CN108755670A - The control of pile crown absolute altitude and protective device and pile crown construction method - Google Patents

The control of pile crown absolute altitude and protective device and pile crown construction method Download PDF

Info

Publication number
CN108755670A
CN108755670A CN201810794681.1A CN201810794681A CN108755670A CN 108755670 A CN108755670 A CN 108755670A CN 201810794681 A CN201810794681 A CN 201810794681A CN 108755670 A CN108755670 A CN 108755670A
Authority
CN
China
Prior art keywords
pile crown
casing
absolute altitude
pile
protective device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810794681.1A
Other languages
Chinese (zh)
Other versions
CN108755670B (en
Inventor
王耀耀
张立国
李宝江
王祥阳
毕首业
羿健卓
王子豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201810794681.1A priority Critical patent/CN108755670B/en
Publication of CN108755670A publication Critical patent/CN108755670A/en
Application granted granted Critical
Publication of CN108755670B publication Critical patent/CN108755670B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/68Mould-pipes or other moulds for making bulkheads or elements thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of controls of pile crown absolute altitude and protective device and pile crown construction method, device to include:Pile crown casing, inside are formed with fender pile space;Sole is supported, the bottom nozzle of pile crown casing is fixed on and extends outwardly circlewise;Casing wing plate is connected between the outer wall of pile crown casing and support sole;For sole will to be supported to be fixed on the fixing anchor bar of pile crown position, supports and offer the anchor hole worn for fixing anchor bar on sole;Absolute altitude controls mirror, be installed in the barrel of pile crown casing and penetrating pile crown casing it is inside and outside;Part flow arrangement, including it is shielded in the plate that binds at the top of the two side flow distribution plates of two side flow distribution plates and closing of the both sides of absolute altitude control mirror.Present invention making is simple and convenient to operate, convenient for being used in turn, and pile crown concrete absolute altitude not only may be implemented and be precisely controlled saving material, but also can be carried out protection to stake and pile crown and be ensured pile crown aesthetics, while also improving the construction efficiency of the broken chisel of pile crown.

Description

The control of pile crown absolute altitude and protective device and pile crown construction method
Technical field
The present invention relates to the realm of building construction more particularly to a kind of controls of pile crown absolute altitude and protective device and pile crown to apply Work method.
Background technology
As environmentally protective theory deepens continuously to construction enterprises, green, energy-saving and environmental protection are constructed into for engineering construction Theme.In conjunction with this engineering main building and podium, CFG pile driving construction amounts are big, to accomplish not only to have ensured cost-effective, raising quality, but also big The big target for improving working efficiency is extremely difficult, is had the following problems according to traditional method:
Conventional method:Manually judge concrete casting elevation with naked-eye observation pile foundation run of steel.This method is being applied Need during work to spend very big energy to be observed and be difficult to ensure absolute altitude, and concrete is easy excessive to cause a large amount of waves Take.Pile crown shape is extremely irregular after conventional method construction, and very big obstacle is brought to follow-up cleaning inter-pile soil.Broken chisel pile crown rank Section, mechanical execution can cause pile body certain destruction.
To sum up analysis conventional method is difficult to realize pile crown absolute altitude and is controlled and protected, and working barrier is more, concrete-pile matter Amount is poor, and can cause a large amount of wastes of material.
Invention content
In order to solve high efficiency during Concrete Grouting Pale, accuracy, economies and it is easy to operation the features such as, One of the technical solution adopted by the present invention is:
It is proposed a kind of control of pile crown absolute altitude and protective device, including:
Pile crown casing, inside are formed with fender pile space;
Sole is supported, the bottom nozzle of the pile crown casing is fixed on and extends outwardly circlewise;
Casing wing plate is connected between the outer wall of the pile crown casing and the support sole;
For the support sole to be fixed on the fixing anchor bar of pile crown position, offered described in confession on the support sole The anchor hole that fixing anchor bar is worn;
Absolute altitude controls mirror, be installed in the barrel of the pile crown casing and the penetrating pile crown casing it is inside and outside; And
Part flow arrangement, including it is shielded in the two side shunting of two side flow distribution plates and closing of the both sides of the absolute altitude control mirror The plate that binds at the top of plate.
In some embodiments of the invention, the casing wing plate is perpendicular to the support sole and the pile crown casing Diametric plane.
In some embodiments of the invention, the absolute altitude control mirror is in a strip shape, and along the height side of the pile crown casing To setting.
In some embodiments of the invention, the two side flow distribution plates are arranged along the short transverse of the pile crown casing.
In some embodiments of the invention, the two side flow distribution plates symmetrically and mutually angled setting.
In some embodiments of the invention, the absolute altitude control mirror is made of transparent toughened glass.
In some embodiments of the invention, the bottom of the side flow distribution plate is fixed on the support sole, the side Extend the top of the pile crown casing, and the top for extending the pile crown casing of the two side flow distribution plates at the top of flow distribution plate It is covered using apron plate and rear backplate between the part in portion.
In some embodiments of the invention, the shape and size of the pile crown casing inner wall are suitable for pile crown to be onstructed Shape and size.
In some embodiments of the invention, the pile crown casing is equipped with hanging ring.
The technical solution adopted by the present invention second is that:
It is proposed a kind of method that pile head construction is irrigated using above-mentioned pile crown absolute altitude control and protective device, packet It includes:
Before filling pile construction, the pile crown casing is fixed on pile crown position by the fixing anchor bar;
During constructing bored concrete pile, using the pile crown casing as pile crown template, pile crown concrete is poured, and lead to The height for crossing the absolute altitude control sem observation pile crown concrete, until pile crown concrete reaches design height.
The present invention due to the adoption of the above technical scheme, makes it have following advantageous effect:
The support leg in the case where pile crown absolute altitude of the present invention is precisely controlled and protective device is to pass through pile crown casing using fixing anchor bar The anchor hole of plate secures the appliance in the soil of concrete-pile stake position.Pile crown casing bottom welding support sole is used to support dress It sets;Casing wing plate is welded perpendicular to casing side to reinforce for casing;One piece of transparent toughened glass is installed as mixed on casing face Solidifying soil absolute altitude controls mirror, for controlling concreting face;The part flow arrangement of casing side is for clearing up the control of concrete absolute altitude The soil on mirror periphery.Device can be used in turn, and installation operation is simple, and sem observation is controlled by concrete absolute altitude during use Concrete casting elevation saves concrete, reduces construction cost.Supporting for concrete pile head can be effectively realized by the device Shield, and cleared up in inter-pile soil operation process it is possible to prevente effectively from collision of the mechanical equipment to pile crown, to drop in subsequent construction The disturbance of low concrete stake, and the device ensure that the beauty and systematicness of pile crown, reduce the difficulty of the broken chisel of pile crown, significantly Improve construction efficiency.
Description of the drawings
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for For those of ordinary skill in the art, without creative efforts, other are can also be obtained according to these attached drawings Attached drawing.
Fig. 1 is the control of pile crown absolute altitude and the side structure schematic diagram of protective device of the embodiment of the present invention.
Fig. 2 is the control of pile crown absolute altitude and the top structure schematic diagram of protective device of the embodiment of the present invention.
Fig. 3 is the side structure schematic diagram of the pile crown absolute altitude control of the embodiment of the present invention and the use state of protective device.
Fig. 4 is the Facad structure signal that the pile crown absolute altitude control of the embodiment of the present invention and the concrete absolute altitude of protective device control mirror Figure.
Fig. 5 is the side structure signal that the pile crown absolute altitude control of the embodiment of the present invention and the concrete absolute altitude of protective device control mirror Figure.
Fig. 6 is the top structure signal that the pile crown absolute altitude control of the embodiment of the present invention and the concrete absolute altitude of protective device control mirror Figure.
Specific implementation mode
Illustrate that embodiments of the present invention, those skilled in the art can be by this specification below by way of specific specific example Disclosed content understands other advantages and effect of the present invention easily.The present invention can also pass through in addition different specific realities The mode of applying is embodied or practiced, the various details in this specification can also be based on different viewpoints with application, without departing from Various modifications or alterations are carried out under the spirit of the present invention.
The present invention is irregular for concrete absolute altitude control hardly possible, waste of material, pile crown during Concrete Grouting Pale Caused by the problems such as mechanical disturbance, pass through a kind of pile crown caused by cast-in-place concrete pile during construction obstacle and broken pile head Absolute altitude is precisely controlled and protective device, bored concrete pile stake top concrete absolute altitude can be precisely controlled, complete after rule is beautiful, machine The tool cleaning inter-pile soil stage protects pile body by mechanical disturbance, not substantially increase construction efficiency, save concrete material.
The present invention is described in detail in the following with reference to the drawings and specific embodiments.
Shown in Fig. 1~3, the pile crown absolute altitude control of the embodiment of the present invention and protective device include mainly:Pile crown Casing 11, support sole 12, casing wing plate 13, fixing anchor bar 14, absolute altitude control mirror 15 and part flow arrangement 16.It is main to utilize fixation Anchor pole 14 passes through 2 in 11 times soil for supporting the anchor hole of soles 12 to secure the appliance to concrete-pile stake position of pile crown casing.Pile crown 11 bottom of casing welding support sole 12 is used to support device;Perpendicular to 11 side of pile crown casing welding casing wing plate 13, it is used for Reinforce pile crown casing;One piece of absolute altitude is installed on pile crown casing surface and controls mirror 15, for observing and monitoring pile crown concreting Face;The part flow arrangement 16 of 11 side of pile crown casing is used to clear up the soil on 15 periphery of concrete absolute altitude control mirror.
Specifically, it is formed with a fender pile space in the inside of pile crown casing 11, pile crown casing 11 is installed on mixed when in use The pile crown of solidifying soil bored concrete pile is outer (pile crown size is more than 3 size of pile body), the shape and size in fender pile space with filling to be onstructed The shape and size for noting pile head are consistent, can be using pile crown casing 11 as pile crown template when subsequent construction pile crown, phase Directly the pile crown external mold to be formed is accumulated to drill out the soil body, it is clear that the pile crown casing made of sizing than traditional filling pile head 11 can greatly improve the molding quality of pile crown so that the pile crown rule of making is beautiful, convenient for effectively realizing concrete pile head Maintenance is cleared up in inter-pile soil operation process in subsequent construction it is possible to prevente effectively from machinery moreover, distance between stake can be accurately controlled Collision of the equipment to pile crown also ensures the beauty and systematicness of pile crown to reduce the disturbance of concrete-pile.
In the present embodiment, pile crown casing 11 is that (diameter is straight according to site operation cast-in-place concrete pile by diameter D Depending on diameter, the about 200mm than stake diameter), high 500mm, thickness 10mm steel cylinder be made.
Support sole 12 is fixedly welded on the bottom nozzle of pile crown casing 11 and extends outwardly circlewise.Support sole be by The steel plate (internal diameter is identical as pile crown casing diameter, and outer diameter is bigger 400mm than internal diameter) of thick 10mm is made.Support sole 12, which encloses, to be set At a circle, interior edge is weldingly fixed on the bottom nozzle of pile crown casing 11.3 a diameter of 30mm of annular spread on support sole 12 Anchor hole 121, for coordinating fixing anchor bar 14 to carry out fixing device.
It is 10mm steel plates (highly identical as pile crown casing, width and support sole width phase that casing wing plate 13, which is by thickness, It is made together), casing wing plate 13 is welded perpendicular to 11 outer surface of pile crown casing and 12 upper surface of support sole, For reinforcing pile crown casing 11.
Fixing anchor bar 14 uses existing Soil Anchor Design, mainly with shank portion and the spiral shell being screwed together in shank portion Mother, for sole 12 will to be supported to be fixed on the working face of pile crown position, on soil 2.The shank portion of fixing anchor bar 14 passes through The anchor hole 121 opened up on support sole 12, nut are tightened in the upper surface of support sole 12, secure the appliance to filling concrete In the soil 2 of stake stake position.
Absolute altitude control mirror 15 is transparent rigid glass plate (such as transparent steel by a block size for 500mm × 50mm × 10mm Change glass) it is made, it is installed on pile crown casing 11 and (replaces the cylinder of the part pile crown casing with concrete absolute altitude control mirror 15 Wall), absolute altitude controls the inside and outside of 15 penetrating pile crown casing 11 of mirror, can be in concreting process for observing regulation and control Concrete casting elevation.
Part flow arrangement 16 includes the two side flow distribution plates of two side flow distribution plates 161 and closing for the both sides for being shielded in absolute altitude control mirror 15 The plate 162 that binds at 161 top.Two side flow distribution plates 161 are by thick 10mm, and the steel plate of high 700mm is at hexagonal angle perpendicular to support leg Be welded on plate and pile crown casing face, be shielded in absolute altitude control mirror 15 both sides and top, for by work progress from filling The soil taken out of in note stake branches to 15 both sides of concrete absolute altitude control mirror, prevents the visual field of blocking concrete absolute altitude control mirror 15.
Preferably, absolute altitude control mirror 15 is in a strip shape, and is arranged along the short transverse of pile crown casing 11, and mirror 15 is controlled in absolute altitude Side be arranged scale, in order to directly observe the height value that pile crown casing inner concrete pours face.The two of part flow arrangement 16 Side flow distribution plate 161 is also arranged along the short transverse of pile crown casing 11, two side flow distribution plates, 161 symmetrical and mutually angled setting.
Coordinate shown in Fig. 4~6, the bottom vertical welding of the side flow distribution plate 161 of part flow arrangement 16 is in the upper of support sole 12 The top nozzle of pile crown casing 11 is extended at the top on surface, side flow distribution plate 16, and the pile crown that extends of two side flow distribution plates 161 protects It is covered using apron plate 163 and rear backplate 164 between the part at the top of cylinder 11, the cross section of part flow arrangement 16 is in fan Shape, absolute altitude control mirror 15 and are mounted on the smaller one end of the sector, and larger one end of the sector is typically wide-open, in order to see Absolute altitude control mirror 15 is examined, the both sides of the sector are two side flow distribution plates 161, and the top surface of the sector is the plate 162 that binds.Work as shunting When the top of device 16 is higher than the top of pile crown casing 11, the self-styled top plate 162 of the soil taken out of that can avoid in bored concrete pile is past dirty And influence the visual field of absolute altitude control mirror 15.At this point, for two side flow distribution plates 161 of the part at the top of eminence pile crown casing Inside and outside (towards pile crown casing side and backwards to pile crown casing and flared side) 164 He of a rear backplate is respectively adopted One apron plate 163 is attached, and the visual field that absolute altitude controls mirror 15 is blocked to prevent soil from point therefrom flowing into part flow arrangement 16 two.
Preferably, being equipped with hanging ring 111 on pile crown casing 11, for hanging ring 111 using rigid hanging ring, rigid hanging ring is by 3 The round steel patch of diameter 10mm is welded in 11 top of pile crown casing, and the broken pile head stage catches on hanging ring using machinery and removes device.
The pile crown absolute altitude of the present invention is precisely controlled and protective device hangs pile crown casing, support sole, casing wing plate, rigidity Ring and part flow arrangement are welded into entirety, and making is simple and convenient to operate, convenient for being used in turn, and pile crown coagulation both may be implemented Native absolute altitude is precisely controlled saving material, and can carry out protection to stake and pile crown and ensure pile crown aesthetics, while also improving stake The construction efficiency of the broken chisel of head.
It is precisely controlled making the pile crown absolute altitude and when protective device, pile crown casing is welded on support sole, then Part flow arrangement vertical welding in rigid hanging ring on pile crown casing and support leg plate face, to be welded in the top of pile crown casing, two Block casing wing plate is fixed on pile crown casing and makes in advance perpendicular to pile crown casing and support sole vertical welding, concrete absolute altitude control mirror In good mirror trough, finally the anchor hole of support sole is passed through to secure the appliance to ground using fixing anchor bar.
Be described below use above-described embodiment in pile crown absolute altitude control and protective device be irrigated pile head and apply The construction method of work, major programme include:
Before filling pile construction, pile crown casing 11 is fixed on pile crown position by fixing anchor bar 14;
During constructing bored concrete pile, using pile crown casing 11 as pile crown template, pile crown concrete is poured, and pass through Absolute altitude controls the height that mirror 15 observes pile crown concrete, until pile crown concrete reaches design height.
The pile crown absolute altitude of the present invention is precisely controlled and protective device making is simple and convenient to operate, and can be used in turn, and is installed All parts are assembled by entirety by welding method in the process.It is first secured the appliance to according to live stake point before filling pile construction Then ground starts to construct, the soil taken out of in work progress is branched to the both sides that concrete absolute altitude controls mirror by part flow arrangement, is led to Observation concrete absolute altitude control mirror is crossed to control pile crown concrete absolute altitude, to realize the effect for saving concrete, and passes through this The pile crown rule that device makes is beautiful.It is to construct to reduce many obstacles, and device is effectively protected in the cleaning inter-pile soil stage Pile crown has been protected, disturbance of the machinery to stake has been reduced, ensure that the quality of stake and improve construction efficiency.
The pile crown absolute altitude of the present invention is precisely controlled and protective device, can both solve concrete top during filling concrete The uncontrollable problem in face, and can solve the problems, such as brokenly that damage pile body, efficiency are low in chisel pile crown construction.A kind of pile crown absolute altitude essence Quasi- control and protective device can be precisely controlled pile crown concrete absolute altitude, to save material;The height of concrete can be realized again Effect conserves and avoids mechanical disturbance, ensures the quality of concrete-pile.
Pile crown absolute altitude is precisely controlled and protective device is that the anchor hole that sole is supported under pile crown casing is passed through using fixing anchor bar It secures the appliance in the soil of concrete-pile stake position.Pile crown casing bottom welding support sole is used to support device;Perpendicular to It welds casing wing plate and is reinforced for casing in casing side;One piece of transparent toughened glass is installed to pour for controlling concrete on casing face Build face;The part flow arrangement of casing side is used to clear up the soil on concrete absolute altitude control mirror periphery.
Pile crown absolute altitude is precisely controlled and protective device can be used in turn, and installation operation is simple, by mixed during use Solidifying soil absolute altitude control mirror controls concrete casting elevation, saves concrete, reduces construction cost.It can be effectively real by the device The maintenance of existing concrete pile head, and cleared up in inter-pile soil operation process in subsequent construction it is possible to prevente effectively from mechanical equipment is to stake The collision of head, to reduce the disturbance of concrete-pile, and the device ensure that the beauty and systematicness of pile crown, reduce pile crown The difficulty of broken chisel, substantially increases construction efficiency.
It should be noted that structure, ratio, size etc. depicted in this specification institute accompanying drawings, only coordinating The bright revealed content of book is not limited to the enforceable limit of the present invention so that those skilled in the art understands and reads Fixed condition, therefore do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size, not It influences under the effect of present invention can be generated and the purpose that can reach, should all still fall and be obtained in disclosed technology contents In the range of capable of covering.Meanwhile it is cited such as "upper", "lower", "left", "right", " centre " and " one " in this specification Term is merely convenient to being illustrated for narration, rather than to limit the scope of the invention, the change of relativeness or tune It is whole, in the case where changing technology contents without essence, when being also considered as the enforceable scope of the present invention.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, in the range of not departing from technical solution of the present invention, when the technology contents using the disclosure above make a little change or repair Decorations are the equivalent embodiment of equivalent variations, as long as being the content without departing from technical solution of the present invention, technology according to the present invention is real Any simple modification, equivalent change and modification made by confrontation above example still fall within the range of technical solution of the present invention It is interior.

Claims (10)

1. a kind of pile crown absolute altitude control and protective device, which is characterized in that including:
Pile crown casing, inside are formed with fender pile space;
Sole is supported, the bottom nozzle of the pile crown casing is fixed on and extends outwardly circlewise;
Casing wing plate is connected between the outer wall of the pile crown casing and the support sole;
For the support sole to be fixed on the fixing anchor bar of pile crown position, the confession fixation is offered on the support sole The anchor hole that anchor pole is worn;
Absolute altitude controls mirror, be installed in the barrel of the pile crown casing and the penetrating pile crown casing it is inside and outside;And
Part flow arrangement, including be shielded in the two side flow distribution plates of two side flow distribution plates and closing of the both sides of the absolute altitude control mirror The plate that binds at top.
2. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The casing wing plate is perpendicular to institute State the diametric plane of support sole and the pile crown casing.
3. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The absolute altitude control mirror is in item Shape, and be arranged along the short transverse of the pile crown casing.
4. pile crown absolute altitude control as claimed in claim 3 and protective device, it is characterised in that:The two side flow distribution plates are described in The short transverse of pile crown casing is arranged.
5. pile crown absolute altitude control as claimed in claim 4 and protective device, it is characterised in that:The two side flow distribution plates are mutually right Title and mutually angled setting.
6. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The absolute altitude control mirror is using saturating Bright tempered glass makes.
7. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The bottom of the side flow distribution plate is solid Due on the support sole, extending the top of the pile crown casing at the top of the side flow distribution plate, and the two sides shuntings It is covered using apron plate and rear backplate between the part at the top for extending the pile crown casing of plate.
8. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The shape of the pile crown casing inner wall Shape and size are suitable for the shape and size of pile crown to be onstructed.
9. pile crown absolute altitude control as described in claim 1 and protective device, it is characterised in that:The pile crown casing is equipped with and hangs Ring.
10. a kind of side being irrigated pile head construction using pile crown absolute altitude as described in claim 1 control and protective device Method, which is characterized in that including:
Before filling pile construction, the pile crown casing is fixed on pile crown position by the fixing anchor bar;
During constructing bored concrete pile, using the pile crown casing as pile crown template, pile crown concrete is poured, and pass through institute The height for stating absolute altitude control sem observation pile crown concrete, until pile crown concrete reaches design height.
CN201810794681.1A 2018-07-19 2018-07-19 Pile head elevation control and protection device and pile head construction method Active CN108755670B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810794681.1A CN108755670B (en) 2018-07-19 2018-07-19 Pile head elevation control and protection device and pile head construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810794681.1A CN108755670B (en) 2018-07-19 2018-07-19 Pile head elevation control and protection device and pile head construction method

Publications (2)

Publication Number Publication Date
CN108755670A true CN108755670A (en) 2018-11-06
CN108755670B CN108755670B (en) 2024-01-23

Family

ID=63970387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810794681.1A Active CN108755670B (en) 2018-07-19 2018-07-19 Pile head elevation control and protection device and pile head construction method

Country Status (1)

Country Link
CN (1) CN108755670B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001248154A (en) * 2000-03-07 2001-09-14 Tokyu Constr Co Ltd Method of processing pile head, head structure of cast-in- place concrete pile, and form for processing pile head, for use in method of constructing cast-in-place concrete pile
CN201520977U (en) * 2009-09-24 2010-07-07 中交一航局第四工程有限公司 Drilling bored pile underwater pouring concrete pile top elevation controller
CN202048919U (en) * 2011-05-23 2011-11-23 北京首钢建设集团有限公司 Multifunctional elevation benchmark device
CN102966096A (en) * 2012-11-30 2013-03-13 天津第三市政公路工程有限公司 Construction method for double pile casings of large-diameter cast-in-situ bored pile
CN203334279U (en) * 2013-07-05 2013-12-11 大同泰瑞集团建设有限公司 Positioning device of pile heads of bored concrete pile combined foundations
CN204125977U (en) * 2014-09-05 2015-01-28 中国能源建设集团山西省电力勘测设计院 The convenient linkage of tubular pile head
CN206052697U (en) * 2016-07-27 2017-03-29 浙江水利水电学院 A kind of anti-settling steel pile casting
CN206408657U (en) * 2016-12-13 2017-08-15 北京城建集团有限责任公司 Integrated bored concrete pile for static test
CN107620311A (en) * 2017-09-25 2018-01-23 中国冶集团有限公司 A kind of mud off pore-creating filling pile prevents the method that aperture casing sinks
CN208650046U (en) * 2018-07-19 2019-03-26 中国建筑第八工程局有限公司 The control of pile crown absolute altitude and protective device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001248154A (en) * 2000-03-07 2001-09-14 Tokyu Constr Co Ltd Method of processing pile head, head structure of cast-in- place concrete pile, and form for processing pile head, for use in method of constructing cast-in-place concrete pile
CN201520977U (en) * 2009-09-24 2010-07-07 中交一航局第四工程有限公司 Drilling bored pile underwater pouring concrete pile top elevation controller
CN202048919U (en) * 2011-05-23 2011-11-23 北京首钢建设集团有限公司 Multifunctional elevation benchmark device
CN102966096A (en) * 2012-11-30 2013-03-13 天津第三市政公路工程有限公司 Construction method for double pile casings of large-diameter cast-in-situ bored pile
CN203334279U (en) * 2013-07-05 2013-12-11 大同泰瑞集团建设有限公司 Positioning device of pile heads of bored concrete pile combined foundations
CN204125977U (en) * 2014-09-05 2015-01-28 中国能源建设集团山西省电力勘测设计院 The convenient linkage of tubular pile head
CN206052697U (en) * 2016-07-27 2017-03-29 浙江水利水电学院 A kind of anti-settling steel pile casting
CN206408657U (en) * 2016-12-13 2017-08-15 北京城建集团有限责任公司 Integrated bored concrete pile for static test
CN107620311A (en) * 2017-09-25 2018-01-23 中国冶集团有限公司 A kind of mud off pore-creating filling pile prevents the method that aperture casing sinks
CN208650046U (en) * 2018-07-19 2019-03-26 中国建筑第八工程局有限公司 The control of pile crown absolute altitude and protective device

Also Published As

Publication number Publication date
CN108755670B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN106088530A (en) Large area method for constructing terrace
CN103015744B (en) Method for removing reinforced concrete chimney
CN102966365B (en) Novel air bridge construction method
CN208650046U (en) The control of pile crown absolute altitude and protective device
CN207393216U (en) A kind of fixed structure of tunnel double-lining back-grouting pipe
CN108755670A (en) The control of pile crown absolute altitude and protective device and pile crown construction method
CN205676902U (en) Arched framework slope protection construction typified form
CN206844138U (en) A kind of bar construction of domatic isolated footing
CN104805864B (en) The cementing Waterproof Construction Technique that closes of basement top-down method exterior wall tongue and groove and sealing
CN108396783A (en) A kind of pre- closure grouting devices and methods therefor of basement roof pouring after settlement
CN211849500U (en) Slope anchor spraying device for engineering construction
CN103046765B (en) Construction process for continued application of air-raid shelter
CN110761562A (en) Auxiliary tool for pouring concrete and using method
CN108708377B (en) Pile head breaking and shearing device for bridge cast-in-place pile and using method
CN203613531U (en) Jet grouting and stirring composite construction drill bit for large-diameter compound section cement-soil pile
CN206902768U (en) A kind of post-cast strip adjustable supporting
CN106759526B (en) A kind of purlin before Brace in Deep Footing Groove beam demolition blasting protects preprocess method
CN101725355A (en) Palisade structure for underground architectural shaft and shield machine cutting construction method thereof
CN110056170A (en) A kind of pointing device of novel and multifunctional environmental protection
CN206815347U (en) A kind of shaped steel pile for prestressed pipe combines upright supports stake
CN206539052U (en) A kind of both balconied strengthening reconstruction structure
CN207295806U (en) A kind of civil engineering digging machine bucket
CN101725354A (en) Cable tunnel shaft enclosure structure and shield machine cutting construction method thereof
CN211080280U (en) Large-diameter pile foundation enclosure miniature pile group
CN208430770U (en) Clinker warehouse cylinder slip form construction device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant