CN110258495A - A kind of Pile Foundations Design and construction method of karst area - Google Patents

A kind of Pile Foundations Design and construction method of karst area Download PDF

Info

Publication number
CN110258495A
CN110258495A CN201910504810.3A CN201910504810A CN110258495A CN 110258495 A CN110258495 A CN 110258495A CN 201910504810 A CN201910504810 A CN 201910504810A CN 110258495 A CN110258495 A CN 110258495A
Authority
CN
China
Prior art keywords
drilling
stake
long
theoretical
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910504810.3A
Other languages
Chinese (zh)
Other versions
CN110258495B (en
Inventor
陈兆雄
尹春明
黄丹
尹谦钧
陶林惠
张略秋
周雷靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Original Assignee
China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd filed Critical China Energy Engineering Group Guangdong Electric Power Design Institute Co Ltd
Priority to CN201910504810.3A priority Critical patent/CN110258495B/en
Publication of CN110258495A publication Critical patent/CN110258495A/en
Application granted granted Critical
Publication of CN110258495B publication Critical patent/CN110258495B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/02Investigation of foundation soil in situ before construction work
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes

Abstract

The present invention provides a kind of Pile Foundations Design of karst area and construction methods, include the following steps, carry out an advance drilling in the corresponding position of frame column to be built and form the first drilling;The geology of first drilling is surveyed, the geologic column of the first drill hole is drawn, determines the depth of the stabilization rock face of the first drilling, the theoretical stake of calculating first is long, is greater than preset value when theoretical stake is long, respectively bores one second drilling in the two sides of the first drilling;The geology of second drilling is surveyed, draw the geologic column of each second drill hole, determine the depth of the stabilization rock face of the second drilling, it is long to calculate the second theoretical stake, the data long to theoretical stake are compared, and position of the long shortest drilling of Choice Theory stake as piling, piling arrange cushion cap, conversion beam and connection beam to form pile foundation in stake.Using the Pile Foundations Design and construction method of the karst area of technical solution of the present invention, it is long to shorten stake to greatest extent, reduces project cost, shortens the construction period.

Description

A kind of Pile Foundations Design and construction method of karst area
Technical field
The present invention relates to piling Technology fields, and in particular to a kind of Pile Foundations Design and construction party of karst area Method.
Background technique
In engineering construction, the case where encountering karst foundation, is much, especially solution cavity is widely distributed, solution cavity scale Biggish region, if will cause the disasters such as karst collapse without correct technical treatment.
In the prior art, the widest foundation treatment mode that karst area uses is pile foundation form, and general use is filling Cushion cap is built in note stake and attachment beam forms the form of pile foundation.The position of the frame column corresponding position of building is required to drive piles To the effect of fixed support, therefore the quantity of stake and the quantity of frame column corresponding position have corresponding relationship, common for a frame One stake is set under trestle.Bored concrete pile need to pass through solution cavity when driving piles, and guarantee that an end is fallen on the stabilization rock face of not solution cavity And deep stable rock face certain depth.But in karst area, the distribution of bead string type can be usually presented in solution cavity, stablize rock Bury very deep in stone face.This can make stake long very long.The long difficulty for not only greatly increasing pile driving construction of too long stake, also adds engineering and makes Valence increases the duration.
Summary of the invention
The object of the present invention is to provide a kind of Pile Foundations Design of karst area and construction method, the karsts developing areas It is long that the Pile Foundations Design and construction method in area can shorten stake to greatest extent, and reduction project cost shortens the construction period.
Based on this, the present invention provides a kind of Pile Foundations Design of karst area and construction methods, include the following steps,
S1, first drilling of advance drilling formation is carried out in the corresponding position of frame column to be built;
S2, the geology of first drilling is surveyed, the geology column of the first drill hole is drawn according to exploration result Figure reads the depth l of the stabilization rock face of the first drilling by geologic column1, and the first of calculation block trestle corresponding position The theoretical long L of stake1, L1=l1+ m, wherein m > 0;
By the first long L of theoretical stake1It is compared with preset value, as the long L of theoretical stake1Greater than preset value, then S3 is entered step; As the long L of theoretical stake1Less than or equal to preset value, S6 is otherwise entered step;
S3, one second drilling is respectively bored in the two sides of the first drilling;
S4, the geology of the second drilling is surveyed, the geologic column of the second drill hole is drawn according to exploration result, is led to Cross the depth l that geologic column reads the stabilization rock face of the second drilling2、l3, and the second of calculation block trestle corresponding position is theoretical Stake is long: L2=l2+ m, L3=l3+m;Wherein, m > 0;
S5, to the L in step S2 and S41、L2、L3Data be compared, and the long shortest drilling conduct of Choice Theory stake The position of piling;
S6, it drives piles at the position that step S5 is selected;
S7, arrange cushion cap, conversion beam and connection beam to form pile foundation in stake.
Preferably, in step S3, the second drilling is equal to the original two first adjacent spacings of wells at a distance from the first drilling From half.
Preferably, in step S1, step S2 is carried out again after first completing K advance borehole, wherein K is frame column to be built Quantity.
Preferably, in step S6, when piling, it need to confirm and just start to construct after the intensity of a upper pile need to reach setting intensity Next pile.
Preferably, in step S6, according to place and different zones karstic development pattern and degree, suitable stake is selected Type.
Preferably, m is more than or equal to 0.5m.
Preferably, in step S7, conversion beam need to have enough rigidity, and conversion depth of beam is more than or equal to 1500mm, conversion The width of beam is more than or equal to the width of frame column.
Preferably, in step S7, the width of connection beam is 300-500mm, and connection depth of beam is 900-1100mm.
The implementation of the embodiments of the present invention has the following beneficial effects:
By boring the first borehole investigations in the corresponding position of frame column, the geology of the first drill hole is drawn according to exploration result Histogram reads the depth of the stabilization rock face of the first drilling, and the of calculation block trestle corresponding position by geologic column One theoretical stake is long.By first it is theoretical stake is long is compared with preset value, be greater than preset value when the first theoretical stake is long, then in the first brill One second drilling is respectively bored in the two sides in hole, surveys to the geology of the second drilling, draws the second drill hole according to exploration result Geologic column, the depth of the stabilization rock face of the second drilling is read by geologic column, and calculation block trestle corresponds to position The theoretical stake of second set is long;It is long to the first theoretical stake and second it is theoretical stake is long is compared, the long shortest drilling of Choice Theory stake Position as piling;To which the stake for reducing pile foundation position to the full extent is long, the difficulty of construction is reduced, further, also Project cost is reduced, the duration is shortened.
Detailed description of the invention
Fig. 1 is the flow chart of the Pile Foundations Design and construction method of karst area in the embodiment of the present invention.
Fig. 2 is the schematic diagram of geologic column in the embodiment of the present invention.
Fig. 3 is the operation chart of step S1 in the embodiment of the present invention.
Fig. 4 is the operation chart of step S3 in the embodiment of the present invention.
Fig. 5 is the operation chart of step S4 in the embodiment of the present invention.
Fig. 6 is the operation chart of step S5 in the embodiment of the present invention.
Fig. 7 is the operation chart of step S7 in the embodiment of the present invention.
Fig. 8 is the sectional view of A campshed base in step S7 in the embodiment of the present invention.
Fig. 9 is the sectional view of B campshed base in step S7 in the embodiment of the present invention.
In figure: 1, frame column, the 2, first drilling, the 3, second drilling, 4, the position driven piles, 5, cushion cap, 6, conversion beam, 7, connection Binder, 8, bored concrete pile;TA, silty clay layer, TB, micro- decomposed rock interlayer, TC, solution cavity, TD, gentle breezeization stablize rock, TE, stablize rock Stone face.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
It should be understood that various information are described in the present invention using term " first ", " second " etc., but these information It should not necessarily be limited by these terms, these terms are only used to for same type of information being distinguished from each other out.For example, not departing from the present invention In the case where range, " first " information can also be referred to as " second " information, and similar, " second " information can also be referred to as " first " information.
As shown in Figure 1, the present embodiment provides a kind of Pile Foundations Design of karst area and construction methods, including walk as follows Suddenly,
S1, first drilling 2 of advance drilling formation is carried out in the corresponding position of frame column to be built;
S2, the geology of the first drilling 2 is surveyed, being drawn as shown in Figure 2 according to exploration result includes ground layer name With the geologic column of thickness, the depth l of the stabilization rock face of the first drilling 2 is read by geologic column1, and Computational frame The long L of the theoretical stake of the first of 1 corresponding position of column1, L1=l1+ m, wherein m > 0;
By the first long L of theoretical stake1It is compared with preset value, as the long L of theoretical stake1Greater than preset value, then S3 is entered step; As the long L of theoretical stake1Less than or equal to preset value, S6 is otherwise entered step;
S3, one second drilling 3 is respectively bored in the two sides of the first drilling 2;
S4, the geology of the second drilling 3 is surveyed, being drawn as shown in Figure 2 according to exploration result includes ground layer name With the geologic column of thickness, the depth l of the stabilization rock face of the second drilling 3 is read by geologic column2、l3, and calculation block The theoretical stake of the second of 1 corresponding position of trestle is long: L2=l2+ m, L3=l3+m;Wherein, m > 0;
S5, to the L in step S2 and S41、L2、L3Data be compared, and the long shortest drilling conduct of Choice Theory stake The position 4 of piling;
S6, it drives piles at the position that step S5 is selected;
S7, arrange cushion cap 5, conversion beam 6 and connection beam 7 to form pile foundation in stake.
Based on above technical scheme, by boring the first drilling 2 in the corresponding position of frame column 1;To the ground at the first drilling 2 Matter is surveyed, and draws the geologic column at the first drilling 2 according to exploration result, reads the first drilling by geologic column The depth l of 2 stabilization rock face1, and the first long L of theoretical stake of 1 corresponding position of calculation block trestle1, L1=l1+ m, wherein m > 0.By the first long L of theoretical stake1It is compared with preset value, as the first long L of theoretical stake1Greater than preset value, then in the first drilling 2 One second drilling 3 is respectively bored in two sides, surveys to the geology of the second drilling 3, is drawn at the second drilling 3 according to exploration result Geologic column reads the depth l of the stabilization rock face of the second drilling 3 by geologic column2、l3, and calculation block trestle is corresponding The theoretical stake of the second of position is long: L2=l2+ m, L3=l3+m;Wherein, m > 0;To L1、L2、L3It is compared, Choice Theory stake is long Position of the shortest drilling as piling;To which the stake for reducing pile foundation position to the full extent is long, the difficulty of construction is reduced, into One step, project cost is also reduced, the duration is shortened.
Preferably, in step S3, the second drilling 3 is equal between original two the first adjacent drillings 2 at a distance from the first drilling 2 The half of distance.So that the arrangement of stake keeps symmetric relation as far as possible, the stability of pile foundation is improved.
Specifically, carrying out step S2 again after first completing K advance borehole, wherein K is frame column 1 to be built in step S1 Quantity.Thus it can first complete drilling to be surveyed again, frequent more exchange device be avoided, convenient for operation.
Further, in step S6, when piling, it need to confirm and just start to apply after the intensity of a upper pile need to reach setting intensity The lower pile of work.
Preferably, in step S6, according to place and different zones karstic development pattern and degree, suitable stake is selected Type.
Specifically, m is more than or equal to 0.5m, and when the theoretical stake of the present embodiment calculating is long, selected stabilization scar Thickness be not less than 5m.
In the present embodiment, in step S7, conversion beam 6 need to have enough rigidity, and the height of conversion beam 6 is more than or equal to 1500mm, the width of conversion beam 6 are more than or equal to the width of frame column 1.
In addition, the width of connection beam 7 is 300-500mm in step S7, the height of connection beam 7 is 900-1100mm.
Step of the invention is specifically described for arranging better simply two rows of frame structures, as shown in figure 3, root The quantity and initial position of stake needed for determining according to the position of the frame column 1 of building and quantity, the quantity of stake needed for A, B are two rows of are equal It is 5, in the carry out advance drilling for needing to arrange the position of frame column 1, bores 10 first drillings 2;Using detection instrument to each Geology at one drilling 2 is surveyed, and is drawn the geologic column at each first drilling 2 according to exploration result, is passed through geology Histogram, which is read, is located at silty clay layer TA, and the gentle breezeization below micro- decomposed rock interlayer TB, solution cavity TC stablizes the position of rock TD, from And determine the depth l between the upper surface and stable rock face TE of the silty clay layer TA at each first drilling 2, and calculate 10 The theoretical stake of the first of a 1 corresponding position of frame column is long, and in the present embodiment, safety value takes 5m, preset value 30m.By the first reason It is compared by stake is long with preset value, is greater than preset value when the first theoretical stake is long, then increases the quantity of drilling.
As shown in Fig. 4 to Fig. 9, one second is respectively bored in the two sides of long the first drilling 2 greater than preset value of the first theoretical stake Drilling 3;The geology at the second drilling 3 is surveyed using detection instrument, root draws each first drilling 2 according to exploration result The geologic column at place, the depth l of the stabilization rock face of each second drilling 3 is read by geologic column, and calculates second Theoretical stake is long, and data long to the theoretical stake of all calculating resulting first and that the second theoretical stake is long record, and facilitates description, such as The shown stake by A row of Fig. 5 is long to be indicated with A1-A11, and the stake of B row is long to be indicated with B1-B11.As shown in fig. 6, A row is compared, A1, It is A3, A5, A8, A10 long most short, select this at five drilling as the position 4 driven piles;Similarly, B row compared, select B2, B5, B7, The position 4 of B9, B11 as piling;It drives piles in 10 selected drill holes to form bored concrete pile 8, then as shown in fig. 7, in stake Upper arrangement cushion cap 5, conversion beam 6 and connection beam 7 are to form pile foundation.Wherein, the effect of conversion beam 6 is by the cushion cap 5 of same row It is attached, because needing setting frame column 1 on conversion beam 6, conversion beam 6 need to have enough rigidity, and the height of conversion beam 6 is not less than 1500mm, the width of conversion beam 6 are not less than the width of frame column 1.Connection beam 5 is between the cushion cap 5 of different lines entire basis System is linked to be entirety, and the width of connection beam 7 is 400mm, and the height of connection beam 7 is 1000mm or so, to increase entire basis The rigidity of system.
Using the Pile Foundations Design and construction method of the karst area of the embodiment of the present invention, by corresponding in frame column 1 Position bore first drilling 2;Geology at first drilling 2 is surveyed, the ground at the first drilling 2 is drawn according to exploration result Matter histogram reads the depth l of the stabilization rock face of the first drilling 2 by geologic column1, and the corresponding position of calculation block trestle 1 The the first long L of theoretical stake set1, L1=l1+ m, wherein m > 0.By the first long L of theoretical stake1It is compared with preset value, when first The theoretical long L of stake1Greater than preset value, then first drilling 2 two sides respectively bore one second drilling 3, to second drilling 3 geology into Row exploration, draws the geologic column at the second drilling 3 according to exploration result, reads the second drilling 3 by geologic column Stablize the depth l of rock face2、l3, and the second theoretical stake of calculation block trestle corresponding position is long: L2=l2+ m, L3=l3+m;Its In, m > 0;To L1、L2、L3It is compared, position of the long shortest drilling of Choice Theory stake as piling;To utmostly The upper stake for reducing pile foundation position is long, reduces the difficulty of construction, further, also reduces project cost, shorten the duration.
In the description of the present invention, it is to be understood that, term " on ", "lower", "left", "right", "top", "bottom" etc. indicate Orientation or positional relationship be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description the present invention and simplification retouch It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvement and replacement can also be made, these are improved and replacement Also it should be regarded as protection scope of the present invention.

Claims (8)

1. the Pile Foundations Design and construction method of a kind of karst area, it is characterised in that: include the following steps,
S1, first drilling of advance drilling formation is carried out in the corresponding position of frame column to be built;
S2, the geology of first drilling is surveyed, the geologic column of the first drill hole is drawn according to exploration result, is led to Cross the depth l that geologic column reads the stabilization rock face of the first drilling1, and the first theoretical stake of calculation block trestle corresponding position Long L1, L1=l1+ m, wherein m > 0;
By the first long L of theoretical stake1It is compared with preset value, as the long L of theoretical stake1Greater than preset value, then S3 is entered step;Work as reason By the long L of stake1Less than or equal to preset value, S6 is otherwise entered step;
S3, one second drilling is respectively bored in the two sides of the first drilling;
S4, the geology of the second drilling is surveyed, the geologic column of the second drill hole is drawn according to exploration result, passes through ground Matter histogram reads the depth l of the stabilization rock face of the second drilling2、l3, and the second theoretical stake of calculation block trestle corresponding position is long L2、L3: L2=l2+ m, L3=l3+m;Wherein, m > 0;
S5, to the L in step S2 and S41、L2、L3Data be compared, and the long shortest drilling of Choice Theory stake is as piling Position;
S6, it drives piles at the position that step S5 is selected;
S7, arrange cushion cap, conversion beam and connection beam to form pile foundation in stake.
2. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S3 In, second drilling with first drilling at a distance from equal to the original two first adjacent spacings of wells from half.
3. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S1 In, step S2 is carried out again after first completing K advance borehole, and wherein K is the quantity of frame column to be built.
4. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S6 In, when piling, it need to confirm and just start next pile of constructing after the intensity of a upper pile need to reach setting intensity.
5. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S6 In, according to place and different zones karstic development pattern and degree, select suitable pile-type.
6. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: m be greater than etc. In 0.5m.
7. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S7 In, conversion depth of beam is more than or equal to 1500mm, and the width of conversion beam is more than or equal to the width of frame column.
8. the Pile Foundations Design and construction method of karst area according to claim 1, it is characterised in that: step S7 In, the width of connection beam is 300-500mm, and connection depth of beam is 900-1100mm.
CN201910504810.3A 2019-06-12 2019-06-12 Pile foundation design and construction method for karst development area Active CN110258495B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910504810.3A CN110258495B (en) 2019-06-12 2019-06-12 Pile foundation design and construction method for karst development area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910504810.3A CN110258495B (en) 2019-06-12 2019-06-12 Pile foundation design and construction method for karst development area

Publications (2)

Publication Number Publication Date
CN110258495A true CN110258495A (en) 2019-09-20
CN110258495B CN110258495B (en) 2020-12-01

Family

ID=67917737

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910504810.3A Active CN110258495B (en) 2019-06-12 2019-06-12 Pile foundation design and construction method for karst development area

Country Status (1)

Country Link
CN (1) CN110258495B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110866294A (en) * 2019-11-20 2020-03-06 浙江省交通规划设计研究院有限公司 Auxiliary analysis system for designing bridge pile foundation in karst area
CN111719412A (en) * 2020-06-16 2020-09-29 中铁第四勘察设计院集团有限公司 Method for adjusting abutment of bridge in karst area
CN114182749A (en) * 2021-12-29 2022-03-15 中交一公局集团有限公司 Karst complex geological pile foundation construction process and karst complex geological pile foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104929146A (en) * 2015-05-06 2015-09-23 中国地质大学(武汉) Multilayer karst development zone pile foundation engineering construction method
JP2016199861A (en) * 2015-04-07 2016-12-01 大成建設株式会社 Pile foundation structure
CN109024569A (en) * 2018-08-22 2018-12-18 中国建筑第四工程局有限公司 A kind of beading solution cavity pretreatment construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016199861A (en) * 2015-04-07 2016-12-01 大成建設株式会社 Pile foundation structure
CN104929146A (en) * 2015-05-06 2015-09-23 中国地质大学(武汉) Multilayer karst development zone pile foundation engineering construction method
CN109024569A (en) * 2018-08-22 2018-12-18 中国建筑第四工程局有限公司 A kind of beading solution cavity pretreatment construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄长华等: "岩溶地区高层建筑桩基计算长度的确定", 《武汉大学学报(工学版)》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110866294A (en) * 2019-11-20 2020-03-06 浙江省交通规划设计研究院有限公司 Auxiliary analysis system for designing bridge pile foundation in karst area
CN110866294B (en) * 2019-11-20 2023-10-20 浙江数智交院科技股份有限公司 Auxiliary analysis system for karst area bridge pile foundation design
CN111719412A (en) * 2020-06-16 2020-09-29 中铁第四勘察设计院集团有限公司 Method for adjusting abutment of bridge in karst area
CN114182749A (en) * 2021-12-29 2022-03-15 中交一公局集团有限公司 Karst complex geological pile foundation construction process and karst complex geological pile foundation

Also Published As

Publication number Publication date
CN110258495B (en) 2020-12-01

Similar Documents

Publication Publication Date Title
CN110258495A (en) A kind of Pile Foundations Design and construction method of karst area
CN102979501B (en) Automatically promote the method that drill bit leaves the perforate bottom surface in subsurface formations
Barkved et al. Valhall field-still on plateau after 20 years of production
CN105064990B (en) A kind of construction modeling method by horizontal well three-dimensional visualization Strata Comparison
CN104854555A (en) System, method and computer program product for a rug plot for geosteering applications
DE102010006141A1 (en) DDS for deep geothermal energy
Clifford et al. Integration of 4D seismic data into the management of oil reservoirs with horizontal wells between fluid contacts
RU2303101C1 (en) Ground consolidation method
JP5250488B2 (en) Injection method support processing apparatus, injection method support processing method, and injection method
CN112854245A (en) Classification design method for earth rock foundation pit support based on depth and medium-stroke fossil rock burial depth
Aasheim Oseberg: Increased recoverable resources by optimal reservoir management and use of new technology
Rosland et al. Collaborative Well Planning and Optimization of Well Placement: A Case Study From Mangala Field Development, Rajasthan India
Burke et al. Superjet grouting: New technology for in situ soil improvement
Robertson et al. Subzone redevelopment of the long beach unit, Wilmington oil field: a case study
RU2788189C1 (en) Method for developing oil deposits
JP2004197415A (en) Supporting device and method for injection work
JPS5920822B2 (en) Seismic reinforcement method for embankments
RU2191892C2 (en) Method of nonuniform oil deposit development
RU2122107C1 (en) Method for control of development of oil pools with the help of maps of residual oil-saturated strata
JPS61296207A (en) Method for measuring subsidence and inclination of caisson at time of construction
Mulder et al. Sole pit: Improving performance and increasing reserves by horizontal drilling
Benson et al. Assessment of potential karst conditions for a new bridge in the Florida Keys
CN108931822A (en) A kind of underground full packing solution cavity exploitation method
Nguyen et al. The effects of groundwater pumping on piled foundations
Phillips et al. 3D Modelling/Visualization Guides Horizontal Well Program In Wilmington Field

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant