CN108952159A CN201811096563.XA CN201811096563A CN108952159A CN 108952159 A CN108952159 A CN 108952159A CN 201811096563 A CN201811096563 A CN 201811096563A CN 108952159 A CN108952159 A CN 108952159A
Authority
CN
China
Prior art keywords
mould
support device
hook
hanging
hang
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811096563.XA
Other languages
Chinese (zh)
Inventor
潘小洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811096563.XA priority Critical patent/CN108952159A/en
Publication of CN108952159A publication Critical patent/CN108952159A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/18Devices for suspending or anchoring form elements to girders placed in ceilings, e.g. hangers

Abstract

The invention discloses a kind of support devices and construction method for hanging mould, including for holding in the palm the right angle support for hanging mould, characterized by comprising: lower end is vertical with the right angle support to be connect, outward opening and downward major arc shape hook;One end is fixedly connected with the hook middle inside, and the other end hangs mould gag lever post to oblique interval direction right angle support vertical edge.The hook vertical edges can extend downwards, and can set several gag lever posts.The hook and right angle support is in one plane bent by steel bar or reinforcing bar.The device and construction method due to support device be hooked in steel reinforcement cage main reinforcement or high-low bay external corner side reinforcing bar on, and each hook is also fixedly connected by tied silk with the stirrup of steel reinforcement cage or lateral vertical reinforcement, reliable and stable.Tradition can be replaced to hang the support device and construction method of mould, reduce overall cost, accelerate speed of application, raising is construction quality, there is practicability.

Description

Hang the support device and construction method of mould
Technical field
The present invention relates to support devices and construction method that a kind of building element, especially drop plate hang mould.
Technical background
There are more drop plate situations in the floor of modern architecture, such as: balcony, toilet, kitchen drop plate, and doing workshop When, encountering diamond dust ground, tile sections need to do flat with diamond dust ground, it is also required to do pre- drop when doing structure and applying, and For requiring straightness higher at drop edges of boards, traditional handicraft is difficult to meet the requirements.The prior art is hung in drop plate and is asked present on mould Topic has: 1, dimensions disunity, and it is not straight to hang mould positioning for the random spot welding supporting point in scene;2, collet uses spot welding, and top is adopted Draw anchoring fixed with iron wire, iron wire is easy to loosen deformation, and it is poor to hang mould stationarity;3, live shear reinforcement, using electric welding machine optional point Weldering, then iron nail is bound with iron wire, it pulls through floor and fixes, it is artificial big to hang mould positioning cost;4, it needs to consume electric welding machine welding rod, iron Nail, very long large size iron wire, consumptive material are big;5, it hangs that mould is fixed to pull through beam slab face using iron wire due to existing, causes to leak;Especially The case where balcony, kitchen, toilet lead to structural leakage after reinforcing using tradition is high-incidence;6, step is more, such as: shear-steel muscle, welding, It positions, wear iron wire, fix and hang mould, the construction operation time is long;7, need get angry welding, and electric welding machine freezes there are spark, exists Security risk;8, welding gas is to human injury;9, welding is more casual, leads to side, lower gluten cover to reinforcement not One, due to hanging mould built on the sand, causes protective layer different, not can guarantee the thickness for hanging cover to reinforcement at mould.
Good, high-efficient, convenient for construction and safety the support device for hanging mould of mould stationarity is hung the object of the present invention is to provide a kind of.
In order to achieve the above object, the technical solution of the present invention is as follows:
A kind of support device for hanging mould, including for holding in the palm the right angle support for hanging mould, characterized by comprising:
Lower end is vertical with the right angle support to be connect, outward opening and downward major arc shape hook;
One end is fixedly connected with the outer middle side part of the hook, and the other end is limited to the mould that hangs that right angle support vertical edge is directed toward at oblique interval Bar.
The hook vertical edges can extend downwards, and can set one or several gag lever posts.
The hook and right angle support is in one plane bent by steel bar or reinforcing bar.
The connection of hook and gag lever post is welding.
Construction method the following steps are included:
(1) according to Design Requirement Drawing high-low bay plate face height difference numerical value, according to the manufacture of height difference numerical value, " all " words hang mould support dress It sets;
(2) beam reinforced steel bar of difference of height is bound and is completed;
(3) " all " words that will fall hang mould support device and are hung on beam main tendon or high-low bay external corner side reinforcing bar by major arc shape, make It will hang mould support device and beam stirrup or side by " all " words on beam stirrup or lateral vertical reinforcement, then with binding iron wire To vertical reinforcement binding securely, the spacing that " all " words hang mould support device is generally 10cm ~ 50cm, can be according to stirrup spacing Or lateral vertical reinforcement spacing appropriate adjustment, it is ensured that be capable of fixing and hang mould;
(4) it template will be hung sticks into down " all " words and hang in mould support device, and keep the right angle support hanging template with hanging in mould support device tight Closely connected conjunction;
(5) beam slab concrete is poured;
(6) remove side form, non-bearing side template should concrete strength can guarantee its surface and corner angle not reason demoulding and be damaged Bad when, can remove, and side template should can be generally removed when concrete crushing strength reaches 2.5MPa;
(7) " all " words that falls for cutting off protrusion hang mould support device straightway, and construction is completed.
The support device for hanging mould of the above structure appears like inverted " all " fonts, in practical applications multiple intervals Support device by hang in beam steel cage main reinforcement or high-low bay external corner side reinforcing bar on it is in a row, hold surely hang mould enough, It is all held in the palm in each right angle support and hangs mould;Due to support device be hooked in steel reinforcement cage main reinforcement by major arc shape or high-low bay sun On arm of angle reinforcing bar, and each hook is also fixedly connected by tied silk with the stirrup of steel reinforcement cage or lateral vertical reinforcement, is stablized Reliably.Advantage is: 1, processing cost is low;2, speed of application is fast;3, firm to mould reinforcing is hung;4, avoiding iron wire from pulling through beam slab causes Leakage;5, ensured that the drop plate yin-yang angle for pouring out is straight;6, it avoids and burns the gas that electric welding generation is harmful to the human body;7, it keeps away Building site is exempted from and has got angry that there may be the security risks of fire;8, whole impression quality is improved;9, cover to reinforcement is ensured Thickness.Tradition can be replaced to hang the support device and construction method of mould, reduce overall cost, accelerate speed of application, improved Construction quality.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention;
Fig. 2 is the structural schematic diagram that the present invention lengthens;
Fig. 3 is the present invention and hangs the structural schematic diagram that mould, template and beam steel cage are used cooperatively;
1 is linked up in the figure, and board bottom template 4 drops in gag lever post 2, right angle support 3, drops board bottom laminate muscle 5, drops board finish plate muscle 6, hangs mould 7, tied silk 8, board finish reinforcing bar 9, plate bottom layer of the reinforcing steel 10, normal panel bottom template 11, beam steel cage 12, concrete/concrete 13.
Specific embodiment
With reference to the accompanying drawing, the invention will be further described.
It is structural schematic diagram of the invention shown in Fig. 1, it can be seen that the present invention hangs the support device of mould, including is used for Support hangs the right angle support 3 of mould, and further including that lower end is vertical with the right angle support 3 connect, outward opening and downward major arc shape hook 1, And one end is fixedly connected with 1 outer middle side part of the hook, the other end is limited to the mould that hangs that 3 vertical edge of right angle support is directed toward at oblique interval Bar 2, the tilt angle of gag lever post 2 are 30 ~ 75 degree.Shown in Fig. 2, it is the structural schematic diagram that the present invention lengthens, can be seen by figure, when 1 vertical edges of hook described in hanging when mould 7 increases extend downwards, to adapt to increased degree, and set additonal limit bar on extending side Height is higher to hang mould for limiting jointly by 2a, gag lever post 2 and additional 2a, makes to hang mould stable and firm.Certainly, if hanging the height of mould Very high, 1 vertical edges of hook extend downwards more, and more additonal limit bar 2a, 2b and 2c of 2 space set of gag lever post etc. are used Mould 7 is hung with firm.The structure for hanging mould 7 is shown in Fig. 3.Gag lever post 2 is other than it can play the role of consolidating and hang mould, in the vertical direction The metric space of formation can reserve space for pouring for concrete cover.Wherein, the hook 1 and right angle support 3 are by steel Item or reinforcing bar are in one plane bent;The connection of hook 1 and gag lever post 2 is welding.2 other end of gag lever post tilts down Be conducive to that mould will be hung to stick into and hang in mould support device, while can also prevent from hanging mould when concreting and up float.
Shown in Fig. 3, be the present invention with hang the structural schematic diagram that mould, template and beam steel cage are used cooperatively, include in the figure Major arc shape hook 1, this support device for hanging mould gag lever post 2 and right angle support 3 are placed in beam steel by several major arc shapes hook 1 In 12 main reinforcement of cage, the internal diameter of major arc shape hook 1 is slightly larger than the diameter of main reinforcement, tightly to hook steel reinforcement cage main reinforcement;Gag lever post 2 with Mould 7 is hung for placing in space between 3 vertical edge of right angle support.Described hangs mould 7 as square logical, flitch or side template, hangs mould support dress The right angle support set can be closely closely fitted with the mould that hangs of histogram shape, make to hang mould keep it is straight with it is reliable.If hanging mould 7 is higher by hook 1 it is many when, then use extended version as shown in Figure 2.In order to which further firmly stable supporting device makes it not generate displacement, also exist The lower end of hook 1 is fixedly connected with tied silk 8 with 12 stirrup of beam steel cage.Normal panel face is by including board finish reinforcing bar 9, board bottom layer steel Muscle 10, normal panel bottom template 11 and beam steel cage 12, and casting concrete is made;Plate is dropped by including drop board bottom template 4, drop plate Bottom plate muscle 5 and drop board finish plate muscle 6, and casting concrete 13 is made.
The construction technology of the prior art are as follows: the mould that hangs that " ten " word or " T " word shape are arbitrarily welded into reinforcing bar positions steel Muscle, then spacer bar is probably put and is welded on beam steel, mould is hung in placement, is pulled through beam slab positioning using iron wire and is hung mould, reaches fixed The purpose of mould is hung, this fixation be easy to cause beam slab face to leak.Since spacer bar is arbitrarily welding, it not can guarantee and be located in On same plane, it is also unable to control concrete thickness, construction operation is slow, and step is more, and cost is artificial more, and quality not can guarantee. Electric welding is needed, there are security risk, welding scene needs special messenger to nurse and be equipped with fire extinguisher.
Hang the fabrication and installation technique of mould support device are as follows: according to drop plate height, production hang mould 7, using duroplasts, reinforcing bar, Alloy material or cast iron materials etc. fabricate in producer and hang mould support device at " all " fonts, and steel bar can be used or reinforcing bar is curved Folding and welding processing form, usually with steel bar or reinforcing bar be in one plane bent into hook 1, vertical edges [A2] and directly Angle support 3, and weld upper limit bar 2 and 2a etc., " all " fonts are made down and hang the support device of mould, then are transported to construction site use i.e. It can;Then hook 1, right angle support 3 and gag lever post 2 can also be transported to construction site in processing factory using integrated molding is poured.It is constructing Scene is easy to use without welding, and is directly hung in 12 main reinforcement of steel reinforcement cage by hook 1, is fixed in stirrup using tied silk 8 On, then mould will be hung and sticked into hook.Easy to operate, speed of application is fast, saves artificial, the reduction duration.
Construction method the following steps are included:
(1) according to Design Requirement Drawing high-low bay plate face height difference numerical value, according to the manufacture of height difference numerical value, " all " words hang mould support dress It sets, conventional difference of height is 5cm, 20cm and 50cm etc.;
(2) beam reinforced steel bar of difference of height 5,6,9,10 and 12 is bound and is completed;
(3) " all " words that will fall hang mould support device and hang on beam main tendon or high-low bay external corner side reinforcing bar, make it close to beam stirrup or On lateral vertical reinforcement, then with binding iron wire 8 will fall " all " words hang mould support device and beam stirrup or lateral vertical reinforcement Securely, the spacing that " all " words hang mould support device is generally 10cm ~ 50cm for binding, can be according to stirrup spacing or laterally vertical Bar spacing appropriate adjustment, it is ensured that be capable of fixing and hang mould;It is consistent each to hang mould support device manufactured size, it is ensured that hang Template Location In the same plane, to ensure that the drop plate yin-yang angle after pouring is straight;
(4) it mould 7 will be hung sticks into down " all " words and hang in mould support device, and keep the right angle support hanging template with hanging in mould support device close Fitting, to ensure to hang template straight fixation in same level;
(5) drop plate concrete 13 is poured;The vertical space of about 2 gag lever post forms mixed earth protective layer, gag lever post 2 after the completion of pouring Horizontal vertical distance be protective layer thickness, ensure that effective uniform thickness of protective layer;
(6) remove side form, non-bearing side template should concrete strength can guarantee its surface and corner angle not reason demoulding and be damaged Bad when, can remove, and side template should can be generally removed when concrete crushing strength reaches 2.5MPa;
(7) " all " words that falls for cutting off protrusion hang mould support device straightway 3, form a complete plane, and construction is completed.

Claims (6)

1. a kind of support device for hanging mould, including for holding in the palm the right angle support for hanging mould, characterized by comprising:
Lower end is vertical with the right angle support to be connect, outward opening and downward major arc shape hook;
One end is fixedly connected with the outer middle side part of the hook, and the other end is limited to the mould that hangs that right angle support vertical edge is directed toward at oblique interval Bar.
2. hanging the support device of mould according to requiring 1, it is characterised in that:
The hook vertical edges can extend downwards, and can set one or several gag lever posts.
3. hanging the support device of mould according to requiring 1, it is characterised in that:
The hook and right angle support is in one plane bent by steel bar or reinforcing bar.
4. hanging the support device of mould according to requiring 1, it is characterised in that:
The connection of the hook and gag lever post is welding, and the tilt angle of gag lever post is 30 ~ 75 degree.
5. hanging the support device of mould according to requiring 1, it is characterised in that:
Right angle support, major arc shape hook and the gag lever post is made of duroplasts, reinforcing bar, cast iron, cast aluminium or alloy material.
6. hanging the support device of mould according to requiring 1, it is characterised in that construction method the following steps are included:
(1) according to Design Requirement Drawing high-low bay plate face height difference numerical value, according to the manufacture of height difference numerical value, " all " words hang mould support dress It sets;
(2) beam reinforced steel bar of difference of height is bound and is completed;
(3) " all " words that will fall hang mould support device and are hung on beam main tendon or high-low bay external corner side reinforcing bar by major arc shape, make It will hang mould support device and beam stirrup or side by " all " words on beam stirrup or lateral vertical reinforcement, then with binding iron wire To vertical reinforcement binding securely, the spacing that " all " words hang mould support device is generally 10cm ~ 50cm, can be according to stirrup spacing Or lateral vertical reinforcement spacing appropriate adjustment, it is ensured that be capable of fixing and hang mould;
(4) it template will be hung sticks into down " all " words and hang in mould support device, and keep the right angle support hanging template with hanging in mould support device tight Closely connected conjunction;
(5) beam slab concrete is poured;
(6) remove side form, non-bearing side template should concrete strength can guarantee its surface and corner angle not reason demoulding and be damaged Bad when, can remove, and side template should can be generally removed when concrete crushing strength reaches 2.5MPa;
(7) " all " words that falls for cutting off protrusion hang mould support device straightway, form a complete plane, and construction is completed.
CN201811096563.XA 2018-09-19 2018-09-19 Hang the support device and construction method of mould Pending CN108952159A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811096563.XA CN108952159A (en) 2018-09-19 2018-09-19 Hang the support device and construction method of mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811096563.XA CN108952159A (en) 2018-09-19 2018-09-19 Hang the support device and construction method of mould

Publications (1)

Publication Number Publication Date
CN108952159A true CN108952159A (en) 2018-12-07

Family

ID=64471470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811096563.XA Pending CN108952159A (en) 2018-09-19 2018-09-19 Hang the support device and construction method of mould

Country Status (1)

Country Link
CN (1) CN108952159A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202000639U (en) * 2011-03-16 2011-10-05 中国建筑第二工程局有限公司 Section steel suspended formwork
CN203626234U (en) * 2013-12-20 2014-06-04 中建四局第六建筑工程有限公司 Partially-recyclable floor slab dropping suspended-formwork device
CN204920204U (en) * 2015-07-15 2015-12-30 中国建筑第七工程局有限公司 Fall board and hang mould support frame
CN205153532U (en) * 2015-11-20 2016-04-13 中建海峡建设发展有限公司 Waterproof floor of formula of sinking hangs support frame for mould
CN206053326U (en) * 2016-08-30 2017-03-29 中建八局第四建设有限公司 One kind hangs mould support meanss
CN107083840A (en) * 2017-04-21 2017-08-22 北京首钢建设集团有限公司 A kind of anti-bank one-shot forming formwork erection method in toilet
CN208844924U (en) * 2018-09-19 2019-05-10 潘小洪 Hang the support device of mould

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202000639U (en) * 2011-03-16 2011-10-05 中国建筑第二工程局有限公司 Section steel suspended formwork
CN203626234U (en) * 2013-12-20 2014-06-04 中建四局第六建筑工程有限公司 Partially-recyclable floor slab dropping suspended-formwork device
CN204920204U (en) * 2015-07-15 2015-12-30 中国建筑第七工程局有限公司 Fall board and hang mould support frame
CN205153532U (en) * 2015-11-20 2016-04-13 中建海峡建设发展有限公司 Waterproof floor of formula of sinking hangs support frame for mould
CN206053326U (en) * 2016-08-30 2017-03-29 中建八局第四建设有限公司 One kind hangs mould support meanss
CN107083840A (en) * 2017-04-21 2017-08-22 北京首钢建设集团有限公司 A kind of anti-bank one-shot forming formwork erection method in toilet
CN208844924U (en) * 2018-09-19 2019-05-10 潘小洪 Hang the support device of mould

Similar Documents

Publication Publication Date Title
CN107614813B (en) The building block of cast-in-place wall core and mold, manufacturing method and building method connect muscle pipe, bent baseline box
CN108457421A (en) A kind of assembled steel reinforced Concrete U Vierendeel girder and its construction method
CN106223516B (en) ALC steam-pressing aero-concrete batten tilts curtain wall structure and construction method
CN103046645B (en) A kind of whole casting structure and construction method of Large-span Precast
CN107816173B (en) Pseudo-classic architecture wood eave-rafter and cast-in-situ steel reinforced concrete Guttr board monolithic construction method
CN106150087B (en) A kind of combined frame column template and its construction method
CN208844924U (en) Hang the support device of mould
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN103615075B (en) The continuous casting forming method of concrete sloping roof
CN104213728B (en) Oblique beam for grandstand of stadium and construction process for oblique beam
CN108952159A (en) Hang the support device and construction method of mould
CN101748893A (en) Method for manufacturing high-rise building balcony boards
CN209703510U (en) A kind of template system suitable for the ring-like foundation pile of major diameter manually digging hole
CN104164882A (en) Construction method for building support structural beam foundation on slope and structure thereof
CN206570700U (en) The continuous lowering system of steel jacket box
CN215484618U (en) A pour template structure for assembled shear force wall and post
CN211447707U (en) Cantilever type steel coupling beam construction supporting platform
CN109610795B (en) Construction method of inverted cone-shaped building
CN107642241A (en) The stress supporting construction and construction method of a kind of prefabricated balcony
CN208534015U (en) A kind of underwater armored concrete prefab-form
CN208455941U (en) A kind of building precast beam
CN207846677U (en) The ductility connecting structure of first floor vertical member and basement roof
CN109235709B (en) Full cast-in-place outer wall structure of building
CN107288028B (en) Large volume concrete structural and its construction method
CN215484103U (en) Building engineering floor thickness controller

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination