CN108755692A - Underground structure concrete casting method - Google Patents

Underground structure concrete casting method Download PDF

Info

Publication number
CN108755692A
CN108755692A CN201810613041.6A CN201810613041A CN108755692A CN 108755692 A CN108755692 A CN 108755692A CN 201810613041 A CN201810613041 A CN 201810613041A CN 108755692 A CN108755692 A CN 108755692A
Authority
CN
China
Prior art keywords
concrete
pours
layer
wall
concreting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810613041.6A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810613041.6A priority Critical patent/CN108755692A/en
Publication of CN108755692A publication Critical patent/CN108755692A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention belongs to concreting technical fields, more particularly, to underground structure concrete casting method.Its casting method:When carrying out plane pouring, it then follows from as far as it is close, to the ramp structure formula of pushing ahead pour operation from the bottom up;When winter construction is constructed, to control concrete molding temperature will control at 10 DEG C or more, carry out heat and moisture preserving maintenance after pouring in time;Walls concrete answers placement layer by layer, first layer concreting height to control in 300mm or so, pours height every time later and 500mm is not to be exceeded, and pours height and is controlled with the ruler brushed by lift height different colours paint;Layering is finally carried out to vibrate.The technological process and operating method that its stringent control underground cement pours, to ensure the stability of the structure of buried concrete, while specification pours fixed form and the connection method of pipeline, to ensure being perfectly safe for construction.

Description

Underground structure concrete casting method
Technical field
The invention belongs to concreting technical fields, more particularly, to underground structure concrete casting method.
Background technology
Concreting refers to concreting entering mould the process until plasticizing.Buried concrete pours different earth's surfaces It pours, more problems needed to be considered, and traditional buried concrete casting method is relatively rough, it is impossible to ensure that engineering matter Amount, needs the later stage to be repaired, cumbersome.
Invention content
In view of the defects and deficiencies of the prior art, the present invention intends to provide a kind of simple in structure, reasonable design makes With convenient underground structure concrete casting method, it strictly controls the technological process and operating method that underground cement pours, with Ensure the stability of the structure of buried concrete, while specification pours fixed form and the connection method of pipeline, to ensure to apply Work is perfectly safe.
To achieve the above object, the technical solution adopted by the present invention is:Its construction method and flow:
Step 1:Sole plate concreting
When A, using delivery pipe delivering concrete, Ying Youyuan and closely pour, the concrete in the same area, should be by first vertical structure The sequence of horizontal structure afterwards, stratified continuous pouring;I.e. casting direction takes inclined plane delamination to promote from one end to the other end, once from Bottom to top casting method pours, and elevator foundation pit and catch pit should be first poured when pouring, after its absolute altitude is consistent with board bottom absolute altitude again Pour large area;
B, concreting should be carried out continuously, and stringent control is poured from one and pours interval;Such as necessary interval, the intermittent time answers Shorten as possible, the intermittent time is not more than the presetting period, and should be complete by sublevel concreting before front layer concrete initial set Finish, and layer concrete 50mm before vibrating spear underthrust;Underplate concrete pours a period of time in advance at elevator, catch pit, but wants Ensure to pour elevator, crater wall of catchmenting concrete before initial set;
The actual conditions of one gradient of self-assembling formation when C, being poured according to pumping are poured in per pass and are vibrated with front and back arrangement three Stick, preceding road vibrating spear are arranged at the placing of reinforcement of bottom and at concrete slope foot, and vibrating spear is carried out with concrete surface at 40~45 degree Vibrate, it is ensured that lower part concrete compaction, rear road vibrating spear are arranged in pouring out concrete point, solve top concrete vibrate with it is close It is real;
D, sole plate thickness is 700mm, inclined plane delamination should be used to be segmented the method poured, avoid the occurrence of cold seam;It can be by 1:6- 1:10 sloping concreting in lifts;Pouring middle concrete will pave uniformly, collapse consistent, and fully vibrating enables each layer concrete to be formed One is whole, keeps its contraction distortion consistent;
E, vibrating spear is inserted pull out slowly soon, preferably slightly twitches vibrating spear up and down in process of vibrating, so that up-down vibration is uniform;Vibrating spear moves Dynamic spacing≤400mm.Every vibrating time 15-30 seconds, vibrate to the bleeding of concrete surface whole, bubble-free, do not sink subject to; Vibrate last layer when should be inserted into lower layer 50mm to eliminate the seam of two interlayers;
F, base exterior wall leads wall concreting to the middle part of steel plate for sealing water (3mm thickness, 250mm high), pours sequence first to pour Underplate concrete pours exterior wall and leads wall concrete after pouring 2~3 hours close to exterior wall underplate concrete;
G, during concreting, steel bar stress, positioning bar, the built-in fitting etc. for arranging displacement in time and deforming, and and When remove concrete surface bleeding;
H, construction is it is noted that prevent surface concrete contraction fissure and thermal cracking, the concrete surface of horizontal structure, in initial set First 2-3 hours comes into effect and smears pressure, to smooth out rubbing and pressure with wooden float in due course, make real, and arrange reinforcement location;In concrete final set First 2-3 hours carries out second plastering to its surface again or repeatedly smears pressure processing, and contraction fissure, desciccation crack is made to be closed;
I, when winter construction is constructed, to control concrete molding temperature will control at 10 DEG C or more, be protected in time after pouring Warm moisture-keeping maintaining, heat preserving method are first to cover layer of plastic film, then cover the double-deck straw screen or mat quilt;The duration of moisture-keeping maintaining is not It obtains and is less than 14d;
Step 2: wall concrete placings
A, before wall concrete placings, first the cement bonded sand that 50-100mm thickness removes with walls concrete match ratio stone is uniformly poured in bottom Slurry, is used in combination spade to enter mould, does not apply hopper directly to pour into mould;
B, walls concrete pours blanking point and answers dispersed placement, and wall height directly can descend ash to pour within 3m in wall top, pump line or Hose should be added at hopper discharge outlets and is goed deep within the walls, and to ensure that concrete freely inclines drop height degree less than 2 meters, wall height is more than 3m When, string bucket blanking should be used;
C, walls concrete, which pours, to be carried out continuously, and 2h is not to be exceeded in interval time;
D, walls concrete answers placement layer by layer, first layer concreting height to control in 300mm or so, pours height every time later 500mm is not to be exceeded in degree, pours height and is controlled with the ruler brushed by lift height different colours paint;
E, walls concrete is vibrated using poker vibrator layering, and vibrating spear should accomplish " fast insert is pulled out slowly " when vibrating, and be inserted into Point arrangement is uniform, and the spacing of 30mm or more should be kept with template, and to collide reinforcing bar and built-in fitting when without vibration, vibrating spear moves Dynamic spacing is 1.25 times of its operating radius (35cm-38.5cm) and is not more than 500mm;To ensure that levels concrete can combine Integral, when carrying out upper layer concrete vibrating, vibrating spear should be inserted into lower-layer concrete and be not less than 50 mm, and mixed in next layer Before solidifying soil initial set, upper layer concrete vibrating is finished.Concrete vibration time is no longer significantly sunk with concrete, surface bubble-free And when flashing mud until;
F, concreting, which is vibrated, finishes, and should be arranged the reinforcing bar suitable for reading thrown away, presses predetermined elevation line with wooden float, will mix Solidifying soil surface smoothes out;Walls concrete pours height and necessarily is greater than floor lower surface 20mm, in order to wall top concrete laitance It rejects and the joint part of construction joint reason answers first snap the line to determine the concrete component section ruler at the position when construction joint position is handled It is very little, then go out to pick chisel range along sectional dimension wire cutting with cutting machine, chisel range inner concrete surface laitance will be picked and loosen stone Son is rejected, and picks chisel to stone is exposed, and chisel should be picked from wall two towards centre when picking chisel.
G, it before walls concrete pours, is rinsed with clear water and is sufficiently humidified so as to construction seam surface, but must not have product in template Water.
2, underground structure concrete casting method according to claim 1, it is characterised in that:The cloth of the pump line It sets:
One, the principle that pump line arrangement follows " route is short, elbow is few, connector is tight " is originally poured, emphasis is to following when pump line is arranged Problem is controlled:
A, pump line of the present invention selects caliber 125, the abrasion-proof manganese steel seamless steel pipe of wall thickness 3.6mm.
B, at pump machine exit cone, do not allow directly to connect bend pipe, should at least pick out 10 meters or more of straight tube, then connect again 90 ° of elbows turn to vertical transport.When pump line is piped vertically upward, horizontal length of tube should be not less than vertical length of tube four/ One, and it is not less than 15m.When pump line is piped downwards, air bleeding valve should be set in the upper end of inclined tube.When need to do 90 ° of steerings, song should be used Rate radius is more than 1 meter or more of big elbow.
C, concrete pipeline does not allow to bear any pulling force in concrete delivery service.
D, each piping connection should be secured, stable, and pipe bent position, which adds, to be firmly fixed a little, in case pipeline generation is shaken when pumping It shakes, loosen.Pump line pipe clamp should not be contacted with ground or supporter, in order to dismount, while should be fastened in place, to ensure that pump line connects Head is tight, not spillage, gas leakage, and horizontal pipeline, which is laid under pump line, should secure support.
Two, it originally pours pump line to fix, must not be supported directly on reinforcing bar, template, outrigger and built-in fitting, and should meet following Regulation:
A, horizontal tube:It is fixed with holder, cushion, suspender etc. every 2~3m distances(Per the effective two steel pipe branch of horizontal on ground Frame is fixed), in order to exclude plugging, assembly and disassembly and Cleaning pipes;
B, vertical tube:Concrete pump pipe hole is reserved on floor, pump line pierced and fixed with timber wedge from construction.
With the above structure, the present invention has the beneficial effect that:Underground structure concrete casting method of the present invention, it The technological process and operating method that stringent control underground cement pours, to ensure the stability of the structure of buried concrete, simultaneously Specification pours fixed form and the connection method of pipeline, to ensure being perfectly safe for construction.The present invention have it is simple in structure, if The advantages that it is reasonable to set, low manufacture cost.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention without having to pay creative labor, may be used also for those of ordinary skill in the art With obtain other attached drawings according to these attached drawings.
Fig. 1 is that the vibrating spear of the present invention is layered the schematic diagram that vibrates.
Fig. 2 is that the concrete application minor diameter vibrating spear of the present invention vibrates schematic diagram.
Fig. 3 is the floor concrete casting absolute altitude control schematic diagram of the present invention.
Fig. 4 is the erection form schematic diagram of the pump line of the present invention.
Fig. 5 is the concrete pump line through-flooring node diagram of the present invention.
Specific implementation mode
Below in conjunction with the accompanying drawings, the present invention is further illustrated.
Present embodiment adopts the following technical scheme that:Step 1:Sole plate concreting
When A, using delivery pipe delivering concrete, Ying Youyuan and closely pour, the concrete in the same area, should be by first vertical structure The sequence of horizontal structure afterwards, stratified continuous pouring;I.e. casting direction takes inclined plane delamination to promote from one end to the other end, once from Bottom to top casting method pours, and elevator foundation pit and catch pit should be first poured when pouring, after its absolute altitude is consistent with board bottom absolute altitude again Pour large area;
B, concreting should be carried out continuously, and stringent control is poured from one and pours interval;Such as necessary interval, the intermittent time answers Shorten as possible, the intermittent time is not more than the presetting period, and should be complete by sublevel concreting before front layer concrete initial set Finish, and layer concrete 50mm before vibrating spear underthrust;Underplate concrete pours a period of time in advance at elevator, catch pit, but wants Ensure to pour elevator, crater wall of catchmenting concrete before initial set;
The actual conditions of one gradient of self-assembling formation when C, being poured according to pumping are poured in per pass and are vibrated with front and back arrangement three Stick, preceding road vibrating spear are arranged at the placing of reinforcement of bottom and at concrete slope foot, and vibrating spear is carried out with concrete surface at 40~45 degree Vibrate, it is ensured that lower part concrete compaction, rear road vibrating spear are arranged in pouring out concrete point, solve top concrete vibrate with it is close It is real;
D, sole plate thickness is 700mm, inclined plane delamination should be used to be segmented the method poured, avoid the occurrence of cold seam;It can be by 1:6- 1:10 sloping concreting in lifts;Pouring middle concrete will pave uniformly, collapse consistent, and fully vibrating enables each layer concrete to be formed One is whole, keeps its contraction distortion consistent;
E, vibrating spear is inserted pull out slowly soon, preferably slightly twitches vibrating spear up and down in process of vibrating, so that up-down vibration is uniform;Vibrating spear moves Dynamic spacing≤400mm.Every vibrating time 15-30 seconds, vibrate to the bleeding of concrete surface whole, bubble-free, do not sink subject to; Vibrate last layer when should be inserted into lower layer 50mm to eliminate the seam of two interlayers;
F, base exterior wall leads wall concreting to the middle part of steel plate for sealing water (3mm thickness, 250mm high), pours sequence first to pour Underplate concrete pours exterior wall and leads wall concrete after pouring 2~3 hours close to exterior wall underplate concrete;
G, during concreting, steel bar stress, positioning bar, the built-in fitting etc. for arranging displacement in time and deforming, and and When remove concrete surface bleeding;
H, construction is it is noted that prevent surface concrete contraction fissure and thermal cracking, the concrete surface of horizontal structure, in initial set First 2-3 hours comes into effect and smears pressure, to smooth out rubbing and pressure with wooden float in due course, make real, and arrange reinforcement location;In concrete final set First 2-3 hours carries out second plastering to its surface again or repeatedly smears pressure processing, and contraction fissure, desciccation crack is made to be closed;
I, when winter construction is constructed, to control concrete molding temperature will control at 10 DEG C or more, be protected in time after pouring Warm moisture-keeping maintaining, heat preserving method are first to cover layer of plastic film, then cover the double-deck straw screen or mat quilt;The duration of moisture-keeping maintaining is not It obtains and is less than 14d;
Step 2: wall concrete placings
A, before wall concrete placings, first the cement bonded sand that 50-100mm thickness removes with walls concrete match ratio stone is uniformly poured in bottom Slurry, is used in combination spade to enter mould, does not apply hopper directly to pour into mould;
B, walls concrete pours blanking point and answers dispersed placement, and wall height directly can descend ash to pour within 3m in wall top, pump line or Hose should be added at hopper discharge outlets and is goed deep within the walls, and to ensure that concrete freely inclines drop height degree less than 2 meters, wall height is more than 3m When, string bucket blanking should be used;
C, walls concrete, which pours, to be carried out continuously, and 2h is not to be exceeded in interval time;
D, walls concrete answers placement layer by layer, first layer concreting height to control in 300mm or so, pours height every time later 500mm is not to be exceeded in degree, pours height and is controlled with the ruler brushed by lift height different colours paint;
E, such as Fig. 1, walls concrete are vibrated using poker vibrator layering, and vibrating spear should accomplish " fast insert is pulled out slowly " when vibrating, And insertion point arrangement is uniform, and the spacing of 30mm or more should be kept to shake to collide reinforcing bar and built-in fitting when without vibration with template Tamper moves 1.25 times that spacing is its operating radius (35cm-38.5cm) and is not more than 500mm;To ensure levels concrete It can combine integral, when carrying out upper layer concrete vibrating, vibrating spear should be inserted into lower-layer concrete not less than 50 mm, and under Before one layer concrete initial set, upper layer concrete vibrating is finished.Concrete vibration time is no longer significantly sunk with concrete, surface Until when bubble-free and flashing mud;
F, concreting, which is vibrated, finishes, and should be arranged the reinforcing bar suitable for reading thrown away, presses predetermined elevation line with wooden float, will mix Solidifying soil surface smoothes out;Walls concrete pours height and necessarily is greater than floor lower surface 20mm, in order to wall top concrete laitance It rejects and the joint part of construction joint reason answers first snap the line to determine the concrete component section ruler at the position when construction joint position is handled It is very little, then go out to pick chisel range along sectional dimension wire cutting with cutting machine, chisel range inner concrete surface laitance will be picked and loosen stone Son is rejected, and picks chisel to stone is exposed, and chisel should be picked from wall two towards centre when picking chisel.
G, it before walls concrete pours, is rinsed with clear water and is sufficiently humidified so as to construction seam surface, but must not have product in template Water.
In addition, beam, board concrete casting method:
A, beam, board concrete pour simultaneously, and casting method uses " catching up with slurry processes ", i.e., first casting beams concrete, by beam according to deck-molding Placement layer by layer pours together with board concrete, with rank again at stairstepping when beam concreting height reaches board bottom position Trapezoidal continuous extension, beam slab concreting are continuously carried forward.
When casting beams board concrete, cloth, cloth must not should be moved horizontally in 2-3 meters of ranges in same place continuous cloth Material is preferably perpendicular to template, and fabric thickness should be higher 2-3mm than floorslab concrete finished surface.Profit pipe mortar should be discharged into ash-pit, Forbid to be directly discharged on top plate.
B, beam slab concrete using vibrator as a plug along casting direction it is dilatory vibrate by the way of, must not in process of vibrating Leakage, to ensure concrete compaction;Do not allow to spread out and put on concrete with vibrating spear when casting beams board concrete, it is necessary to be paved with spade Concrete;Ruler should be inserted with iron check concrete thickness, and bracing wire control concrete upper surface absolute altitude at any time in work progress.
When bean column node position reinforcing bar is closeer, concrete application minor diameter vibrating spear vibrates, referring to Fig. 2
C, after beam slab concreting to initial set before, first concrete surface should be struck off with long darby, with wooden float first Secondary compacting after initial set, is compacted for second with wooden float, rubs hair with the hands, before waiting for concrete final set, i.e., when foot steps on slightly footprint, used Wooden float third time is compacted, and rubs hair with the hands, when third time is compacted rub hair with the hands, it should be noted that the moving law of wooden float makes the line after stranding hair There is certain regularity on road.
D, it is still necessary to use plasterer's trowel after using 3m darbys, surface to be put down with wooden float stranding when levelling away from wall side 200mm range plate faces Press polish, plate face flatness tolerance control within 2mm, to reduce the gap under template between mouth and floor, prevent wall Occurs spillage phenomenon when concreting;Referring to Fig. 3.
E, the compression strength of concrete should can continue casting concrete when not less than 1.2MPa at Beam-Slab Construction seam. Before continuing casting concrete, concrete surface should reject laitance at construction joint, and dabbing is rinsed with water and fills to after exposing stone Divide moistening.It should be first cut into cutting machine before dabbing at construction joint and pick the chisel position line, then can pick chisel, pick the same wall of chisel method Body.
Wherein, the method for arranging of the pump line:
One, the principle that pump line arrangement follows " route is short, elbow is few, connector is tight " is originally poured, emphasis is to following when pump line is arranged Problem is controlled:
A, pump line of the present invention selects caliber 125mm, the abrasion-proof manganese steel seamless steel pipe of wall thickness 3.6mm.
B, at pump machine exit cone, do not allow directly to connect bend pipe, should at least pick out 10 meters or more of straight tube, then connect again 90 ° of elbows turn to vertical transport.When pump line is piped vertically upward, horizontal length of tube should be not less than vertical length of tube four/ One, and it is not less than 15m.When pump line is piped downwards, air bleeding valve should be set in the upper end of inclined tube.When need to do 90 ° of steerings, song should be used Rate radius is more than 1 meter or more of big elbow.
C, concrete pipeline does not allow to bear any pulling force in concrete delivery service.
D, each piping connection should be secured, stable, and pipe bent position, which adds, to be firmly fixed a little, in case pipeline generation is shaken when pumping It shakes, loosen.Pump line pipe clamp should not be contacted with ground or supporter, in order to dismount, while should be fastened in place, to ensure that pump line connects Head is tight, not spillage, gas leakage, and horizontal pipeline, which is laid under pump line, should secure support.The erection form of pump line refers to lower Fig. 4.
Two, it originally pours pump line to fix, must not be supported directly on reinforcing bar, template, outrigger and built-in fitting, and should meet following Regulation:
A, horizontal tube:It is fixed with holder, cushion, suspender etc. every 2~3m distances(Per the effective two steel pipe branch of horizontal on ground Frame is fixed), in order to exclude plugging, assembly and disassembly and Cleaning pipes;
B, vertical tube:Concrete pump pipe hole is reserved on floor, pump line pierced and fixed with timber wedge from construction.Fixed form is detailed See Figure 5:
With the above structure, the present invention has the beneficial effect that:Underground structure concrete casting method of the present invention, it is stringent The technological process and operating method that control underground cement pours, to ensure the stability of the structure of buried concrete, while specification Fixed form and the connection method for pouring pipeline, to ensure being perfectly safe for construction.
The above is merely illustrative of the technical solution of the present invention and unrestricted, and those of ordinary skill in the art are to this hair The other modifications or equivalent replacement that bright technical solution is made, as long as it does not depart from the spirit and scope of the technical scheme of the present invention, It is intended to be within the scope of the claims of the invention.

Claims (8)

1. underground structure concrete casting method, it is characterised in that:Its sole plate concreting flow:
When a, using delivery pipe delivering concrete, Ying Youyuan and closely pour, the concrete in the same area, should be by first vertical structure The sequence of horizontal structure afterwards, stratified continuous pouring;I.e. casting direction takes inclined plane delamination to promote from one end to the other end, once from Bottom to top casting method pours, and elevator foundation pit and catch pit should be first poured when pouring, after its absolute altitude is consistent with board bottom absolute altitude again Pour large area;
B, concreting should be carried out continuously, and stringent control is poured from one and pours interval;Such as necessary interval, the intermittent time answers Shorten as possible, the intermittent time is not more than the presetting period, and should be complete by sublevel concreting before front layer concrete initial set Finish, and layer concrete 50mm before vibrating spear underthrust;Underplate concrete pours a period of time in advance at elevator, catch pit, but wants Ensure to pour elevator, crater wall of catchmenting concrete before initial set;
The actual conditions of one gradient of self-assembling formation when c, being poured according to pumping are poured in per pass and are vibrated with front and back arrangement three Stick, preceding road vibrating spear are arranged at the placing of reinforcement of bottom and at concrete slope foot, it is ensured that lower part concrete compaction, rear road vibrating spear arrangement In pouring out concrete point, solve top concrete vibrate with it is closely knit;
D, sole plate thickness is 700mm, inclined plane delamination should be used to be segmented the method poured, avoid the occurrence of cold seam;It can be by 1:6- 1:10 sloping concreting in lifts;Pouring middle concrete will pave uniformly, collapse consistent, and fully vibrating enables each layer concrete to be formed One is whole, keeps its contraction distortion consistent;
E, vibrating spear is inserted pull out slowly soon, preferably slightly twitches vibrating spear up and down in process of vibrating, so that up-down vibration is uniform;Vibrate upper one Lower layer 50mm should be inserted into eliminate the seam of two interlayers when layer;
F, base exterior wall leads wall concreting to the middle part of steel plate for sealing water (3mm thickness, 250mm high), pours sequence first to pour Underplate concrete pours exterior wall and leads wall concrete after pouring 2-3 hours close to exterior wall underplate concrete;
G, during concreting, steel bar stress, positioning bar, the built-in fitting etc. for arranging displacement in time and deforming, and and When remove concrete surface bleeding;
H, construction is it is noted that prevent surface concrete contraction fissure and thermal cracking, the concrete surface of horizontal structure, in initial set First 2-3 hours comes into effect and smears pressure, to smooth out rubbing and pressure with wooden float in due course, make real, and arrange reinforcement location;In concrete final set First 2-3 hours carries out second plastering to its surface again or repeatedly smears pressure processing, and contraction fissure, desciccation crack is made to be closed.
2. underground structure concrete casting method, it is characterised in that:Its wall concrete placings flow:
1) before wall concrete placings, first the cement bonded sand that 50-100mm thickness removes with walls concrete match ratio stone is uniformly poured in bottom Slurry, is used in combination spade to enter mould, does not apply hopper directly to pour into mould;
2) walls concrete pours blanking point and answers dispersed placement, and wall height directly can descend ash to pour within 3m in wall top, pump line or Hose should be added at hopper discharge outlets and is goed deep within the walls, and to ensure that concrete freely inclines drop height degree less than 2 meters, wall height is more than 3m When, string bucket blanking should be used;
3) walls concrete, which pours, to be carried out continuously, and 2h is not to be exceeded in interval time;
4) walls concrete answers placement layer by layer, first layer concreting height to control in 300mm or so, pours height every time later 500mm is not to be exceeded in degree, pours height and is controlled with the ruler brushed by lift height different colours paint;
5) walls concrete is vibrated using poker vibrator layering, and vibrating spear should accomplish " fast insert is pulled out slowly " when vibrating, and be inserted into Point arrangement is uniform, and the spacing of 30mm or more should be kept with template, and to collide reinforcing bar and built-in fitting when without vibration, vibrating spear moves Dynamic spacing is 1.25 times of its operating radius (35cm-38.5cm) and is not more than 500mm;Concrete vibration time with concrete not Significantly sink again, when surface bubble-free and flashing mud until;
6) concreting, which is vibrated, finishes, and should be arranged the reinforcing bar suitable for reading thrown away, presses predetermined elevation line with wooden float, will mix Solidifying soil surface smoothes out;Walls concrete pours height and necessarily is greater than floor lower surface 20mm, in order to wall top concrete laitance It rejects and the joint part of construction joint reason answers first snap the line to determine the concrete component section ruler at the position when construction joint position is handled It is very little, then go out to pick chisel range along sectional dimension wire cutting with cutting machine, chisel range inner concrete surface laitance will be picked and loosen stone Son is rejected, and picks chisel to stone is exposed, and chisel should be picked from wall two towards centre when picking chisel;
7) it before walls concrete pours, is rinsed with clear water and is sufficiently humidified so as to construction seam surface, but must not have ponding in template.
3. underground structure concrete casting method according to claim 1, it is characterised in that:The arrangement side of the pump line Method:
Originally the principle that pump line arrangement follows " route is short, elbow is few, connector is tight " is poured, emphasis is asked following when pump line is arranged Topic is controlled:
I, pump line of the present invention selects caliber 125, the abrasion-proof manganese steel seamless steel pipe of wall thickness 3.6mm;
II, at pump machine exit cone, do not allow directly to connect bend pipe, should at least pick out 10 meters or more of straight tube, then connect again 90 ° it is curved Head turns to vertical transport;When pump line is piped vertically upward, horizontal length of tube should be not less than a quarter of vertical length of tube, and And it is not less than 15m;When pump line is piped downwards, air bleeding valve should be set in the upper end of inclined tube;When need to do 90 ° of steerings, curvature half should be used Diameter is more than 1 meter or more of big elbow;
C, concrete pipeline does not allow to bear any pulling force in concrete delivery service;
D, each piping connection is answered secured, stable, and pipe bent position, which adds, to be firmly fixed a little, in case pipeline generation rocks, is loose when pumping It is de-;Pump line pipe clamp should not be contacted with ground or supporter, in order to dismount, while should be fastened in place, to ensure that pump pipe union is tight Close, not spillage, gas leakage, horizontal pipeline, which is laid under pump line, should secure support.
4. underground structure concrete casting method according to claim 1, it is characterised in that:The pump line fixation side Method:
Originally it pours pump line to fix, must not be supported directly on reinforcing bar, template, outrigger and built-in fitting, and should meet the following requirements:
A, horizontal tube:It is fixed with holder, cushion, suspender etc. every 2-3m distances(Per the effective two steel pipe branch of horizontal on ground Frame is fixed), in order to exclude plugging, assembly and disassembly and Cleaning pipes;
B, vertical tube:Concrete pump pipe hole is reserved on floor, pump line pierced and fixed with timber wedge from construction.
5. underground structure concrete casting method according to claim 1, it is characterised in that:The roads step c Zhong Qian Vibrating spear vibrates with concrete surface at 40-45 degree.
6. underground structure concrete casting method according to claim 1, it is characterised in that:It vibrates in the step e Stick moves spacing≤400mm;Every vibrating time 15-30 seconds, vibrates to the bleeding of concrete surface whole, bubble-free, does not sink Subject to.
7. underground structure concrete casting method according to claim 1, it is characterised in that:One-piece casting process is in the teletostage When construction, to control concrete molding temperature will control at 10 DEG C or more, carry out heat and moisture preserving maintenance, heat preservation side after pouring in time Method is first to cover layer of plastic film, then cover the double-deck straw screen or mat quilt;The duration of moisture-keeping maintaining must not be less than 14d.
8. underground structure concrete casting method according to claim 2, it is characterised in that:In step 5, to ensure to go up, Lower-layer concrete can be in conjunction with integral, when carrying out upper layer concrete vibrating, and vibrating spear should be inserted into lower-layer concrete not less than 50 Mm, and before next layer concrete initial set, upper layer concrete vibrating is finished.
CN201810613041.6A 2018-06-14 2018-06-14 Underground structure concrete casting method Pending CN108755692A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810613041.6A CN108755692A (en) 2018-06-14 2018-06-14 Underground structure concrete casting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810613041.6A CN108755692A (en) 2018-06-14 2018-06-14 Underground structure concrete casting method

Publications (1)

Publication Number Publication Date
CN108755692A true CN108755692A (en) 2018-11-06

Family

ID=64022280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810613041.6A Pending CN108755692A (en) 2018-06-14 2018-06-14 Underground structure concrete casting method

Country Status (1)

Country Link
CN (1) CN108755692A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372264A (en) * 2018-12-07 2019-02-22 南京科技职业学院 Cesspool pool wall casting system and its construction method in a kind of industrial premises room
CN109469292A (en) * 2018-12-24 2019-03-15 漳州职业技术学院 A kind of construction method of moulding and double drips
CN110485463A (en) * 2019-08-30 2019-11-22 中建五局土木工程有限公司 Vertically to wall pouring construction method and pouring construction device
CN112248183A (en) * 2020-09-16 2021-01-22 绍兴中亚工贸园有限公司 Winter casting process for pipe sheet
CN113944480A (en) * 2021-10-14 2022-01-18 中国水利水电科学研究院 Temperature control anti-cracking method for door wall of shield working well
CN114164932A (en) * 2021-11-17 2022-03-11 中建八局西南建设工程有限公司 Simple concrete pouring thickness control device and method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264676A (en) * 2014-09-25 2015-01-07 沈建东 Construction method of mass concrete of high-rise building foundations

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104264676A (en) * 2014-09-25 2015-01-07 沈建东 Construction method of mass concrete of high-rise building foundations

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
常建立等: "《建筑工程施工技术(下)》", 31 January 2013, 北京理工大学出版社 *
谭洪光等: "《预拌混凝土实用技术—2015CCPA预拌混凝土分会年会暨第二届绿色混凝土发展高峰论坛论文集》", 31 October 2015, 中国建筑工业出版社 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109372264A (en) * 2018-12-07 2019-02-22 南京科技职业学院 Cesspool pool wall casting system and its construction method in a kind of industrial premises room
CN109469292A (en) * 2018-12-24 2019-03-15 漳州职业技术学院 A kind of construction method of moulding and double drips
CN110485463A (en) * 2019-08-30 2019-11-22 中建五局土木工程有限公司 Vertically to wall pouring construction method and pouring construction device
CN110485463B (en) * 2019-08-30 2024-03-26 中建五局土木工程有限公司 Vertical wall pouring construction method and pouring construction device
CN112248183A (en) * 2020-09-16 2021-01-22 绍兴中亚工贸园有限公司 Winter casting process for pipe sheet
CN113944480A (en) * 2021-10-14 2022-01-18 中国水利水电科学研究院 Temperature control anti-cracking method for door wall of shield working well
CN114164932A (en) * 2021-11-17 2022-03-11 中建八局西南建设工程有限公司 Simple concrete pouring thickness control device and method

Similar Documents

Publication Publication Date Title
CN108755692A (en) Underground structure concrete casting method
CN103821364B (en) The construction method of reinforced concrete water pond
CN106192907B (en) Add the construction method of 150m~300m grade high concrete panel rock-fill dams of cement sand and gravel structure sheaf
CN102003069B (en) Construction method and pouring device for framework masonry infill wall structure
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
US2729093A (en) Swimming pool and method of construction
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN106759126B (en) Construction method of side slope support drainage channel
CN107653894A (en) A kind of construction technology that foundation platform is made by precast concrete
CN113668928B (en) Method for controlling construction cracks of ultra-large-volume concrete water pool
CN107090777A (en) A kind of T beam manufacture methods for reducing blibbing
CN109457728A (en) A kind of steel reinforced concrete pipe gallery quickly builds construction method
CN110792200A (en) Masonry construction method without post-picking and pipe wrapping structure thereof
CN110485218A (en) It is a kind of to help wide construction method for railway bed
CN107476567A (en) It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN111535545B (en) Construction process of large-area concrete wear-resistant terrace
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN108457190A (en) Anchor ceiling board construction method before anchorage
CN110004787A (en) Pier storage yard road concrete surface construction method
CN110528524A (en) Volume of concrete foundation unit cellular-type construction method
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN109610842A (en) A kind of concrete jacking pump send construction method
CN106968398A (en) A kind of process that support column is poured below balcony
CN113914530B (en) Inclined roof fish scale type concrete structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181106

WD01 Invention patent application deemed withdrawn after publication