) * | 2022-08-19 | 2022-11-01 | 中铁二局集团有限公司 | Construction method and device for penetrating closed karst cave layer through pile foundation engineering |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2054502C1 (en) * | 1993-11-15 | 1996-02-20 | Санкт-Петербургский государственный архитектурно-строительный университет | Method for making cement/soil piles in caved-in soils |
CN101864763A (en) * | 2010-05-29 | 2010-10-20 | 中国二十二冶集团有限公司 | Foundation integrated processing construction method of cover type karst area |
CN104278667A (en) * | 2013-07-02 | 2015-01-14 | 浙江国泰建设集团有限公司 | Underground karst cave filling treatment method |
CN205591226U (en) * | 2016-05-10 | 2016-09-21 | 惠州市公路管理局 | String of beads formula karst bubble mixes pump sending of light material and fills structure |
CN107938676A (en) * | 2017-11-21 | 2018-04-20 | 重庆建工市政交通工程有限责任公司 | A kind of pile base construction method for passing through full packing type solution cavity |
-
2018
- 2018-08-22 CN CN201810961595.5A patent/CN109024569A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2054502C1 (en) * | 1993-11-15 | 1996-02-20 | Санкт-Петербургский государственный архитектурно-строительный университет | Method for making cement/soil piles in caved-in soils |
CN101864763A (en) * | 2010-05-29 | 2010-10-20 | 中国二十二冶集团有限公司 | Foundation integrated processing construction method of cover type karst area |
CN104278667A (en) * | 2013-07-02 | 2015-01-14 | 浙江国泰建设集团有限公司 | Underground karst cave filling treatment method |
CN205591226U (en) * | 2016-05-10 | 2016-09-21 | 惠州市公路管理局 | String of beads formula karst bubble mixes pump sending of light material and fills structure |
CN107938676A (en) * | 2017-11-21 | 2018-04-20 | 重庆建工市政交通工程有限责任公司 | A kind of pile base construction method for passing through full packing type solution cavity |
Non-Patent Citations (1)
Title |
---|
李学文等: "《桩位岩溶探测新技术——管波探测法》", 《工程地球物理学报》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110056326A (en) * | 2019-04-29 | 2019-07-26 | 中铁第四勘察设计院集团有限公司 | Hole sealing structure and implementation method for drilling with bead type solution cavity |
CN110258495A (en) * | 2019-06-12 | 2019-09-20 | 中国能源建设集团广东省电力设计研究院有限公司 | A kind of Pile Foundations Design and construction method of karst area |
CN110889249A (en) * | 2019-11-07 | 2020-03-17 | 中国建筑第四工程局有限公司 | Resistivity karst cave identification method based on population evolution algorithm |
CN111254933A (en) * | 2020-01-20 | 2020-06-09 | 武汉正洪岩土工程有限公司 | Karst grouting construction method for sleeve valve pipe |
CN111254933B (en) * | 2020-01-20 | 2021-05-28 | 武汉正洪岩土工程有限公司 | Karst grouting construction method for sleeve valve pipe |
CN112030647A (en) * | 2020-03-04 | 2020-12-04 | 河北鸿森公路工程技术有限公司 | Repairing construction process for road of filling and digging boundary roadbed road section |
CN112813981A (en) * | 2021-02-05 | 2021-05-18 | 云南建投基础工程有限责任公司 | Karst geological cast-in-place pile quality defect repairing grouting assembly and construction method |
CN113417644A (en) * | 2021-05-31 | 2021-09-21 | 中铁十六局集团北京轨道交通工程建设有限公司 | Karst cave detection method in shield construction process |
CN113417644B (en) * | 2021-05-31 | 2024-04-30 | 中铁十六局集团北京轨道交通工程建设有限公司 | Karst cave detection method in shield construction process |
CN115262563A (en) * | 2022-08-19 | 2022-11-01 | 中铁二局集团有限公司 | Construction method and device for penetrating closed karst cave layer through pile foundation engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109024569A (en) | A kind of beading solution cavity pretreatment construction method | |
CN105239563B (en) | A kind of supporting rotary drilling rig dry method pore-creating filling pile structure of grouting behind shaft or drift lining and construction method | |
CN101638987B (en) | Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall | |
CN106837351A (en) | Tunnel Karst water detects Treatment Methods | |
CN101575969B (en) | Method for measuring pressure of coalbed gas | |
CN107675696A (en) | A kind of Intelligent deep hole orientation slip casting and monitoring system | |
CN103410119A (en) | Method for water interception curtain grouting in leakage concrete | |
CN107975375A (en) | A kind of miniature steel pipe pile reinforced soft foundation construction method of city tunnel | |
CN108533271A (en) | A kind of two-tube tunnel radial grouting construction method in a hole | |
CN111254933B (en) | Karst grouting construction method for sleeve valve pipe | |
CN106595548A (en) | Displacement measuring method for the inner part of enclosing rock for tunnel inner face | |
CN108034815A (en) | A kind of tailing original position extract technology and tailing original position leaching system | |
CN106643967A (en) | Protecting hole for monitoring underground water level, hole sealing device and combination method thereof | |
CN110593254A (en) | Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone | |
CN114319388A (en) | Construction method of foundation pit enclosure structure in existing building in karst area | |
CN108756910A (en) | A kind of intelligent early-warning formula earth pressure balanced shield, EPBS pre-grouting device and construction method | |
CN207904908U (en) | A kind of orientation slip casting of Intelligent deep hole and monitoring system | |
CN108677959A (en) | A kind of grouting tube and grouting construction method suitable for mortar depositing construction under the conditions of limited space | |
CN103573269A (en) | Shield tunnel grouting layer performance detection method | |
CN105604163A (en) | Sewage pipeline internal plugging and external grouting construction method | |
CN105178966A (en) | Grouting process for water blocking by wall breaking for mine vertical shafts | |
CN115094956B (en) | Device and method for in-situ isolation treatment of polluted soil in local area | |
CN207964542U (en) | A kind of monitoring ultrasonic system for sand pile quality real-time control | |
CN105544547A (en) | Covering type soil filled and soft soil stratum segmented reinforcing device and method | |
CN110455915A (en) | Tunnel Second Lining supplements grouting method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181218 |