CN108984807A - A kind of coal mine down-hole tunnel deformation monitoring method - Google Patents

A kind of coal mine down-hole tunnel deformation monitoring method Download PDF

Info

Publication number
CN108984807A
CN108984807A CN201710410834.3A CN201710410834A CN108984807A CN 108984807 A CN108984807 A CN 108984807A CN 201710410834 A CN201710410834 A CN 201710410834A CN 108984807 A CN108984807 A CN 108984807A
Authority
CN
China
Prior art keywords
coal mine
mine down
monitoring method
deformation monitoring
hole tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710410834.3A
Other languages
Chinese (zh)
Inventor
刘庆利
任建喜
陈江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI BINZHANG WANJIAPO MINING CO Ltd
Original Assignee
SHAANXI BINZHANG WANJIAPO MINING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI BINZHANG WANJIAPO MINING CO Ltd filed Critical SHAANXI BINZHANG WANJIAPO MINING CO Ltd
Priority to CN201710410834.3A priority Critical patent/CN108984807A/en
Publication of CN108984807A publication Critical patent/CN108984807A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Agronomy & Crop Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Health & Medical Sciences (AREA)
  • Marine Sciences & Fisheries (AREA)
  • General Business, Economics & Management (AREA)
  • Animal Husbandry (AREA)
  • Economics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Force Measurement Appropriate To Specific Purposes (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The present invention is a kind of coal mine down-hole tunnel deformation monitoring method, the specific steps are as follows: (1) numerical simulation analysis is tentatively unfolded to roadway deformation;(2) convergence monitoring is carried out to drift section;(3) delamination monitoring is carried out to top plate;(4) monitoring is pried through using drilling to tunnel;(5) anchor pole, anchor cable stress in tunnel are monitored;(6) comprehensive analysis is carried out to result out obtained as above.Operation of the present invention is simple, easily implements, and from theoretical values sunykatuib analysis to live practical more means monitorings, the data of coal mine down-hole tunnel deformation more detailed can be obtained, to provide more accurate foundation for design of its support.

Description

A kind of coal mine down-hole tunnel deformation monitoring method
Technical field
The present invention relates to coal mining fields, and in particular to a kind of coal mine down-hole tunnel deformation monitoring method.
Background technique
Coal mine down-hole tunnel is by action of underground, and inducement is complicated, and influence factor is more, the deformation that mostly occurs, country rock convergence Equal strata behaviors.Previous monitoring means is mostly single method, it is difficult to surrouding rock deformation rule is more comprehensively grasped, thus Roadway support design is based on insufficient grounds, so the roadway deformation monitoring method of more suites of measure is used to provide more for roadway support design Accurate data are added to be of great significance.
Summary of the invention
Technical problem to be solved by the present invention lies in view of the above shortcomings of the prior art, provide a kind of underground coal mine lane Road deformation monitoring method.
To solve the above problems, the present invention proposes a kind of coal mine down-hole tunnel deformation monitoring method, the specific steps are as follows: (1) numerical simulation analysis is tentatively unfolded to roadway deformation;(2) convergence monitoring is carried out to drift section;(3) top plate is carried out Delamination monitoring;(4) monitoring is pried through using drilling to tunnel;(5) anchor pole, anchor cable stress in tunnel are monitored;(6) right Result out obtained as above carries out comprehensive analysis.
The step (1) method particularly includes: the geologic information of collection research regional roadway establishes model, carries out numerical value Sunykatuib analysis.
The step (2) requires are as follows: the production of ring of convergence uses gasket, is vertically welded on anchor rod pallet board, is fixed on anchor It on bar, is measured with digital readout convergence meter, the measurement accuracy of convergence gauge is 0.01mm.
The roof delamination monitoring of the step (3) is monitored using 9 roof separation indicators, roof separation indicator buried depth Respectively 8m, 7.5m, 7m, 5m, 2.8m, 2.5m, 2m, 1.5m, 1.0m.
The step (4) is helped using air drill in back and two and base angle corresponding position beats moving-coil monitoring holes, with brill Hole endoscope carries out prying through record in hole, and carries out data analysis.
The step (5) is monitored anchor pole, anchor cable force-bearing situation using anchor pole, anchor dynamometer.
The step (6) analyzes above step measured result, obtains roadway deformation monitoring result, is roadway support Design provides foundation.
Compared with the prior art, the present invention has the following advantages:
Operation of the present invention is simple, easily implements;It, can be more detailed from theoretical values sunykatuib analysis to live practical more means monitorings The data for obtaining coal mine down-hole tunnel deformation, to provide more accurate foundation for design of its support.
Invention is further described in detail with reference to the accompanying drawings and examples.
Detailed description of the invention
Fig. 1 is flow chart of the present invention.
Specific embodiment
Example is to carry out deformation monitoring, according to Fig. 1, a kind of coal mine down-hole tunnel deformation monitoring to certain mine underworkings Method, the specific steps are as follows: (1) numerical simulation analysis is tentatively unfolded to roadway deformation;(2) convergence prison is carried out to drift section It surveys;(3) delamination monitoring is carried out to top plate;(4) monitoring is pried through using drilling to tunnel;(5) to anchor pole in tunnel, anchor cable by Power is monitored;(6) comprehensive analysis is carried out to result out obtained as above.
The geologic information of step (1) collection research regional roadway establishes model, carries out numerical simulation analysis.
The production of step (2) ring of convergence uses gasket, is vertically welded on anchor rod pallet board, is fixed on anchor pole, uses Digital readout convergence meter is measured, and the measurement accuracy of convergence gauge is 0.01mm.
The roof delamination monitoring of step (3) is monitored using 9 roof separation indicators, roof separation indicator buried depth difference For 8m, 7.5m, 7m, 5m, 2.8m, 2.5m, 2m, 1.5m, 1.0m.
Step (4) using air drill in back and two to being helped and base angle corresponding position beats moving-coil monitoring holes, with drilling Endoscope carries out prying through record in hole, and carries out data analysis.
Step (5) is monitored anchor pole, anchor cable force-bearing situation using anchor pole, anchor dynamometer.
Step (6) analyzes above step measured result, obtains roadway deformation monitoring result.
The above is preferred version of the invention, but a specific embodiment of the invention is not limited to examples detailed above.

Claims (7)

1. a kind of coal mine down-hole tunnel deformation monitoring method, the specific steps are as follows: (1) numerical simulation is tentatively unfolded to roadway deformation Analysis;(2) convergence monitoring is carried out to drift section;(3) delamination monitoring is carried out to top plate;(4) prison is pried through using drilling to tunnel It surveys;(5) anchor pole, anchor cable stress in tunnel are monitored;(6) comprehensive analysis is carried out to result out obtained as above.
2. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that collection research region The geologic information in tunnel establishes model, carries out numerical simulation analysis.
3. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that the production of ring of convergence It using gasket, is vertically welded on anchor rod pallet board, is fixed on anchor pole, measured with digital readout convergence meter, convergence gauge Measurement accuracy is 0.01mm.
4. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that roof delamination monitoring Be monitored using 9 roof separation indicators, roof separation indicator buried depth be respectively 8m, 7.5m, 7m, 5m, 2.8m, 2.5m, 2m, 1.5m、1.0m。
5. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that using air drill in lane Road top plate and two is helped and base angle corresponding position beats moving-coil monitoring holes, is carried out prying through record in hole with inspection instrument for borehole, and carry out Data analysis.
6. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that use anchor pole, anchor Rope dynamometer is monitored anchor pole, anchor cable force-bearing situation.
7. a kind of coal mine down-hole tunnel deformation monitoring method according to claim 1, which is characterized in that above step institute It surveys result to be analyzed, obtains roadway deformation monitoring result, provide foundation for roadway support design.
CN201710410834.3A 2017-06-04 2017-06-04 A kind of coal mine down-hole tunnel deformation monitoring method Pending CN108984807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710410834.3A CN108984807A (en) 2017-06-04 2017-06-04 A kind of coal mine down-hole tunnel deformation monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710410834.3A CN108984807A (en) 2017-06-04 2017-06-04 A kind of coal mine down-hole tunnel deformation monitoring method

Publications (1)

Publication Number Publication Date
CN108984807A true CN108984807A (en) 2018-12-11

Family

ID=64501167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710410834.3A Pending CN108984807A (en) 2017-06-04 2017-06-04 A kind of coal mine down-hole tunnel deformation monitoring method

Country Status (1)

Country Link
CN (1) CN108984807A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882193A (en) * 2019-04-08 2019-06-14 安徽理工大学 A kind of circulation internal pressure loading method of large scale simulation roadway support body
CN110318795A (en) * 2019-04-23 2019-10-11 安徽理工大学 A kind of coal mine roadway deformation characteristics of rocks combination monitoring system and monitoring method
CN110992197A (en) * 2019-10-29 2020-04-10 天地科技股份有限公司 Early warning method and system for coal mine roadway deformation
CN111271129A (en) * 2020-01-31 2020-06-12 天地科技股份有限公司 Method for acquiring deformation and fracture expansion rule of stoping roadway surrounding rock

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109882193A (en) * 2019-04-08 2019-06-14 安徽理工大学 A kind of circulation internal pressure loading method of large scale simulation roadway support body
CN109882193B (en) * 2019-04-08 2021-10-01 安徽理工大学 Cyclic internal pressure loading method for large-size simulation roadway support body
CN110318795A (en) * 2019-04-23 2019-10-11 安徽理工大学 A kind of coal mine roadway deformation characteristics of rocks combination monitoring system and monitoring method
CN110992197A (en) * 2019-10-29 2020-04-10 天地科技股份有限公司 Early warning method and system for coal mine roadway deformation
CN111271129A (en) * 2020-01-31 2020-06-12 天地科技股份有限公司 Method for acquiring deformation and fracture expansion rule of stoping roadway surrounding rock

Similar Documents

Publication Publication Date Title
CN108984807A (en) A kind of coal mine down-hole tunnel deformation monitoring method
CN105927211B (en) A kind of the rock mass mechanics characteristic original position drilling test method and device of deep underground engineering
CN103293560B (en) A kind of method of testing adopting triple stress court
CN103967476B (en) With boring physical prospecting forward probe device and detection method
AU2017317602B2 (en) Sound level meter-based tunnel roof rock Protodyakovnov coefficient detecting-while-drilling apparatus and method
CN105318824B (en) A kind of method that wall rock loosening ring is measured based on distributed resistance foil gauge
CN103529488A (en) Mine roof and floor water inrush monitoring and prediction system and method
CN103821183A (en) Testing apparatus for simulating phenomenon and law of soil heave-piping failure
CN103148770A (en) Monitoring method for mechanical deformation of mine filling body
CN105372298A (en) Analysis method for formation rock mineral constituents
CN104089595B (en) Stope base object model ruptures determination of distance method in advance
CN203687823U (en) Mining telescopic measuring rod
CN103954197B (en) A kind of lane surface displacement, deep displacement coordination measuring method
CN105003258A (en) Method for acquiring density framework parameters of methane fluid in high temperature high pressure air layer
Dawn Technologies of ground support monitoring in block caving operations
CN111350545A (en) Mine dynamic disaster system and method based on multi-dimensional monitoring
CN206721943U (en) A kind of pile foundation displacement auxiliary detection device
CN205400721U (en) Long -range survey device of well head gas
CN114061428B (en) Rock stratum displacement monitoring device and method for three-dimensional similarity simulation experiment
CN204705337U (en) A kind of mine working basic point displacement measuring device
CN103323279B (en) Evaluate the test method of size effect on tunnel excavation response impact
CN102937436B (en) Overground disoriented core orientation method
CN205404017U (en) Can measure petrosal foramen tangential strain's sleeve device
CN201891382U (en) Device for acquiring pressured parameters of drill bit during forward movement of drilling machine
CN110454155A (en) A kind of method determining the Quaternary Stratigraphic age using magnetic susceptibility log method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181211