CN108767749A - Control cable support and control cable laying system - Google Patents

Control cable support and control cable laying system Download PDF

Info

Publication number
CN108767749A
CN108767749A CN201811028233.7A CN201811028233A CN108767749A CN 108767749 A CN108767749 A CN 108767749A CN 201811028233 A CN201811028233 A CN 201811028233A CN 108767749 A CN108767749 A CN 108767749A
Authority
CN
China
Prior art keywords
cable
side plate
testing bridge
mounting hole
control cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811028233.7A
Other languages
Chinese (zh)
Inventor
孙玉彤
陈晓彬
黎高程
杨忠亮
李晓飚
陈洁生
连楷敏
黄华吉
陈钧孚
邓小玉
王雪
朱颖
陈贤彬
黄勇东
卢丹
谢育斌
刘耿彬
陈钦彬
王喜东
王跃新
谢惠藩
王波
王一波
黄锐坤
王琪
王锃
黄明辉
李海涛
邢文忠
孙旭
郭少玲
李暖群
陈泽星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Co ltd
ZHUHAI ELECTRIC POWER DESIGN INSTITUTE CO LTD
Guangdong Power Grid Co Ltd
Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd
Grid Planning Research Center of Guangdong Power Grid Co Ltd
Original Assignee
Shenzhen Power Supply Co ltd
ZHUHAI ELECTRIC POWER DESIGN INSTITUTE CO LTD
Guangdong Power Grid Co Ltd
Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd
Grid Planning Research Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Co ltd, ZHUHAI ELECTRIC POWER DESIGN INSTITUTE CO LTD, Guangdong Power Grid Co Ltd, Jieyang Power Supply Bureau of Guangdong Power Grid Co Ltd, Grid Planning Research Center of Guangdong Power Grid Co Ltd filed Critical Shenzhen Power Supply Co ltd
Priority to CN201811028233.7A priority Critical patent/CN108767749A/en
Publication of CN108767749A publication Critical patent/CN108767749A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention relates to the technical field of cabling engineering devices, in particular to a control cable bracket and a control cable laying system. A control cable support comprising: the cable bridge comprises a cable bridge body, a first connecting part, a second connecting part and a separator; the cable bridge body is provided with a plurality of plugging parts which are uniformly distributed at intervals along the length direction of the cable bridge body, and a plurality of separators are plugged with the plugging parts so as to form a plurality of cable layer laying areas on the cable bridge body; the first connecting portion with the second connecting portion are a plurality of, and are a plurality of first connecting portion with it is a plurality of the second connecting portion evenly distributed be in the both sides of cable testing bridge, so that the cable testing bridge body can be fixed on the installed part. The technical problems that cables at different starting points are mostly laid alternately, are stacked layer by layer and are seriously stacked, and the cables cannot be detached once laid in the prior art are solved.

Description

Control cable bearer and control cable laying system
Technical field
The present invention relates to laying cable engineering device arts, more particularly, to a kind of control cable bearer and control electricity Cable laying system.
Background technology
Protection screen, the observing and controlling of the mechanism case, central console, spacing terminal case and secondary device of electric system primary equipment Screen is required to realize connection by cable, optical cable or cable between failure wave-recording screen, power supply panel etc., to realize above-mentioned connection, according to The difference in building and space is designed with different cable passages, including cable duct, cable shaft, cable interlayer etc., at these The various holders of current supply cable laying are designed in space.
Since existing cable layer portal structure is simple, the sequence of unit in charge of construction's cable laying work is first to proceed through electricity The long cable laying of cable layer carries out stub cable laying again, and long cable is usually the terminal box, convergence control cabinet or mechanism by primary equipment Cable floor below case to protection communication room enters corresponding screen cabinet, and stub cable is usually between primary equipment or secondary device screen cabinet Pass through the connecting cable of cable floor.When carrying out long cable laying, temporal influence is brought in order to reduce replacement cable model, The primary equipment intervening sequences that a kind of long cable of model is related to by current period engineering have usually first laid in unit in charge of construction, then The long cable of another model of laying, and so on.
Present indoor substation is more and more, and the connecting cable between indoor each layer equipment is laid by each layer cable duct To corresponding position, therefore cable duct is designed in each floor plate.These cable ducts can be made due to the limitation of floor construction It is smaller with area, and any holder is used without design in this kind of cable duct at present, cause control cable can not be by starting Point carries out subregion laying, and the cable of different starting points is alternating application mostly, and is layering, accumulates seriously, and cable is once apply Setting can not just remove, and the usable space of cable duct is deactivated cable and largely occupies, and give the reorganization and expansion band of indoor substation Carry out great difficulty.
Invention content
The purpose of the present invention is to provide control cable beareves, to alleviate the electricity of different starting points existing in the prior art Cable is alternating application mostly, and is layering, accumulates serious, cable the technical issues of can not just removing once laying is gone down.
A kind of control cable bearer provided by the invention, including:Cable testing bridge ontology, first connecting portion, second connecting portion And separator;
Multiple plug divisions are provided on the cable testing bridge ontology, multiple plug divisions are along the cable testing bridge ontology Length direction is evenly spaced on, and multiple separators are with the plug division grafting so as to be formed on the cable testing bridge ontology There is multiple cable floor layings area;
The first connecting portion and the second connecting portion are multiple, multiple first connecting portions and multiple described Two interconnecting pieces are evenly distributed on the both sides of the cable testing bridge, so that the cable testing bridge ontology can be fixed on mountings.
Further, the first connecting portion is identical with the structure of the second connecting portion.
Further, the first connecting portion is the first link block, and the first threaded hole is provided on first link block; The second connecting portion is the second link block, and the second threaded hole is provided on second link block.
Further, multiple first connecting portions and multiple second connecting portions are symmetricly set on the cable testing bridge The both sides of ontology.
Further, the plug division includes the first mounting hole, the second mounting hole, the first spliced eye and the second spliced eye;
First mounting hole and second mounting hole are symmetricly set on the both sides of the cable testing bridge ontology, and described One spliced eye and second spliced eye are arranged between first mounting hole and second mounting hole, the separator energy It is enough to coordinate with first mounting hole and second mounting hole across first spliced eye and second spliced eye, it will It is divided into multiple cable floor layings area on the cable testing bridge ontology.
Further, the cable testing bridge ontology includes the first side plate, the second side plate and top plate, first side plate and institute The both sides that the second side plate is symmetricly set on the top plate are stated, are provided with first mounting hole on first side plate, described Second mounting hole is provided on two side plates, first mounting hole and second mounting hole are separately positioned on described first Side plate and the described one end of second side plate far from the top plate, first spliced eye and second spliced eye are arranged described On top plate.
Further, it is provided with the first binding hole on first side plate, the second binding is provided on second side plate Hole;
First binding hole is multiple, and multiple first binding holes are uniformly divided along the extending direction of first side plate Cloth, first binding hole are arranged in first side plate close to the side of the top plate;
Second binding hole is multiple, and multiple second binding holes are uniformly divided along the extending direction of second side plate Cloth, second binding hole are arranged in second side plate close to the side of the top plate;
Multiple first binding holes and multiple second binding holes are arranged in a one-to-one correspondence;
Multiple first binding holes are staggered with multiple first mounting holes.
Further, the separator is subregion spring;
The subregion spring includes U-typed spring body and clamping portion;
The clamping portion is arranged in the open end of the U-typed spring body, and the clamping portion is used for and the plug division It is connected.
Further, the clamping portion includes first connecting rod and second connecting rod, the first connecting rod and the second connecting rod Be separately positioned on the both sides of the open end of the U-typed spring body, and the first connecting rod and the second connecting rod with it is described U-typed spring body is vertically arranged.
A kind of control cable laying system has multiple control cable beareves as described above;
The distribution that multiple control cable beareves are spaced successively, multiple cable laying areas controlled on cable beareves Form the laying track for laying control cable.
A kind of control cable bearer provided by the invention, including:Cable testing bridge ontology, first connecting portion, second connecting portion And separator;Multiple plug divisions are provided on the cable testing bridge ontology, multiple plug divisions are along the cable testing bridge ontology Length direction be evenly spaced on, multiple separators and the plug division grafting are so that shape on the cable testing bridge ontology Area is laid at there are multiple cable floors;The first connecting portion and the second connecting portion are multiple, multiple first connections Portion and multiple second connecting portions are evenly distributed on the both sides of the cable testing bridge, so that the cable testing bridge ontology can be consolidated Determine on mountings.Using above-mentioned scheme, it is provided with multiple plug divisions on cable testing bridge ontology, passes through separator and plug division Cooperation so as to form multiple independent cable floors layings areas on cable testing bridge ontology, while in the both sides of cable testing bridge ontology It is provided with first connecting portion and second connecting portion, the setting of first connecting portion and second connecting portion can make cable testing bridge ontology exist The stability higher connected when on external installation part is set, to alleviate the cable of different starting points existing in the prior art It is alternating application mostly, and is layering, accumulates serious, cable the technical issues of can not just removing once laying is gone down.
A kind of control cable laying system provided by the invention has multiple control cable beareves as described above;It is multiple The distribution that the control cable bearer is spaced successively, multiple cable laying areas controlled on cable beareves are formed for laying Control the laying track of cable.Its advantageous effect generated is identical as the control advantageous effect of cable bearer, repeats no more.
Description of the drawings
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in being described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, other drawings may also be obtained based on these drawings.
Fig. 1 is the vertical view of control cable bearer provided in an embodiment of the present invention;
Fig. 2 is the side view of control cable bearer provided in an embodiment of the present invention;
Fig. 3 is the front view of control cable bearer provided in an embodiment of the present invention;
Fig. 4 is the front view of separator on control cable bearer provided in an embodiment of the present invention;
Fig. 5 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the master of a piece cable of the every layer of laying in area View;
Fig. 6 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays bowing for every layer of area piece cable of laying View;
Fig. 7 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the master of two cables of the every layer of laying in area View;
Fig. 8 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays every layer of area laying different number cable Vertical view;
Fig. 9 is the front view of control cable bearer provided in an embodiment of the present invention being arranged in cable bearer room.
Icon:100- cable testing bridge ontologies;200- first connecting portions;300- second connecting portions;400- separators;110- Side plate;The second side plates of 120-;130- top plates;The first threaded holes of 210-;The second threaded holes of 310-;410- U-typed spring bodies; The clamping portions 420-;The first mounting holes of 111-;112- first binds hole;The first spliced eyes of 131-;The second spliced eyes of 132-.
Specific implementation mode
Technical scheme of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill The every other embodiment that personnel are obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for the description present invention and simplify description, do not indicate or imply the indicated device or element must have a particular orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for description purposes only, and is not understood to indicate or imply relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
Fig. 5 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the master of a piece cable of the every layer of laying in area View;Fig. 6 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the vertical view of a piece cable of the every layer of laying in area Figure;Fig. 7 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the front view of two cables of the every layer of laying in area; Fig. 8 is that the cable floor of control cable bearer provided in an embodiment of the present invention lays the vertical view of the every layer of laying different number cable in area Figure;Fig. 9 is the front view of control cable bearer provided in an embodiment of the present invention being arranged in cable bearer room.As shown in figures 5-9, A kind of control cable bearer provided by the invention, including:Cable testing bridge ontology 100, first connecting portion 200, second connecting portion 300 With separator 400;
Multiple plug divisions are provided on the cable testing bridge ontology 100, multiple plug divisions are along the cable testing bridge sheet The length direction of body 100 is evenly spaced on, and multiple separators 400 are with the plug division grafting so that the cable testing bridge Multiple cable floor layings area is formed on ontology 100;
The first connecting portion 200 and the second connecting portion 300 are multiple, multiple 200 Hes of the first connecting portion Multiple second connecting portions 300 are evenly distributed on the both sides of the cable testing bridge, so that the cable testing bridge ontology 100 can It fixes on mountings.
Wherein, the interval of two adjacent separators 400 can differ, in this way on a cable testing bridge ontology 100 i.e. The cable floor laying area of multiple and different length can be formed, the control of different number is provided in the cable floor laying area of different length Cable, and it is both provided with cable start of installation in each cable floor laying area.
A kind of control cable bearer provided by the invention, including:Cable testing bridge ontology 100, first connecting portion 200, second Interconnecting piece 300 and separator 400;Multiple plug divisions are provided on the cable testing bridge ontology 100, multiple plug divisions are along institute The length direction for stating cable testing bridge ontology 100 is evenly spaced on, multiple separators 400 and the plug division grafting so that Multiple cable floor layings area is formed on the cable testing bridge ontology 100;The first connecting portion 200 and the second connecting portion 300 be multiple, and multiple first connecting portions 200 and multiple second connecting portions 300 are evenly distributed on the cable bridge The both sides of frame, so that the cable testing bridge ontology 100 can be fixed on mountings.Using above-mentioned scheme, cable testing bridge sheet Multiple plug divisions are provided on body 100, by the cooperation of separator 400 and plug division so as to be formed on cable testing bridge ontology 100 Multiple independent cable floors lay areas, while the both sides of cable testing bridge ontology 100 being provided with first connecting portion 200 and second The setting of interconnecting piece 300, first connecting portion 200 and second connecting portion 300 can be such that cable testing bridge ontology 100 is being arranged in outside Installation part on when the stability higher that connects, the cable to alleviate different starting points existing in the prior art is alternating mostly Laying, and be layering, accumulate serious, cable once lay down the technical issues of can not just removing.
Fig. 1 is the vertical view of control cable bearer provided in an embodiment of the present invention;Fig. 2 is control provided in an embodiment of the present invention The side view of cable bearer processed;Fig. 3 is the front view of control cable bearer provided in an embodiment of the present invention;As shown in Figs. 1-3, exist On the basis of above-described embodiment, further, the first connecting portion 200 is identical with the structure of the second connecting portion 300.
Further, the first connecting portion 200 is the first link block, and the first screw thread is provided on first link block Hole 210;The second connecting portion 300 is the second link block, and the second threaded hole 310 is provided on second link block.
Further, multiple first connecting portions 200 and multiple second connecting portions 300 are symmetricly set on the electricity The both sides of cable crane span structure ontology 100.
Wherein, first connecting portion 200 and second connecting portion 300 can be alternately arranged in the both sides of cable testing bridge ontology 100, As long as can be connect with installation part.
In the present embodiment, multiple first link blocks and multiple second are symmetrically arranged in the both sides of cable testing bridge ontology 100 Link block is provided with the first threaded hole 210 on the first link block, in cable testing bridge ontology 100 and external connection, in external object The second threaded hole 310 is provided on body, expansion bolt passes through the first threaded hole 210 and the second threaded hole 310 to coordinate, by cable Crane span structure ontology 100 and external connection.
On the basis of the above embodiments, further, the plug division include the first mounting hole 111, the second mounting hole, First spliced eye 131 and the second spliced eye 132;
First mounting hole 111 and second mounting hole are symmetricly set on the both sides of the cable testing bridge ontology 100, First spliced eye 131 and second spliced eye 132 setting first mounting hole 111 and second mounting hole it Between, the separator 400 can pass through first spliced eye and second spliced eye and first mounting hole 111 and institute The cooperation of the second mounting hole is stated, multiple cable floor layings area will be divided on the cable testing bridge ontology 100.
Wherein, the first mounting hole 111, the second mounting hole, the first spliced eye 131 and the second spliced eye 132 are an a pair It should be arranged, multiple first mounting holes 111 and multiple second mounting holes uniformly divide along the extending direction of cable testing bridge ontology 100 Cloth, while the first mounting hole 111, the second mounting hole, the first spliced eye 131 and the second spliced eye 132 are in the same plane, and the Plane where one mounting hole 111, the second mounting hole, the first spliced eye 131 and the second spliced eye 132 and cable testing bridge ontology 100 is vertical, in order to which separator 400 is connect with plug division.
In the present embodiment, plug division include the first mounting hole 111, the second mounting hole, the first spliced eye 131 and second insert Connect hole 132, separator 400 pass through after the first spliced eye 131 and the second spliced eye 132 both ends respectively with the first mounting hole 111 and Second mounting hole is clamped, so that separator 400 is fixed on cable testing bridge ontology 100, it is multiple that cable testing bridge ontology 100, which is divided, Cable floor lays area.
On the basis of the above embodiments, further, the cable testing bridge ontology 100 includes the first side plate 110, second Side plate 120 and top plate 130, first side plate 110 and second side plate 120 are symmetricly set on the both sides of the top plate 130, It is provided with first mounting hole 111 on first side plate 110, described second is provided on second side plate 120 and is fixed Hole, first mounting hole 111 and second mounting hole are separately positioned on first side plate 110 and second side plate 120 one end far from the top plate 130, first spliced eye and second spliced eye are arranged on the top plate 130.
Wherein, the top plate 130 on cable testing bridge ontology, the first side plate 110 and the second side plate 120 are hollow structure, and It is provided with multigroup reinforcing rib in top plate 130, the first side plate 110 and the second side plate 120.
In the present embodiment, it is fixedly connected between the first side plate 110, the second side plate 120 and top plate 130, so that cable testing bridge Ontology 100 is formed as the hollow housing of one end open, and 110 He of the first side plate is arranged in first connecting portion 200 and second connecting portion 300 Second one end of side plate 120 far from top plate 130, the first mounting hole 111 and the second mounting hole are symmetricly set on 110 He of the first side plate On second side plate 120, the first spliced eye 131 and the second spliced eye 132 are arranged on top plate 130, multiple first spliced eye, 131 Hes Multiple second spliced eyes 132 are arranged in a one-to-one correspondence, between symmetrically arranged first mounting hole, 111 and second mounting hole a pair of in this way There are one the first spliced eyes 131 and second spliced eye 132 can be formed with plug division for setting, and the mode of this set can Coordinate convenient for separator 400 and plug division.
On the basis of the above embodiments, further, the first binding hole 112, institute are provided on first side plate 110 It states and is provided with the second binding hole on the second side plate 120;
First binding hole 112 is multiple, extension of multiple first binding holes 112 along first side plate 110 Direction is uniformly distributed, and first binding hole 112 is arranged in first side plate 110 close to the side of the top plate 130;
Second binding hole is multiple, and multiple second binding holes are equal along the extending direction of second side plate 120 Even distribution, second binding hole are arranged in second side plate 120 close to the side of the top plate 130;
Multiple first binding holes 112 and multiple second binding holes are arranged in a one-to-one correspondence;
Multiple first binding holes 112 are staggered with multiple first mounting holes 111.
In the present embodiment, the first binding hole 112 and are also respectively provided on the first side plate 110 and the second side plate 120 Two binding holes, the first binding hole 112 and second bind hole and are separately positioned on the first side plate 110 and the second side plate 120 close to top plate 130 one end, while the connecting line in multiple first bindings hole 112 is parallel with the connecting line of the first mounting hole 111, multiple second tie up The connecting line for pricking hole is parallel with multiple connecting lines of second mounting hole, and multiple first bindings hole 112 interlocks with the first mounting hole 111 Setting, multiple second bindings hole are staggered with the second mounting hole, are controlling cable setting when cable floor lays area in this way, the One binding hole 112 and second, which binds hole, can fix control cable.
Fig. 4 is the front view of separator on control cable bearer provided in an embodiment of the present invention.As shown in figure 4, above-mentioned On the basis of embodiment, further, the separator 400 is subregion spring;
The subregion spring includes U-typed spring body 410 and clamping portion 420;
The clamping portion 420 is arranged in the open end of the U-typed spring body 410, and the clamping portion 420 is used for and institute State plug division mating connection.
Further, the clamping portion 420 includes first connecting rod and second connecting rod, and the first connecting rod and described second connect Bar is separately positioned on the both sides of the open end of the U-typed spring body 410, and the first connecting rod and the second connecting rod with The U-typed spring body 410 is vertically arranged.
In the present embodiment, separator 400 includes U-typed spring body 410 and clamping portion 420, due to U-typed spring body 410 setting makes upper part and end be circular design, prevents Damage Coutrol cable and scratches staff;U-typed spring master Body 410 coordinates with the first spliced eye of element and the second spliced eye, keeps U-typed spring body 410 or so inactive, U-typed spring Main body 410 is after the first spliced eye and the second spliced eye, and head rod and the second connecting rod are i.e. along the first side plate 110 and second The madial wall of side plate 120 is moved at the first mounting hole 111 and the second mounting hole, and is fixed with the first mounting hole 111 and second Hole connects, to reach the purpose being stably placed on cable testing bridge ontology 100.
A kind of control cable laying system provided by the invention has multiple control cable beareves as described above;It is multiple The distribution that the control cable bearer is spaced successively, multiple cable laying areas controlled on cable beareves are formed for laying Control the laying track of cable.Its advantageous effect generated is identical as the control advantageous effect of cable bearer, repeats no more.
Wherein, the shape for the laying track that multiple control cable beareves are formed can be adjusted according to specific needs.
Finally it should be noted that:The above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Present invention has been described in detail with reference to the aforementioned embodiments for pipe, it will be understood by those of ordinary skill in the art that:Its according to So can with technical scheme described in the above embodiments is modified, either to which part or all technical features into Row equivalent replacement;And these modifications or replacements, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (10)

1. a kind of control cable bearer, which is characterized in that including:Cable testing bridge ontology, first connecting portion, second connecting portion and point Spacing body;
Multiple plug divisions, length of multiple plug divisions along the cable testing bridge ontology are provided on the cable testing bridge ontology Direction is evenly spaced on, and multiple separators are with the plug division grafting so as to be formed on the cable testing bridge ontology more A cable floor lays area;
The first connecting portion and the second connecting portion are multiple, and multiple first connecting portions and multiple described second connect Socket part is evenly distributed on the both sides of the cable testing bridge, so that the cable testing bridge ontology can be fixed on mountings.
2. control cable bearer according to claim 1, which is characterized in that the first connecting portion and second connection The structure in portion is identical.
3. control cable bearer according to claim 2, which is characterized in that the first connecting portion is the first link block, It is provided with the first threaded hole on first link block;The second connecting portion is the second link block, on second link block It is provided with the second threaded hole.
4. control cable bearer according to claim 3, which is characterized in that multiple first connecting portions and multiple described Second connecting portion is symmetricly set on the both sides of the cable testing bridge ontology.
5. control cable bearer according to claim 4, which is characterized in that the plug division includes the first mounting hole, the Two mounting holes, the first spliced eye and the second spliced eye;
First mounting hole and second mounting hole are symmetricly set on the both sides of the cable testing bridge ontology, and described first inserts It connects hole and second spliced eye is arranged between first mounting hole and second mounting hole, the separator can be worn First spliced eye and second spliced eye is crossed with first mounting hole and second mounting hole to coordinate, it will be described It is divided into multiple cable floor layings area on cable testing bridge ontology.
6. control cable bearer according to claim 5, which is characterized in that the cable testing bridge ontology includes the first side Plate, the second side plate and top plate, first side plate and second side plate are symmetricly set on the both sides of the top plate, and described first It is provided with first mounting hole on side plate, second mounting hole, first mounting hole are provided on second side plate It is separately positioned on first side plate and the described one end of second side plate far from the top plate with second mounting hole, described One spliced eye and second spliced eye are arranged on the top plate.
7. control cable bearer according to claim 6, which is characterized in that be provided with the first binding on first side plate Hole is provided with the second binding hole on second side plate;
First binding hole is multiple, and multiple first binding holes are uniformly distributed along the extending direction of first side plate, First binding hole is arranged in first side plate close to the side of the top plate;
Second binding hole is multiple, and multiple second binding holes are uniformly distributed along the extending direction of second side plate, Second binding hole is arranged in second side plate close to the side of the top plate;
Multiple first binding holes and multiple second binding holes are arranged in a one-to-one correspondence;
Multiple first binding holes are staggered with multiple first mounting holes.
8. control cable bearer according to claim 1, which is characterized in that the separator is subregion spring;
The subregion spring includes U-typed spring body and clamping portion;
The clamping portion is arranged in the open end of the U-typed spring body, and the clamping portion is used to coordinate with the plug division Connection.
9. control cable bearer according to claim 8, which is characterized in that the clamping portion includes first connecting rod and second Connecting rod, the first connecting rod and the second connecting rod are separately positioned on the both sides of the open end of the U-typed spring body, and institute First connecting rod and the second connecting rod is stated to be vertically arranged with the U-typed spring body.
10. a kind of control cable laying system, which is characterized in that have multiple as claim 1-9 any one of them controls Cable bearer;
The distribution that multiple control cable beareves are spaced successively, multiple cable laying areas controlled on cable beareves are formed Laying track for laying control cable.
CN201811028233.7A 2018-09-04 2018-09-04 Control cable support and control cable laying system Pending CN108767749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811028233.7A CN108767749A (en) 2018-09-04 2018-09-04 Control cable support and control cable laying system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811028233.7A CN108767749A (en) 2018-09-04 2018-09-04 Control cable support and control cable laying system

Publications (1)

Publication Number Publication Date
CN108767749A true CN108767749A (en) 2018-11-06

Family

ID=63968068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811028233.7A Pending CN108767749A (en) 2018-09-04 2018-09-04 Control cable support and control cable laying system

Country Status (1)

Country Link
CN (1) CN108767749A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109449830A (en) * 2018-12-17 2019-03-08 国家电网有限公司 Cable laying bracket

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5149027A (en) * 1992-01-31 1992-09-22 Alcatel Network Systems, Inc. Multiple leg height snap fit cable holder apparatus
US9841123B1 (en) * 2015-06-05 2017-12-12 James C. White Company, Inc. Cable tray system
CN207664579U (en) * 2017-11-07 2018-07-27 广东百基智能电气设备有限公司 A kind of power engineering cable duct cable bearer
CN208835610U (en) * 2018-09-04 2019-05-07 广东电网有限责任公司 Control cable support and control cable laying system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5149027A (en) * 1992-01-31 1992-09-22 Alcatel Network Systems, Inc. Multiple leg height snap fit cable holder apparatus
US9841123B1 (en) * 2015-06-05 2017-12-12 James C. White Company, Inc. Cable tray system
CN207664579U (en) * 2017-11-07 2018-07-27 广东百基智能电气设备有限公司 A kind of power engineering cable duct cable bearer
CN208835610U (en) * 2018-09-04 2019-05-07 广东电网有限责任公司 Control cable support and control cable laying system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109449830A (en) * 2018-12-17 2019-03-08 国家电网有限公司 Cable laying bracket

Similar Documents

Publication Publication Date Title
US9491895B2 (en) Power distribution rack bus bar assembly and method of assembling the same
WO2012121457A1 (en) Method for uninterruptible bypass construction of power distribution lines using insulated guiders for maintaining distance
CN109066511A (en) Cable support and cable laying device
CN106451220A (en) Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower
CN108767749A (en) Control cable support and control cable laying system
CN208835610U (en) Control cable support and control cable laying system
CN208508431U (en) Installation type cable support
CN208508432U (en) Cable support and cable laying device
CN208508433U (en) Control cable support and control cable laying device
CN208508429U (en) Installation type cable support
CN206195248U (en) Electrified bypass equipment who changes with equipment on pole multiloop shaft tower
CN108767776A (en) Control cable support and control cable laying device
CN209626839U (en) A kind of electrical engineering cable fixer
CN208508483U (en) Pre-buried cable support
CN208707246U (en) Control cable support and control cable laying device
CN108767778A (en) Cable bridge rack device
CN208508428U (en) Cable bridge rack device
CN208508430U (en) Pre-buried cable support
CN108988233A (en) A kind of network engineering wiring adjuster
CN108767777A (en) Control cable support and control cable laying device
CN208835649U (en) Pre-buried cable support
CN202978015U (en) Network intelligent power distribution cabinet
CN210640491U (en) Creel stand for transformer cabinet
CN108832565A (en) Installation type cable support and method for laying control cable in cable trench
CN109066561A (en) Pre-buried cable support and method for laying control cable in cable trench

Legal Events

Date Code Title Description
PB01 Publication