CN108951608A - Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method - Google Patents
Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method Download PDFInfo
- Publication number
- CN108951608A CN108951608A CN201810814323.2A CN201810814323A CN108951608A CN 108951608 A CN108951608 A CN 108951608A CN 201810814323 A CN201810814323 A CN 201810814323A CN 108951608 A CN108951608 A CN 108951608A
- Authority
- CN
- China
- Prior art keywords
- underwater
- template
- area
- grouting
- repaired
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/06—Constructions, or methods of constructing, in water
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention discloses reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method, including the following steps: marine organisms are cleared up in area to be repaired submarine inspection, area to be repaired, loose concrete chisel removal, underwater reinforcing bar repair welding reinforcing, underwater drilling are laid form tie, underwater formwork erection and sealing, underwater grouting and demoulding and checked and accepted in area to be repaired.Advantages of the present invention: having many advantages, such as that repairing and reinforcement is high-efficient, easy to operate, safe and reliable, and repairing and reinforcement effect is easy to that detection, repair materials intensity height, repair materials low cost, that damaged face cleaning efficiency is high, template support is solid and reliable, pressure grouting is guaranteed the quality is efficient.
Description
Technical field
The present invention relates to underwater concrete structural strengthening and recovery technique field, in particular to reinforce Diaphragm Wall Wharf
Underwater concrete structure construction engineering method.
Background technique
In recent years, diaphram wall sheet pile harbour due to its exclusive land construction, construction equipment is simple, speed of application
Fastly, the relatively low a variety of advantages of small, cost being influenced by weather and being able to more application and development, the country mainly uses reinforcing bar
Concrete ground connects wall construction, but since ground-connecting-wall wall construction is mainly constructed in underground excavation slot section, it will usually there is dew
Two kinds of common quality defects of seam hidden danger of muscle and wall.It detects unit and underwater conventional detection is carried out to Jingdang Port ground-connecting-wall harbour
When, it has been found that this kind of defect, or even there is local seam crossing rear stockyard filler leakage, there are larger security risk, while steel
Muscle is exposed in the seawater, and corrosion rate is high, and the durability of reinforcing bar is unable to get guarantee, and eventually leading to wall stress not can guarantee.
Summary of the invention
The present invention is above-mentioned various in order to solve the problems, such as, provide a kind of repairing and reinforcement is high-efficient, easy to operate, safety can
It leans on, the reinforcing Diaphragm Wall Wharf underwater concrete structure construction engineering method that repairing and reinforcement effect is easy to detect.
In order to solve the above technical problems, technical solution provided by the invention are as follows: reinforce the underwater coagulation of Diaphragm Wall Wharf
Soil structure construction, including following construction procedure:
A, area to be repaired submarine inspection: at preliminary cleaning damaged area after marine organisms, the progress of subaqueous survey net is laid
It measures and files measurement data;
B, marine organisms are cleared up in area to be repaired: according to data measured by step A, determining what marine organisms need to clear up
Range is simultaneously cleaned out marine growth from area to be repaired using high-pressure rotary-spray jet apparatus, exposes concrete base layer;
C, loose concrete chisel removal in area to be repaired: 10 are relaxed to damaged area each side of the edge and is used to 15cm range
Hydraulic pick carries out dabbing processing, is cut under water to concrete loose in restoring area using Hydraulic pick, edge uses
Hydraulic chain saw carry out excision and it is straight;
D, underwater reinforcing bar repair welding is reinforced: first measure bar diameter, after design requirement is less than to diameter reinforcing bar be welded with
New reinforcing bar operation;If reinforcing bar large area corrode, need it is prefabricated by land be welded into reinforced mesh, then hang in water with original steel
Muscle net mutually welds;
E, underwater drilling lays form tie: hydraulic drilling device is used, is drilled on horizontal and vertical every 30cm, drilling
Partial hole afterwards is implanted into an anchoring reinforcing bar, installation template mechanical swelling pull rod in another part hole;
F, formwork erection underwater formwork erection and sealing: is carried out using glued board when damaged area height is less than 1.5m;Work as damage zone
Formwork erection is carried out using steel template when domain height is greater than 1.5m, being all made of the materials such as flitch, sealing brown piece, sealing cotton after formwork erection makes
Formwork seal is good;
G, grout hole underwater grouting: is reserved and by Grouting Pipe from lower from template by Underwater Concrete mix conveying integrated machine
Upper injection is inserted into bottom from the reserved grouting mouth in template top using by Grouting Pipe, and marginal not slurry side, which is promoted, is in the milk;
H, demoulding is checked and accepted: after underwater grouting completes 72h, underwater demolition template is carried out form tie protruding parts underwater
Excision carries out preservative treatment to pull rod part exsertion part after excision.After being disposed, subaqueous survey net is laid again, to repairing
Multiple outer dimension repetition measurement forms as-constructed plan record.
As an improvement, the subaqueous survey net is the dedicated subaqueous survey net of BND type and specification is 500mm × 500mm, institute
The lower suspension for the subaqueous survey net stated is equipped with weight.
As an improvement, the surge of the high-pressure rotary-spray jet apparatus is 16 to 20MPa, band angle can be formed and cut
Power removes marine organisms.
As an improvement, being adopted after the grouting material of reparation is not by dispersing flocculants, special-type grouting material and tap water match under water
It is continuously stirred and is conveyed with dedicated Underwater Concrete mix conveying integrated machine and poured.
The advantages of the present invention over the prior art are that: repairing and reinforcement generallys use underwater formwork and carries out grouting reparation,
The method has repairing and reinforcement high-efficient, easy to operate, safe and reliable, and repairing and reinforcement effect is easy to detect, and eliminating, underground is continuous
There is very big economic benefit, environmental benefit and social benefit in terms of two kinds of common quality defects of wall dock structure;While the engineering method is also
With repair materials intensity height, repair materials low cost, damaged face cleaning efficiency is high, template support is solid and reliable, pressure grouting
It guarantees the quality the advantages that efficient.
Detailed description of the invention
Fig. 1 is the non-dispersible underwater concrete that the present invention reinforces Diaphragm Wall Wharf underwater concrete structure construction engineering method
Underwater pouring shaping schematic view.
Specific embodiment
Present invention will be described in further detail below with reference to the accompanying drawings.
Technological principle of the invention: the cardinal principle for the repairing and reinforcement that is in the milk is by configuring the grouting of organic or inorganic
Material is poured into crack or the hole of object to be reinforced using force feeds equipment such as grouting pumps using hydraulic principle, makes slurries in quilt
Fill and permeate in carrier, spread, fill, be gelled and solidified after a certain period of time, the water of fault location and hole are squeezed exclude until
Grouting material is filled in completely to be full of, thus the purpose of realizing antiseepage, leak stopping and reinforcing.Concrete operations technological principle is: passing through high pressure
Whirl spraying fluidics is clean to marine growth thorough cleaning on the concrete surface and reinforcing bar of damaged area and restoring area to be reinforced,
Followed by hydraulic diamond chain saw or Hydraulic pick to concrete loose around region, then punched by hydraulic drill embedded
By dies plate tap after mechanical swelling pull rod, restoring area sealing is in the milk into restoring area, to under the conditions of test block reach design
Demoulding inspection after intensity.
Specific implementation step of the invention:
A, area to be repaired submarine inspection: the mass defect region, that is, submerged structure damaged area provided according to detection unit
Position, preliminary to clear up defect nearby after marine organisms, flaw size can be observed by reaching.It lays under BND type dedicated water
Net is measured, survey grid is distributed using 500mm × 500mm grid, lower suspension weight, it is ensured that survey grid is along wall vertical run, net
Lattice point of intersection reference mark point.Diver enters water, is recorded a video using underwater video recording to entire area to be repaired, is measured after video recording
Deep three parameters of defect whole region length and width, draw defect area schematic diagram after water outlet, schematic diagram at least (should be embodied and be lacked comprising main view
Fall into length and width dimensions) and sectional view (embodying depth of defect).Schematic diagram should by diver, after documenter and field engineer's signature and
Video recording forms data backup, as final archive file.
B, marine growth is cleared up in area to be repaired: by first step process measurement data, determining marine growth cleanup area.It is logical
Normal, marine growth will become important barrier of the repair materials with the guarantee of steel mesh bond stress and in conjunction with old metope, meanwhile, no
Marine growth on reinforcing bar can be cleaned out, reinforcing bar will be unable to be passivated again under alkaline environment.Using high-pressure rotary-spray jet apparatus
Band angle water flow cutting is formed in high speed whirl spraying using water, surge can be up to 16 to 20MPa, can by marine growth from
Area to be repaired separates.The cleaning of high-pressure rotary-spray jet stream with high-efficient, clears up thorough advantage than conventional cleaning.
C, loose concrete chisel removal in area to be repaired: loose concrete is also a weight for influencing concrete repairing quality
The rate-determining steps wanted relax 10 to damaged area each side of the edge and carry out dabbing processing using Hydraulic pick to 15cm range, to repairing
Loose concrete is cut under water using Hydraulic pick in multiple region, edge using hydraulic chain saw carry out excision with it is straight.
D, underwater reinforcing bar repair welding is reinforced: if lower section, which has reinforcing bar to expose reinforcing bar simultaneously, has occurred and that corrosion, measurement reinforcing bar is straight
Diameter, if steel area loss is smaller, diameter meets design requirement, and then be used directly original reinforcing bar, if original bar diameter is not
Meet design requirement, then needs to be welded with new reinforcing bar on original reinforcing bar.If reinforcing bar large area is corroded, prefabricated weldering by land is needed
Be connected into reinforced mesh, reinforcing bar arrangement of reinforcement when material with former diaphram wall steel mesh.Then the reinforced mesh that land fabrication is good
It hangs in water, diver binds and welds with original reinforcing bar under water.Welding ensures effectively to weld with original steel mesh, guarantees new
Continuity between old reinforced mesh.
E, underwater drilling lays form tie: hydraulic drilling device is used, in horizontal and vertical each 30cm drilling, drilling
Partial hole is implanted into an anchoring reinforcing bar afterwards, on the one hand ensures the binding force in new-old concrete face, after on the other hand also can be used as
Mend the drawknot node of reinforced mesh, installation template mechanical swelling pull rod in another part hole, drawknot node when to template support.It is above-mentioned
After the completion of work, diver leaves and takes photologging using underwater video recording, retains as quality examination and concealment acceptance data.
F, underwater formwork erection and sealing: before selecting template, according to engineering experience and template bearing load capacity calculation, steel is chosen
Two kinds of materials of pallet and glued board, damaged area height use glued board when being less than 1.5m;Damaged area height is greater than 1.5m
Shi Caiyong steel template.
1) plywood form installs main points:
1. being installed using the technique that layering installs, is made and installed by actual repair area, every layer of template is most
Big height 80cm, maximum width 200cm, two connection part of templates are reinforced using reinforcing strip.Template thickness is 10mm, in template
Side brushing high polymer release agent, it is insoluble which meets water, it can be ensured that stripping result and does not influence institute's casting concrete
Quality.
2. using channel steel reinforcing template on the outside of template to prevent template to be split up by concrete, channel steel length is larger than mould
Board width, every 30cm install an emissions groove steel (channel steel model 10# channel steel), and template is fixed to be consolidated using the method for screwed connection
It is fixed, by screw rod by being soldered to reinforcing bar, beat expansion bolt under water and be fixed on two methods in concrete and fix, then screw thread will be had
The channel steel in hole is threadedly coupled with the screw rod fixed, can be by screw rod after the completion of concreting using detachable screw rod
It removes, and removes the hole left after screw rod using same type of material reparation.
3. formwork erection is installed, it is higher by former ground-connecting-wall sea side 8cm on the inside of template, template is in damaged area surrounding
10cm is had more respectively, keeps formwork seal good using materials such as flitch, sealing brown piece, sealing cottons in the bottom surface of template and 2 sides
It is good.
4. after template is installed, diving operation squad leader copes with the sealing situation of template surrounding and the weldering of channel steel, template
Binding is connect to be checked, if the unqualified timely progress template reparation of discovery, and writing record and underwater camera are carried out, form money
Material.
2) steel template installs main points
1. using plane combined steel formwork, template thickness 3mm, the high 55mm of rib, form height and length foundation are actually repaired
Coverlay product carries out live processing.Every layer of steel form maximum height is 1.5m, maximum width 5m.Connection type between template is adopted
With the U-shaped card of Ф 12.Brushing high polymer release agent on the inside of template, it is insoluble which meets water, it can be ensured that stripping result and
The quality of institute's casting concrete is not influenced.Template to the progress mechanical grinding derusting of template outer surface, and on surface before use, apply
Brush antirust agent coating, application process are land dry construction, and zinc content reaches 96% or more in dry coating, can possess with
The same rust-proof effect of hot galvanizing, zinc and iron in film directly contact, and utilize electrochemical principle anti-corrosion.
2. vertically every 30cm, the reserved diameter of lateral every 100cm are observation fabrication hole 1 of 5cm to template, fabrication hole can be closed
And unlatching, to observe grouting material casting situation.
It is fixed 3. template is fixed using the method for screwed connection, by screw rod by being soldered to reinforcing bar, playing expansion under water
Bolt is fixed on two methods in concrete and fixes, then the rigid template with threaded bore is carried out screw thread company with the screw rod fixed
It connects, using detachable screw rod, after remove screw rod after the completion of concreting, and after use same type of material reparation dismounting screw rod
The hole left.After pull rod passes through template preformed hole, water stop gel ring is installed on pull rod, prevents grouting liquid from flowing from form tie hole
Out, then the fixation tabletting of installation pull rod and nut, next use hydraulic spanner at the beginning of nut thoroughly fasten, it is ensured that peripheral water stopping adhesive tape
With the complete gluing, sealing of metope.
4. formwork erection is installed, it is higher by former ground-connecting-wall sea side 10cm on the inside of template, template is in damaged area four
Week has more 10cm respectively, makes formwork seal using materials such as flitch, sealing brown piece, sealing cottons in the bottom surface of template and 2 sides
Well.
5. it is 4.5m that template maximum, which installs height, when there is the case where damaged height is greater than 4.5m, construct in batches.
After 6. template is installed, diving operation squad leader should the sealing situation to template surrounding check, if discovery
Unqualified timely progress template replacement and reparation, and writing record and underwater camera are carried out, form data.
G, underwater grouting: the grouting material of reparation is by not dispersing flocculants under water: special-type grouting material: after tap water matches,
After being continuously stirred using Special pulping equipment, grout hole is reserved by template by grouting pump and is injected from bottom to top by Grouting Pipe
Or it is inserted into bottom from the reserved grouting mouth in template top using by Grouting Pipe, marginal not is starched side and is promoted.This grouting way is being repaired
Original structure component strength grade can be higher than in terms of the intensity of position, while fluidity is relatively large, it is ensured that rejected region institute
Some gaps are all filled, while being not necessarily to vibration compacting, Self-leveling, self-compaction.
H, demoulding is checked and accepted: after underwater grouting completes 72h, underwater demolition template is carried out form tie protruding parts underwater
Excision carries out preservative treatment to pull rod part exsertion part after excision.After being disposed, lays surveyed under BND type dedicated water again
Net is measured, to restoration contour size repetition measurement, forms as-constructed plan record, while being recorded a video under water, all data are by diver, data
After member and field engineer sign and video recording forms data backup, as final archive file.
The material and equipment that the specific embodiment of the invention is used:
1. material
1) flocculant material specification and performance
2) grouting material material specification and performance
High Strength Non-shrinking Filling Material the key technical indexes
2. capital equipment
1) diving apparatus: screw air compressor, underwater video recorder, diving suit etc.
2) marine growth cleaning and grinding apparatus: underwater whirl spraying jet cleaning equipment, marine growth special shovel.
3) underwater concrete is cut and punch device: hydraulic workstation, hydraulic diamond chain saw, Hydraulic pick, hydraulic drill.
4) underwater reinforcement welding equipment: underwater electric welding machine and cutting machine
5) dies plate tap equipment: hydraulic spanner.
The quality of material and work progress of the present invention controls
1. Material quality control
1) selection of flocculant
When concrete works select additive, should according to the performance requirement of concrete, construction technology and weather conditions, in conjunction with
The raw material property of concrete, match ratio and to factors such as the adaptability of cement, pass through to test and determine its kind and volume.No
It should store, mark respectively with kind additive, must not be polluted when transport is with storage.
2) selection of grouting material
Carefully verification producer's product certificate and third party's examining report are needed when grouting material admission, are used and are said according to product
Bright configuration is simultaneously sampled and is sent to laboratory inspection, and product can use after the assay was approved.
3) selection of reinforcing bar
When the entering of reinforcing steel bar, work certificate and Delivery Inspection Report should be checked, and carry out appearance by the regulation of relevant criterion
And intensity sampling observation, it is ensured that quality is met the requirements.
2. work progress quality controls
1) underwater cleaning quality
Underwater cleaning quality is mainly recorded a video according to diver under water to be judged, because in conjunction with subaqueous survey net, for clear
The range and cleaning quality of reason intuitively can calculate and see.Reinforcing bar will derust to ST2 grades, and especially marine organisms need
It cleans out.
2) anchor bolt and template support inspection
After the completion of anchor bolt and template support, water is grown by operation group group and is checked, to the peace of anchor bolt
Holding position and quantity are checked, while whether having been covered all damaged area and template to template range and having been repaired position original
Structure fitting situation is checked, is allowed for access after passed examination and is constructed in next step.And writing record is formed simultaneously to inspection result
Label take as data it is for future reference.
3) underwater grouting material match ratio inspection
The underwater grouting material product determined according to project carries out mix using match ratio, carries out before mix to material therefor amount
It checks, mix can be carried out after meeting the requirements, while should check the actual conditions of mix material, not special conditions of contract
Under the influence of, it must not arbitrarily adjust each material utilization amount in match ratio.
4) underwater grouting material strength checking
In order to be detected to underwater grouting material intensity, when being poured non-dispersible underwater concrete simultaneously preparation under water regardless of
Concrete sample is dissipated, test method is detailed in:
1. underwater grouting material shaping method of specimen
Testing equipment:
A die trial size takes 150mmx 150mm x 150mm;
B standard curing room is not less than 95% controlled at (20 ± 2) DEG C, relative humidity, when there is no standard curing room,
Test specimen allows to conserve in the hydrostatic of (20 ± 2) DEG C, and indicates in report;
C tank height can guarantee test during die trial top surface with headwater depth maintain 150mm, water tank length and width according to
Test it needs to be determined that.
Underwater molded test step:
The die trial of underwater molding is placed in water tank by a, and water is added to the die trial top surface with headwater depth 150mm, keeps it
Water temperature is in (20 ± 2) DEG C;
B is poured into die trial, each inventory is examination for shoveling underwater grouting material mix from falling from the water surface into water
1/10 or so of mould volume, continuous dosing are 0.5-lmin, underwater pouring to die trial surface, the charging time of each die trial is exceeded
Method is as shown in Fig. 1;
C takes out die trial from water, stands 5-l0min;
D promotes draining with two sides that wooden mallet touches die trial, is then placed back into water;
E is smoothed out before initial set with spatula beyond the concrete of die trial, is placed 2d demoulding, is carried out standard curing in water,
Certain distance is kept between test specimen, each age is with 3 test specimens for one group;
F takes out test specimen from water when reaching predetermined age, is tested.
2. land molded test step:
The die trial of land molding is placed in air by a, and room temperature should be maintained at (20 ± 2) DEG C;
B is for shoveling grouting material mix does not pour into die trial continuously under water, and continuous dosing is to die trial surface is exceeded, each
The skill material time of die trial is 0.5-lmin;
C is smoothed out before initial set with spatula beyond the concrete of die trial, is placed 2d demoulding, is carried out standard curing in water,
Certain distance should be kept between test specimen, each age is with 3 test specimens for one group;
D takes out test specimen test when reaching predetermined age from water.
3. non-dispersible underwater concrete land and water compressive strength rate measuring method
Testing equipment should meet following requirements:
The test error of indication of a pressure testing machine is not more than ± the 2% of standard value;
B pressurization back plate sizes are had a competition, and part pressure-bearing surface is slightly larger, and surface smoothness is within 0.02mm;
C die trial size takes 150mmx 150mm x 150mm.
Test should follow these steps to carry out:
A test specimen when maintenance to regulation age, prevents from doing after taking out in water in the water of (20 ± 2) DEG C with wet cloth covering
It is dry;
By test specimen wiped clean before b test, appearance is measured size and checked, sample dimensions measurement is accurate to lmm;
The center of the upper and lower end face of c test specimen is directed at the center of upper lower platen, and testing machine pressing plate and test specimen compression face coincide;
Continuously and uniformly until test specimen destroys, loading speed is determined according to test piece intensity for loading when d is tested, and strength grade is small
Take 0.3-0.5MPa/s when C30, when C30 or more takes 0.5-0.8MPa/s.
Test result calculates:
A concrete crushing strength is calculated as follows:
F in formulacuOne concrete crushing strength (MPa), calculating are accurate to 0.1MPa;
Mono- failing load of P (kN);
Mono- test specimen bearing area (mm2) of A.
B compression strength value takes the arithmetic mean of instantaneous value of 3 test piece intensities of group.When the maximum value in 3 test piece intensities or most
When the difference of small value and median is more than the 15% of median, median is taken;When in 3 test piece intensities maximum value and minimum value with
When the difference of median is more than the 15% of median, this group of test result is cancelled;
The land and water c compressive strength rate is the ratio of underwater shaping test piece compression strength and land shaping test piece compression strength, meter
It calculates result and is accurate to 1%.
5) repairing quality inspection
Measurement net video recording twice, the i.e. comparison of reparation antero-posterior extent can be compared to the inspection of repair coverage.
Appearance can be checked by video recording by repairing grouting material Forming Quality.
Intensity carries out mechanical property inspection by core boring sampling.
Claims (4)
1. reinforcing Diaphragm Wall Wharf underwater concrete structure construction engineering method, it is characterised in that: including following construction procedure:
A, it area to be repaired submarine inspection: at preliminary cleaning damaged area after marine organisms, lays subaqueous survey net and measures
And measurement data is filed;
B, marine organisms are cleared up in area to be repaired: according to data measured by step A, determining the range that marine organisms need to clear up
And cleaned out marine growth from area to be repaired using high-pressure rotary-spray jet apparatus, expose concrete base layer;
C, 10 loose concrete chisel removal in area to be repaired: are relaxed to 15cm range using hydraulic to damaged area each side of the edge
Pick carries out dabbing processing, is cut under water to concrete loose in restoring area using Hydraulic pick, edge is using hydraulic
Chain saw carry out excision and it is straight;
D, underwater reinforcing bar repair welding is reinforced: first measure bar diameter, after design requirement is less than to diameter reinforcing bar carry out being welded with new steel
Muscle operation;If reinforcing bar large area corrode, need it is prefabricated by land be welded into reinforced mesh, then hang in water with original steel mesh
Mutually weld;
E, underwater drilling lays form tie: using hydraulic drilling device, drills on horizontal and vertical every 30cm, after drilling
Partial hole is implanted into an anchoring reinforcing bar, installation template mechanical swelling pull rod in another part hole;
F, formwork erection underwater formwork erection and sealing: is carried out using glued board when damaged area height is less than 1.5m;When damaged area height
Formwork erection is carried out using steel template when degree is greater than 1.5m, being all made of the materials such as flitch, sealing brown piece, sealing cotton after formwork erection makes template
Good seal;
G, underwater grouting: grout hole is reserved from template by Underwater Concrete mix conveying integrated machine and is infused from bottom to top by Grouting Pipe
Enter or be inserted into bottom from the reserved grouting mouth in template top using by Grouting Pipe, marginal not slurry side, which is promoted, is in the milk;
H, demoulding is checked and accepted: after underwater grouting completes 72h, underwater demolition template cuts off form tie protruding parts under water,
Preservative treatment is carried out to pull rod part exsertion part after excision.After being disposed, subaqueous survey net is laid again, to restoration contour
Size repetition measurement forms as-constructed plan record.
2. reinforcing Diaphragm Wall Wharf underwater concrete structure construction engineering method according to claim 1, it is characterised in that:
The subaqueous survey net is the dedicated subaqueous survey net of BND type and specification is 500mm × 500mm, the subaqueous survey net
Lower suspension is equipped with weight.
3. reinforcing Diaphragm Wall Wharf underwater concrete structure construction engineering method according to claim 1, it is characterised in that:
The surge of the high-pressure rotary-spray jet apparatus is 16 to 20MPa, can form band angle cutting force and remove marine organisms.
4. reinforcing Diaphragm Wall Wharf underwater concrete structure construction engineering method according to claim 1, it is characterised in that:
After the grouting material of reparation is not by dispersing flocculants, special-type grouting material and tap water match under water, using dedicated Underwater Concrete mix
Conveying integrated machine is continuously stirred and is conveyed and pours.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810814323.2A CN108951608A (en) | 2018-07-23 | 2018-07-23 | Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810814323.2A CN108951608A (en) | 2018-07-23 | 2018-07-23 | Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108951608A true CN108951608A (en) | 2018-12-07 |
Family
ID=64463476
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810814323.2A Pending CN108951608A (en) | 2018-07-23 | 2018-07-23 | Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108951608A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109680648A (en) * | 2019-02-22 | 2019-04-26 | 水利部交通运输部国家能源局南京水利科学研究院 | A kind of high-pile beam wharf member section recovery template |
CN110409324A (en) * | 2019-06-13 | 2019-11-05 | 杭州国电大坝安全工程有限公司 | Underwater rapid reinforcement repairs structure, repairing construction equipment and construction method |
CN113638377A (en) * | 2021-08-16 | 2021-11-12 | 天津大学 | Enclosure equipment type dry land repairing method for underwater concrete damage |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0493422A (en) * | 1990-08-10 | 1992-03-26 | Ohbayashi Corp | Construction method for underground structure |
CN104153392A (en) * | 2014-06-17 | 2014-11-19 | 杭州华能大坝安全工程技术有限公司 | Underwater PBM polymer concrete construction method |
CN105672250A (en) * | 2016-01-20 | 2016-06-15 | 中铁隆工程集团有限公司 | Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete |
-
2018
- 2018-07-23 CN CN201810814323.2A patent/CN108951608A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0493422A (en) * | 1990-08-10 | 1992-03-26 | Ohbayashi Corp | Construction method for underground structure |
CN104153392A (en) * | 2014-06-17 | 2014-11-19 | 杭州华能大坝安全工程技术有限公司 | Underwater PBM polymer concrete construction method |
CN105672250A (en) * | 2016-01-20 | 2016-06-15 | 中铁隆工程集团有限公司 | Rabbet connecting mechanism and construction method for underground diaphragm wall and underwater concrete |
Non-Patent Citations (3)
Title |
---|
华克专等: "《建筑修缮施工技术手册》", 31 December 1992, 中国建筑工业出版社 * |
朱元光等: "《混凝土的胶接 密封与修补》", 31 December 1994, 中国铁道出版社 * |
陈日中: "《高速公路企业经营管理实务全书 第二卷》", 30 April 2002, 内蒙古文化出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109680648A (en) * | 2019-02-22 | 2019-04-26 | 水利部交通运输部国家能源局南京水利科学研究院 | A kind of high-pile beam wharf member section recovery template |
CN109680648B (en) * | 2019-02-22 | 2023-08-11 | 水利部交通运输部国家能源局南京水利科学研究院 | Repairing method for section of high pile beam slab wharf component |
CN110409324A (en) * | 2019-06-13 | 2019-11-05 | 杭州国电大坝安全工程有限公司 | Underwater rapid reinforcement repairs structure, repairing construction equipment and construction method |
CN113638377A (en) * | 2021-08-16 | 2021-11-12 | 天津大学 | Enclosure equipment type dry land repairing method for underwater concrete damage |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109026065B (en) | Tunnel secondary lining zero-defect construction method | |
CN109629455B (en) | Construction method for reconstructing bridge of highway | |
CN104314070B (en) | A kind of Π shape diaphragm wall shield structure export & import construction method | |
CN109611102B (en) | Construction method for cold excavation underpass overpass | |
CN106917409B (en) | A kind of rock lid weight consolidation grouting construction method | |
CN108951608A (en) | Reinforce Diaphragm Wall Wharf underwater concrete structure construction engineering method | |
CN110486023A (en) | Tunnel defect administering method | |
CN100473790C (en) | Tower crane foundation for construction and manufacturing method thereof | |
CN105926470B (en) | Elevated bridge remodeling method | |
CN108330835A (en) | The construction method of setting bracket | |
CN205662837U (en) | Overhead bridge transformation structure | |
CN112049143B (en) | Large-sized concrete bearing platform construction method for large-sized low-temperature storage tank | |
CN109137885A (en) | A kind of construction method of underground continuous wall | |
CN111894204A (en) | Steel pipe concrete composite column construction method | |
CN106120835B (en) | A kind of circle concrete structures toe board panel guide rail and its levelling construction | |
CN110952586A (en) | Construction process for bearing platform below expressway | |
CN115539095A (en) | Waterproof and monitoring method for shield construction | |
CN113884364B (en) | Sample preparation method for rock-soil body in-situ penetration test | |
CN107905609A (en) | Underground people's air defense construction method | |
CN106120793A (en) | A kind of tilt the method for correcting error of pile for prestressed pipe and structure | |
CN103243912B (en) | Multilayer is without plate framework construction method | |
CN110468729A (en) | A kind of frame bridge construction method | |
JP2840566B2 (en) | Deep reinforcement method for concrete structures | |
CN115110520A (en) | Construction method of bridge pile foundation on highway | |
CN110230271A (en) | Bridge biased displacement post-reinforcing resets construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181207 |