CN108829055B - A kind of steel mill's raw material scheduled production method - Google Patents

A kind of steel mill's raw material scheduled production method Download PDF

Info

Publication number
CN108829055B
CN108829055B CN201810576772.8A CN201810576772A CN108829055B CN 108829055 B CN108829055 B CN 108829055B CN 201810576772 A CN201810576772 A CN 201810576772A CN 108829055 B CN108829055 B CN 108829055B
Authority
CN
China
Prior art keywords
module
heap
raw material
expect
request
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810576772.8A
Other languages
Chinese (zh)
Other versions
CN108829055A (en
Inventor
徐林伟
何洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CISDI Technology Research Center Co Ltd
Original Assignee
CISDI Technology Research Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CISDI Technology Research Center Co Ltd filed Critical CISDI Technology Research Center Co Ltd
Priority to CN201810576772.8A priority Critical patent/CN108829055B/en
Publication of CN108829055A publication Critical patent/CN108829055A/en
Application granted granted Critical
Publication of CN108829055B publication Critical patent/CN108829055B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/4189Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by the transport system
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The present invention provides a kind of steel mill's raw material scheduled production method, include: S1: end module, which receives heap, will expect that requesting and control stacker device reaches heap module, scheduler module controls end reclaimer device, sealing-tape machine route, stacker device and unloads raw material to the heap module, heap module windrow finishes, and stacker device stops operation;S2: heap module, which receives slot, will expect to request, and scheduler module controls heap module reclaimer device and reaches the heap module, start sealing-tape machine route transferring raw material to corresponding channel mould block, channel mould block feeding finishes, and heap module reclaimer device stops operation;Instead of application of the manual decision in steel mill's raw material scheduled production production procedure, improve automation, the information system management level of steel mill's scheduled production, and by heap module and channel mould block two-level cache, solve the problems, such as that raw material input and consumption of raw materials scheduled production process are cumbersome and inconvenient in management.

Description

A kind of steel mill's raw material scheduled production method
Technical field
The present invention relates to industrial control fields, more particularly to a kind of steel mill's raw material scheduled production method.
Background technique
It is receiving, storage, working process and mixing Ferrous Metallurgy raw material and fuel that iron and steel enterprise's raw material system, which is one, Place, have the function of storing raw material, process raw material, ore matching and mixing.Its system job process is complicated, and each system is mutual The influence factor of work compound operation is more, especially when each production requirement such as material kind, production capacity, material proportion changes When, decision-making level is difficult accurately to make effective embodiment of reply system change.Traditional mode of production mode artificial judgment decision specific gravity It is larger, unnecessary loss caused by easily occurring because of factors such as post work experience deficiency, maloperations.
Summary of the invention
In view of the foregoing deficiencies of prior art, the purpose of the present invention is to provide a kind of steel mill's raw material scheduled production method, It is not easy to management for solving the problem of in artificial scheduled production in the prior art that manual decision's error rate is higher, improves steel mill's original Expect the automation and information system management level of scheduled production, and then improve production efficiency, guarantees safe production.
In order to achieve the above objects and other related objects, the present invention provides a kind of steel mill's raw material scheduled production method, comprising:
S1: end module, which receives heap, will expect that requesting and control stacker device reaches heap module, and scheduler module control end takes Equipment, sealing-tape machine route, stacker device unloading raw material are expected to the heap module, and heap module windrow finishes, and stacker device stops making Industry;
S2: heap module, which receives slot, will expect to request, and scheduler module controls heap module reclaimer device and reaches the heap module, open Sealing-tape machine route transferring raw material is moved to corresponding channel mould block, channel mould block feeding finishes, and heap module reclaimer device stops operation.
It optionally, further include S21, S21 specifically: when raw material is lower than channel mould block position in detection slot module, channel mould block Issuing slot to heap module by scheduler module will expect to request.
It optionally, further include S3, S3 specifically: when detecting heap module Central Plains material lower than heap mould block position, heap module is logical Crossing scheduler module will expect to request to end module sending heap.
Optionally, S21 further includes S211, S211 specifically: when scheduler module, which receives slot, to expect request, is judged whether There are available heap module and heap module reclaimer device, judges that issuing slot will expect whether the channel mould block position of request is minimum, judgement Whether urgent channel mould block is not present, to expect to request if so then execute slot, if otherwise finishing will expect to request.
Optionally, S21 further includes S212, S212 specifically: when request will be expected by issuing slot, forbids residue to store of the same race The channel mould block of class raw material, which issues slot, will expect to request.
Optionally, S21 further includes S213, S213 specifically: judge that slot will expect the priority of request, if priority is high, Heap module reclaimer device and sealing-tape machine route are reserved, if priority is low, finishing will expect to request.
Optionally, S3 further includes S31, S31 specifically: judges that issuing heap with the heap module of type raw material without storage will expect to ask It asks, judges whether there is available end module and stacker device, judge whether route can be used, to expect to ask if so then execute heap It asks, if otherwise terminating heap will expect to request.
Optionally, S3 further includes S32, S32 specifically: judges that heap will expect that the priority of request is reserved if priority is high Stacker device, if priority is low, terminating heap will expect to request.
Optionally, S3 further includes S33, S33 specifically: when stacker device is run to heap module and unloads raw material for heap module When, this stacker device and this heap module are labeled as down state;When stacker device and windrow module complete unloading raw material When, this stacker device and this heap module are labeled as available mode.
Optionally, end module includes principal dock, railway, coal wharf, sub-code head.
As described above, steel mill's raw material product plan of the invention, has the advantages that
1, the application instead of manual decision in steel mill's raw material scheduled production production procedure, improves the automatic of steel mill's scheduled production Change, information system management level;
2, it by heap module and channel mould block two-level cache, solves raw material input and consumption of raw materials scheduled production process is cumbersome and inconvenient In management the problem of;
3, be conducive to manage the input of steel mill's raw material and consumption, prevent raw material accumulation or insufficient raw material from influencing daily production It happens;
4, production efficiency and management level are improved.
Detailed description of the invention
Fig. 1 is shown as the flow diagram of S1 in steel mill's raw material scheduled production method of the embodiment of the present invention.
Fig. 2 is shown as the flow diagram of S2 in steel mill's raw material scheduled production method of the embodiment of the present invention.
Fig. 3 is shown as the flow diagram of S3 in steel mill's raw material scheduled production method of the embodiment of the present invention.
Fig. 4 is shown as the flow diagram of S21 in steel mill's raw material scheduled production method of the embodiment of the present invention.
Specific embodiment
Illustrate embodiments of the present invention below by way of specific specific example, those skilled in the art can be by this specification Other advantages and efficacy of the present invention can be easily understood for disclosed content.The present invention can also pass through in addition different specific realities The mode of applying is embodied or practiced, the various details in this specification can also based on different viewpoints and application, without departing from Various modifications or alterations are carried out under spirit of the invention.
It please refers to Fig.1 to Fig.4.It should be noted that diagram provided in the present embodiment only illustrates this in a schematic way The basic conception of invention, only shown in schema then with related component in the present invention rather than package count when according to actual implementation Mesh, shape and size are drawn, when actual implementation kenel, quantity and the ratio of each component can arbitrarily change for one kind, and its Assembly layout kenel may also be increasingly complex.This specification structure depicted in this specification institute accompanying drawings, ratio, size etc., only to Cooperate the revealed content of specification, so that those skilled in the art understands and reads, being not intended to limit the invention can be real The qualifications applied, therefore do not have technical essential meaning, the tune of the modification of any structure, the change of proportionate relationship or size It is whole, in the case where not influencing the effect of present invention can be generated and the purpose that can reach, it should all still fall in disclosed skill Art content obtains in the range of capable of covering.Meanwhile in this specification it is cited as "upper", "lower", "left", "right", " centre " and The term of " one " etc. is merely convenient to being illustrated for narration, rather than to limit the scope of the invention, relativeness It is altered or modified, under the content of no substantial changes in technology, when being also considered as the enforceable scope of the present invention.
Fig. 1 and Fig. 2 are please referred to, in order to achieve the above objects and other related objects, the present invention provides a kind of steel mill's raw material row Production method, comprising:
S1: end module, which receives heap, will expect that requesting and control stacker device reaches heap module, and scheduler module control end takes Equipment, sealing-tape machine route, stacker device unloading raw material are expected to the heap module, and heap module windrow finishes, and stacker device stops making Industry;
S2: heap module, which receives slot, will expect to request, and scheduler module controls heap module reclaimer device and reaches the heap module, open Sealing-tape machine route transferring raw material is moved to corresponding channel mould block, channel mould block feeding finishes, and heap module reclaimer device stops operation, we Case is by being arranged heap module and channel mould block progress " two-level cache " and " two-stage regulation " in end module and between being used for, on the one hand Prevent from the raw material of end module from inputting directly to export to user, bring management is inconvenient, on the other hand, by scheduling heap module and Channel mould block is convenient for automatic management, and when exporting increase, feedback regulation channel mould block, which issues slot to heap module, will expect request and heap Module, which issues heap to end module, will expect to request, and reduce effect of the manual decision in steel mill's raw material scheduled production, improve letter Breathization management level, improves production efficiency, avoids because of the influence that manual decision makes mistakes to production procedure.
It preferably, further include S21, S21 specifically: when raw material is lower than channel mould block position in detection slot module, channel mould block Issuing slot to heap module by scheduler module will expect to request;Steel mill's raw material scheduled production method further includes S3, S3 specifically: works as inspection When surveying heap module Central Plains material lower than heap mould block position, heap module, which issues heap to end module by scheduler module, will expect to request;It is logical It crosses and certain request threshold value (heap mould block position perhaps channel mould block position) is set when heap module or slot to heap module and channel mould block Raw material is lower than request threshold value in module, then heap module or channel mould block issue heap respectively will expect that request or slot will expect to request, just The quantity of raw material is cached in feedback control, timely reactor module and channel mould block.
Since the type of steel mill's raw material is more, including but not limited to coking coal, thermal coal, injection coal, anthracite, pelletizing fine ore It needs to supply different types of raw material and transport is managed, please refer to figure under actual condition demand with sintering fine ore 4, S21 further include S211, S211 specifically: when scheduler module, which receives slot, to expect request, judges whether there is available heap mould Block and heap module reclaimer device judge that issuing slot will expect whether the channel mould block position of request is minimum, judge whether that there is no tight Anxious channel mould block will expect to request if so then execute slot, if otherwise finishing will expect to request;
Further, S21 further includes S212, S212 specifically: when request will be expected by issuing slot, residue is forbidden to store together The channel mould block of type raw material, which issues slot, will expect to request, and when the lack of material of a certain type, when request will be expected by issuing slot, illustrate slot The raw material of module and the user demand type, forbidding the remaining channel mould block for storing same type raw material to issue slot will expect to request, It prevents same type raw material regulation and the generation of the case where oversupply occurs, and ensure that issuing slot in this raw material will expect to request, Other different raw material, which issues slot, will expect have route available when request;
Further, S21 further includes S213, S213 specifically: judges that slot will expect the priority of request, if priority Height then reserves heap module reclaimer device and sealing-tape machine route, if priority is low, finishing will expect to request, and under normal circumstances, uses Family needs preferentially to ensure the demand to be expected of blast furnace, user exports preferential outward in stockyard in the highest priority to be expected of blast furnace Grade is higher than the priority inwardly inputted.
Referring to Fig. 3, S3 further includes S31, S31 specifically: judge that issuing heap with the heap module of type raw material without storage wants Material request, judges whether there is available end module and stacker device, judges whether route can be used, to expect if so then execute heap Request, if otherwise terminating heap will expect to request;
Further, S3 further includes S32, S32 specifically: judges that heap will expect the priority of request, if priority is high, in advance About stacker device, if priority is low, terminating heap will expect to request;
Further, S3 further includes S33, S33 specifically: when stacker device is run to heap module and is unloaded for heap module When raw material, this stacker device and this heap module are labeled as down state;When stacker device and windrow module complete unloading When raw material, this stacker device and this heap module are labeled as available mode.
Detailed, end module includes principal dock, railway, coal wharf, sub-code head.
The above-described embodiments merely illustrate the principles and effects of the present invention, and is not intended to limit the present invention.It is any ripe The personage for knowing this technology all without departing from the spirit and scope of the present invention, carries out modifications and changes to above-described embodiment.Cause This, institute is complete without departing from the spirit and technical ideas disclosed in the present invention by those of ordinary skill in the art such as At all equivalent modifications or change, should be covered by the claims of the present invention.

Claims (7)

1. a kind of steel mill's raw material scheduled production method characterized by comprising
S1: end module, which receives heap, will expect that requesting and control stacker device reaches heap module, and scheduler module control end feeding is set Standby, sealing-tape machine route, stacker device unloading raw material are to the heap module, and heap module windrow finishes, and stacker device stops operation;
S2: heap module, which receives slot, will expect to request, and scheduler module controls heap module reclaimer device and reaches the heap module, start glue Band machine route transferring raw material is to corresponding channel mould block, and channel mould block feeding finishes, and heap module reclaimer device stops operation;
S21: when raw material is lower than channel mould block position in detection slot module, channel mould block issues slot to heap module by scheduler module and wants Material request;
S211: it when scheduler module, which receives slot, to expect request, judges whether there is available heap module and heap module feeding is set It is standby, judge that issuing slot will expect whether the channel mould block position of request is minimum, judge whether that urgent channel mould block is not present, if so then execute Slot will expect to request, if otherwise finishing will expect to request;
S3: when detecting heap module Central Plains material lower than heap mould block position, heap module issues heap to end module by scheduler module Expect to request.
2. steel mill's raw material scheduled production method according to claim 1, it is characterised in that: S21 further includes S212, and S212 is specific Are as follows: when request will be expected by issuing slot, forbidding the remaining channel mould block for storing same type raw material to issue slot will expect to request.
3. steel mill's raw material scheduled production method according to claim 2, it is characterised in that: S21 further includes S213, and S213 is specific Are as follows: judge that slot will expect that the priority of request reserves heap module reclaimer device and sealing-tape machine route if priority is high, if preferentially Grade is low, then finishing will expect to request.
4. steel mill's raw material scheduled production method according to claim 1, it is characterised in that: S3 further includes S31, S31 specifically: is sentenced It is disconnected to expect to request with the heap module sending heap of type raw material without storage, it judges whether there is available end module and windrow is set It is standby, judge whether route can be used, to expect to request if so then execute heap, if otherwise terminating heap will expect to request.
5. steel mill's raw material scheduled production method according to claim 4, it is characterised in that: S3 further includes S32, S32 specifically: is sentenced Disconnected heap will expect that the priority of request reserves stacker device if priority is high, if priority is low, terminating heap will expect to request.
6. steel mill's raw material scheduled production method according to claim 5, it is characterised in that: S3 further includes S33, S33 specifically: when When stacker device runs to heap module and unloads raw material for heap module, this stacker device and this heap module are labeled as unavailable shape State;When stacker device and windrow module complete unloading raw material, this stacker device and this heap module are labeled as available mode.
7. steel mill's raw material scheduled production method according to claim 1, it is characterised in that: end module include principal dock, railway, Coal wharf, sub-code head.
CN201810576772.8A 2018-06-05 2018-06-05 A kind of steel mill's raw material scheduled production method Active CN108829055B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810576772.8A CN108829055B (en) 2018-06-05 2018-06-05 A kind of steel mill's raw material scheduled production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810576772.8A CN108829055B (en) 2018-06-05 2018-06-05 A kind of steel mill's raw material scheduled production method

Publications (2)

Publication Number Publication Date
CN108829055A CN108829055A (en) 2018-11-16
CN108829055B true CN108829055B (en) 2019-04-05

Family

ID=64144233

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810576772.8A Active CN108829055B (en) 2018-06-05 2018-06-05 A kind of steel mill's raw material scheduled production method

Country Status (1)

Country Link
CN (1) CN108829055B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113673173B (en) * 2021-09-07 2024-02-27 中冶赛迪信息技术(重庆)有限公司 Selection recommendation method of iron and steel raw material production flow and iron and steel raw material production system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006055143A2 (en) * 2004-11-19 2006-05-26 Advanced Micro Devices, Inc. Scheduling amhs pickup and delivery ahead of schedule
CN101694576A (en) * 2009-10-26 2010-04-14 马鞍山钢铁股份有限公司 Stockyard operation dynamic display and real-time management system and management method thereof
CN102662363A (en) * 2012-04-18 2012-09-12 中冶南方工程技术有限公司 Remote automatic control system and method for bucket wheel stacker reclaimers
WO2012123526A1 (en) * 2011-03-16 2012-09-20 Siemens Aktiengesellschaft Method for production scheduling in small-scale rolling mill and system thereof
CN107578154A (en) * 2017-08-25 2018-01-12 武汉理工大学 A kind of method for optimizing scheduling of stacker-reclaimer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006055143A2 (en) * 2004-11-19 2006-05-26 Advanced Micro Devices, Inc. Scheduling amhs pickup and delivery ahead of schedule
CN101694576A (en) * 2009-10-26 2010-04-14 马鞍山钢铁股份有限公司 Stockyard operation dynamic display and real-time management system and management method thereof
WO2012123526A1 (en) * 2011-03-16 2012-09-20 Siemens Aktiengesellschaft Method for production scheduling in small-scale rolling mill and system thereof
CN102662363A (en) * 2012-04-18 2012-09-12 中冶南方工程技术有限公司 Remote automatic control system and method for bucket wheel stacker reclaimers
CN107578154A (en) * 2017-08-25 2018-01-12 武汉理工大学 A kind of method for optimizing scheduling of stacker-reclaimer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
原料场智能混匀堆积作业指导系统的研究与实现;马怡;《冶金自动化》;20160531;第40卷(第3期);第1-3节

Also Published As

Publication number Publication date
CN108829055A (en) 2018-11-16

Similar Documents

Publication Publication Date Title
CN102541036B (en) Intelligent fire coal scheduling system for thermal power plant
CN105731012A (en) Full-automatic battery stack dismounting and conveying system for joining storage with production
CN108829055B (en) A kind of steel mill's raw material scheduled production method
CN106148680A (en) A kind of sintering deposit Automatic Burden Control method and control system
CN111522316A (en) Optimal dynamic selection method for belt conveying process of stock yard
CN110942203B (en) Automatic container terminal AGV path optimization method
CN103014204A (en) Blast furnace burden distribution optimization method based on mode recognition and expert system as well as system
CN104401678B (en) Full-automatic intelligent Work transfer method
CN106125554A (en) A kind of continuous batching feed bin charging Operating Ratio automatic adjusting method
CN103752378A (en) Full-automatic ball feeding system
CN112573221A (en) Control system and method for intelligent belt transmission flow of stock yard
CN211282950U (en) Blast furnace scrap steel feeding and charging system
CN103143295B (en) Lime briquetting production line
CN208062192U (en) A kind of Full-automatic lithium battery battery automatic sprigging device
CN104950841A (en) Synergic scheduling method of large-scale intelligent ammeter automatic verification
Wang et al. The heuristic preemptive dispatching rule using stocker for conveyor-based material handling system of 450-mm wafer fabrication
CN106383505A (en) Whole-process automatic operating method with closed-loop application
CN104599076A (en) Steel production solid waste recycling scheduling system and method
CN106185138B (en) A kind of closed silicon core automatic access device
CN205132564U (en) Seal stock ground with store and homogenization function
CN105438819B (en) One kind going out hold cargo object and organizes plate method and group plate system automatically
CN110857837B (en) Multi-blast-furnace-based intelligent control method for raw fuel delivery logistics
CN202704356U (en) Intelligent physical distribution loading and unloading transport system
CN209008952U (en) Abandoned catalyst in direct synthesis methylchlorosilane recovery system
CN113807620A (en) Intelligent operation method and system for raw material conveying

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant