CN108914746A - 一种新型人造草坪运动场的施工方法 - Google Patents
一种新型人造草坪运动场的施工方法 Download PDFInfo
- Publication number
- CN108914746A CN108914746A CN201810929269.6A CN201810929269A CN108914746A CN 108914746 A CN108914746 A CN 108914746A CN 201810929269 A CN201810929269 A CN 201810929269A CN 108914746 A CN108914746 A CN 108914746A
- Authority
- CN
- China
- Prior art keywords
- construction method
- artificial grass
- sports field
- novel artificial
- grass sports
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/08—Surfaces simulating grass ; Grass-grown sports grounds
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明涉及一种新型人造草坪运动场的施工方法,旨在提供一种有利于生态环境的保护,符合国家环保产业发展政策的人造草坪运动场,其施工步骤包括如下,步骤一,清除杂物,平整场地;步骤二,按千分之五的坡度打出标高点,找坡;步骤三,素土层碾压;步骤四,铺设防水卷材;步骤五,铺设多功能基层垫;步骤六,铺设人造草坪;步骤七,填充石英砂;步骤八,填充天然软木颗粒或合成橡胶颗粒,本发明通过在土壤表面铺设防水卷材,起到防止雨水与土壤接触的作用,可以节省大量的碎石、石粉、水泥等建筑材料,大大降低基础建设成本,节省工期,减少开山炸石,有利于生态环境的保护,符合国家环保产业发展政策。
Description
技术领域
本发明涉及一种运动场地的施工方法,具体涉及一种新型人造草坪运动场的施工方法。
背景技术
足球,有“世界第一运动”的美誉,是全球最具影响力的单项体育运动。在我国,足球已越来越受国人喜爱,从事足球运动的人数每年成倍增加。足球运动离不开足球场地,足球场主要分为天然草足球场和人造草坪足球场,天然草足球场因维护成本高,不能满足高频率的使用,于是,大家把目标集中在了人造草足球场的建设上。
现有人造草坪足球场大多是直接把人造草坪铺在水泥或沥青基础上,这种做法,存在四大弊端,一是基础建设成本过高、工期太长,特别是国家号召利用荒山荒地、绿化用地建设球场以后,这种做法,导致农地、林地、绿化地复耕难,成本高;二是场地太硬,容易造成伤害,包括运动损伤或摔伤;三是排水不畅,场地容易积水,影响训练和比赛;四是暴雨时雨水只能在草坪表面排,填充颗粒容易被水冲走,导致颗粒流失,场地不平整。
近几年,有部分场地采取铺设化学交联聚乙烯(XPE)发泡材料以增加弹性,但同样也存在上面的四大弊端,此外这种材料太软,球员容易疲劳,启动慢,追球追不上,永久变形大,回弹差,场地会高低不平,容易导致球员受伤。
发明内容
本发明针对现有技术中的不足提供一种新型人造草坪运动场的施工方法。
本发明通过以下技术方案实现该目的:
一种新型人造草坪运动场的施工方法,该施工方法包括以下步骤:
(1)平整场地,将原有土地上的植物及杂物清除;
(2)以场地中线的中点作为标高点,以标高点为基准,朝向四周设有坡度,形成中间高、
四周低的龟背式排水结构;
(3)素土层碾压,采用10-15吨带震动压路机反复碾压密实,防止土层沉降不均匀;
(4)铺设防水卷材,在平整压实后的土壤表面铺设一层防水卷材;
(5)铺设多功能基层垫,所述多功能基层垫平铺在防水卷材的表面;
(6)铺设人造草坪,所述人造草坪平铺在多功能基层垫的表面;
(7)填充石英砂,用专业机械或人工在人造草坪的表面填充石英砂;
(8)填充缓冲颗粒,在石英砂的表面填充天然软木颗粒或合成橡胶颗粒。
其中,在步骤(2)中,所述坡度为千分之五。
其中,在步骤(3)中,碾压后的素土层的密实度达到95%及以上。
作为优选的,在步骤(4)中,所述防水卷材为防水布、防水薄膜、防水油毡、防渗土工膜或起到防水、防渗作用的任一一种的卷材。
作为优选的,在步骤(4)中,铺设所述防水卷材时,径向每卷按20-30cm搭接,在每卷边缘2-5cm处,每隔1m用长钉固定在土壤上。
作为优选的,在步骤(5)中,所述多功能基层垫包括缓冲减震层及设置于缓冲减震层上的排水通孔。
作为优选的,在步骤(6)中,先用专用草坪胶和连接布将每卷草坪粘结在一起,这样人造草坪就形成了一个整体,不会有凸起、分开等现象,便于运动员在上面跑动和球的滚动。
作为优选的,在步骤(7)中,石英砂的粒径为0.5-1.5mm,填充量为20-25kg/m2。
作为优选的,在步骤(8)中,天然软木颗粒的填充量为3-5kg/m2,合成橡胶颗粒的填充量为7-9kg/m2。
相对于现有技术,本发明的有益效果为:
1、本发明通过在土壤表面铺设防水卷材,起到防止雨水与土壤接触的作用,可以节省大量的碎石、石粉、水泥等建筑材料,大大降低基础建设成本,节省工期,减少开山炸石,有利于生态环境的保护,符合国家环保产业发展政策。
2、本发明通过铺设多功能基层垫,起到很好的缓冲减震和排水作用,大大提高场地的舒适性和使用率。
具体实施方式
以下结合具体实施例对本发明进行详细描述。
实施例1。
本实施例提供一种新型人造草坪运动场的施工方法,具体施工步骤包括如下:
(1)将原有土地上植物及杂物清除,平整场地;
(2)以场地中线的中点作为标高点,以标高点为基准,朝向四周设有千分之五的坡度,形成中间高、四周低的龟背式排水结构,类似龟背,利于排水,足球场一般采用龟背式排水。
(3)素土层碾压,采用10-15吨带震动压路机反复碾压密实,使得密实度达到95%或以上,防止土层沉降不均匀;
(4)铺设防水卷材,在平整压实后的土壤表面铺设一层防水卷材,防水卷材可以是防水布、防水油毡、防水薄膜等,起到阻止雨水与土壤接触的作用,铺设防水卷材时,径向每卷按20-30cm搭接,在每卷边缘2-5cm处,每隔1m用长钉固定在土壤上,以免下一到工序铺设时移动,接缝处用防水不干胶布等材料粘帖,防止雨水渗透至土壤,避免造成土壤软化或泥浆化,造成基础不稳定。经实验证明,这种做法,完全可以代替原有水泥或沥青面层做法。人造草使用年限一般是6-8年,防水卷材可根据足球场使用年限选择不同质量的产品。
(5)铺设多功能基层垫,所述多功能基层垫平铺在防水卷材的表面,多功能基层垫包括一种缓冲减震层及设置于缓冲减震层上的排水通孔,具有缓冲减震、排水等功能,可以有效解决场地硬,排水不畅等问题,如意大利马克菲尔多功能基层垫,这种垫经国际足联指定实验室Labosport检测,其冲击吸收高达47%,垂直渗透在3000mm/h以上,水平排水在0.483L/s.m,使用寿命可达25年。
(6)铺设人造草坪,所述人造草坪平铺在多功能基层垫的表面,在铺设之前,应先用专用草坪胶和连接布将每卷草坪粘结在一起,形成一个整体,使得人造草坪边缘能够进行相互牵引,不易翻折翘起,从而在使用的过程中不易拌到行人,并且场地也更加的美观。
(7)填充石英砂,用专业机械或人工在人造草坪的表面填充石英砂,石英砂的粒径为0.5-1.5mm,填充量为20-25kg/m2。
(8)填充缓冲颗粒,在石英砂的表面填充天然软木颗粒或合成橡胶颗粒,天然软木颗粒的填充量为3-5kg/m2,合成橡胶颗粒的填充量为7-9kg/m2。
本发明中的新型人造草坪运动场的施工方法,除了能用于足球场外,还可以用作其他人造草坪铺设的场地上,如曲棍球场、棒球场、橄榄球场、休闲广场、绿化等。
本发明通过在土壤表面铺设防水卷材,起到防止雨水与土壤接触的作用,可以节省大量的碎石、石粉、水泥等建筑材料,大大降低基础建设成本,节省工期,减少开山炸石,有利于生态环境的保护,符合国家环保产业发展政策。通过铺设多功能基层垫,起到很好的缓冲减震和排水作用,大大提高场地的舒适性和使用率。
所属领域的普通技术人员应当理解:以上任何实施例的讨论仅为示例性的,并非旨在暗示本公开的范围(包括权利要求)被限于这些例子;在本发明的思路下,以上实施例或者不同实施例中的技术特征之间也可以进行组合,并存在如上所述的本发明的不同方面的许多其它变化,为了简明它们没有在细节中提供。因此,凡在本发明的精神和原则之内,所做的任何省略、修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (9)
1.一种新型人造草坪运动场的施工方法,其特征是,该施工方法包括以下步骤:
(1)平整场地,将原有土地上的植物及杂物清除;
(2)以场地中线的中点作为标高点,以标高点为基准,朝向四周设有坡度,形成中间高、四周低的龟背式排水结构;
(3)素土层碾压,采用10-15吨带震动压路机反复碾压密实,防止土层沉降不均匀;
(4)铺设防水卷材,在平整压实后的土壤表面铺设一层防水卷材;
(5)铺设多功能基层垫,所述多功能基层垫平铺在防水卷材的表面;
(6)铺设人造草坪,所述人造草坪平铺在多功能基层垫的表面;
(7)填充石英砂,用专业机械或人工在人造草坪的表面填充石英砂;
(8)填充缓冲颗粒,在石英砂的表面填充天然软木颗粒或合成橡胶颗粒。
2.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(2)中,所述坡度为千分之五。
3.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(3)中,碾压后的素土层的密实度达到95%及以上。
4.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(4)中,所述防水卷材为防水布、防水薄膜、防水油毡或防渗土工膜中的任一一种。
5.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(4)中,铺设所述防水卷材时,径向每卷按20-30cm搭接,在每卷边缘2-5cm处,每隔1m用长钉固定在土壤上。
6.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(5)中,所述多功能基层垫包括一种缓冲减震层及设置于缓冲减震层上的排水通孔。
7.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(6)中,先用专用草坪胶和连接布将每卷草坪粘结在一起,形成一个整体,再铺设人造草坪。
8.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(7)中,石英砂的粒径为0.5-1.5mm,填充量为20-25kg/m2。
9.如权利要求1所述的新型人造草坪运动场的施工方法,其特征是:在步骤(8)中,天然软木颗粒的填充量为3-5kg/m2,合成橡胶颗粒的填充量为7-9kg/m2。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810929269.6A CN108914746A (zh) | 2018-08-15 | 2018-08-15 | 一种新型人造草坪运动场的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810929269.6A CN108914746A (zh) | 2018-08-15 | 2018-08-15 | 一种新型人造草坪运动场的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108914746A true CN108914746A (zh) | 2018-11-30 |
Family
ID=64404933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810929269.6A Pending CN108914746A (zh) | 2018-08-15 | 2018-08-15 | 一种新型人造草坪运动场的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108914746A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110804923A (zh) * | 2019-10-25 | 2020-02-18 | 杭州宝力体育设施工程有限公司 | 一种硅pu塑胶球场施工方法 |
CN111305482A (zh) * | 2020-03-13 | 2020-06-19 | 贵州建工第五建筑工程有限责任公司 | 一种能回收雨水的建筑屋面海绵式运动场及其施工方法 |
CN113605173A (zh) * | 2021-08-09 | 2021-11-05 | 广东亚设体育产业有限公司 | 一种海绵足球场整体解决方法 |
CN114145188A (zh) * | 2021-11-17 | 2022-03-08 | 广州星卫草业股份有限公司 | 一种把普通绿地改造成天然草坪足球场的施工方法 |
CN114375772A (zh) * | 2021-12-10 | 2022-04-22 | 海口绿之海生态农业科技有限公司 | 一种运动场草坪的模块化建造方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1986969A (zh) * | 2005-12-23 | 2007-06-27 | 曼顿有限公司 | 合成草皮地面和铺设该合成草皮地面的方法 |
KR20120047480A (ko) * | 2010-11-04 | 2012-05-14 | (주) 테크원 | 잔디 구조체 |
US20170232487A1 (en) * | 2012-02-03 | 2017-08-17 | Lite Earth Llc | Manufactured composite having synthetic vegetation and impermeable geomembrane, and capping system using same |
CN107190616A (zh) * | 2017-04-26 | 2017-09-22 | 南京汉威体育工程实业有限公司 | 塑胶运动场地施工方法 |
CN108360333A (zh) * | 2018-02-02 | 2018-08-03 | 广州傲胜人造草股份有限公司 | 一种颗粒填充物及一种人造草坪 |
-
2018
- 2018-08-15 CN CN201810929269.6A patent/CN108914746A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1986969A (zh) * | 2005-12-23 | 2007-06-27 | 曼顿有限公司 | 合成草皮地面和铺设该合成草皮地面的方法 |
US20070148398A1 (en) * | 2005-12-23 | 2007-06-28 | Mondo S.P.A. | Synthetic-grass flooring and method for laying same |
KR20120047480A (ko) * | 2010-11-04 | 2012-05-14 | (주) 테크원 | 잔디 구조체 |
US20170232487A1 (en) * | 2012-02-03 | 2017-08-17 | Lite Earth Llc | Manufactured composite having synthetic vegetation and impermeable geomembrane, and capping system using same |
CN107190616A (zh) * | 2017-04-26 | 2017-09-22 | 南京汉威体育工程实业有限公司 | 塑胶运动场地施工方法 |
CN108360333A (zh) * | 2018-02-02 | 2018-08-03 | 广州傲胜人造草股份有限公司 | 一种颗粒填充物及一种人造草坪 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110804923A (zh) * | 2019-10-25 | 2020-02-18 | 杭州宝力体育设施工程有限公司 | 一种硅pu塑胶球场施工方法 |
CN111305482A (zh) * | 2020-03-13 | 2020-06-19 | 贵州建工第五建筑工程有限责任公司 | 一种能回收雨水的建筑屋面海绵式运动场及其施工方法 |
CN111305482B (zh) * | 2020-03-13 | 2021-07-20 | 贵州建工集团第五建筑工程有限责任公司 | 一种能回收雨水的建筑屋面海绵式运动场及其施工方法 |
CN113605173A (zh) * | 2021-08-09 | 2021-11-05 | 广东亚设体育产业有限公司 | 一种海绵足球场整体解决方法 |
CN114145188A (zh) * | 2021-11-17 | 2022-03-08 | 广州星卫草业股份有限公司 | 一种把普通绿地改造成天然草坪足球场的施工方法 |
CN114145188B (zh) * | 2021-11-17 | 2023-10-13 | 广州星卫草业股份有限公司 | 一种把普通绿地改造成天然草坪足球场的施工方法 |
CN114375772A (zh) * | 2021-12-10 | 2022-04-22 | 海口绿之海生态农业科技有限公司 | 一种运动场草坪的模块化建造方法 |
CN114375772B (zh) * | 2021-12-10 | 2024-04-26 | 武汉易知鸟科技有限公司 | 一种运动场草坪的模块化建造方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108914746A (zh) | 一种新型人造草坪运动场的施工方法 | |
US4501420A (en) | Playing surfaces sports | |
CA2639586A1 (en) | Method for producing synthetic turfs | |
KR20140038961A (ko) | 스포츠 경기장의 스포츠 표면용 기재를 형성하는 방법, 상기 기재 및 상기 기재를 구비한 스포츠 경기장 | |
CN107938954A (zh) | 一种种植屋面耐根穿刺复合防水系统 | |
CN109056459A (zh) | 用于人造草坪运动场地的软木填充颗粒及其制备方法 | |
CN104499397A (zh) | 一种基于协调路基路面变形的沥青路面结构 | |
CN204589746U (zh) | 一种适用于吹填软土地区重载交通条件的复合路面结构 | |
KR100497253B1 (ko) | 폐타이어, 폐우레탄 컬러 고무칩을 이용한 투수성 탄성포장재 | |
CN205839512U (zh) | 一种适用于重交通的保水降温沥青路面结构 | |
JP2009024460A (ja) | 人工芝下地用路盤及びその造成方法 | |
CN208701449U (zh) | 一种新型的易施工的环保型高回弹聚氨酯跑道 | |
CN207405431U (zh) | 一种生态环保的绿化分隔带 | |
CN207619767U (zh) | 一种适用于半刚性基层的抗裂型路面结构 | |
CN207159728U (zh) | 一种抗裂高强度公路路面 | |
CN206752248U (zh) | 一种透气型塑胶跑道 | |
KR200444169Y1 (ko) | 인조잔디 시공구조 | |
WO1994004755A1 (en) | Recreational surface | |
WO2005002323A1 (en) | Grass growing superstrate and methods of use | |
CN204139023U (zh) | 与合成材料制成的拼装式塑料地板结合使用的人造草系统 | |
CN207003166U (zh) | 公路路面结构和路面 | |
KR101031997B1 (ko) | 운동장의 인조잔디 포설방법 및 포설구조 | |
CN115058940B (zh) | 一种长效保湿型红土运动场建造方法 | |
CN213836152U (zh) | 一种球场8mm硅pu面层 | |
CN207047647U (zh) | 一种塑胶跑道 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181130 |
|
RJ01 | Rejection of invention patent application after publication |