CN108756960A - A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device - Google Patents
A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device Download PDFInfo
- Publication number
- CN108756960A CN108756960A CN201810854180.8A CN201810854180A CN108756960A CN 108756960 A CN108756960 A CN 108756960A CN 201810854180 A CN201810854180 A CN 201810854180A CN 108756960 A CN108756960 A CN 108756960A
- Authority
- CN
- China
- Prior art keywords
- reinforcing bar
- trolley
- steel bar
- steel
- door frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/40—Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/381—Setting apparatus or devices
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device,Steel bar hanger correspondence is fixed first between the rotation hanger of a pair of of dossal trolley,Then the reinforcing bar placed on ground is passed through to the reinforced steel bar perforation of reinforcing bar carding by root,Then again by reinforcing bar fixation corresponding with the steel holding holes in reinforcing bar fixing card,Start drive car at this time,Drive car drives dossal trolley to be moved along trolley track,Steel bar hanger movement is driven while dossal trolley moves,Steel bar hanger drives reinforced steel bar ring frame body to be moved,When dossal trolley is moved to the other side of door frame from the side of door frame,Complete the laying work of splash guard reinforcing bar,After the laying work for completing splash guard reinforcing bar,It only needs the Steel bar hanger between the rotation hanger of a pair of of dossal trolley being replaced with splash guard,The laying work of splash guard can be completed,The splash guard reinforcing bar and dossal that the present invention is laid with are smooth,It improves and is laid with splash guard reinforcing bar operating efficiency.
Description
Technical field
The present invention relates to tunnel special mechanical equipment field, especially a kind of anchor bar of waterproof plate in tunnels is laid with and reinforcing bar positioning is promoted
The application method of device.
Background technology
Currently, during constructing tunnel, the tunnel constructed using composite lining, in order to ensure Tunnel Second Lining
Supporting quality needs to be laid with splash guard first and splash guard reinforcing bar carries out carrying out water-proofing treatment to tunnel, so before secondary lining
Uniform gunite concrete carries out support reinforcement on splash guard reinforcing bar afterwards, utilizes the strong feature of concrete anti-compression performance, Yi Jifang
The characteristics of water slab muscle pull resistance, increase the integer support intensity in tunnel, splash guard reinforcing bar needs before gunite concrete
Horizontal and vertical whole is connected as an entirety on splash guard reinforcing bar, just can ensure that the pull resistance of splash guard reinforcing bar, waterproof slab
Muscle, due to being influenced by tunnel height, can not carry out manual work, need in tunnel platform when carrying out horizontal and vertical and connection
Job platform is built on vehicle temporarily to construct, here it is the main method of current composite lining tunnel construction, use is this
When method is constructed, needs to build a large amount of simple platform, manually carries out operation, not only waste a large amount of production time,
And cause the labor intensity of worker big, the problems such as danger coefficient is high, when being manually laid with splash guard reinforcing bar, inevitably
There are certain errors, therefore how to solve composite lining tunnel construction and need largely to build simple platform, and how to solve
Certainly splash guard and splash guard reinforcing bar are laid with uneven, the problem of influencing tunnel integral strength, become insoluble for a long time
Technical barrier.
In view of the foregoing, a kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device is now developed.
Invention content
Purpose of the invention is to overcome the shortcomings in the prior art, solves to need to build a large amount of letter when constructing tunnel
Easy platform causes the labor intensity of worker big, the high problem of danger coefficient, and solves splash guard and the laying of splash guard reinforcing bar not
Uniformly, the problem of influencing tunnel integral strength, provides a kind of user of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device
Method, the configuration of the present invention is simple, the splash guard reinforcing bar and dossal of laying are smooth, greatly improve and are laid with splash guard reinforcing bar operation effect
Rate.
The present invention to achieve the goals above, adopts the following technical scheme that:A kind of anchor bar of waterproof plate in tunnels is laid with and reinforcing bar positioning
The application method of lifting device, the anchor bar of waterproof plate in tunnels be laid with and reinforcing bar position lifting device, be by:Door frame, Tong Liang, bottom
Beam, upper frame, walking mechanism, track, trolley track, dossal trolley, drive car, steel wire rope, traction wheel, directive wheel, behaviour
Make platform, reinforcing bar locating wheel, carding fixed frame, reinforcing bar carding, Steel bar hanger, reinforcing bar fixing card, connecting rod to constitute;Tunnel is anti-
Water plate reinforcement trolley at least three door frames of setting, the portal frame that door frame is constituted for two root posts top setting beam welding, three
A door frame is followed successively by front door frame, middle door frame, rear door frame from front to back;The column bottom of three door frame both sides is respectively provided with bottom girder, and three
Logical beam is welded in top, middle part, the lower part of a door frame both sides, is arranged upper frame above the crossbeam of front door frame and middle door frame, door frame and
Upper frame collectively forms the frame of anchor bar of waterproof plate in tunnels reinforcement trolley;Walking mechanism is respectively provided on the column of front door frame and rear door frame, row
It walks and track is set below the wheel of mechanism, the anchor bar of waterproof plate in tunnels reinforcement trolley frame is moved by walking mechanism before and after track
Driving mechanism dynamic, that the periphery setting splash guard of anchor bar of waterproof plate in tunnels reinforcement trolley frame is laid with and reinforcing bar positioning is promoted;
The splash guard is laid with and the structure of the driving mechanism of reinforcing bar positioning promotion is:The top of front door frame and middle door frame and
The trolley track of a pair of of arc of external setting of both sides, the company of being respectively set between a pair of of trolley track and front door frame and middle door frame
Bar is symmetrical arranged two dossal trolleies on the slideway of a pair of of trolley track, Steel bar hanger is arranged between two dossal trolleies;It is a pair of
Traction wheel is uniformly distributed on trolley track, the traction wheel on a pair of of trolley track is arranged symmetrically, the cross of front door frame and middle door frame
It is symmetrical arranged two drive cars above beam, driving wheel, front door is respectively set on the output shaft of two drive cars
Symmetrical directive wheel on the frame body of frame and middle door frame, on the driving wheel, front door frame and middle door frame frame body on drive car
Directive wheel, winding setting steel wire rope respectively on the traction wheel on a pair of of trolley track, a pair of of steel wire rope is set as cyclic annular, a pair of
Both ends of the end of steel wire rope respectively with two dossal trolleies are correspondingly connected with, and the paving that reinforcing bar is positioned, promoted is arranged in Steel bar hanger
If mechanism;
The reinforcing bar positions, the structure of the laying mechanism of promotion is:It is symmetrically set on front door frame and the logical beam of middle door frame both sides
Operating platform is set, reinforcing bar locating wheel is arranged in the one side edge of operating platform;Longitudinal reinforcing bar is uniformly distributed in Steel bar hanger to fix
Block, reserved steel bar mounting hole in reinforcing bar fixing card, reinforcing bar is set in steel holding holes;The bottom surface of the bottom girder of front door frame and middle door frame
Upper setting carding fixed frame is uniformly distributed longitudinal reinforcing bar carding in the frame of carding fixed frame, and reinforcing bar carding is
Cylinder hollow pipe, reserved steel bar perforation on reinforcing bar carding, reinforced steel bar perforation corresponds to steel holding holes and is arranged, on the crossbeam of upper frame
Two pairs of mandrils are vertically arranged between trolley track, the top of two pairs of mandrils is respectively provided with reinforcing bar locating wheel;
When reinforcing bar laying construction, Steel bar hanger correspondence is fixed first between the rotation hanger of a pair of of dossal trolley,
Then the reinforcing bar placed on ground is passed through to the reinforced steel bar perforation of reinforcing bar carding by root, it then again will be on reinforcing bar and reinforcing bar fixing card
Steel holding holes correspond to and fix, start drive car at this time, drive cricoid steel wire rope to move by drive car
It is dynamic.
While drive car drives cricoid steel wire rope movement, steel wire rope is driven by traction wheel and directive wheel and is hung
Cloth trolley is moved along trolley track, and Steel bar hanger movement, reinforcing bar are moved by rotating suspension armband while dossal trolley moves
When lifting appliance moving, reinforced steel bar ring frame body is driven to be moved, reinforcing bar passes through the steel of operating platform one side edge in the process of moving
Muscle locating wheel dredges reinforcing bar, while can play the role of mitigating reinforcing bar resistance when the rotation of reinforcing bar locating wheel, works as dossal
When trolley is moved to the other side of door frame from the side of door frame, the laying work of splash guard reinforcing bar is completed.
After the laying work for completing splash guard reinforcing bar, operating personnel station carries out binding binding in operating platform;It is laid with waterproof
When plate, it is only necessary to the Steel bar hanger between the rotation hanger of a pair of of dossal trolley are replaced with splash guard, then repeat above-mentioned step
The rapid laying work that splash guard can be completed drives tunnel after one section of engineering construction in tunnel finishes by walking mechanism
Road lining trolley frame marches to next section of job location along track, then repeats the above steps and constructs.
The beneficial effects of the invention are as follows:The configuration of the present invention is simple, strong operability, the splash guard reinforcing bar and dossal of laying are flat
It is whole, it is easy to use, it greatly improves and is laid with splash guard reinforcing bar operating efficiency, reduce cost of labor, reduce the labour of worker
Intensity improves splash guard reinforcing bar laying quality, is appropriate for promoting the use of.
Description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is general assembly structural schematic diagram;
Fig. 2 is the side structure schematic view of Fig. 1;
In Fig. 1,2:Door frame 1, logical beam 1.1, bottom girder 1.2, upper frame 2, walking mechanism 3, track 4, trolley track 5, dossal are small
Vehicle 6, drive car 7, steel wire rope 71, traction wheel 8, directive wheel 81, operating platform 9, reinforcing bar locating wheel 10, carding are fixed
Frame 11, reinforcing bar carding 12, Steel bar hanger 13, reinforcing bar fixing card 14, connecting rod 15.
Specific implementation mode
With reference to embodiment, invention is further described in detail with specific implementation mode:
Embodiment 1
At least three door frames 1 are arranged in anchor bar of waterproof plate in tunnels reinforcement trolley, and door frame 1 is that beam welding structure is arranged in two root posts top
At portal frame, three door frames 1 are followed successively by front door frame, middle door frame, rear door frame from front to back;The column of three 1 both sides of door frame
Bottom is respectively provided with bottom girder 1.2, and logical beam 1.1 is welded in top, middle part, the lower part of three 1 both sides of door frame, front door frame and middle door frame
Upper frame 2 is set above crossbeam, and door frame 1 and upper frame 2 collectively form the frame of anchor bar of waterproof plate in tunnels reinforcement trolley;Front door frame and rear door frame
Column on be respectively provided with walking mechanism 3, track 4, the anchor bar of waterproof plate in tunnels reinforcement trolley frame are set below the wheel of walking mechanism 3
Frame is moved forward and backward by walking mechanism 3 along track 4, and the periphery setting splash guard of anchor bar of waterproof plate in tunnels reinforcement trolley frame is laid with and steel
The driving mechanism that muscle positioning is promoted;
The splash guard is laid with and the structure of the driving mechanism of reinforcing bar positioning promotion is:The top of front door frame and middle door frame and
The trolley track 5 of a pair of of arc of external setting of both sides, the company of being respectively set between a pair of of trolley track 5 and front door frame and middle door frame
Bar 15 is symmetrical arranged two dossal trolleies 6 on the slideway of a pair of of trolley track 5, Steel bar hanger is arranged between two dossal trolleies 6
13;Traction wheel 8 is uniformly distributed on a pair of of trolley track 5, the traction wheel 8 on a pair of of trolley track 5 be it is arranged symmetrically, front door frame and
It is symmetrical arranged two drive cars 7 above the crossbeam of middle door frame, is respectively set on the output shaft of two drive cars 7
Symmetrical directive wheel 81 on the frame body of driving wheel, front door frame and middle door frame, driving wheel, front door frame on drive car 7
Setting steel wire rope 71 is wound respectively on the directive wheel 81 on middle door frame frame body, the traction wheel 8 on a pair of of trolley track 5, it is a pair of
Steel wire rope 71 is set as cyclic annular, and the both ends of the end of a pair of of steel wire rope 71 respectively with two dossal trolleies 6 are correspondingly connected with, and reinforcing bar is hung
The laying mechanism that setting reinforcing bar is positioned, promoted on tool 13;
The reinforcing bar positions, the structure of the laying mechanism of promotion is:It is symmetrical on front door frame and the logical beam 1.1 of middle door frame both sides
Operating platform 9, the one side edge setting reinforcing bar locating wheel 10 of operating platform 9 are set;It is uniformly distributed in Steel bar hanger 13 longitudinal
Reinforcing bar is arranged in steel holding holes in reinforcing bar fixing card 14, reserved steel bar mounting hole in reinforcing bar fixing card 14;Front door frame and middle door frame
Bottom girder 1.2 bottom surface on setting carding fixed frame 11, be uniformly distributed longitudinal reinforcing bar in the frame of carding fixed frame 11
Carding 12, reinforcing bar carding 12 are cylinder hollow pipe, and reserved steel bar perforation, reinforced steel bar perforation correspond to steel on reinforcing bar carding 12
Muscle mounting hole is arranged, and two pairs of mandrils is vertically arranged between trolley track 5 on the crossbeam of upper frame 2, the top of two pairs of mandrils is all provided with
Set reinforcing bar locating wheel 10;
When reinforcing bar laying construction, Steel bar hanger 13 is corresponded to first between the rotation hanger of a pair of of dossal trolley 6 and is fixed
It is good, then the reinforcing bar placed on ground by root is passed through to the reinforced steel bar perforation of reinforcing bar carding 12, then again consolidate reinforcing bar and reinforcing bar
Surely the steel holding holes on card 14, which correspond to, fixes, and starts drive car 7 at this time, ring-type is driven by drive car 7
Steel wire rope 71 move.
While drive car 7 drives cricoid steel wire rope 71 to move, steel wire rope 71 passes through traction wheel 8 and directive wheel
81 drive dossal trolleies 6 are moved along trolley track 5, are moved reinforcing bar by rotating suspension armband while dossal trolley 6 moves and are hung
13 movement of tool, when Steel bar hanger 13 moves, drives reinforced steel bar ring frame body to be moved, and reinforcing bar is flat by operating in the process of moving
The reinforcing bar locating wheel 10 of platform one side edge dredges reinforcing bar, while can play mitigation reinforcing bar when the rotation of reinforcing bar locating wheel 10
The effect of resistance completes the laying of splash guard reinforcing bar when dossal trolley 6 is moved to the other side of door frame 1 from the side of door frame 1
Work.
After the laying work for completing splash guard reinforcing bar, operating personnel station carries out binding binding in operating platform 9;It is laid with waterproof
When plate, it is only necessary to the Steel bar hanger 13 between the rotation hanger of a pair of of dossal trolley 6 are replaced with splash guard, then repeated above-mentioned
The laying work of splash guard can be completed in step, after one section of engineering construction in tunnel finishes, is driven by walking mechanism 3
Tunnel lining trolley frame marches to next section of job location along track 4, then repeats the above steps and constructs.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810854180.8A CN108756960A (en) | 2018-07-30 | 2018-07-30 | A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810854180.8A CN108756960A (en) | 2018-07-30 | 2018-07-30 | A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108756960A true CN108756960A (en) | 2018-11-06 |
Family
ID=63971940
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810854180.8A Pending CN108756960A (en) | 2018-07-30 | 2018-07-30 | A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108756960A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667605A (en) * | 2019-02-20 | 2019-04-23 | 中铁隧道集团三处有限公司 | A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh |
| CN109736859A (en) * | 2019-02-28 | 2019-05-10 | 庆云汉诚隧道工程机械有限公司 | A self-propelled multifunctional tunnel construction vehicle body, trolley and construction method |
| CN112943315A (en) * | 2021-01-28 | 2021-06-11 | 常州畅韵工程材料有限公司 | Low-vibration waterproof board auxiliary laying construction device for high-speed rail tunnel |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104533466A (en) * | 2014-11-21 | 2015-04-22 | 中铁一局集团有限公司 | Multifunctional flexible traction type paving rack for waterproof board |
| CN105129602A (en) * | 2015-09-24 | 2015-12-09 | 中铁四局集团第二工程有限公司 | Sling capable of integrally lifting long and large-diameter vertical steel bars |
| CN105422143A (en) * | 2015-12-25 | 2016-03-23 | 德阳思远重工有限公司 | Intelligent trolley for tunnel construction |
| CN105569692A (en) * | 2016-01-29 | 2016-05-11 | 黄高飞 | Trolley for welding tunnel waterproof board hanging cloth |
| CN205823303U (en) * | 2016-07-25 | 2016-12-21 | 中车建设工程有限公司 | The Multifunctional bench that a kind of tunnel special lining cutting reinforcement installation and splash guard are laid |
| CN205977243U (en) * | 2016-08-01 | 2017-02-22 | 湖南五新隧道智能装备股份有限公司 | A platform truck for tunnel water proofing board is laid and reinforcement |
| CN106988770A (en) * | 2017-05-19 | 2017-07-28 | 龚岗 | Geotextiles waterproof cloth and two lined steel muscle are plated in integrated bogie hearth |
| CN107100651A (en) * | 2017-05-13 | 2017-08-29 | 山东佳信机械设备有限公司 | A kind of tunnel-liner is seamlessly connected reinforcing bar positioning, splash guard laying chassis |
| CN107956488A (en) * | 2017-12-27 | 2018-04-24 | 中铁工程装备集团有限公司 | A kind of splash guard reinforcing bar spreads hanging platform car |
| CN208564592U (en) * | 2018-07-30 | 2019-03-01 | 洛阳高飞桥隧机械有限公司 | A kind of anchor bar of waterproof plate in tunnels is laid with and reinforcing bar positions lifting device |
-
2018
- 2018-07-30 CN CN201810854180.8A patent/CN108756960A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104533466A (en) * | 2014-11-21 | 2015-04-22 | 中铁一局集团有限公司 | Multifunctional flexible traction type paving rack for waterproof board |
| CN105129602A (en) * | 2015-09-24 | 2015-12-09 | 中铁四局集团第二工程有限公司 | Sling capable of integrally lifting long and large-diameter vertical steel bars |
| CN105422143A (en) * | 2015-12-25 | 2016-03-23 | 德阳思远重工有限公司 | Intelligent trolley for tunnel construction |
| CN105569692A (en) * | 2016-01-29 | 2016-05-11 | 黄高飞 | Trolley for welding tunnel waterproof board hanging cloth |
| CN205823303U (en) * | 2016-07-25 | 2016-12-21 | 中车建设工程有限公司 | The Multifunctional bench that a kind of tunnel special lining cutting reinforcement installation and splash guard are laid |
| CN205977243U (en) * | 2016-08-01 | 2017-02-22 | 湖南五新隧道智能装备股份有限公司 | A platform truck for tunnel water proofing board is laid and reinforcement |
| CN107100651A (en) * | 2017-05-13 | 2017-08-29 | 山东佳信机械设备有限公司 | A kind of tunnel-liner is seamlessly connected reinforcing bar positioning, splash guard laying chassis |
| CN106988770A (en) * | 2017-05-19 | 2017-07-28 | 龚岗 | Geotextiles waterproof cloth and two lined steel muscle are plated in integrated bogie hearth |
| CN107956488A (en) * | 2017-12-27 | 2018-04-24 | 中铁工程装备集团有限公司 | A kind of splash guard reinforcing bar spreads hanging platform car |
| CN208564592U (en) * | 2018-07-30 | 2019-03-01 | 洛阳高飞桥隧机械有限公司 | A kind of anchor bar of waterproof plate in tunnels is laid with and reinforcing bar positions lifting device |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667605A (en) * | 2019-02-20 | 2019-04-23 | 中铁隧道集团三处有限公司 | A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh |
| CN109736859A (en) * | 2019-02-28 | 2019-05-10 | 庆云汉诚隧道工程机械有限公司 | A self-propelled multifunctional tunnel construction vehicle body, trolley and construction method |
| CN109736859B (en) * | 2019-02-28 | 2020-04-17 | 庆云汉诚隧道工程机械有限公司 | Self-propelled multifunctional tunnel construction vehicle body, trolley and construction method |
| CN112943315A (en) * | 2021-01-28 | 2021-06-11 | 常州畅韵工程材料有限公司 | Low-vibration waterproof board auxiliary laying construction device for high-speed rail tunnel |
| CN112943315B (en) * | 2021-01-28 | 2022-02-08 | 常州畅韵工程材料有限公司 | Low-vibration waterproof board auxiliary laying construction device for high-speed rail tunnel |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105736016B (en) | Tunnel double-lining framework of steel reinforcement construction equipment and its application | |
| CN108331603B (en) | A multifunctional trolley and its construction method | |
| CN102913259B (en) | Steel arch assembling machine of tunnel vault for repairing damages of existing railway tunnel | |
| CN102061927A (en) | Tunnel waterproof material laying equipment and method | |
| CN102042021A (en) | Automatically walking stepped mobile trestle | |
| CN106012717B (en) | One kind is vibrated apparatus for leveling | |
| CN104533460B (en) | Support replacement formula formwork jumbo and the construction method of underpass concreting | |
| CN110424277A (en) | PC beam bridge Wavelike steel webplate hanging apparatus and construction method with low gantry crane | |
| CN204662952U (en) | A kind of self-propelled tool single side formwork formwork system | |
| CN108756960A (en) | A kind of application method of anchor bar of waterproof plate in tunnels laying and reinforcing bar positioning lifting device | |
| CN108798727A (en) | A kind of tunnel self-propelled splash guard dossal reinforcing bar positioning integrally multi-functional trolley and application | |
| CN202544854U (en) | Lining trolley for subway station | |
| CN113123800A (en) | Construction method of starting base of large-diameter shield tunnel steel structure | |
| CN202926344U (en) | Tunnel vault steel arch frame mounting machine for existing railway tunnel disease repairing | |
| CN208564592U (en) | A kind of anchor bar of waterproof plate in tunnels is laid with and reinforcing bar positions lifting device | |
| KR101892243B1 (en) | Construction cage apparatus with gondora | |
| CN206215824U (en) | Filling pile cage of reinforcement processing unit (plant) | |
| CN210659228U (en) | A movable single-sided formwork system for subway construction | |
| CN208870380U (en) | Mobile device and removable wall form for wall form | |
| CN104453951A (en) | Combined lining formwork trolley for subway station | |
| JP5400829B2 (en) | Temporary pier construction method and scaffolding equipment for construction of temporary pier | |
| CN205743934U (en) | Self-propelled tunnel inverted arch reinforcing bar spelling installs chassis | |
| CN202117689U (en) | Light-duty trolley which is matched with shield station-passing for structure formwork | |
| CN212835507U (en) | Concrete reinforcement cage ligature and conversion equipment | |
| CN201908665U (en) | Movable variable-cross section lining trolley |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181106 |