Prior art keywords
core pipe
tunnel
underground structure
underground
drainage arrangement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810943692.1A
Other languages
Chinese (zh)
Inventor
郭永发
殷洪波
付斌
田鲁鲁
杨进京
丁文云
张海波
陶伟明
刘正初
杨翔
肖勇刚
李贵民
袁云洪
李传琳
赵海燕
孙希望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Kunming Survey Design and Research Co Ltd
Original Assignee
CREEC Kunming Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Kunming Survey Design and Research Co Ltd filed Critical CREEC Kunming Survey Design and Research Co Ltd
Priority to CN201810943692.1A priority Critical patent/CN108755722A/en
Publication of CN108755722A publication Critical patent/CN108755722A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

The present invention provides the drainage arrangement and water discharge method of a kind of tunnel and underground structure, drainage arrangement includes when using through tunnel-liner or the outer tube of underground structure, discharge structure control unit in the core pipe that lower end is stretched into outer sleeve upper, is threadedly coupled with outer tube, and merging core pipe;Several second drain holes are provided on the lower part outer wall of outer tube;The lower end of the core pipe has supporting part, and several first drain holes are provided on the lower part outer wall of core pipe;The discharge structure control unit include be placed in core pipe, the stabilization block on supporting part, the lower end guide sleeve connected with block upper end is stablized, the guide rod that lower end is stretched into guide sleeve, is slidably matched with guide sleeve, the connector being connected with guide rod upper end, it is installed on connector upper end, the sealing element with the liquid-tight envelope cooperation of core pipe inner wall, it is set on guide sleeve, the both ends spring connected with block and connector is stablized respectively, the head cover of closing core pipe upper end, an at least transverse drain.

Description

The drainage arrangement and water discharge method in tunnel and underground structure
Technical field
The present invention relates to tunnels and underground engineering equipment technical fields, more particularly, to the row in a kind of tunnel and underground structure Water installations and water discharge method.
Background technology
With China's traffic, the great development of municipal engineering construction, tunnel, subway and municipal underground engineering construction day are cumulative More, since tunnels and underground engineering is influenced by geological conditions, ground water reserve condition is not quite similar, to the ground of structural perimeter country rock Lower water will also carry out draining and dredge, to reduce charge for remittance to lining cutting or underground structure coagulation other than taking effective waterproof measure The osmotic pressure of soil.It is relevant research shows that tunnel inverted arch or underground structure pour after, inverted arch lining cutting and underground structure behind water Pressure shows gradual increased trend, is caused inverted arch or underground structure to float by charge for remittance pressure influence, strong influence Railroad embankment and underground engineering are safe to use.Therefore, effective design is taken during tunnel and underground engineering construction Scheme and reliable working measure carry out Active Drainage, and it is to maintain tunnel and underground work to reduce lining cutting and underground structure external water pressure Cheng Wending, it is ensured that tunnel operation security and underground engineering optimal selection safe to use.
Invention content
The purpose of the present invention is intended to overcome the shortcomings of the prior art, provide one kind can Active Drainage reduce lining cutting or The drainage arrangement and water discharge method of underground structure hydraulic pressure.
In order to solve the above-mentioned technical problem, the present invention is achieved by the following technical solutions:
A kind of drainage arrangement in tunnel and underground structure comprising through tunnel-liner or the outer tube of underground structure when use, Discharge structure control unit in the core pipe that lower end is stretched into outer sleeve upper, is threadedly coupled with outer tube, and merging core pipe; Several second drain holes are provided on the lower part outer wall of the outer tube;The lower end of the core pipe has supporting part, and core pipe Several first drain holes are provided on the outer wall of lower part;The discharge structure control unit includes being placed in core pipe, being located at supporting part On stabilization block, lower end and stablize the connected guide sleeve in block upper end, lower end is stretched into guide sleeve, led with what guide sleeve was slidably matched To bar, the connector being connected with guide rod upper end is installed on connector upper end, the sealing element with the liquid-tight envelope cooperation of core pipe inner wall, It is set on guide sleeve, the both ends spring connected with block and connector is stablized respectively, the head cover of closing core pipe upper end, at least one The transverse drain for being set in core pipe external wall of upper portion, being connected to core pipe, and be set on stable block, for detecting hydraulic pressure Wireless hydraulic pressure detector;When the hydraulic pressure suffered by the spring is less than the rated value of spring, the sealing surface of sealing element is not higher than transverse drainage The lower edge of pipe, when the hydraulic pressure suffered by the spring is more than the rated value of spring, sealing element moves up, make the lower space of core pipe with it is horizontal It is connected to drainpipe and realizes draining.
Preferably, further include being located at sealing element upper end draw ring.
Preferably, further include being installed on outer tube lower end, the header tank made of pervious concrete.
Preferably, the head cover is connect with core pipe by helicitic texture.
Preferably, the transverse drain is two, is symmetrically disposed in core pipe.
Preferably, the connector is integrated with sealing element.
Preferably, the guide rod is connect with connector by helicitic texture.
Preferably, the guide sleeve is connect with block is stablized by helicitic texture.
Preferably, the mounting hole of wireless water pressure monitor is installed in the side wall setting of the stable block.
The water discharge method in a kind of tunnel and underground structure, using drainage arrangement as described above, according to tunnel or underground work The specific hydrogeologic condition of journey, drainage arrangement is arranged in tunnel or underground structure at a certain distance;According to design requirement in tunnel Equipment installation position is reserved in tunnel side wall, inverted arch bottom or underground structure before just spray or underground structure pour in road;It will be outer It is installed after casing package non-woven fabrics, fixing clearance is stablized using thin cobble or coarse sand backfill;Wait for cast in situs tunnel double-lining, inverted arch Or outer tube top uses cylindricality template protection when underground structure, it is ensured that outer tube is not blocked during casting concrete and protected Demonstrate,prove connection space;Then carry out construction of shotcrete;Guide rod is placed in inside guide sleeve, guide rod is then passed through into screw thread With the connector on top, guide sleeve is connected by screw thread with the stabilization block with lower part, wireless water pressure monitor is placed in stabilization Block lower recess, spring is by connector and stablizes reserved spiral shape hole installation fixation on block, to form discharge structure control Unit processed;The control unit is integrally placed in core pipe, head cover is installed by screw thread on head cover and core pipe top screw thread later Core pipe is closed;After waiting for that secondary lining or underground structure perform, outer tube installation is screwed by core pipe;Dry season water When pressure is smaller, spring is in free state, and closure member blocks drain pipe channel in core pipe, inside tunnel or underground structure just Often draining will not penetrate into lining cutting or underground structure by core pipe behind;After underground water enrichment hydraulic pressure becomes larger, underground water is through housing Enter in core pipe after pipe filtering, to form pushing tow to the sealing element in core pipe, when hydraulic pressure reaches setting value, spring elongation, Water pressure pushing sealing element is integrally steadily moved up along guide rod, to open the drainage channel of underground water, realizes tunnel-liner Or underground structure behind underground water is actively drained.
Compared with prior art, the invention has the advantages that:
1, drop and drainage structure is applied in advance in tunnel side wall, inverted arch or underground structure when the present invention uses, and is actively arranged to realize Letting out underground charge for remittance reduces the purpose of tunnel-liner or underground structure water pressure, while ensure that tunnel or underground structure internal drainage Inverted arch arch bottom or underground structure bottom will not be entered, lining caused by preventing conventional drainage from entering tunnel double-lining or underground structure behind Build environmental degradation.
2, each section of the present invention is mutual indepedent, can independently replace without influencing other parts structure function, working service side Just.
3, core pipe top of the invention is threaded, and has added cap structure, the maintenance of internal structure can be facilitated to replace.
4, using being threadedly coupled between outer tube of the invention and core pipe, leakproofness is preferable, it is ensured that tunnel or underground knot Charge for remittance can only be discharged after entering chamber via core pipe on the outside of structure, it is ensured that the accuracy of water pressure monitoring, while being also convenient for structure Between replacement maintenance.
5, the present invention stablizes block by increase, avoids the disadvantage that Internal control structure bottom end must link into an integrated entity with core pipe End, Internal control structure can individually become an entirety and carry out convenient dismounting installation;It is provided with simultaneously on sealing element top Internal control structure can be taken out maintenance by draw ring and replaced, without taking out core pipe by draw ring when uncapping maintenance.
6, the present invention uses outer tube charge for remittance, and excavation size is small, to tunnel or underground engineering original structure stability influence It is smaller;And work as features as poor geologic condition, when tunnel or underground engineering predict that water yield is big, the mode for adding pervious concrete case can be used Increase catchment area, increasing water discharge capacity.
7, wireless water pressure monitor of the invention is placed in link block lower part, for monitoring lining cutting external water pressure, and can will supervise It surveys signal real-time radio and is transmitted to reception terminal, realize the intelligent management during tunnel operation.
8, the present invention in vertical drainage pipe both sides connects transverse drain, can be in vertical drainage pipe dismantles installation process Increase torque arm length easy disassembly.
9, the present invention is provided with guide rod in spring inner, can ensure the mobile side of internal structure in variation in water pressure To, it is ensured that mobile is steady;Guide rod can be inside tunnel or underground structure when proper drainage simultaneously, the position of fixed closed part It sets, ensures the one-way of draining.
10, the stabilization block of the connector and lower part on spring of the invention and top is connected by reserved spiral-shaped orifices Connect, it is easy for installation and can according to hydrogeologic condition adjust spring, adapt to different dewatering needs.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Other attached drawings are obtained according to these attached drawings.
Fig. 1 is schematic diagram of the present invention in tunnel inverted arch arrangement, and which use header tanks;
Fig. 2 is the stereogram of the present invention;
Fig. 3 is the front view of the present invention;
Fig. 4 is the left view of Fig. 3;
Fig. 5 is the vertical view of Fig. 3;
Fig. 6 is the stereogram that core pipe of the present invention and head cover assemble;
Fig. 7 is the front view that core pipe of the present invention and head cover assemble;
Fig. 8 is the left view of Fig. 7;
Fig. 9 is the vertical view of Fig. 7;
Figure 10 is the stereogram of core pipe of the present invention;
Figure 11 is the stereogram of head cover in the present invention;
Figure 12 is the stereogram of discharge structure control unit in the present invention;
Figure 13 is the sectional view of discharge structure control unit in the present invention;
Figure 14 is the sectional view of the present invention(Dry season);
Figure 15 is the sectional view of the present invention(Wet season);
In figure respectively marked as:1-head cover;2-transverse drains;3-core pipes;4-outer tubes;5-the first drain hole;6-draw Ring;7-sealing elements;8-connectors;9-guide rods;10-springs;11-guide sleeves;12-stablize block;13-wireless hydraulic pressure Detector;14-header tanks, the 15-the second drain hole.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of not making the creative labor Embodiment shall fall within the protection scope of the present invention.In the following description, of the invention structure and work side in order to clearly demonstrate Formula will be described on the basis of attached drawing by many Directional words, but should by "front", "rear", "left", "right", The Word Understandings such as "upper", "lower" are not construed as word of limitation for convenience of term.
The drainage arrangement in tunnel and underground structure shown in Fig. 1-15 comprising tied through tunnel-liner 20 or underground when use The outer tube 4 of structure, the core pipe 3 that lower end is stretched into 4 upper end of outer tube, is threadedly coupled with outer tube 4, and be placed in core pipe 3 Discharge structure control unit;Several second drain holes 15 are provided on the lower part outer wall of the outer tube 4;Under the core pipe 3 End has supporting part, and several first drain holes 5 are provided on the lower part outer wall of core pipe 3;The discharge structure control unit packet Include be placed in core pipe 3, the stabilization block 12 on supporting part, lower end and stablize the connected guide sleeve 11 in 12 upper end of block, lower end is stretched Enter the guide rod 9 being slidably matched in guide sleeve 11, with guide sleeve 11, the connector 8 being connected with 9 upper end of guide rod, the company of being installed on 8 upper end of fitting, the sealing element 7 with the liquid-tight envelope cooperation of 3 inner wall of core pipe, be set on guide sleeve 11, both ends respectively with stablize block 12 And the spring 10 that connector 8 is connected, the head cover 1 of 3 upper end of closing core pipe, two be set in 3 external wall of upper portion of core pipe, with core pipe 3 The transverse drain 2 of connection, and be set on stable block 12, the wireless hydraulic pressure detector 13 for detecting hydraulic pressure;Work as spring When hydraulic pressure suffered by 10 is less than the rated value of spring 10, the sealing surface of sealing element 7 is not higher than the lower edge of transverse drain 2, works as spring When hydraulic pressure suffered by 10 is more than the rated value of spring 10, sealing element 7 moves up, and makes the lower space and transverse drain 2 of core pipe 3 Draining is realized in connection.
Particularly, further include being located at 7 upper end draw ring 6 of sealing element, taken out out of core pipe convenient for sealing element and corresponding component, The structure type of rubber piston or metallic piston encryption seal ring, such as inflator piston can be used in sealing element.
Particularly, further include being installed on 4 lower end of outer tube, header tank 14 made of pervious concrete, header tank Size can size according to hydrogeologic condition and prediction water yield determine.
Particularly, the head cover 1 is connect with core pipe 3 by helicitic texture, it is clear that the progress such as flange arrangement also can be used Connection.
Particularly, two transverse drains 2 of the present embodiment are symmetrically disposed in core pipe 3, it is clear that transverse drain 2 Quantity can reasonably be increased and decreased according to caliber and flow area.
Particularly, the connector 8 is integrated with sealing element 7.
Particularly, the guide rod 9 is connect with connector 8 by helicitic texture, it is ensured that close connection, it is clear that also Welding or clamping etc. can be used.
Particularly, the guide sleeve 11 is connect with block 12 is stablized by helicitic texture, it is clear that also can be used welding or Clamping etc..
Particularly, the mounting hole of wireless water pressure monitor is installed in the side wall setting of the stable block 12, is convenient for wireless water Press the dismounting and maintenance of monitor.Wireless water pressure monitor, can be by monitoring signals real-time radio for monitoring inverted arch lower part hydraulic pressure It is transmitted to reception terminal.
Sealing element 7 in the present embodiment is made of water proof material, and spring 10 is made of waterproof anti-corrosion material.
The water discharge method of the present invention is as follows:Using drainage arrangement as described above, according to tunnel or the specific water of underground engineering Literary geological conditions arranges drainage arrangement at a certain distance in tunnel or underground structure;Sprayed at the beginning of the tunnel according to design requirement or Underground structure reserves equipment installation position before pouring in tunnel side wall, inverted arch bottom or underground structure, according to hydrogeology Situation, it is determined whether use header tank 14.It is installed after outer tube is wrapped up non-woven fabrics, fixing clearance is returned using thin cobble or coarse sand Fill out stabilization;Outer tube top uses cylindricality template protection when cast in situs tunnel double-lining, inverted arch or underground structure, it is ensured that housing Pipe is not blocked during casting concrete ensures connection space;Then carry out construction of shotcrete.Guide rod 9 is placed in Inside guide sleeve 11, then by guide rod 9 by screw thread and the connector on top 8, guide sleeve 11 is passed through into screw thread and the lower part and Stabilization block 12 connect, wireless water pressure monitor 13 is placed in 12 lower recess of stable block, spring 10 passes through connector 8 and stablizes Spiral shape hole installation is reserved on block 12 to fix(Obviously also solderable or be bolted), to form discharge structure control Unit;The control unit is integrally placed in core pipe 13, head cover 1 is installed by screw thread on head cover and core pipe top screw thread later Core pipe 3 is closed;After waiting for that secondary lining or underground structure perform, outer tube 4 is screwed by core pipe 3 and is installed.Low water When phase hydraulic pressure is smaller, spring 10 is in free state, and closure member 7 blocks drain pipe channel in core pipe 3, is tied in tunnel or underground Proper drainage will not penetrate into lining cutting or underground structure behind to cause lining cutting or underground structure environment to dislike by core pipe 3 inside structure Change.After underground water enrichment hydraulic pressure becomes larger, underground water enters after the filtering of outer tube 4 in core pipe 3, to close in core pipe 3 Sealing 7 forms pushing tow, and when hydraulic pressure reaches setting value, spring 10 stretches, and water pressure pushing sealing element 7 is whole steady along guide rod 9 It moves up, to open the drainage channel of underground water, realizes that tunnel-liner or underground structure behind underground water are actively drained, drop Low tunnel or underground structure external water pressure, prevent Lining cracks.After ground water pressure reduction, spring 10 restores with dynamic seal 7 To original position, drainage channel is closed.This structure can be used for tunnel side wall, inverted arch bottom, the full packet waterproof section of municipal works, Wireless water pressure monitor 13 is installed to lining cutting or underground structure in subway station, the engineerings such as basement position in combination with requirement of engineering Behind hydraulic pressure is monitored in real time, and accuracy and the technicalization for improving tunnel or underground engineering later maintenance improvement are horizontal.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention god.

Claims (10)

1. the drainage arrangement in a kind of tunnel and underground structure, it is characterised in that:It is tied through tunnel-liner or underground when including using The outer tube of structure(4), outer tube is stretched into lower end(4)In upper end and outer tube(4)The core pipe of threaded connection(3), and merging core Pipe(3)Interior discharge structure control unit;The outer tube(4)Lower part outer wall on be provided with several second drain holes(15); The core pipe(3)Lower end there is supporting part, and core pipe(3)Lower part outer wall on be provided with several first drain holes(5);It is described Discharge structure control unit includes being placed in core pipe(3)Stabilization block interior, on supporting part(12), lower end and stablize block(12)On The connected guide sleeve in end(11), guide sleeve is stretched into lower end(11)Interior and guide sleeve(11)The guide rod being slidably matched(9), and lead To bar(9)The connected connector in upper end(8), it is installed on connector(8)Upper end and core pipe(3)The sealing of the liquid-tight envelope cooperation of inner wall Part(7), it is set in guide sleeve(11)Upper, both ends respectively with stablize block(12)And connector(8)Connected spring(10), close core Pipe(3)The head cover of upper end(1), at least one is set to core pipe(3)In external wall of upper portion and core pipe(3)The transverse drain of connection (2), and it is set to stable block(12)Upper, the wireless hydraulic pressure detector for detecting hydraulic pressure(13);Work as spring(10)Suffered water It forces down in spring(10)Rated value when, sealing element(7)Sealing surface be not higher than transverse drain(2)Lower edge, work as spring (10)Suffered hydraulic pressure is more than spring(10)Rated value when, sealing element(7)It moves up, makes core pipe(3)Lower space with it is horizontal To drainpipe(2)Draining is realized in connection.
2. the drainage arrangement of tunnel and underground structure according to claim 1, it is characterised in that:Further include being located at sealing element (7)Upper end draw ring(6).
3. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:Further include outside being installed on Casing(4)Lower end, the header tank made of pervious concrete(14).
4. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The head cover(1)With core Pipe(3)It is connected by helicitic texture.
5. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The transverse drain (2)It is two, is symmetrically disposed on core pipe(3)On.
6. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The connector(8)With Sealing element(7)It is integrated.
7. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The guide rod(9)With Connector(8)It is connected by helicitic texture.
8. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The guide sleeve(11) With stablize block(12)It is connected by helicitic texture.
9. the drainage arrangement in tunnel according to claim 1 or claim 2 and underground structure, it is characterised in that:The stable block(12) Side wall setting the mounting hole of wireless water pressure monitor is installed.
10. the water discharge method in a kind of tunnel and underground structure, it is characterised in that drainage arrangement as described in claim 1 is used, It includes the following contents:According to tunnel or the specific hydrogeologic condition of underground engineering, between being pressed centainly in tunnel or underground structure Away from arrangement drainage arrangement;Sprayed at the beginning of the tunnel according to design requirement or underground structure pour before tunnel side wall, inverted arch bottom or Equipment installation position is reserved in underground structure;It is installed after outer tube is wrapped up non-woven fabrics, fixing clearance uses thin cobble or coarse sand Backfill is stablized;Outer tube top uses cylindricality template protection when cast in situs tunnel double-lining, inverted arch or underground structure, it is ensured that outer Casing is not blocked during casting concrete ensures connection space;Then carry out construction of shotcrete;Guide rod is set Inside guide sleeve, then by guide rod by the connector of screw thread and top, guide sleeve is passed through into screw thread and steady with lower part Determine block connection, wireless water pressure monitor is placed in stable block lower recess, spring is by connector and stablizes reserved spiral on block The installation of shape hole is fixed, to form discharge structure control unit;The control unit is integrally placed in core pipe, passes through top later It covers screw thread and screw thread installation head cover in core pipe top closes core pipe;It waits for that secondary lining or underground structure perform to finish Afterwards, outer tube installation is screwed by core pipe;When dry season hydraulic pressure is smaller, spring is in free state, and closure member blocks in core pipe Drain pipe channel, proper drainage will not penetrate into lining cutting or underground structure by core pipe behind inside tunnel or underground structure; After underground water enrichment hydraulic pressure becomes larger, underground water enters after outer tube filters in core pipe, to the sealing element shape in core pipe At pushing tow, when hydraulic pressure reaches setting value, spring elongation, water pressure pushing sealing element is integrally steadily moved up along guide rod, from And the drainage channel of underground water is opened, realize that tunnel-liner or underground structure behind underground water are actively drained.
CN201810943692.1A 2018-08-18 2018-08-18 The drainage arrangement and water discharge method in tunnel and underground structure Withdrawn CN108755722A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810943692.1A CN108755722A (en) 2018-08-18 2018-08-18 The drainage arrangement and water discharge method in tunnel and underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810943692.1A CN108755722A (en) 2018-08-18 2018-08-18 The drainage arrangement and water discharge method in tunnel and underground structure

Publications (1)

Publication Number Publication Date
CN108755722A true CN108755722A (en) 2018-11-06

Family

ID=63966222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810943692.1A Withdrawn CN108755722A (en) 2018-08-18 2018-08-18 The drainage arrangement and water discharge method in tunnel and underground structure

Country Status (1)

Country Link
CN (1) CN108755722A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486085A (en) * 2019-03-12 2019-11-22 浙江交工宏途交通建设有限公司 A kind of Karst Geological Landscape constructing tunnel drainage arrangement
CN115680765A (en) * 2022-12-30 2023-02-03 山西诚达公路勘察设计有限公司 Highway tunnel construction is with preventing stifled type ponding drainage device

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0119305A1 (en) * 1983-03-16 1984-09-26 Lang Apparatebau Gmbh Back-flow preventer, especially for drinking-water conduits
JPH05209500A (en) * 1991-06-27 1993-08-20 Kazunari Miyazaki Setting work of water-collecting tube for draining groundwater under ground of tunnel wall
JPH06193101A (en) * 1992-12-25 1994-07-12 Power Reactor & Nuclear Fuel Dev Corp Method and apparatus for sampling ground water
KR970002061A (en) * 1995-06-01 1997-01-24 서영만 Automatic water supply valve and its control device
RU2315247C1 (en) * 2005-06-03 2008-01-20 РЕГУЛУС, спол. с.р.о. Safety device for water-heating system (variants)
CN201056748Y (en) * 2007-05-29 2008-05-07 刘敏 Automatic flushing valve
DE202009010632U1 (en) * 2009-08-06 2009-10-01 Centrotherm Thermal Solutions Gmbh + Co. Kg Connector for gas or liquid lines
KR20100127497A (en) * 2009-05-26 2010-12-06 건국대학교 산학협력단 Device for controlling water pressure of tunnel
CN102128046A (en) * 2010-01-15 2011-07-20 淮南矿业(集团)有限责任公司 Automatic water discharge device
CN202560320U (en) * 2012-05-02 2012-11-28 中铁十一局集团第五工程有限公司 Frost-damage preventing drainage system for tunnels
CN203421330U (en) * 2013-08-19 2014-02-05 安徽省交通规划设计研究院有限公司 Detachable-washing double-wall sand filtering drain pipe
CN103899521A (en) * 2014-04-04 2014-07-02 天津机辆轨道交通装备有限责任公司 Automatic intermittent coal bed gas draining and generating method and device thereof
CN204082187U (en) * 2014-09-17 2015-01-07 黄胜 Recyclable thread bush tubular type anchor rod device
CN204983026U (en) * 2015-08-21 2016-01-20 山东绿屏工业消防设备有限公司 Outdoor fire hydrant
CN105840475A (en) * 2016-04-08 2016-08-10 郭菲 Durable low-cost automatic water level control switch
EP3064649A1 (en) * 2015-03-05 2016-09-07 Hydro Geotechnique Drainage device for deep soil
CN105971667A (en) * 2016-07-20 2016-09-28 中铁二院昆明勘察设计研究院有限责任公司 Preventing and treating structure for water-rich railway tunnel ballast bed mud pumping
CN106089296A (en) * 2016-06-16 2016-11-09 陕西省煤田地质有限公司 A kind of prevention and treatment method of roof absciss layer water
CN106968712A (en) * 2017-05-12 2017-07-21 西南交通大学 Water rich strata tunnel bottom discharge structure and its construction method
US20180002902A1 (en) * 2015-07-03 2018-01-04 Somjit Mandal Automatic fluid flow controlling device for stopping flow of running fluid
CN208685638U (en) * 2018-08-18 2019-04-02 中铁二院昆明勘察设计研究院有限责任公司 The drainage arrangement in tunnel and underground structure

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0119305A1 (en) * 1983-03-16 1984-09-26 Lang Apparatebau Gmbh Back-flow preventer, especially for drinking-water conduits
JPH05209500A (en) * 1991-06-27 1993-08-20 Kazunari Miyazaki Setting work of water-collecting tube for draining groundwater under ground of tunnel wall
JPH06193101A (en) * 1992-12-25 1994-07-12 Power Reactor & Nuclear Fuel Dev Corp Method and apparatus for sampling ground water
KR970002061A (en) * 1995-06-01 1997-01-24 서영만 Automatic water supply valve and its control device
RU2315247C1 (en) * 2005-06-03 2008-01-20 РЕГУЛУС, спол. с.р.о. Safety device for water-heating system (variants)
CN201056748Y (en) * 2007-05-29 2008-05-07 刘敏 Automatic flushing valve
KR20100127497A (en) * 2009-05-26 2010-12-06 건국대학교 산학협력단 Device for controlling water pressure of tunnel
DE202009010632U1 (en) * 2009-08-06 2009-10-01 Centrotherm Thermal Solutions Gmbh + Co. Kg Connector for gas or liquid lines
CN102128046A (en) * 2010-01-15 2011-07-20 淮南矿业(集团)有限责任公司 Automatic water discharge device
CN202560320U (en) * 2012-05-02 2012-11-28 中铁十一局集团第五工程有限公司 Frost-damage preventing drainage system for tunnels
CN203421330U (en) * 2013-08-19 2014-02-05 安徽省交通规划设计研究院有限公司 Detachable-washing double-wall sand filtering drain pipe
CN103899521A (en) * 2014-04-04 2014-07-02 天津机辆轨道交通装备有限责任公司 Automatic intermittent coal bed gas draining and generating method and device thereof
CN204082187U (en) * 2014-09-17 2015-01-07 黄胜 Recyclable thread bush tubular type anchor rod device
EP3064649A1 (en) * 2015-03-05 2016-09-07 Hydro Geotechnique Drainage device for deep soil
US20180002902A1 (en) * 2015-07-03 2018-01-04 Somjit Mandal Automatic fluid flow controlling device for stopping flow of running fluid
CN204983026U (en) * 2015-08-21 2016-01-20 山东绿屏工业消防设备有限公司 Outdoor fire hydrant
CN105840475A (en) * 2016-04-08 2016-08-10 郭菲 Durable low-cost automatic water level control switch
CN106089296A (en) * 2016-06-16 2016-11-09 陕西省煤田地质有限公司 A kind of prevention and treatment method of roof absciss layer water
CN105971667A (en) * 2016-07-20 2016-09-28 中铁二院昆明勘察设计研究院有限责任公司 Preventing and treating structure for water-rich railway tunnel ballast bed mud pumping
CN106968712A (en) * 2017-05-12 2017-07-21 西南交通大学 Water rich strata tunnel bottom discharge structure and its construction method
CN208685638U (en) * 2018-08-18 2019-04-02 中铁二院昆明勘察设计研究院有限责任公司 The drainage arrangement in tunnel and underground structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486085A (en) * 2019-03-12 2019-11-22 浙江交工宏途交通建设有限公司 A kind of Karst Geological Landscape constructing tunnel drainage arrangement
CN110486085B (en) * 2019-03-12 2020-12-11 浙江交工宏途交通建设有限公司 Karst geology tunnel construction drainage device
CN115680765A (en) * 2022-12-30 2023-02-03 山西诚达公路勘察设计有限公司 Highway tunnel construction is with preventing stifled type ponding drainage device

Similar Documents

Publication Publication Date Title
CN106285693B (en) A kind of closed reception construction method of shield steel bushing
CN106836285B (en) Building informatization-based underground pipe gallery monitoring waterproof structure
CN110566273B (en) Drainage system and drainage method for treating tunnel surrounding rock fracture water
CN206441014U (en) A kind of irrigation and water conservancy disaster alarm and system of defense
CN208441890U (en) A kind of construction tunnel long range counter-slope drainage system
CN108755722A (en) The drainage arrangement and water discharge method in tunnel and underground structure
CN107542106A (en) The pipe gallery built using the pavement underground space
CN110185020A (en) A kind of siphon drainage collection system
CN208685638U (en) The drainage arrangement in tunnel and underground structure
CN106168142A (en) The water discharge method of tunnel bedrock underground water
CN205714215U (en) Tunnel-liner decompression section of jurisdiction and pipe-plate lining structure
CN212958756U (en) Intelligent water drainage pressure reducing device for water-rich tunnel
CN109339215A (en) Replacement of not cutting off the water supply passes in and out the device and method of sluice gate
CN109024640A (en) One kind closing water valve device, shut-in well structure and its construction method
CN108252278B (en) The row of replaceable filtration core seeps device and filtration core replacing options in Tailings Dam
CN208633873U (en) A kind of tunnels and underground engineering structure is with can maintenance type drainage system
CN107489096B (en) A kind of quick collection system of urban elevated road rainwater and its construction method
CN207513633U (en) The pressure limiting drainage system of tunnel anti-hydraulic pressure section
CN214499054U (en) Shield belt conveyor with slag receiving box and rapid discharge equipment
CN205329674U (en) Underground continuous wall structure under fluid bowl or channelling geological conditions
CN209760395U (en) Municipal administration rainwater drainage system
CN110644602B (en) Automatic rainwater of adjusting is held and is oozed utilization system
CN209227570U (en) Stratum dewatering construction device
CN209166503U (en) A kind of opening arrangement for underground bottom plate outflow test
CN206625322U (en) Separate type road is pre-buried to use drain pipe equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20181106

WW01 Invention patent application withdrawn after publication