CN108952154A - A kind of simple plugging device of vertical duct preformed hole and its construction method - Google Patents
A kind of simple plugging device of vertical duct preformed hole and its construction method Download PDFInfo
- Publication number
- CN108952154A CN108952154A CN201810882787.7A CN201810882787A CN108952154A CN 108952154 A CN108952154 A CN 108952154A CN 201810882787 A CN201810882787 A CN 201810882787A CN 108952154 A CN108952154 A CN 108952154A
- Authority
- CN
- China
- Prior art keywords
- finished product
- steel bushing
- fitting
- vertical
- plastic module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 23
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 33
- 239000010959 steel Substances 0.000 claims abstract description 33
- 239000004033 plastic Substances 0.000 claims abstract description 25
- 241001074085 Scophthalmus aquosus Species 0.000 claims abstract description 24
- 238000004519 manufacturing process Methods 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims abstract description 7
- 238000005266 casting Methods 0.000 abstract description 4
- 239000000463 material Substances 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 238000013461 design Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000009435 building construction Methods 0.000 description 2
- 239000000945 filler Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000004064 recycling Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000004513 sizing Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G15/00—Forms or shutterings for making openings, cavities, slits, or channels
- E04G15/06—Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
- E04G15/063—Re-usable forms
- E04G15/068—Re-usable forms for channels open towards the surface
Abstract
A kind of vertical preformed hole plugging device, including steel bushing finished product built-in fitting, fixed brill and the plastic module made according to vertical duct caliber.Its construction method is: 1. root determines the production of reserved opening size field or customization steel bushing finished product built-in fitting, fixed brill and plastic module, the construction line-putting determines vertical duct reserved opening position, it is put in template using steel bushing finished product built-in fitting, is pierced in template using fixed brill and fix steel bushing finished product built-in fitting;Fixed brill is first removed when dismounting requires 2. reaching, then removes steel bushing finished product built-in fitting;3. vertical duct installs and after passed examination, plastic module is symmetrically wedged into reserved opening, rotation is fixed on vertical duct;4. checking whether plastic module and reserved opening are tight, check errorless rear into next procedure.The present invention is safe and reliable, may make between template and concrete, pipeline have enough frictional force to be poured, so that casting concrete is combined closely.
Description
Technical field
The invention belongs to technical field of building construction, it is related to a kind of vertical preformed hole plugging device and its construction method.
Background technique
At present in the realm of building construction, plugging construction method master of the industrial and civil buildings for vertical duct hole to be provided
Use: 1, production sizing plank sheathing is spliced and is stuck on pipeline, then is worn plank sheathing with iron wire and be hung on pipeline, with wood
Template is poured concrete enclosing reserved holes of pipes as support system;2, producer's customization typified form carries out at vertical duct road junction
Consolidation process.
Be using the shortcoming of the first construction method: scene processing, production need to occupy a certain proportion of artificial, material
Material, machinery etc. are time-consuming and laborious, since plank sheathing is not fixed easily and the problems such as material self performance, construction site is in casting concrete
After blocking pipe hole to be provided, it will appear surface irregularity mostly, splice imprecision at form joint, cause to run mode ship slurry now
As influencing Surface Quality of Concrete, when surface smoothness does not meet design and code requirement, also needing artificial secondary repairing of doing over again.
When using second of construction method, typified form using lease or is purchased in most cases, and it is lower that material is used in turn rate, cost
Increase.Such as making can be because stencil design complexity, field fabrication be difficult to realize problem etc..
Summary of the invention
It is an object of the invention to overcome above-mentioned the deficiencies in the prior art, and provide a kind of vertical preformed hole closure
Device, the apparatus structure is simple and practical, simple to install, be easy to make, has enough to meet the need convenient, pours suitable for vertical duct hole to be provided is secondary
Infuse concrete.
It is a further object of the present invention to provide the construction method of above-mentioned vertical preformed hole plugging device, construction method safety
Reliably, construction cost is low, and may make between template and concrete, pipeline has enough frictional force to be poured, so that
Casting concrete is combined closely.
As above design, the technical scheme is that a kind of vertical preformed hole plugging device, it is characterised in that: including steel
Sleeve finished product built-in fitting, fixed brill and the plastic module made according to vertical duct caliber;The fixed brill pass through steel bushing at
Product built-in fitting is simultaneously fixed in template, and the steel bushing finished product built-in fitting bottom both ends are each configured with plastic module.
The steel bushing finished product built-in fitting is using portable.
The section of the steel bushing finished product built-in fitting is wide at the top and narrow at the bottom trapezoidal.
The fixed brill be it is "T"-shaped, bottom end is vertically successively formed with multiple cone-shaped nails.
Rubber stopper is housed on the inside of the plastic module.
A kind of construction method following steps of vertical preformed hole plugging device carry out:
1. determining the production of reserved opening size field or customization steel bushing according to the vertical pipe diameter determing of drawing and code requirement
Finished product built-in fitting, fixed brill and plastic module, the construction line-putting determines vertical duct reserved opening position, pre- using steel bushing finished product
Embedded part is put in template, is pierced in template using fixed brill and is fixed steel bushing finished product built-in fitting;
Fixed brill is first removed when dismounting requires 2. reaching, then removes steel bushing finished product built-in fitting;
3. vertical duct installs and after passed examination, plastic module is symmetrically wedged into reserved opening, rotation is fixed on
On vertical duct;
4. checking whether plastic module and reserved opening are tight, check errorless rear into next procedure.
The beneficial effects of the present invention are:
1, apparatus of the present invention are simple and practical in structure, simple to install, are easy to make, have enough to meet the need conveniently, and it is pre- to be suitable for vertical duct
Box out second pouring concrete.
2, construction method of the present invention is safe and reliable, construction cost is low, and may make between template and concrete, pipeline has enough
Frictional force be poured so that casting concrete is combined closely.
3, operation of the present invention is simple, construction efficiency is high, can save artificial and material cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the simple plugging device of vertical duct preformed hole of the present invention;
Fig. 2 is the schematic diagram of steel bushing finished product built-in fitting;
Fig. 3 is the schematic diagram of fixed brill;
Fig. 4 is the 1-1 sectional view of Fig. 1;
Fig. 5 is construction schematic diagram of the invention;
Fig. 6 is the schematic diagram of plastic module;
Fig. 7 is the 2-2 sectional view of Fig. 5.
Specific embodiment
It is as shown in Figs 1-4: a kind of vertical preformed hole plugging device, including steel bushing finished product built-in fitting 1, fixed brill 2 and root
The plastic module 7 made according to vertical duct caliber;The fixed brill passes perpendicularly through steel bushing finished product built-in fitting and is fixed on template 3
On, the steel bushing finished product built-in fitting bottom both ends are each configured with plastic module 7.
For the steel bushing finished product built-in fitting using portable, section is wide at the top and narrow at the bottom trapezoidal.The fixed brill is " T "
Shape, bottom end are successively formed with multiple cone-shaped nails.Rubber stopper 8 is housed on the inside of the plastic module, the work of seam crossing sealing can be played
With.
As illustrated in figs. 5-7: a kind of above-mentioned construction method following steps progress of vertical preformed hole plugging device:
1, according to the vertical pipe diameter determing of drawing and code requirement, the production of reserved opening size field or customization steel bushing are determined
Finished product built-in fitting 1, fixed brill 2, plastic module 7, the construction line-putting determine 5 reserved opening position of vertical duct, using steel bushing at
Product built-in fitting 1 passes through structure sheaf 4 and is put in template 3, is pierced in template using fixed brill 2, fixes steel bushing finished product built-in fitting
1, into next procedure before check whether there is loosening, it is ensured that it is solid and reliable.
2, fixed brill 2 is first removed when reaching dismounting and requiring, then removes steel bushing finished product built-in fitting 1.Steel is cleared up after recycling
The sundries on 2 surface of sleeve finished product built-in fitting 1 and fixed brill is simultaneously used in turn.
3, vertical duct 5 installs and after passed examination, and using plastic module 7, symmetrically wedging reserved opening, rotation are solid
It is scheduled on vertical duct, and fills in rubber stopper 8 between vertical duct and plastic module;
4, it before next procedure construction, first carries out 45min and closes water experiment.Check whether plastic module 7 and reserved opening are tight,
It checks errorless rear into next procedure.
5, in 7 upslide of plastic module intumescent filler material 6 in a subtle way, ensure to block according to filler material product requirement closely knit.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (6)
1. a kind of vertical preformed hole plugging device, it is characterised in that: including steel bushing finished product built-in fitting, fixed brill and according to vertical
The plastic module of pipe diameter production;The fixed brill passes through steel bushing finished product built-in fitting and is fixed in template, the steel bushing
Cylinder finished product built-in fitting bottom both ends are each configured with plastic module.
2. a kind of vertical preformed hole plugging device according to claim 1, it is characterised in that: the steel bushing finished product is pre-buried
Part is using portable.
3. a kind of vertical preformed hole plugging device according to claim 1, it is characterised in that: the steel bushing finished product is pre-buried
The section of part is wide at the top and narrow at the bottom trapezoidal.
4. a kind of vertical preformed hole plugging device according to claim 1, it is characterised in that: the fixed brill be it is "T"-shaped,
Its bottom end is vertically successively formed with multiple cone-shaped nails.
5. a kind of vertical preformed hole plugging device according to claim 1, it is characterised in that: dress on the inside of the plastic module
There is rubber stopper.
6. a kind of construction method of vertical preformed hole plugging device a kind of according to claim 1, it is characterised in that: following step
It is rapid to carry out:
1. determining the production of reserved opening size field or customization steel bushing finished product according to the vertical pipe diameter determing of drawing and code requirement
Built-in fitting, fixed brill and plastic module, the construction line-putting determine vertical duct reserved opening position, use steel bushing finished product built-in fitting
It is put in template, is pierced in template using fixed brill and fix steel bushing finished product built-in fitting;
Fixed brill is first removed when dismounting requires 2. reaching, then removes steel bushing finished product built-in fitting;
3. vertical duct installs and after passed examination, plastic module is symmetrically wedged into reserved opening, rotation is fixed on vertical
On pipeline;
4. checking whether plastic module and reserved opening are tight, check errorless rear into next procedure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810882787.7A CN108952154A (en) | 2018-08-06 | 2018-08-06 | A kind of simple plugging device of vertical duct preformed hole and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810882787.7A CN108952154A (en) | 2018-08-06 | 2018-08-06 | A kind of simple plugging device of vertical duct preformed hole and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108952154A true CN108952154A (en) | 2018-12-07 |
Family
ID=64467523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810882787.7A Pending CN108952154A (en) | 2018-08-06 | 2018-08-06 | A kind of simple plugging device of vertical duct preformed hole and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108952154A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113969625A (en) * | 2020-07-24 | 2022-01-25 | 中航天建设工程集团有限公司 | I-shaped overhanging steel-based wall-penetrating reserved hole plugging method and die |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10121744A (en) * | 1996-10-17 | 1998-05-12 | Sakae Goshima | Hole filling up repairing method for piping hole |
CN202125074U (en) * | 2011-06-24 | 2012-01-25 | 江苏双楼建设集团有限公司 | Double cone floorslab reserved-hole die |
CN202187556U (en) * | 2011-07-26 | 2012-04-11 | 北京城建北方建设有限责任公司 | Tool-type hole reserving mould |
CN103015721A (en) * | 2012-12-20 | 2013-04-03 | 山东万鑫建设有限公司 | Leakage prevention construction method of reserved holes in kitchen and toilet |
CN204571288U (en) * | 2015-04-17 | 2015-08-19 | 李卫国 | Floor slab preformed hole mould |
CN205134728U (en) * | 2015-11-26 | 2016-04-06 | 文登蓝岛建筑工程有限公司 | Hole prevention of seepage mechanism is reserved to SIP side fascia |
CN107989205A (en) * | 2018-01-10 | 2018-05-04 | 山西三建集团有限公司 | The plugging system of toilet bath room floor sewer pipe preformed hole |
CN208918276U (en) * | 2018-08-06 | 2019-05-31 | 中冶天工集团有限公司 | A kind of simple plugging device of vertical duct preformed hole |
-
2018
- 2018-08-06 CN CN201810882787.7A patent/CN108952154A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10121744A (en) * | 1996-10-17 | 1998-05-12 | Sakae Goshima | Hole filling up repairing method for piping hole |
CN202125074U (en) * | 2011-06-24 | 2012-01-25 | 江苏双楼建设集团有限公司 | Double cone floorslab reserved-hole die |
CN202187556U (en) * | 2011-07-26 | 2012-04-11 | 北京城建北方建设有限责任公司 | Tool-type hole reserving mould |
CN103015721A (en) * | 2012-12-20 | 2013-04-03 | 山东万鑫建设有限公司 | Leakage prevention construction method of reserved holes in kitchen and toilet |
CN204571288U (en) * | 2015-04-17 | 2015-08-19 | 李卫国 | Floor slab preformed hole mould |
CN205134728U (en) * | 2015-11-26 | 2016-04-06 | 文登蓝岛建筑工程有限公司 | Hole prevention of seepage mechanism is reserved to SIP side fascia |
CN107989205A (en) * | 2018-01-10 | 2018-05-04 | 山西三建集团有限公司 | The plugging system of toilet bath room floor sewer pipe preformed hole |
CN208918276U (en) * | 2018-08-06 | 2019-05-31 | 中冶天工集团有限公司 | A kind of simple plugging device of vertical duct preformed hole |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113969625A (en) * | 2020-07-24 | 2022-01-25 | 中航天建设工程集团有限公司 | I-shaped overhanging steel-based wall-penetrating reserved hole plugging method and die |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203755673U (en) | Cast-in-situ formwork system for floor slab reserved holes | |
CN208056637U (en) | A kind of concrete shear force wall sealing hole device | |
CN106088148B (en) | Pipe gallery template and its application | |
CN103938864A (en) | Infilled wall constructional column construction method | |
CN103061504A (en) | Concrete board pipeline installation reserved hole construction mould and construction method | |
CN103485537A (en) | Construction method and structure of embedded reinforcement of super high-rise horizontal secondary structure | |
CN106223496A (en) | A kind of post-cast strip antiseepage grouting device | |
CN106400982A (en) | Stirrup-densified splicing joint for fabricated reinforced concrete columns | |
CN106437197A (en) | Static crushing structure for removing concrete and construction method thereof | |
CN206337819U (en) | A kind of bracing means of concrete structure templates for expansion joints | |
CN208918276U (en) | A kind of simple plugging device of vertical duct preformed hole | |
CN108952154A (en) | A kind of simple plugging device of vertical duct preformed hole and its construction method | |
CN208105876U (en) | A kind of mold for top plate hole to be provided | |
CN206071050U (en) | Mould is hung in a kind of pipeline pipe root closure | |
CN206220465U (en) | One kind is to drawing wall-connecting piece | |
CN206752693U (en) | A kind of assembled steel reinforced concrete column of stirrup encryption and post splicing node | |
CN208777690U (en) | A kind of reserved floor sealing hole template component of drainage pipeline | |
CN208502801U (en) | A kind of tunnel fast lifting baffle | |
CN104453235B (en) | Current conversion station fire wall construction technology | |
CN207348463U (en) | A kind of pulling-on piece component for aluminum alloy mould plate | |
CN206052996U (en) | A kind of post-cast strip antiseepage grouting device | |
CN205875714U (en) | A consolidate fixture for retainer plate beam mold board | |
CN108086542A (en) | A kind of concrete structure pipe construction through walls reserves structure and construction method | |
CN205558271U (en) | Building engineering box out ware | |
CN104941968B (en) | Device used for crushing plug in sounding pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |