CN108978449B - A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints - Google Patents
A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints Download PDFInfo
- Publication number
- CN108978449B CN108978449B CN201810933991.7A CN201810933991A CN108978449B CN 108978449 B CN108978449 B CN 108978449B CN 201810933991 A CN201810933991 A CN 201810933991A CN 108978449 B CN108978449 B CN 108978449B
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- pier
- fixed
- grouting
- sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 86
- 239000010959 steel Substances 0.000 claims description 86
- 239000004570 mortar (masonry) Substances 0.000 claims description 26
- 238000002347 injection Methods 0.000 claims description 11
- 239000007924 injection Substances 0.000 claims description 11
- 238000009434 installation Methods 0.000 claims description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 18
- 238000000034 method Methods 0.000 abstract description 7
- 230000009286 beneficial effect Effects 0.000 abstract description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 2
- 239000011440 grout Substances 0.000 abstract 1
- 239000000463 material Substances 0.000 description 7
- 239000011374 ultra-high-performance concrete Substances 0.000 description 6
- 238000005260 corrosion Methods 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000003292 glue Substances 0.000 description 2
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 238000000844 transformation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域Technical field
本发明涉及桥梁建造技术领域,具体涉及一种接头采用灌浆套筒的承插式构造预制拼装桥墩。The invention relates to the technical field of bridge construction, and in particular to a socket-type prefabricated assembled bridge pier whose joints adopt grouting sleeves.
背景技术Background technique
桥梁结构遭遇地震时,桥墩是易损部位。目前采用高强砂浆连接或结构胶连接的拼装桥墩,接头多采用平面接缝形式,难以消除节段间可能发生的剪切错动,其整体性和抗震性能不如整体现浇的桥墩,一般用于地震危险性较低的地区。另一方面,平面接缝对拼接面的施工精度要求非常高,高强砂浆或结构胶与预制混凝土之间的材料力学性能差异较大,其接缝的耐久性问题较为突出。而且,预制拼装桥墩的现场拼接工作相对于灌浇式桥墩而言,安装的危险性也更大。When the bridge structure encounters an earthquake, the bridge piers are vulnerable parts. At present, assembled bridge piers are connected with high-strength mortar or structural glue. The joints are mostly in the form of plane joints, which makes it difficult to eliminate possible shear dislocation between segments. Their integrity and seismic resistance are not as good as those of integrally cast-in-situ bridge piers. They are generally used for Areas with low earthquake risk. On the other hand, plane joints require very high construction accuracy of the splicing surface. The mechanical properties of materials between high-strength mortar or structural adhesive and precast concrete are quite different, making the durability of the joints more prominent. Moreover, the on-site splicing work of prefabricated assembled bridge piers is also more dangerous than the installation of cast-in-place bridge piers.
发明内容Contents of the invention
为了克服上述现有技术的缺陷,本发明所要解决的技术问题是:提供一种便于现场施工,提升现场施工安全度的预制拼装桥墩。In order to overcome the above-mentioned shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a prefabricated assembled bridge pier that facilitates on-site construction and improves the safety of on-site construction.
为了解决上述技术问题,本发明采用的技术方案为:In order to solve the above technical problems, the technical solution adopted by the present invention is:
一种接头采用灌浆套筒的承插式构造预制拼装桥墩,包括预制承台和预制桥墩,所述预制桥墩安装于所述预制承台上,多个的所述预制桥墩层叠安装;所述预制承台的顶面和所述预制桥墩的顶面设置有榫槽,所述预制桥墩的底部设置有凸榫,所述凸榫的尺寸与所述榫槽相适配;A prefabricated assembled bridge pier with a socket-type structure for joints using grouting sleeves, including a prefabricated pedestal and a prefabricated pier. The prefabricated piers are installed on the prefabricated pier, and a plurality of the prefabricated piers are installed in a stack; the prefabricated piers are The top surface of the platform and the top surface of the prefabricated pier are provided with tenon grooves, and the bottom of the prefabricated bridge pier is provided with a tenon, and the size of the tenon is adapted to the tenon groove;
所述预制桥墩的底面设置有开口向下的桥墩灌浆套筒;所述预制桥墩内预埋有桥墩钢筋,所述桥墩钢筋的一端伸入所述预制桥墩底面的桥墩灌浆套筒内,另一端伸出所述预制桥墩的顶面并伸入上方相邻的所述预制桥墩的桥墩灌浆套筒内;The bottom surface of the prefabricated pier is provided with a pier grouting sleeve with an opening downward; pier steel bars are pre-embedded in the prefabricated pier, and one end of the pier steel bar extends into the pier grouting sleeve on the bottom surface of the prefabricated pier, and the other end Extend out the top surface of the precast pier and extend into the pier grouting sleeve of the adjacent precast pier above;
所述预制承台内预埋有承台钢筋,所述承台钢筋从所述预制承台的顶面伸出并伸入上方所述预制桥墩的桥墩灌浆套筒内;There are capping steel bars embedded in the prefabricated capping platform, and the capping reinforcing bars extend from the top surface of the prefabricated capping platform and extend into the pier grouting sleeve of the prefabricated bridge pier above;
所述榫槽内嵌设有钢管,所述凸榫尺寸与所述钢管相适配,所述凸榫嵌入所述钢管中。A steel pipe is embedded in the tenon groove, the size of the tenon matches the steel pipe, and the tenon is embedded in the steel pipe.
进一步的,所述凸榫上套设有钢制套筒,所述钢制套筒的外径与所述钢管相适配。Further, a steel sleeve is placed on the tenon, and the outer diameter of the steel sleeve is adapted to the steel pipe.
进一步的,所述桥墩灌浆套筒的孔壁上设置有注料孔和出料孔。Further, the hole wall of the pier grouting sleeve is provided with an injection hole and a discharge hole.
进一步的,所述钢管管道内和所述桥墩灌浆套筒内填塞有砂浆。Further, the steel pipe and the pier grouting sleeve are filled with mortar.
进一步的,所述砂浆为超高性能砂浆。Furthermore, the mortar is ultra-high performance mortar.
进一步的,所述预制承台的顶面设置有凸起部,所述凸起部上设置有所述榫槽。Further, the top surface of the prefabricated platform is provided with a raised portion, and the raised portion is provided with the tongue and groove.
进一步的,还包括固定板,所述固定板分别设置于所述凸起部和所述预制桥墩的连接处的外壁以及两个的所述预制桥墩连接处的外壁上。Further, it also includes fixing plates, which are respectively provided on the outer wall of the connection between the protrusion and the prefabricated pier and on the outer walls of the connection of the two prefabricated piers.
进一步的,所述凸起部的侧壁和所述预制桥墩的上下两端侧壁上分别开设有固定通孔,多个所述固定通孔的轴线相互平行,所述固定通孔内设置有固定钢筋,所述固定钢筋的两端伸出所述固定通孔并穿过所述固定板。Further, fixed through holes are respectively provided on the side walls of the raised portion and the upper and lower end side walls of the prefabricated pier. The axes of the plurality of fixed through holes are parallel to each other. There are provided in the fixed through holes. Fixed steel bars, both ends of which extend out of the fixed through holes and pass through the fixed plate.
进一步的,还包括锚具,所述锚具设置在所述固定钢筋的端部。Further, it also includes an anchor provided at the end of the fixed steel bar.
本发明的有益效果在于:通过凸榫和榫槽的设计,在拼接预制承台和预制桥墩的时候,防止出现倾覆等危险事故,增加了施工过程中结构的稳定性;桥墩灌浆套筒、桥墩钢筋和承台钢筋的设置,能够在灌浆完成之后,保证整体结构的稳定性,增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力;钢管31的设置进一步增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力,增加了安全性。The beneficial effects of the present invention are: through the design of tenons and tenon grooves, dangerous accidents such as overturning are prevented when splicing prefabricated caps and prefabricated piers, and the stability of the structure during the construction process is increased; pier grouting sleeves, bridge piers The arrangement of steel bars and platform steel bars can ensure the stability of the overall structure after grouting is completed, and increase the horizontal shear resistance of prefabricated assembled bridge piers with socket-type structures where grouting sleeves are used as joints; The arrangement further increases the horizontal shear resistance of the prefabricated assembled bridge piers with a socket structure using grouting sleeves for joints according to the invention, and increases safety.
附图说明Description of the drawings
图1为本发明具体实施方式的一种接头采用灌浆套筒的承插式构造预制拼装桥墩的正剖视图;Figure 1 is a front cross-sectional view of a prefabricated assembled bridge pier with a socket structure using a grouting sleeve for joints according to a specific embodiment of the present invention;
图2为本发明具体实施方式的一种接头采用灌浆套筒的承插式构造预制拼装桥墩的预制承台的俯视图;Figure 2 is a top view of a prefabricated cap platform of a prefabricated assembled bridge pier with a socket-type structure where the joint adopts a grouting sleeve according to the specific embodiment of the present invention;
标号说明:Label description:
1、预制承台;11、承台钢筋;1. Prefabricated cap; 11. Rebar for cap;
2、预制桥墩;21、桥墩灌浆套筒;22、桥墩钢筋;23、注料孔;24、出料孔;2. Prefabricated pier; 21. Bridge pier grouting sleeve; 22. Bridge pier steel bar; 23. Injection hole; 24. Discharge hole;
3、榫槽;31、钢管;3. Tongue and groove; 31. Steel pipe;
4、凸榫;4. Tenon;
5、固定板;5. Fixed plate;
6、固定钢筋;61、锚具;6. Fixed steel bars; 61. Anchors;
7、砂浆。7. Mortar.
具体实施方式Detailed ways
为详细说明本发明的技术内容、所实现目的及效果,以下结合实施方式并配合附图予以说明。In order to describe the technical content, achieved objectives and effects of the present invention in detail, the following description will be made in conjunction with the embodiments and the accompanying drawings.
本发明最关键的构思在于:通过凸榫和榫槽的设计,在拼接预制承台和预制桥墩的时候,防止出现倾覆等危险事故,增加了施工过程中结构的稳定性。The most critical idea of the present invention is to prevent dangerous accidents such as overturning when splicing prefabricated caps and prefabricated piers through the design of tenons and tenon grooves, and increase the stability of the structure during the construction process.
请参照图1和图2所示,一种接头采用灌浆套筒的承插式构造预制拼装桥墩,包括预制承台1和预制桥墩2,所述预制桥墩2安装于所述预制承台1上,多个的所述预制桥墩2层叠安装;所述预制承台1的顶面和所述预制桥墩2的顶面设置有榫槽3,所述预制桥墩2的底部设置有凸榫4,所述凸榫4的尺寸与所述榫槽3相适配;Please refer to Figures 1 and 2, a prefabricated assembled bridge pier with a socket-type structure using grouting sleeves for joints, including a prefabricated platform 1 and a prefabricated pier 2. The prefabricated pier 2 is installed on the prefabricated platform 1. , a plurality of the prefabricated piers 2 are installed in a stack; the top surface of the prefabricated platform 1 and the top surface of the prefabricated pier 2 are provided with tenons 3, and the bottom of the prefabricated piers 2 is provided with tenons 4, so The size of the tenon 4 is adapted to the tenon groove 3;
所述预制桥墩2的底面设置有开口向下的桥墩灌浆套筒21;所述预制桥墩2内预埋有桥墩钢筋22,所述桥墩钢筋22的一端伸入所述预制桥墩2底面的桥墩灌浆套筒21内,另一端伸出所述预制桥墩2的顶面并伸入上方相邻的所述预制桥墩2的桥墩灌浆套筒21内;The bottom surface of the prefabricated pier 2 is provided with a pier grouting sleeve 21 that opens downward; a pier steel bar 22 is pre-embedded in the prefabricated pier 2, and one end of the pier steel bar 22 extends into the pier grouting hole on the bottom surface of the prefabricated pier 2. In the sleeve 21, the other end extends out of the top surface of the prefabricated pier 2 and extends into the pier grouting sleeve 21 of the adjacent prefabricated pier 2 above;
所述预制承台1内预埋有承台钢筋11,所述承台钢筋11从所述预制承台1的顶面伸出并伸入上方所述预制桥墩2的桥墩灌浆套筒21内;There are platform steel bars 11 embedded in the prefabricated platform 1. The platform steel bars 11 extend from the top surface of the prefabricated platform 1 and extend into the pier grouting sleeve 21 of the above prefabricated pier 2;
所述榫槽3内嵌设有钢管31,所述凸榫4尺寸与所述钢管31相适配,所述凸榫4嵌入所述钢管31中。A steel pipe 31 is embedded in the tongue groove 3 , the size of the tongue 4 matches the steel pipe 31 , and the tongue 4 is embedded in the steel pipe 31 .
从上述描述可知,上述的一种接头采用灌浆套筒的承插式构造预制拼装桥墩的有益效果在于:通过凸榫4和榫槽3的设计,在拼接预制承台1和预制桥墩2的时候,防止出现倾覆等危险事故,增加了施工过程中结构的稳定性;桥墩灌浆套筒21、桥墩钢筋22和承台钢筋11的设置,能够在灌浆完成之后,保证整体结构的稳定性,增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力;钢管31的设置进一步增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力,增加了安全性。From the above description, it can be seen that the beneficial effect of the above-mentioned prefabricated assembled bridge piers using a socket-type structure of a grouting sleeve is: through the design of the tenon 4 and the tenon groove 3, when the prefabricated platform 1 and the prefabricated pier 2 are spliced to prevent dangerous accidents such as overturning and increase the stability of the structure during the construction process; the settings of the pier grouting sleeve 21, the pier steel bar 22 and the cap steel bar 11 can ensure the stability of the overall structure after the grouting is completed, increasing the The joints according to the present invention adopt a socket-type structure of grouting sleeves to improve the horizontal shear resistance of prefabricated assembled bridge piers; the provision of the steel pipe 31 further increases the horizontal shear resistance of the joints according to the present invention using a socket-type structure of grouting sleeves. Horizontal shear resistance for added safety.
进一步的,所述凸榫4上套设有钢制套筒,所述钢制套筒的外径与所述钢管31相适配。Furthermore, the tenon 4 is covered with a steel sleeve, and the outer diameter of the steel sleeve is adapted to the steel pipe 31 .
从上述描述可知,所述凸榫4上套设有钢制套筒,进一步增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力,增加了安全性。It can be seen from the above description that the tenon 4 is covered with a steel sleeve, which further increases the horizontal shear resistance of the prefabricated assembled bridge pier with a socket-type structure using a grouting sleeve for the joint and increases the safety. .
进一步的,所述桥墩灌浆套筒21的孔壁上设置有注料孔23和出料孔24。Further, the hole wall of the pier grouting sleeve 21 is provided with an injection hole 23 and a discharge hole 24.
从上述描述可知,注料孔23和出料孔24的设置,能够更加方便注入固定材料,方便了施工操作,增加了施工效率。It can be seen from the above description that the arrangement of the injection hole 23 and the discharge hole 24 can more conveniently inject fixed materials, facilitate construction operations, and increase construction efficiency.
进一步的,所述钢管31管道内和所述桥墩灌浆套筒21内填塞有砂浆7。Further, the steel pipe 31 and the pier grouting sleeve 21 are filled with mortar 7 .
从上述描述可知,砂浆7能够将设置于钢管31管道内的凸榫4、伸出预制承台1顶面的承台钢筋11和桥墩灌浆套筒21内的桥墩钢筋22连接成一个整体,保证了整体结构的稳定性,同时增加了连接处水平面的抗剪能力。It can be seen from the above description that the mortar 7 can connect the tenon 4 provided in the steel pipe 31, the platform steel bar 11 extending out of the top surface of the prefabricated platform 1 and the pier steel bar 22 in the pier grouting sleeve 21 into a whole, ensuring that It improves the stability of the overall structure and increases the shear resistance of the horizontal plane at the connection.
进一步的,所述砂浆7为超高性能砂浆。Furthermore, the mortar 7 is ultra-high performance mortar.
从上述描述可知,超高性能混凝土(简称UHPC)是一种新型的水泥基复合材料,强度高、韧性好,同时具有良好的耐腐蚀性、耐磨性和抗渗性,抗拉强度一般不低于5MPa。剔除粗骨料的UHPC性状上可视为一种砂浆,即为超高性能砂浆(简称UHPM)。As can be seen from the above description, ultra-high performance concrete (UHPC for short) is a new type of cement-based composite material with high strength, good toughness, good corrosion resistance, wear resistance and impermeability. The tensile strength is generally not Below 5MPa. UHPC with coarse aggregate removed can be regarded as a kind of mortar, that is, ultra-high performance mortar (UHPM for short).
进一步的,所述预制承台1的顶面设置有凸起部,所述凸起部上设置有所述榫槽3。Furthermore, the top surface of the prefabricated platform 1 is provided with a raised portion, and the raised portion is provided with the tongue and groove 3 .
进一步的,还包括固定板5,所述固定板5分别设置于所述凸起部和所述预制桥墩2的连接处的外壁以及两个的所述预制桥墩2连接处的外壁上。Furthermore, it also includes fixing plates 5, which are respectively arranged on the outer wall of the connection between the protrusion and the prefabricated pier 2 and the outer wall of the connection between the two prefabricated piers 2.
进一步的,所述凸起部的侧壁和所述预制桥墩2的上下两端侧壁上分别开设有固定通孔,多个所述固定通孔的轴线相互平行,所述固定通孔内设置有固定钢筋6,所述固定钢筋6的两端伸出所述固定通孔并穿过所述固定板5。Further, fixed through holes are respectively provided on the side walls of the raised portion and the upper and lower end side walls of the prefabricated pier 2. The axes of a plurality of fixed through holes are parallel to each other. There are provided in the fixed through holes There is a fixed steel bar 6, and both ends of the fixed steel bar 6 extend out of the fixed through hole and pass through the fixed plate 5.
进一步的,还包括锚具61,所述锚具61设置在所述固定钢筋6的端部。Further, an anchor 61 is included, and the anchor 61 is provided at the end of the fixed steel bar 6 .
从上述描述可知,通过凸起部的设置,能够利用凸起部增设固定板5和固定钢筋6,从而利用凸起杆和固定钢筋6在尚未进行灌浆的时候对预制桥墩2进行初步的固定,增加了施工的安全;固定钢筋6将榫头和榫槽3进行栓接,进一步增加了结构的稳定性。It can be seen from the above description that through the setting of the raised portion, the raised portion can be used to add fixed plates 5 and fixed steel bars 6, so that the raised rods and fixed steel bars 6 can be used to preliminarily fix the prefabricated pier 2 before grouting is carried out. The safety of construction is increased; the fixed steel bars 6 bolt the tenon and the tenon groove 3, further increasing the stability of the structure.
实施例一Embodiment 1
请参照图1和图2所示,一种接头采用灌浆套筒的承插式构造预制拼装桥墩,包括预制承台1和预制桥墩2,所述预制桥墩2安装于所述预制承台1上,多个的所述预制桥墩2层叠安装;所述预制承台1的顶面中部设置有凸起部,所述凸起部和所述预制桥墩2的顶面中部设置有榫槽3,所述预制桥墩2的底部设置有凸榫4,所述榫槽3内嵌设有钢管31,所述凸榫4尺寸与所述钢管31相适配,所述凸榫4嵌入所述钢管31中;所述凸榫4上套设有钢制套筒,所述钢制套筒的外径与所述钢管31相适配;所述预制桥墩2的底面设置有开口向下的桥墩灌浆套筒21;所述预制桥墩2内预埋有桥墩钢筋22,所述桥墩钢筋22的一端伸入所述预制桥墩2底面的桥墩灌浆套筒21内,另一端伸出所述预制桥墩2的顶面并伸入上方相邻的所述预制桥墩2的桥墩灌浆套筒21内;所述预制承台1内预埋有承台钢筋11,所述承台钢筋11从所述预制承台1的顶面伸出并伸入上方所述预制桥墩2的桥墩灌浆套筒21内;所述桥墩灌浆套筒21的孔壁上设置有注料孔23和出料孔24;所述钢管31管道内和所述桥墩灌浆套筒21内填塞有超高性能砂浆;还包括固定板5,所述固定板5分别设置于所述凸起部和所述预制桥墩2的连接处的外壁以及两个的所述预制桥墩2连接处的外壁上;所述凸起部的侧壁和所述预制桥墩2的上下两端侧壁上分别开设有固定通孔,多个所述固定通孔的轴线相互平行,所述固定通孔内设置有固定钢筋6,所述固定钢筋6的两端伸出所述固定通孔并穿过所述固定板5;还包括锚具61,所述锚具61设置在所述固定钢筋6的端部。Please refer to Figures 1 and 2, a prefabricated assembled bridge pier with a socket-type structure using grouting sleeves for joints, including a prefabricated platform 1 and a prefabricated pier 2. The prefabricated pier 2 is installed on the prefabricated platform 1. , a plurality of the prefabricated piers 2 are installed in a stack; the prefabricated platform 1 is provided with a convex portion in the middle of the top surface, and the convex portion and the middle portion of the top surface of the prefabricated pier 2 are provided with tongue and groove 3, so The bottom of the prefabricated pier 2 is provided with a tenon 4, and a steel pipe 31 is embedded in the tenon groove 3. The size of the tenon 4 matches the steel pipe 31, and the tenon 4 is embedded in the steel pipe 31. ; The tenon 4 is covered with a steel sleeve, the outer diameter of the steel sleeve is adapted to the steel pipe 31; the bottom surface of the prefabricated pier 2 is provided with a pier grouting sleeve with an opening downwards 21; There are pier steel bars 22 pre-embedded in the prefabricated pier 2. One end of the pier steel bar 22 extends into the pier grouting sleeve 21 on the bottom surface of the prefabricated pier 2, and the other end extends out of the top surface of the prefabricated pier 2. and extends into the pier grouting sleeve 21 of the adjacent prefabricated pier 2 above; there are capping steel bars 11 embedded in the prefabricated capping platform 1, and the capping reinforcing bars 11 are inserted from the top of the prefabricated capping platform 1. The surface extends out and extends into the pier grouting sleeve 21 of the prefabricated pier 2 above; the hole wall of the pier grouting sleeve 21 is provided with an injection hole 23 and a discharge hole 24; the steel pipe 31 and The pier grouting sleeve 21 is filled with ultra-high performance mortar; it also includes a fixing plate 5. The fixing plates 5 are respectively provided on the outer wall of the connection between the bulge and the prefabricated pier 2 and on both sides. On the outer wall of the connection point of the prefabricated pier 2; fixed through holes are respectively provided on the side walls of the raised portion and the upper and lower end side walls of the prefabricated pier 2, and the axes of the plurality of fixed through holes are parallel to each other. A fixed steel bar 6 is provided in the fixed through hole, and both ends of the fixed steel bar 6 extend out of the fixed through hole and pass through the fixed plate 5; an anchor 61 is also included, and the anchor 61 is provided on the fixed through hole. The end of the fixed steel bar 6.
上述的一种接头采用灌浆套筒的承插式构造预制拼装桥墩施工过程为:The above-mentioned joint adopts a socket-type structure of a grouting sleeve. The construction process of prefabricated assembled bridge piers is:
步骤1:在预制承台1和凸起部的上表面涂抹超超高性能砂浆;Step 1: Apply ultra-high performance mortar on the upper surface of the precast platform 1 and the raised part;
步骤2:将预制桥墩2的凸榫4嵌入预制承台1安装有钢管31的榫槽3内,预制承台1上的承台钢筋11伸入预制桥墩2的桥墩灌浆套筒21内;Step 2: Insert the tenon 4 of the prefabricated pier 2 into the tenon groove 3 of the prefabricated cap 1 with the steel pipe 31 installed, and the cap steel bar 11 on the prefabricated cap 1 extends into the pier grouting sleeve 21 of the prefabricated pier 2;
步骤3:将固定板5设置连接处的相对两侧的侧壁上,贯穿一侧固定板5将固定钢筋6插入固定通孔内,并从通孔的另一侧穿出,固定钢筋6贯穿另一侧的固定板5,再通过锚具61锁扣住固定钢筋6的两端;Step 3: Place the fixing plate 5 on the opposite side walls of the connection, penetrate the fixing plate 5 on one side, insert the fixing steel bar 6 into the fixing through hole, and pass it out from the other side of the through hole, and the fixing steel bar 6 penetrates The fixed plate 5 on the other side is then locked with the two ends of the fixed steel bar 6 through the anchors 61;
步骤4:往注料孔23内注入超高性能砂浆,直至超高性能砂浆溢满从出料孔24流出;Step 4: Inject ultra-high performance mortar into the injection hole 23 until the ultra-high performance mortar overflows and flows out of the discharge hole 24;
步骤5:在下节段预制桥墩2的顶面涂抹超超高性能砂浆,将上节预制桥墩2的凸榫4嵌入下节预制桥墩2顶面安装有钢管31的榫槽3内,下节预制桥墩2上方的桥墩钢筋22伸入上节预制桥墩2的桥墩灌浆套筒21内;将固定板5设置连接处的相对两侧的侧壁上,贯穿一侧固定板5将固定钢筋6插入固定通孔内,并从通孔的另一侧穿出,固定钢筋6贯穿另一侧的固定板5,再通过锚具61锁扣住固定钢筋6的两端;往注料孔23内注入超高性能砂浆,直至超高性能砂浆溢满从出料孔24流出;Step 5: Apply ultra-high performance mortar on the top surface of the lower prefabricated pier 2, and insert the tenon 4 of the upper prefabricated pier 2 into the tenon 3 of the steel pipe 31 installed on the top surface of the lower prefabricated pier 2. The lower prefabricated The pier steel bars 22 above the pier 2 extend into the pier grouting sleeve 21 of the upper section of the prefabricated pier 2; set the fixing plate 5 on the side walls of the opposite sides of the connection, and insert the fixing steel bar 6 through the fixing plate 5 on one side to fix it. into the through hole, and pass out from the other side of the through hole, the fixed steel bar 6 penetrates the fixed plate 5 on the other side, and then locks the two ends of the fixed steel bar 6 through the anchors 61; inject super into the injection hole 23 High-performance mortar until the ultra-high-performance mortar overflows and flows out from the discharge hole 24;
步骤6:重复步骤5,直至上述的一种接头采用灌浆套筒的承插式构造预制拼装桥墩达到标高。Step 6: Repeat step 5 until the above-mentioned prefabricated assembled pier using a socket-type joint with a grouting sleeve reaches the elevation.
综上所述,本发明提供的一种接头采用灌浆套筒的承插式构造预制拼装桥墩,通过凸榫和榫槽的设计,在拼接预制承台和预制桥墩的时候,防止出现倾覆等危险事故,增加了施工过程中结构的稳定性;桥墩灌浆套筒、桥墩钢筋和承台钢筋的设置,能够在灌浆完成之后,保证整体结构的稳定性,增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力;通过凸起部的设置,能够利用凸起部增设固定板和固定钢筋,从而利用凸起杆和固定钢筋在尚未进行灌浆的时候对预制桥墩进行初步的固定,增加了施工的安全;固定钢筋将榫头和榫槽进行栓接,进一步增加了结构的稳定性钢管的设置进一步增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力,增加了安全性;所述凸榫4上套设有钢制套筒,进一步增加了本发明所述的接头采用灌浆套筒的承插式构造预制拼装桥墩的水平抗剪能力,增加了安全性;注料孔和出料孔的设置,能够更加方便注入固定材料,方便了施工操作,增加了施工效率;通过将所述出料孔和所述注料孔设置于同一水平面,并且所述注料孔与所述桥墩灌浆套筒处于同一水平面,能够使注入的固定材料充分填满连接处的所有缝隙,保证了整体结构的稳定性;砂浆能够将设置于钢管管道内的凸榫、伸出预制承台顶面的承台钢筋和桥墩灌浆套筒内的桥墩钢筋连接成一个整体,保证了整体结构的稳定性,同时增加了连接处水平面的抗剪能力;超高性能砂浆具有强度高、耐腐蚀、抗渗性好的特性,通过超高性能砂浆,能够使结构整体具有较强的抗拉能力和可靠性,增加耐久性;采用承插式构造和现浇UHPC相结合的预制拼装桥墩,其中心位置采用承插式构造,在施工时能起到对上节预制桥墩的支承作用,且凸榫与榫槽之间采用UHPM粘结,其粘结面积大,粘结效果比传统的高强砂浆平面接缝或结构胶干接缝好,能提高拼接处的抗剪强度;采用强度高、耐腐蚀、耐磨、抗渗性好的UHPC作为现浇材料,能提高本发明所述的一种接头采用现浇UHPC材料的承插式构造预制拼装桥墩整体性和抗震性能。In summary, the present invention provides a joint that adopts a socket-type structure of grouting sleeves to prefabricate assembled bridge piers. Through the design of tenons and tenon grooves, risks such as overturning can be prevented when the prefabricated cap platform and prefabricated bridge piers are spliced. accidents, which increases the stability of the structure during the construction process; the settings of the pier grouting sleeves, bridge pier steel bars and capping steel bars can ensure the stability of the overall structure after the grouting is completed, and increases the use of grouting sleeves for the joints of the present invention The horizontal shear resistance of the prefabricated assembled bridge piers with the socket-type structure of the cylinder; through the setting of the protruding part, the protruding part can be used to add fixed plates and fixed steel bars, so that the protruding rods and fixed steel bars can be used to strengthen the prefabricated bridge piers before grouting. The bridge piers are initially fixed, which increases the safety of construction; the fixed steel bars bolt the tenon and the tenon groove, further increasing the stability of the structure. The arrangement of the steel pipe further increases the socket type of the joint according to the invention using a grouting sleeve. The horizontal shear resistance of the prefabricated assembled bridge pier is increased, and the safety is increased; the tenon 4 is covered with a steel sleeve, which further increases the prefabricated assembled bridge pier with a socket-type structure in which the joints of the present invention adopt grouting sleeves. The horizontal shear resistance increases safety; the setting of the injection hole and the discharge hole makes it easier to inject fixed materials, facilitates construction operations, and increases construction efficiency; by connecting the discharge hole and the injection hole The holes are arranged on the same horizontal plane, and the injection hole and the pier grouting sleeve are on the same horizontal plane, so that the injected fixing material can fully fill all the gaps in the connection, ensuring the stability of the overall structure; the mortar can set the The tenons in the steel pipe, the cap steel bars extending out of the top surface of the prefabricated cap platform, and the pier steel bars in the pier grouting sleeves are connected into a whole, ensuring the stability of the overall structure and increasing the shear resistance of the horizontal plane at the connection. Capability; ultra-high performance mortar has the characteristics of high strength, corrosion resistance, and good impermeability. Through ultra-high performance mortar, the entire structure can have strong tensile strength and reliability, increasing durability; adopts a socket structure The prefabricated assembled bridge piers combined with cast-in-place UHPC have a socket-type structure in the center, which can support the upper prefabricated bridge piers during construction, and UHPM is used to bond the tenon and tenon groove. The joint area is large and the bonding effect is better than the traditional high-strength mortar plane joints or structural glue dry joints, which can improve the shear strength of the splicing joints; UHPC is used as the existing material with high strength, corrosion resistance, wear resistance and impermeability. Casting materials can improve the integrity and seismic performance of prefabricated assembled bridge piers with a socket-type structure using cast-in-place UHPC materials for joints described in the present invention.
以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等同变换,或直接或间接运用在相关的技术领域,均同理包括在本发明的专利保护范围内。The above are only embodiments of the present invention, and do not limit the patent scope of the present invention. Any equivalent transformations made using the contents of the description and drawings of the present invention, or directly or indirectly applied in related technical fields, are equally included in within the scope of patent protection of this invention.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810933991.7A CN108978449B (en) | 2018-08-16 | 2018-08-16 | A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810933991.7A CN108978449B (en) | 2018-08-16 | 2018-08-16 | A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108978449A CN108978449A (en) | 2018-12-11 |
CN108978449B true CN108978449B (en) | 2023-11-21 |
Family
ID=64553178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810933991.7A Active CN108978449B (en) | 2018-08-16 | 2018-08-16 | A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108978449B (en) |
Families Citing this family (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109837831A (en) * | 2019-03-29 | 2019-06-04 | 上海应用技术大学 | A kind of centrifugation prefabricated assembled concrete bridge pier and construction method |
CN110004966B (en) * | 2019-05-08 | 2024-01-19 | 安徽省交通规划设计研究总院股份有限公司 | Support and pile underwater landing locking connection structure and construction method thereof |
CN110331716B (en) * | 2019-06-25 | 2021-06-04 | 浙江理工大学 | Splicing structure of vertical splicing prefabricated piles and construction method of vertically splicing prefabricated piles |
CN110468691B (en) * | 2019-07-23 | 2021-02-26 | 北京工业大学 | A post-disaster replaceable prefabricated concrete anti-sway bridge pier system |
CN110685216A (en) * | 2019-09-23 | 2020-01-14 | 福建工程学院 | A RUHPC-NC composite bridge pier and its construction method |
CN110952440B (en) * | 2019-11-19 | 2021-06-15 | 东北大学 | Prefabricated section steel concrete and reinforced concrete spliced pier and construction process |
CN110924291A (en) * | 2019-11-19 | 2020-03-27 | 东北大学 | Prefabricated stiff concrete-filled steel tube and reinforced concrete piers and construction technology |
CN110863424B (en) * | 2019-12-04 | 2021-12-10 | 长安大学 | Vertical tenon and horizontal anchor splicing structure of pier and capping beam and construction method |
CN111254809A (en) * | 2019-12-12 | 2020-06-09 | 中铁二院工程集团有限责任公司 | Prefabricated pier stud and prefabricated bent cap quick connect structure |
CN113202017A (en) * | 2020-03-17 | 2021-08-03 | 中国铁路设计集团有限公司 | Connecting structure between prefabricated assembled pier stud and top cap and construction method |
CN111335154A (en) * | 2020-04-15 | 2020-06-26 | 中铁四局集团第二工程有限公司 | Bridge pier column with prefabricated and assembled segments and construction method thereof |
CN111851303A (en) * | 2020-07-24 | 2020-10-30 | 南京林业大学 | A connection method of a cap using a convex groove and a prefabricated pier |
CN111851304A (en) * | 2020-07-24 | 2020-10-30 | 南京林业大学 | A kind of L-shaped slot connection method of prefabricated bridge pier and bearing platform |
CN111910618A (en) * | 2020-08-06 | 2020-11-10 | 浙江舜东建材有限公司 | Solid precast pile with foundation pile joint inserted into section steel |
CN114086460A (en) * | 2020-08-24 | 2022-02-25 | 南京林业大学 | A new connection method of bearing platform and prefabricated piers |
CN112942078A (en) * | 2021-02-03 | 2021-06-11 | 中国地震局工程力学研究所 | L-shaped joint assembly type splicing pier |
CN113389135B (en) * | 2021-06-17 | 2022-10-28 | 北京工业大学 | Assembled multidirectional energy consumption pier with three-dimensional serrated racking and fiber concrete grouting |
CN113373800B (en) * | 2021-06-24 | 2023-03-24 | 上海应用技术大学 | Hollow prefabricated assembled pier adopting grouting sleeve and connecting method thereof |
CN113668369B (en) * | 2021-09-13 | 2022-05-24 | 江南大学 | A kind of prefabricated segment reinforced concrete bridge pier socket connection structure and manufacturing method |
CN114908791A (en) * | 2022-05-12 | 2022-08-16 | 山东建筑大学 | Assembled plate type foundation with splicing structure and construction process |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003193486A (en) * | 2001-10-19 | 2003-07-09 | Mitsubishi Heavy Ind Ltd | Method for connecting jacket structure and pile together, joint structure of the same, and automatic device for mounting joint plug |
CN105019606A (en) * | 2015-08-02 | 2015-11-04 | 长安大学 | Precast concrete unit steel bar grouting connecting piece and connecting method |
CN106368117A (en) * | 2016-09-29 | 2017-02-01 | 上海市政工程设计研究总院(集团)有限公司 | Assembling method for bridge stand column and bearing platform |
CN106592440A (en) * | 2016-12-30 | 2017-04-26 | 河南省交通规划设计研究院股份有限公司 | Construction method of prefabricated segment type pier |
CN206635791U (en) * | 2017-01-23 | 2017-11-14 | 沈阳建筑大学 | A kind of packaged type bridges pillarwork |
CN108049305A (en) * | 2018-01-31 | 2018-05-18 | 福建工程学院 | The splicing construction and joining method of a kind of precast pier and prefabricated cushion cap |
CN108396640A (en) * | 2018-04-23 | 2018-08-14 | 南昌大学 | A kind of assembly concrete pier column structure |
CN208965396U (en) * | 2018-08-16 | 2019-06-11 | 福建工程学院 | A socket-type structure prefabricated pier with grouting sleeves for joints |
-
2018
- 2018-08-16 CN CN201810933991.7A patent/CN108978449B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003193486A (en) * | 2001-10-19 | 2003-07-09 | Mitsubishi Heavy Ind Ltd | Method for connecting jacket structure and pile together, joint structure of the same, and automatic device for mounting joint plug |
CN105019606A (en) * | 2015-08-02 | 2015-11-04 | 长安大学 | Precast concrete unit steel bar grouting connecting piece and connecting method |
CN106368117A (en) * | 2016-09-29 | 2017-02-01 | 上海市政工程设计研究总院(集团)有限公司 | Assembling method for bridge stand column and bearing platform |
CN106592440A (en) * | 2016-12-30 | 2017-04-26 | 河南省交通规划设计研究院股份有限公司 | Construction method of prefabricated segment type pier |
CN206635791U (en) * | 2017-01-23 | 2017-11-14 | 沈阳建筑大学 | A kind of packaged type bridges pillarwork |
CN108049305A (en) * | 2018-01-31 | 2018-05-18 | 福建工程学院 | The splicing construction and joining method of a kind of precast pier and prefabricated cushion cap |
CN108396640A (en) * | 2018-04-23 | 2018-08-14 | 南昌大学 | A kind of assembly concrete pier column structure |
CN208965396U (en) * | 2018-08-16 | 2019-06-11 | 福建工程学院 | A socket-type structure prefabricated pier with grouting sleeves for joints |
Also Published As
Publication number | Publication date |
---|---|
CN108978449A (en) | 2018-12-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108978449B (en) | A prefabricated assembled bridge pier with a socket structure using grouting sleeves for the joints | |
CN105442727B (en) | Composite connection shear wall structure and its assembly method | |
WO2018219196A1 (en) | Precast column base joint and construction method therefor | |
US8448280B2 (en) | Method of providing a parapet wall on a bridge | |
CN103104039B (en) | Assembled framework beam-column joint adopting cover plate connection and construction method thereof | |
CN109457596B (en) | Prefabricated assembled pier connection structure and construction method | |
Dolati et al. | Review of available systems and materials for splicing prestressed-precast concrete piles | |
JP6691880B2 (en) | Precast wall balustrade mounting structure and mounting method | |
CN103711329B (en) | The Method of Reinforcement of the Structure by Attaching the Steel Reinforced Concrete Frame Method | |
CN208965396U (en) | A socket-type structure prefabricated pier with grouting sleeves for joints | |
CN208151844U (en) | The construction that a kind of precast pier and prefabricated cushion cap quickly splice | |
CN106013432A (en) | Joint connecting structure in high-ductility assembled integrated frame and construction method | |
CN110055979A (en) | For the precast prestressed concrete anchor pier of slope reinforcement and production and construction method | |
CN209941467U (en) | A prefabricated large-span ultra-high-performance concrete box girder composite joint | |
CN102352668A (en) | Prefabricated reinforced concrete assembled column and its manufacturing method | |
CN109024249B (en) | Socket type structure prefabricated assembly pier with joint made of cast-in-situ UHPC material | |
Mashal et al. | Quasi-static cyclic tests of emulative precast segmental bridge piers (E-PSBP) | |
CN208762895U (en) | Hinge seam bracing means | |
CN110685215A (en) | A kind of semi-assembled composite bridge pier and its construction method | |
CN105088933B (en) | Hollow slab bridge with inclined hinge joint and building method thereof | |
KR101139058B1 (en) | Precast Segment and Precast Concrete Structure | |
CN106948495A (en) | The prestressing force integral node and its construction method of steel core concrete column and beams of concrete | |
CN208907228U (en) | A prestressed modular retaining wall | |
CN101105077A (en) | Method for connecting reinforced concrete structures | |
CN111827091A (en) | Prefabricated and assembled hollow piers connected by prestress and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |