CN108930637A - A kind of offshore boosting station jacket basis - Google Patents
A kind of offshore boosting station jacket basis Download PDFInfo
- Publication number
- CN108930637A CN108930637A CN201810834525.3A CN201810834525A CN108930637A CN 108930637 A CN108930637 A CN 108930637A CN 201810834525 A CN201810834525 A CN 201810834525A CN 108930637 A CN108930637 A CN 108930637A
- Authority
- CN
- China
- Prior art keywords
- foundation
- offshore
- cable
- construction
- jacket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 17
- 239000010959 steel Substances 0.000 claims description 17
- 238000004873 anchoring Methods 0.000 claims description 6
- 238000000926 separation method Methods 0.000 claims description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 238000010276 construction Methods 0.000 abstract description 38
- 238000000034 method Methods 0.000 abstract description 9
- 230000008520 organization Effects 0.000 abstract description 4
- 238000012423 maintenance Methods 0.000 description 4
- 238000010248 power generation Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D13/00—Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
- F03D13/20—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
- F03D13/25—Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D80/00—Details, components or accessories not provided for in groups F03D1/00 - F03D17/00
- F03D80/80—Arrangement of components within nacelles or towers
- F03D80/82—Arrangement of components within nacelles or towers of electrical components
- F03D80/85—Cabling
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0091—Offshore structures for wind turbines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0095—Connections of subsea risers, piping or wiring with the offshore structure
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/72—Wind turbines with rotation axis in wind direction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/727—Offshore wind turbines
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
- Wind Motors (AREA)
Abstract
Description
技术领域technical field
本发明涉及风电场建设技术领域,具体涉及一种海上升压站导管架基础。The invention relates to the technical field of wind farm construction, in particular to a jacket foundation of an offshore booster station.
背景技术Background technique
海上升压站包括上部组块和下部基础,上部组块在其设计、制造、施工及安装等方面制约因素较多,而下部基础则受制因素较少,可以较快完成。目前我国海上升压站基础从形式上可分为单桩基础、水下先桩法直接插入式导管架基础、水下后桩法桩靴式导管架基础和水上后桩法支撑式导管架基础等,通常在基础上只集成有靠船和J型管结构。各集电线路和送出海缆登陆升压站J型管后均会有13-18m的海缆,此部分海缆若在传统的导管架上进行临时固定(同时必须满足海缆最小弯曲半径要求),则在升压站上部组块吊装时也会与其发生干涉。因此,在传统升压站基础施工完成后,将导致各集成线路和送出海缆不具备登陆升压站以及海缆在电缆层敷设施工的条件,这样就会对整个风电场建设中海缆施工、各风机基础及风机安装施工的组织带来不利影响,从而影响风电场并网发电的进度,使得经济利益严重受损。The offshore booster station includes the upper block and the lower foundation. The upper block has many constraints in its design, manufacture, construction and installation, while the lower foundation has fewer constraints and can be completed quickly. At present, the foundations of my country's offshore booster stations can be divided into single pile foundations, underwater pile-first method direct insertion jacket foundations, underwater back-pile method pile-shoe jacket foundations, and underwater back-pile method supported jacket foundations. etc., usually only berthing and J-tube structures are integrated on the foundation. There will be a 13-18m submarine cable after each collector line and the J-tube of the submarine cable landing booster station. If this part of the submarine cable is temporarily fixed on the traditional jacket (at the same time, the minimum bending radius of the submarine cable must be met ), it will also interfere with it when the upper block of the booster station is hoisted. Therefore, after the foundation construction of the traditional booster station is completed, the integrated lines and outgoing submarine cables will not meet the conditions for landing the booster station and laying the submarine cable on the cable layer. The foundation of each wind turbine and the organization of wind turbine installation and construction bring adverse effects, thereby affecting the progress of wind farm grid-connected power generation, and seriously damaging economic interests.
发明内容Contents of the invention
因此,本发明要解决的技术问题在于克服现有技术中的海上升压站在完成下部基础的施工后,各集成线路和送出海缆不具备登陆升压站及海缆在电缆层敷设施工的条件的缺陷,从而提供一种下部基础施工完成后即可进行各集成线路和送出海缆的登陆施工,且海缆登陆后能够锚固于电缆层的海上升压站导管架基础。Therefore, the technical problem to be solved by the present invention is to overcome the problem that each integrated line and sending out submarine cable do not have the construction of landing booster station and submarine cable laying construction on the cable layer after the offshore booster station in the prior art has completed the construction of the lower foundation. In order to provide a jacket foundation for the offshore step-up station that can carry out the landing construction of the integrated lines and the outgoing submarine cable after the completion of the lower foundation construction, and the submarine cable can be anchored to the cable layer after landing.
为了解决该问题,本发明公开了一种海上升压站导管架基础,包括:In order to solve this problem, the invention discloses a jacket foundation of an offshore booster station, comprising:
下部基础,底端固定在海床中,所述下部基础内部超出海平面的部分集成有电缆层。The bottom of the lower foundation is fixed in the seabed, and the part of the lower foundation above the sea level is integrated with a cable layer.
所述电缆层位于所述下部基础内部靠近顶端的位置。The cable layer is located inside the lower foundation near the top.
所述电缆层自所在平面的中心向远离所述下部基础的方向延伸,直至超出所述下部基础。The cable layer extends from the center of the plane in a direction away from the lower foundation until it exceeds the lower foundation.
所述电缆层延伸出所述下部基础的周缘下部设置有若干支撑件,所述支撑件的另一端固定在所述下部基础上。The lower part of the periphery of the cable layer extending out of the lower foundation is provided with several support members, and the other ends of the support members are fixed on the lower foundation.
所述支撑件为两端分别与所述电缆层的下表面和所述下部基础的侧壁固接的斜杆。The supporting member is an oblique rod whose two ends are fixedly connected to the lower surface of the cable layer and the side wall of the lower foundation respectively.
所述斜杆与所述电缆层之间的夹角为30-70°。The included angle between the inclined rod and the cable layer is 30-70°.
所述下部基础内部,且位于所述电缆层上方设置有构造支撑层。A structural support layer is arranged inside the lower foundation and above the cable layer.
所述构造支撑层内嵌在所述下部基础内部。The structural support layer is embedded within the lower foundation.
所述下部基础由若干相互焊接的钢管构成,相邻两个水平设置的所述钢管之间设置有J型管,且所述J型管的顶端位于所述电缆层中。The lower foundation is composed of several welded steel pipes, a J-shaped pipe is arranged between two adjacent horizontally arranged steel pipes, and the top of the J-shaped pipe is located in the cable layer.
所述电缆层还设置有海缆锚固装置、海缆支架、救生装置和油水分离装置。The cable layer is also provided with a submarine cable anchoring device, a submarine cable support, a lifesaving device and an oil-water separation device.
本发明技术方案,具有如下优点:The technical solution of the present invention has the following advantages:
1.本发明提供的海上升压站导管架基础,在下部基础内部超出海平面的部分集成有电缆层,这样在下部基础施工完成后便可进行各集电线路和送出海缆的登陆施工,使得海缆登陆后能够锚固于电缆层,减少了海缆在海上作业时间,从而加快了风电场并网发电的进度,同时可以从风机基础施工、风机吊装施工和海缆施工等工序上优化风电场建设的施工组织效率,获得更好的经济效益。1. The jacket foundation of the offshore booster station provided by the present invention has a cable layer integrated in the part of the lower foundation that exceeds the sea level, so that after the completion of the lower foundation construction, the landing construction of each power collecting line and sending out submarine cable can be carried out. It enables the submarine cable to be anchored to the cable layer after landing, reducing the working time of the submarine cable at sea, thereby speeding up the progress of wind farm grid-connected power generation, and at the same time optimizing wind power in terms of wind turbine foundation construction, wind turbine hoisting construction and submarine cable construction. Improve the construction organization efficiency of field construction and obtain better economic benefits.
2.本发明提供的海上升压站导管架基础,在电缆层延伸出下部基础的周缘下部设置有若干支撑件,支撑件的另一端固定在下部基础上。这样使得电缆层与下部基础的连接更加稳固,同时提高电缆层的受力性能。2. In the jacket foundation of the offshore step-up station provided by the present invention, a number of supports are arranged at the lower part of the periphery where the cable layer extends out of the lower foundation, and the other end of the support is fixed on the lower foundation. This makes the connection between the cable layer and the underlying foundation more stable, and at the same time improves the mechanical performance of the cable layer.
3.本发明提供的海上升压站导管架基础,还包括设置在下部基础内部,且位于电缆层上方的构造支撑层。这样使得下部基础位于电缆层以上部分的结构更加稳定。3. The jacket foundation of the offshore step-up station provided by the present invention also includes a structural support layer arranged inside the lower foundation and above the cable layer. This makes the structure of the part of the lower foundation above the cable layer more stable.
4.本发明提供的海上升压站导管架基础,下部基础由若干相互焊接的钢管构成,相邻两个水平设置的钢管之间设置有J型管,且J型管的顶端位于电缆层中。海缆在穿过J型管后就可以锚固于海缆层中的海缆支架上,施工更加方便。4. The jacket foundation of the offshore step-up station provided by the present invention, the lower foundation is composed of several steel pipes welded to each other, a J-shaped pipe is arranged between two adjacent horizontal steel pipes, and the top of the J-shaped pipe is located in the cable layer . The submarine cable can be anchored on the submarine cable support in the submarine cable layer after passing through the J-shaped pipe, which makes the construction more convenient.
5.本发明提供的海上升压站导管架基础,在电缆层还设置有海缆锚固装置、海缆支架、救生装置和油水分离装置。这样使得海上升压站还同时具备在施工、在位运行过程中的逃救生、基本救助要求,在位运行过程主变事故状态放油要求、运维船停靠时基本运维工器具吊装要求等。5. The jacket foundation of the offshore step-up station provided by the present invention is also provided with a submarine cable anchoring device, a submarine cable support, a lifesaving device and an oil-water separation device on the cable layer. In this way, the offshore booster station also has the requirements for escape and lifesaving and basic rescue during construction and on-site operation, the requirements for oil discharge in the main transformer accident state during on-site operation, and the hoisting requirements for basic operation and maintenance tools when the operation and maintenance ship is docked, etc. .
附图说明Description of drawings
为了更清楚地说明本发明具体实施方式或现有技术中的技术方案,下面将对具体实施方式或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施方式,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the specific implementation of the present invention or the technical solutions in the prior art, the following will briefly introduce the accompanying drawings that need to be used in the specific implementation or description of the prior art. Obviously, the accompanying drawings in the following description The drawings show some implementations of the present invention, and those skilled in the art can obtain other drawings based on these drawings without any creative work.
图1为本发明的第一种实施方式中提供的海上升压站基础示意图;Fig. 1 is the basic schematic diagram of the offshore step-up station provided in the first embodiment of the present invention;
图2为图1中电缆层的俯视图。Fig. 2 is a top view of the cable layer in Fig. 1 .
附图标记说明:Explanation of reference signs:
1.电缆层 2.构造支撑层 3.海平面 4.海床1. Cable layer 2. Structural support layer 3. Sea level 4. Sea bed
5.J型管 6.海缆 7.支撑件 8.导管架 9.钢管桩5. J-tube 6. Submarine cable 7. Support 8. Jacket 9. Steel pipe pile
11.海缆锚固装置 12.海缆支架 13.吊装区域11. Submarine cable anchoring device 12. Submarine cable support 13. Hoisting area
14.防盗笼 15.外挂式救生软梯 16.救生艇14. Anti-theft cage 15. External lifesaving ladder 16. Lifeboat
17.救助站 18.楼梯 19.油水分离装置17. Rescue station 18. Stairs 19. Oil-water separation device
10.事故油罐 20.集合区 30.格栅 40.救生筏10. Accident oil tank 20. Assembly area 30. Grille 40. Life raft
具体实施方式Detailed ways
下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Apparently, the described embodiments are part of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
此外,下面所描述的本发明不同实施方式中所涉及的技术特征只要彼此之间未构成冲突就可以相互结合。In addition, the technical features involved in the different embodiments of the present invention described below may be combined with each other as long as there is no conflict with each other.
如图1和2所示的海上升压站导管架基础的一种具体实施方式,包括下部基础,底端固定在海床4中,所述下部基础内部超出海平面3的部分集成有电缆层1。A specific implementation of the jacket foundation of the offshore step-up station as shown in Figures 1 and 2, includes a lower foundation, the bottom end of which is fixed in the seabed 4, and the part of the lower foundation that exceeds the sea level 3 is integrated with a cable layer 1.
上述海上升压站导管架基础,在下部基础施工完成后便可进行各集电线路和送出海缆的登陆施工,减少了海缆6在海上作业时间,从而加快了风电场并网发电的进度,同时可以从风机基础施工、风机吊装施工和海缆施工等工序上优化风电场建设的施工组织效率,获得更好的经济效益。For the jacket foundation of the above-mentioned offshore step-up station, after the construction of the lower foundation is completed, the landing construction of the collection lines and the outgoing submarine cable can be carried out, which reduces the working time of the submarine cable 6 at sea, thereby speeding up the progress of wind farm grid-connected power generation , and at the same time, it can optimize the construction organization efficiency of wind farm construction from the wind turbine foundation construction, wind turbine hoisting construction and submarine cable construction and other processes to obtain better economic benefits.
具体地,所述下部基础可以为含过渡段单桩基础、水下先桩法直接插入式导管架基础、水下后桩法桩靴式导管架基础或水上后桩法支撑式导管架基础等。如图1所示,下部基础的底部可以通过钢管桩9嵌入海床4中,以保证施工的牢固度和可靠性。Specifically, the lower foundation may be a single-pile foundation with a transition section, an underwater pile-first method directly inserted jacket foundation, an underwater post-pile method spud-shoe jacket foundation, or an underwater post-pile method supported jacket foundation, etc. . As shown in FIG. 1 , the bottom of the lower foundation can be embedded into the seabed 4 through steel pipe piles 9 to ensure firmness and reliability of construction.
作为一种具体的实施方式,上述电缆层1位于所述下部基础内部靠近顶端的位置。具体地,所述电缆层1位于海平面3之上,其标高需满足在位期间潮位变化、极限浪高和气隙等海上固定式平台相关要求。As a specific implementation manner, the above-mentioned cable layer 1 is located inside the lower foundation near the top. Specifically, the cable layer 1 is located above the sea level 3, and its elevation needs to meet the relevant requirements of fixed offshore platforms such as tide level changes, extreme wave heights, and air gaps during the in-position period.
上述电缆层自所在平面的中心向远离所述下部基础的方向延伸,直至超出所述下部基础。即电缆层的横截面积大于所在平面的相应下部基础的横截面积,以增大电缆层1的承载面积,方便在其上部布设其他必要的装置。The above-mentioned cable layer extends from the center of the plane where it is located in a direction away from the lower foundation until it exceeds the lower foundation. That is, the cross-sectional area of the cable layer is greater than the cross-sectional area of the corresponding lower foundation of the plane, so as to increase the load-bearing area of the cable layer 1 and facilitate the laying of other necessary devices on its upper part.
为了进一步提高电缆层的抗震性能和结构受力强度,在上述电缆层1 延伸出所述下部基础的周缘下部设置有若干支撑件7,若干支撑件7均匀分布在下部基础的周向,所述支撑件7的另一端固定在所述下部基础上。具体地,上述支撑件7为两端分别与所述电缆层1的下表面和所述下部基础的侧壁焊接的钢结构斜杆,焊接可以在工厂预先完成,以减少施工难度,提高施工效率。上述斜杆与所述电缆层1之间的夹角为30-70°。In order to further improve the seismic performance and structural stress strength of the cable layer, several support members 7 are arranged at the lower part of the periphery of the lower foundation extending from the above-mentioned cable layer 1, and several support members 7 are evenly distributed in the circumferential direction of the lower foundation. The other end of the support member 7 is fixed on the lower foundation. Specifically, the above-mentioned support member 7 is a steel structure oblique rod whose two ends are respectively welded to the lower surface of the cable layer 1 and the side wall of the lower foundation. The welding can be pre-finished in the factory to reduce construction difficulty and improve construction efficiency . The included angle between the above-mentioned oblique rod and the cable layer 1 is 30-70°.
在上述下部基础内部,且位于所述电缆层上方设置有构造支撑层2。所述构造支撑层2内嵌在所述下部基础内部。构造支撑层2能够使下部基础位于电缆层1以上部分的结构更加稳定。Inside the above-mentioned lower foundation, and above the cable layer, a structural support layer 2 is arranged. The construction support layer 2 is embedded inside the lower foundation. Constructing the support layer 2 can make the structure of the lower foundation above the cable layer 1 more stable.
上述下部基础为由若干相互焊接的钢管构成的导管架8,若干钢管包括若干竖向钢管、若干横向钢管和用于同时连接竖向钢管和横向钢管的斜管,相邻两个斜管交叉设置,以提高下部基础的整体牢固性和稳定性。相邻两个水平设置的所述钢管之间设置有J型管5,且所述J型管5的顶端位于所述电缆层1中。The above-mentioned lower foundation is a jacket 8 composed of several mutually welded steel pipes. The several steel pipes include several vertical steel pipes, several horizontal steel pipes and inclined pipes for connecting vertical steel pipes and horizontal steel pipes at the same time. Two adjacent inclined pipes are arranged crosswise. , to improve the overall firmness and stability of the lower foundation. A J-shaped pipe 5 is arranged between two adjacent horizontally arranged steel pipes, and the top end of the J-shaped pipe 5 is located in the cable layer 1 .
这样在海缆6穿过J型管5登陆后能够锚固于电缆层1,同时海缆6分项后主电缆和光缆能够固定于海缆支架12,海缆支架12的布置在满足海缆敷设最小弯曲半径要求的同时,也满足上部组块吊装就位后主海缆与主变、 GIS连接工作量最小。In this way, after the submarine cable 6 passes through the J-shaped pipe 5 and lands, it can be anchored to the cable layer 1, and the main cable and the optical cable can be fixed on the submarine cable support 12 after the submarine cable 6 is divided. While meeting the bending radius requirements, it also meets the minimum workload for connecting the main submarine cable with the main transformer and GIS after the upper block is hoisted in place.
所述电缆层还设置有海缆锚固装置11、海缆支架12、救生装置和油水分离装置19。这样本实施例的海上升压站导管架基础就具备海上升压站在施工、在位运行过程中逃救生、基本救助要求,在位运行过程主变事故状态放油要求、运维船停靠时基本运维工器具吊装要求等。具体地,集成后的电缆层可以对以下部件进行设计:海缆锚固装置11、海缆支架12、油水分离装置19、事故油罐10、救生筏40、救生艇16、集合区20、吊装区域 13、防盗笼14、救助站17、外挂式救生软梯15、楼梯18、格栅30和吊机等,但不限于其他。The cable layer is also provided with a submarine cable anchoring device 11 , a submarine cable support 12 , a lifesaving device and an oil-water separation device 19 . In this way, the jacket foundation of the offshore booster station in this embodiment has the requirements for escape from life and rescue and basic rescue during the construction of the offshore booster station and on-site operation, the requirements for oil discharge in the main transformer accident state during the on-site operation, and the requirements for when the operation and maintenance ship is docked. Basic operation and maintenance tools hoisting requirements, etc. Specifically, the integrated cable layer can be designed for the following components: submarine cable anchoring device 11, submarine cable support 12, oil-water separation device 19, emergency oil tank 10, life raft 40, lifeboat 16, assembly area 20, hoisting area 13 , anti-theft cage 14, rescue station 17, external lifesaving ladder 15, stairs 18, grille 30 and crane, etc., but not limited to others.
传统升压站上部组块的电缆层1在最下方,但电缆层1本身荷载较小,却同时需要承受电缆层1之上约2500t的荷载,导致电缆层1结构重量增加。而本实施例中由于将电缆层1下移至升压站下部基础进行集成设计,因此电缆层1结构不需要再承受约2600t-3000t上部组块(已除去电缆层重量)在建造、运输和在位工况下的荷载,在下部基础增加的钢结构重量远小于上部组块减少的重量。The cable layer 1 of the upper block of the traditional step-up station is at the bottom, but the load of the cable layer 1 itself is small, but at the same time it needs to bear the load of about 2500t above the cable layer 1, resulting in an increase in the structural weight of the cable layer 1. In this embodiment, because the cable layer 1 is moved down to the lower foundation of the booster station for integrated design, the structure of the cable layer 1 does not need to bear about 2600t-3000t of the upper block (the weight of the cable layer has been removed) during construction, transportation and Under the in-situ load, the added weight of the steel structure in the lower foundation is far less than the reduced weight of the upper block.
作为替代的实施方式,支撑件7还可以为两端分别与电缆层1的下表面和下部基础的侧壁固接的斜板。As an alternative embodiment, the support member 7 may also be a slant plate whose two ends are respectively fixed to the lower surface of the cable layer 1 and the side wall of the lower foundation.
显然,上述实施例仅仅是为清楚地说明所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本发明创造的保护范围之中。Apparently, the above-mentioned embodiments are only examples for clear description, rather than limiting the implementation. For those of ordinary skill in the art, other changes or changes in different forms can be made on the basis of the above description. It is not necessary and impossible to exhaustively list all the implementation manners here. And the obvious changes or changes derived therefrom are still within the scope of protection of the present invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810834525.3A CN108930637A (en) | 2018-07-26 | 2018-07-26 | A kind of offshore boosting station jacket basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810834525.3A CN108930637A (en) | 2018-07-26 | 2018-07-26 | A kind of offshore boosting station jacket basis |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108930637A true CN108930637A (en) | 2018-12-04 |
Family
ID=64444860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810834525.3A Pending CN108930637A (en) | 2018-07-26 | 2018-07-26 | A kind of offshore boosting station jacket basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108930637A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112086893A (en) * | 2020-08-25 | 2020-12-15 | 中国能源建设集团广东省电力设计研究院有限公司 | Boarding structure of offshore booster station |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202068113U (en) * | 2011-05-25 | 2011-12-07 | 中国水电顾问集团华东勘测设计研究院 | Fixed offshore booster station for offshore wind farm |
CN202672129U (en) * | 2012-05-08 | 2013-01-16 | 江苏海上龙源风力发电有限公司 | Offshore wind electricity self-elevating seaborne booster station |
CN202945588U (en) * | 2012-11-09 | 2013-05-22 | 中国水电顾问集团华东勘测设计研究院 | Custom installation type booster station structure at sea |
CN203475459U (en) * | 2013-08-13 | 2014-03-12 | 广东明阳风电产业集团有限公司 | Three-pile guide pipe frame foundation structure of offshore wind turbine |
CN204435337U (en) * | 2015-01-13 | 2015-07-01 | 江苏金风科技有限公司 | Workbench and single-pile foundation and offshore work platform |
CN205894049U (en) * | 2016-07-29 | 2017-01-18 | 中国电建集团华东勘测设计研究院有限公司 | A first pitching pile formula jacket structure for marine booster station |
CN205986063U (en) * | 2016-08-16 | 2017-02-22 | 中天海洋系统有限公司 | Extra large cable anchor of pre -assembling formula |
CN107476270A (en) * | 2017-07-07 | 2017-12-15 | 中国能源建设集团广东省电力设计研究院有限公司 | Gravity type jacket offshore boosting station |
CN207184012U (en) * | 2017-08-16 | 2018-04-03 | 中国电建集团华东勘测设计研究院有限公司 | A kind of extra large cable protects tubular construction |
CN108240290A (en) * | 2016-12-26 | 2018-07-03 | 大连理工大学 | Jacket type offshore wind turbine platform and construction method thereof |
CN208416811U (en) * | 2018-07-26 | 2019-01-22 | 华电重工股份有限公司 | A kind of offshore boosting station jacket basis |
-
2018
- 2018-07-26 CN CN201810834525.3A patent/CN108930637A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202068113U (en) * | 2011-05-25 | 2011-12-07 | 中国水电顾问集团华东勘测设计研究院 | Fixed offshore booster station for offshore wind farm |
CN202672129U (en) * | 2012-05-08 | 2013-01-16 | 江苏海上龙源风力发电有限公司 | Offshore wind electricity self-elevating seaborne booster station |
CN202945588U (en) * | 2012-11-09 | 2013-05-22 | 中国水电顾问集团华东勘测设计研究院 | Custom installation type booster station structure at sea |
CN203475459U (en) * | 2013-08-13 | 2014-03-12 | 广东明阳风电产业集团有限公司 | Three-pile guide pipe frame foundation structure of offshore wind turbine |
CN204435337U (en) * | 2015-01-13 | 2015-07-01 | 江苏金风科技有限公司 | Workbench and single-pile foundation and offshore work platform |
CN205894049U (en) * | 2016-07-29 | 2017-01-18 | 中国电建集团华东勘测设计研究院有限公司 | A first pitching pile formula jacket structure for marine booster station |
CN205986063U (en) * | 2016-08-16 | 2017-02-22 | 中天海洋系统有限公司 | Extra large cable anchor of pre -assembling formula |
CN108240290A (en) * | 2016-12-26 | 2018-07-03 | 大连理工大学 | Jacket type offshore wind turbine platform and construction method thereof |
CN107476270A (en) * | 2017-07-07 | 2017-12-15 | 中国能源建设集团广东省电力设计研究院有限公司 | Gravity type jacket offshore boosting station |
CN207184012U (en) * | 2017-08-16 | 2018-04-03 | 中国电建集团华东勘测设计研究院有限公司 | A kind of extra large cable protects tubular construction |
CN208416811U (en) * | 2018-07-26 | 2019-01-22 | 华电重工股份有限公司 | A kind of offshore boosting station jacket basis |
Non-Patent Citations (2)
Title |
---|
刘文白 等: "近海风力发电导管架平台结构分析", 计算机辅助工程, vol. 17, no. 4, 31 December 2008 (2008-12-31), pages 55 - 58 * |
胡瑞华: "近海钢质桩基平台", 31 May 1989, 海洋出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112086893A (en) * | 2020-08-25 | 2020-12-15 | 中国能源建设集团广东省电力设计研究院有限公司 | Boarding structure of offshore booster station |
CN112086893B (en) * | 2020-08-25 | 2023-02-03 | 中国能源建设集团广东省电力设计研究院有限公司 | Boarding structure of offshore booster station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US12110862B2 (en) | Off shore wind energy installation foundation system | |
CN100473824C (en) | Foundation for an offshore wind energy plant | |
JP6619204B2 (en) | Deadline method and water barrier structure | |
CN106014874B (en) | How to install offshore wind turbines | |
CN218506092U (en) | C-shaped assembly type floating transportation structure for split floating transportation of offshore substation | |
WO2023284671A1 (en) | Semi-submersible floating fan device and system | |
CN108930637A (en) | A kind of offshore boosting station jacket basis | |
CN110670611A (en) | Inner support assembly type multilayer integral installation method for deep water foundation steel sheet pile cofferdam | |
TWI786427B (en) | Wind turbine full-set installation system and offshore mast-pulling platform ship | |
CN212358365U (en) | Offshore wind turbine supporting structure | |
CN221498383U (en) | Marine floating type photovoltaic platform system | |
CN111101497B (en) | Marine booster station structure capable of being integrally transported and installed | |
CN109038380B (en) | Offshore booster station | |
CN104018481B (en) | A kind of bucket foundation list leg post production platform | |
CN106585920B (en) | A kind of floating type water surface photovoltaic arrays enter water constructing device | |
CN217146308U (en) | Large-size precast concrete cushion block structure underwater transfer device | |
CN117166438A (en) | Suction barrel foundation suitable for submarine booster station and installation resistance calculation method thereof | |
CN206511082U (en) | Ship helps only pillar offshore exploration platform | |
CN107653857A (en) | A kind of offshore platform installation method | |
CN114988310A (en) | A system for inverting and transporting steel beams inside a core tube under a climbing formwork and a construction method thereof | |
CN104594319B (en) | The lifting installation method of integral of deep water ocean platform pump pillar | |
CN208416811U (en) | A kind of offshore boosting station jacket basis | |
CN102444139A (en) | Construction method for installing offshore wind power generation fan | |
CN108149704A (en) | A kind of prefabricated assembled High-Rise Pile Cap Foundation structure of offshore wind turbine and installation method | |
WO2010134881A1 (en) | Method for installing a topside module on an offshore support structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Country or region after: China Address after: 100071 11 / F, block B, building 1, yard 6, Automobile Museum East Road, Fengtai District, Beijing Applicant after: Huadian Technology Co.,Ltd. Address before: 10th Floor, Building B, Huadian Industrial Park, East Road of Automobile Museum, Fengtai District, Beijing Applicant before: HUADIAN HEAVY INDUSTRIES Co.,Ltd. Country or region before: China |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181204 |