CN108744712A - A kind of freezing and filtering equipment of double refrigeration systems - Google Patents

A kind of freezing and filtering equipment of double refrigeration systems Download PDF

Info

Publication number
CN108744712A
CN108744712A CN201810780147.5A CN201810780147A CN108744712A CN 108744712 A CN108744712 A CN 108744712A CN 201810780147 A CN201810780147 A CN 201810780147A CN 108744712 A CN108744712 A CN 108744712A
Authority
CN
China
Prior art keywords
valves
filters
pumps
systems
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810780147.5A
Other languages
Chinese (zh)
Inventor
高云芝
李俊民
常政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810780147.5A priority Critical patent/CN108744712A/en
Publication of CN108744712A publication Critical patent/CN108744712A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D37/00Processes of filtration
    • B01D37/02Precoating the filter medium; Addition of filter aids to the liquid being filtered
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D35/00Filtering devices having features not specifically covered by groups B01D24/00 - B01D33/00, or for applications not specifically covered by groups B01D24/00 - B01D33/00; Auxiliary devices for filtration; Filter housing constructions
    • B01D35/18Heating or cooling the filters
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D37/00Processes of filtration
    • B01D37/04Controlling the filtration

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Vaporization, Distillation, Condensation, Sublimation, And Cold Traps (AREA)

Abstract

It is an object of the invention to provide a kind of freezing and filtering equipment of double refrigeration systems, which improves work efficiency, reduces production cost, realizes freezing and filtering, room temperature filtering, quickly cooling and thermal energy recovery process and refrigeration system a preparation and a use function respectively.

Description

A kind of freezing and filtering equipment of double refrigeration systems
Technical field
The present invention relates to a kind of filter plants in filtering flow field, and in particular to a kind of freezing and filtering of double refrigeration systems Equipment.
Technical background
Currently, in the filtering of the industries liquid such as medicine, chemical industry, light industry, drink, the single work(of freezing and filtering unit in the market It can freeze and filter disjunctor realization to be completed to filter at low temperature by filtrate body, Multifunctional resource, which can not achieve, to be caused to waste;Due to Freezing and filtering unit equipment is multicomponent combination, is not that the equipment component seller of vulnerable part is not usually spare with buyer, is producing Occur equipment single element failure in the process and will result in a whole set of compressor emergency shutdown, it is necessary to until that could be produced after troubleshooting, have Equipment component need repairing or replace, but repair or procurement cycle will be 1 week~3 months, thus delay and produce, such as carry High efficiency performance is more multi-functional to have much room for improvement.
Invention content
In view of the above-mentioned problems, it is an object of the invention to provide a kind of freezing and filtering equipment of double refrigeration systems, which improves Working efficiency reduces production cost, realizes freezing and filtering, room temperature filtering, quickly cooling and thermal energy recovery process and refrigeration respectively System a preparation and a use function.
A kind of freezing and filtering equipment of double refrigeration systems, including:Z8 refrigeration systems, Z8Z refrigeration systems, A cooling waters The circulatory system, AA cooling water recirculation systems, B cooling water recirculation systems, BB cooling water recirculation systems, A coolant circulating systems, AA are cold The cold feed liquor system of matchmaker's circulatory system, B coolant circulating systems, BB coolant circulating systems, A, the cold feed liquor systems of B, the cold feed liquor systems of C, A Filter extension soil series system, B filters hang soil series system, C is filtered and hung soil series system, A systemic circulations cooling system, B systemic circulations cooling system, C systemic circulations drop The normal feed liquor system of warm system, A freezing and filtering systems, B freezing and filtering systems, C freezing and filtering systems, D, the normal feed liquor systems of E, F are normal The normal feed liquor system of feed liquor system, G, D room temperature filtration system, E room temperature filtration system, F room temperature filtration system, G room temperature filtration system, A add-on systems, B add-on systems, A solid-liquid separation systems, B solid-liquid separation systems, C solid-liquid separation systems, A cold liquid extraction system The cold liquid extraction system of system, B, the cold liquid extraction systems of C, the normal liquid extraction systems of D, the normal liquid extraction systems of E, the normal liquid of F are taken out Go out the normal liquid extraction system of system, G.
The A cooling water recirculation systems include:B2 valves, Z12 cooling towers, B1 valves, G6 cooling pumps, T3 valves, T4 valves pass through pipe Road and the condenser inlet and outlet connection of the Z8 refrigeration systems form A cooling water circulation loops;
The AA cooling water recirculation systems include:The B2 valves, the Z12 cooling towers, the B1 valves, the G6 cooling pumps, T3T Valve, T4T valves form AA cooling water circulation loops by pipeline and the inlet and outlet connection of the condenser of the Z8Z refrigeration systems;
The B cooling water recirculation systems include:B3 valves, Z11 exchangers, E6 valves, the Z12 cooling towers, the B1 valves, the G6 Cooling pump, the T3 valves, the T4 valves form B cooling waters by pipeline and the inlet and outlet connection of the condenser of the Z8 refrigeration systems Circulation loop;
The BB cooling water recirculation systems include:The B3 valves, the Z11 exchangers, the E6 valves, the Z12 cooling towers, institute B1 valves, the G6 cooling pumps, the T3T valves, the T4T valves is stated to pass in and out by pipeline and the condenser of the Z8Z refrigeration systems Mouth connection forms BB cooling water circulation loops;
The A coolant circulating systems include:A1 valves, Z9 refrigerant tanks, A2 valves, G7 refrigerant pumps, A3 valves, Z3 exchangers, A4 valves, T1 Valve, T2 valves connect to form A refrigerant circulation circuits by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems;
The AA coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A3 Valve, the Z3 exchangers, the A4 valves, T1T valves, T2T valves are connected by pipeline and the evaporator inlet-outlet of the Z8Z refrigeration systems It connects to form AA refrigerant circulation circuits;
The B coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, A5 valves, Z10 exchangers, A6 valves, the T1 valves, the T2 valves connect shape by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems At B refrigerant circulation circuits;
The BB coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A5 The evaporation that valve, the Z10 exchangers, the A6 valves, the T1T valves, the T2T valves pass through pipeline and the Z8Z refrigeration systems Device inlet and outlet connection forms BB refrigerant circulation circuits;
The cold feed liquor systems of A include:Z1 protects filter, C1 valves, G1 pumps, Z2 exchangers, the Z3 exchangers, C2 valves, A9 valves, G2 Pump, Z4 filters, C3 valves, E5 valves, Z5 agitator tanks, C4 valves, G3 pump, Z6 filters connect to form the cold feed liquor circuits A by pipeline;
The cold feed liquor systems of B include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, the A9 valves, G2 pumps, the Z4 filters connect to form the cold feed liquor circuits B by pipeline;
The cold feed liquor systems of C include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, D2 valves, M7 valves, G3 pumps, the Z6 filters connect to form the cold feed liquor circuits C by pipeline;
Soil series system is hung in the A filters:C8 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the E5 Valve, the Z5 agitator tanks connect to form the Z4 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the B filters:D8 valves, G3 pumps, the Z6 filters, D5 valves, the E5 valves, the Z5 agitator tanks It connects to form the Z6 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the C filters:C7 valves, G4 pumps, Z7 filters, E4 valves, the E5 valves, the Z5 agitator tanks pass through pipeline Connection forms the Z7 filters precoating filter aid circulation loop;
The A systemic circulations cooling system includes:E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, the A9 valves, The G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, the Z6 filters, C5 valves, the Z2 are exchanged Device connects to form A systemic circulations cooling circuit by pipeline;
The B systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described A9 valves, G2 pumps, the Z4 filters, the C3 valves, F1 valves, the Z2 exchangers connect to form B systemic circulations by pipeline Cool down circuit;
The C systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 exchangers connect that form C big by pipeline Circulation temperature lowering circuit;
The A freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, institute State Z6 filters, the C5 valves, the Z2 exchangers, G4 pumps, the Z7 filters, F4 valves, C6 valves are connected by pipeline Form A freezing and filterings circuit;
The B freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the F1 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form B freezing and filterings circuit by pipeline;
The C freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form C freezing and filterings circuit by pipeline;
The normal feed liquor systems of D include:The Z1 shields filter, D1 valves, the D2 valves, the A9 valves, G2 pumps, the Z4 mistakes Filter, the C3 valves, the E5 valves, the Z5 agitator tanks, the C4 valves, G3 pumps, the Z6 filters are connected by pipeline It connects to form the normal feed liquor circuits D;
The normal feed liquor systems of E include:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, the G2 are pumped, are described Z4 filters, the C3 valves, the E5 valves, the Z5 agitator tanks piping connect to form the normal feed liquor circuits E;
The normal feed liquor systems of F include:Z1 shield filter, the D1 valves, the M7 valves, G3 pumps, the Z6 filters, The D5 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits F by pipeline;
The normal feed liquor systems of G include:It is Z1 shield filter, the D1 valves, F2 valves, G4 pumps, the Z7 filters, described F4 valves, the E4 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits G by pipeline;
The D room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, the C3 valves, the C4 valves, G3 pumps, the Z6 filters, D4 valves connect to form D room temperature by pipeline Filtration circuit;
The E room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, D3 valves connect to form E room temperature filtration circuits by pipeline;
The F room temperature filtration system includes:The Z1 shields filter, the D1 valves, the M7 valves, G3 pumps, Z6 filterings Machine, the D4 valves connect to form F room temperature filtration circuits by pipeline;
The G room temperature filtration system includes:The Z1 shields filter, the D1 valves, the F2 valves, G4 pumps, Z7 filterings Machine, the F4 valves, the C6 valves connect to form G room temperature filtration circuits by pipeline;
The A add-on systems include:The Z5 agitator tanks, G5 additions pump, D6 valves, the Z4 filters connect to be formed by pipeline A adds circuit;
The B add-on systems include:The Z5 agitator tanks, G5 additions pump, D7 valves, the Z6 filters are connected by pipeline It forms B and adds circuit;
The A solid-liquid separation systems include:M1 valves, G11 pumps, Z14 centrifuges, G12 pump, M6 valves, the D2 valves, the A9 valves, The G2 pumps, the Z4 filters connect to form A separation of solid and liquid circulation loops by pipeline;
The B solid-liquid separation systems include:M2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M6 valves, institute M7 valves, G3 pumps, the Z6 filters is stated to connect to form B separation of solid and liquid circulation loops by pipeline;
The C solid-liquid separation systems include:F3 valves, the E4 valves, M3 valves, G11 pumps, the Z14 centrifuges, the G12 Pump, the M6 valves, the F2 valves, the G4 pump, the Z7 filters connect to form C separation of solid and liquid circulation loops by pipeline;
The cold liquid of A extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the D5 valves, the Z6 mistakes It is filter, the M2 valves, the C4 valves, the M7 valves, the D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, described Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 valves, the Z7 filters, the F3 valves, the F4 valves, The E4 valves, the F1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, M5 valves are connected by pipeline It forms the cold liquid of A and extracts circuit out;
The cold liquid of B extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 Valve, the C1 valves, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 pump, the Z14 from Scheming, G12 pumps, the M5 valves connect to form B cold liquid extractions circuit by pipeline;
The cold liquid of C extracts system out and includes:The D5 valves, the Z6 filters, the M2 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 Valve, the Z7 filters, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 are pumped, are described Z14 centrifuges, G12 pumps, the M5 valves connect to form C cold liquid extractions circuit by pipeline;
The normal liquid of D extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the A9 valves, the D1 valves, the Z6 filters, the D5 valves, the M2 valves, the M3 valves, the G11 pump, The Z14 centrifuges, G12 pumps, the M5 valves connect to form D normal liquid extractions circuit by pipeline;
The E liquid extracts system out:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, institute State D2 valves, the A9 valves, the D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form E liquid extraction circuit by pipeline;
The F liquid extracts system out:The Z6 filters, the M2 valves, the D5 valves, the C4 valves, the M7 valves, institute D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves is stated to connect to form F liquid by pipeline Body extracts circuit out;
The G liquid extracts system out:The Z7 filters, the F3 valves, the F4 valves, the E4 valves, the M3 valves, institute State C4 valves, the M7 valves, the D1 valves, the F2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form G liquid extraction circuit by pipeline.
Above system is not put into if any valve, is added according to demand in actual fabrication and operation, can not achieve unification The valve of instruction is realized using manual opening-closing cooperation.
The present invention can realize that freezing and filtering, room temperature filtering, quickly cooling are handed over automated and semi-automatic operating procedure respectively Change, speed heat exchange etc. processes use be to select according to demand, operating procedure is described below, before executing each single item system, own System is all that closed state has reached and waits for service requirement, and the pump element in execution system is opened and closed according to designer's design requirement (Pump belongs to closed state into pipe path individually in some execution systems), all elements, which have not represented, opens and closes function as exchanged Device, filter etc..Because equipment operating procedures is more, is not written in patent if any individual links known technology, is solved by designer It releases, example exhaust valve pipeline gets rid of native device etc..
Similarly, the Z8 refrigeration is for the Z8 refrigeration systems and adaption system and the Z8Z refrigeration systems and adaption system System and the Z8Z refrigeration systems category the using and the reserved principle.
Execute a speed heat swap operation:Start the B cooling water recirculation systems, the A coolant circulating systems (or the B Coolant circulating system), start the Z8 refrigeration systems later, the liquid exchanged later starts G10 by pipeline and is pumped into institute It states Z11 exchangers to swap, realizes a speed heat exchange process.
Execute two speed heat swap operations:It is (or described to start the BB cooling water recirculation systems, the AA coolant circulating systems BB coolant circulating systems), start the Z8Z refrigeration systems later, the liquid exchanged later starts the G10 by pipeline and pumps It is sent into the Z11 exchangers to swap, realizes two speed heat exchange process.
Execute a quickly cooling swap operation:Start the A cooling water recirculation systems and the B coolant circulating systems, Zhi Houqi The Z8 refrigeration systems are moved, the liquid exchanged later is pumped into the Z10 exchangers by pipeline startup G8 and swaps, real An existing quickly cooling exchange process.
Execute two quickly cooling swap operations:Start the AA cooling water recirculation systems(Or the BB cooling water recirculation systems)With The BB coolant circulating systems, start the Z8Z refrigeration systems later, and the liquid exchanged later starts the G8 by pipeline It is pumped into the Z10 exchangers to swap, realizes two quickly cooling exchange process.
Execute the A freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the A to be turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the B filters extension soil later System carries out precoating drainage to the Z6 filters and is situated between, completes and closes;Start A cooling water recirculation systems and described simultaneously A coolant circulating systems start the Z8 refrigeration systems and carry out cold energy energy storage later(Or start AA cooling water circulations system simultaneously System and the AA coolant circulating systems start the Z8Z refrigeration systems and carry out cold energy energy storage later);Later when cold energy energy storage reaches To the A systemic circulations cooling system is started when requiring, later when cooling reaches filtering requirement, the A systemic circulations cooling is closed System, starts the A freezing and filtering systems later and the A add-on systems carry out normal filtration.
Execute the B freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the B to be turned off, it is right later The A filters hang soil series system and carry out precoating drainage Jie, complete and close;Start the A cooling water recirculation systems simultaneously and the A is cold Matchmaker's circulatory system starts the Z8 refrigeration systems and carries out cold energy energy storage later(Or start the AA cooling water recirculation systems simultaneously With the AA coolant circulating systems, starts the Z8Z refrigeration systems later and carry out cold energy energy storage);Later when cold energy energy storage reaches It is required that when start the B systemic circulations cooling system, later when cooling reaches filtering requirement, close B systemic circulations cooling system System, starts the B freezing and filtering systems later and the A add-on systems carry out normal filtration.
Execute the C freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the C to be turned off, it is right later The B filters hang soil series system and carry out precoating drainage Jie, complete and close;Start the A cooling water recirculation systems simultaneously and the A is cold Matchmaker's circulatory system starts the Z8 refrigeration systems and carries out cold energy energy storage later(Or start the AA cooling water recirculation systems simultaneously With the AA coolant circulating systems, starts the Z8Z refrigeration systems later and carry out cold energy energy storage);Later when cold energy energy storage reaches It is required that when start the C systemic circulations cooling system, later when cooling reaches filtering requirement, close C systemic circulations cooling system System, starts the C freezing and filtering systems later and the B add-on systems carry out normal filtration.
Execute the D room temperature filtration system operation:Start the normal feed liquor systems of the D, completion feed liquor is turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the B filters extension soil later System carries out precoating drainage to the Z6 filters and is situated between, completes and closes, and starts the D room temperature filtration system and the A later Add-on system, into normal filtration.
Execute the E room temperature filtration system operation:Start the normal feed liquor systems of the E, completion feed liquor is turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the E room temperature mistake later Filter system and the A add-on systems, into normal filtration.
Execute the F room temperature filtration system operation:Start the normal feed liquor systems of the F, completion feed liquor is turned off, Zhi Houqi The dynamic B filters extension soil series system carries out precoating drainage to the Z6 filters and is situated between, completes and closes, and starts the F room temperature mistake later Filter system and the B add-on systems, into normal filtration.
Execute the G room temperature filtration system operation:Start the normal feed liquor systems of the G, completion feed liquor is turned off, Zhi Houqi The dynamic C filters extension soil series system carries out precoating drainage to the Z7 filters and is situated between, completes and closes, and starts the G room temperature mistake later Filter system, into normal filtration.
It after filtering, selects according to demand, adaptation starts the A solid-liquid separation systems, the B is separated by solid-liquid separation system System, the C solid-liquid separation systems, the A liquid extraction system, B liquid extraction system, described C liquid extraction system etc., It completes to be separated by solid-liquid separation and liquid extracts technique etc. out.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
B2 valves, Z12 cooling towers, B1 valves, G6 cooling pumps, T3 valves, T4 valves, T3T valves, T4T valves, B3 valves, Z11 exchangers, E6 valves, A1 Valve, Z9 refrigerant tanks, A2 valves, G7 refrigerant pumps, A3 valves, Z3 exchangers, A4 valves, T1 valves, T2 valves, T1T valves, T2T valves, A5 valves, Z10 are handed over Parallel operation, A6 valves, Z1 shields filter, C1 valves, G1 pumps, Z2 exchangers, C2 valves, A9 valves, G2 pump, Z4 filters, C3 valves, E5 valves, Z5 are stirred Mix tank, C4 valves, G3 pumps, Z6 filters, D2 valves, M7 valves, D5 valves, C8 valves, D8 valves, C7 valves, G4 pump, Z7 filters, E4 valves, E1 Valve, C5 valves, F1 valves, F4 valves, D1 valves, C6 valves, D4 valves, D3 valves, F2 valves, G8 pumps, G10 pumps, G5 additions pump, D6 valves, D7 valves, Z8 systems Cooling system, Z8Z refrigeration systems, M1 valves, G11 pumps, Z14 centrifuges, G12 pump, M6 valves, F3 valves, M3 valves, M2 valves, M5 valves.
Specific implementation mode
In conjunction with attached drawing and foregoing invention content, the present invention is described in further detail.Referring to Fig.1, mesh of the invention A kind of freezing and filtering equipment of double refrigeration systems of offer, which improves work efficiency, reduces production cost, realize respectively Freezing and filtering, room temperature filtering, quickly cooling and thermal energy recovery process and refrigeration system a preparation and a use function.
A kind of freezing and filtering equipment of double refrigeration systems, including:Z8 refrigeration systems, Z8Z refrigeration systems, A cooling waters The circulatory system, AA cooling water recirculation systems, B cooling water recirculation systems, BB cooling water recirculation systems, A coolant circulating systems, AA are cold The cold feed liquor system of matchmaker's circulatory system, B coolant circulating systems, BB coolant circulating systems, A, the cold feed liquor systems of B, the cold feed liquor systems of C, A Filter extension soil series system, B filters hang soil series system, C is filtered and hung soil series system, A systemic circulations cooling system, B systemic circulations cooling system, C systemic circulations drop The normal feed liquor system of warm system, A freezing and filtering systems, B freezing and filtering systems, C freezing and filtering systems, D, the normal feed liquor systems of E, F are normal The normal feed liquor system of feed liquor system, G, D room temperature filtration system, E room temperature filtration system, F room temperature filtration system, G room temperature filtration system, A add-on systems, B add-on systems, A solid-liquid separation systems, B solid-liquid separation systems, C solid-liquid separation systems, A cold liquid extraction system The cold liquid extraction system of system, B, the cold liquid extraction systems of C, the normal liquid extraction systems of D, the normal liquid extraction systems of E, the normal liquid of F are taken out Go out the normal liquid extraction system of system, G.
The A cooling water recirculation systems include:B2 valves, Z12 cooling towers, B1 valves, G6 cooling pumps, T3 valves, T4 valves pass through pipe Road and the condenser inlet and outlet connection of the Z8 refrigeration systems form A cooling water circulation loops;
The AA cooling water recirculation systems include:The B2 valves, the Z12 cooling towers, the B1 valves, the G6 cooling pumps, T3T Valve, T4T valves form AA cooling water circulation loops by pipeline and the inlet and outlet connection of the condenser of the Z8Z refrigeration systems;
The B cooling water recirculation systems include:B3 valves, Z11 exchangers, E6 valves, the Z12 cooling towers, the B1 valves, the G6 Cooling pump, the T3 valves, the T4 valves form B cooling waters by pipeline and the inlet and outlet connection of the condenser of the Z8 refrigeration systems Circulation loop;
The BB cooling water recirculation systems include:The B3 valves, the Z11 exchangers, the E6 valves, the Z12 cooling towers, institute B1 valves, the G6 cooling pumps, the T3T valves, the T4T valves is stated to pass in and out by pipeline and the condenser of the Z8Z refrigeration systems Mouth connection forms BB cooling water circulation loops;
The A coolant circulating systems include:A1 valves, Z9 refrigerant tanks, A2 valves, G7 refrigerant pumps, A3 valves, Z3 exchangers, A4 valves, T1 Valve, T2 valves connect to form A refrigerant circulation circuits by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems;
The AA coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A3 Valve, the Z3 exchangers, the A4 valves, T1T valves, T2T valves are connected by pipeline and the evaporator inlet-outlet of the Z8Z refrigeration systems It connects to form AA refrigerant circulation circuits;
The B coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, A5 valves, Z10 exchangers, A6 valves, the T1 valves, the T2 valves connect shape by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems At B refrigerant circulation circuits;
The BB coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A5 The evaporation that valve, the Z10 exchangers, the A6 valves, the T1T valves, the T2T valves pass through pipeline and the Z8Z refrigeration systems Device inlet and outlet connection forms BB refrigerant circulation circuits;
The cold feed liquor systems of A include:Z1 protects filter, C1 valves, G1 pumps, Z2 exchangers, the Z3 exchangers, C2 valves, A9 valves, G2 Pump, Z4 filters, C3 valves, E5 valves, Z5 agitator tanks, C4 valves, G3 pump, Z6 filters connect to form the cold feed liquor circuits A by pipeline;
The cold feed liquor systems of B include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, the A9 valves, G2 pumps, the Z4 filters connect to form the cold feed liquor circuits B by pipeline;
The cold feed liquor systems of C include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, D2 valves, M7 valves, G3 pumps, the Z6 filters connect to form the cold feed liquor circuits C by pipeline;
Soil series system is hung in the A filters:C8 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the E5 Valve, the Z5 agitator tanks connect to form the Z4 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the B filters:D8 valves, G3 pumps, the Z6 filters, D5 valves, the E5 valves, the Z5 agitator tanks It connects to form the Z6 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the C filters:C7 valves, G4 pumps, Z7 filters, E4 valves, the E5 valves, the Z5 agitator tanks pass through pipeline Connection forms the Z7 filters precoating filter aid circulation loop;
The A systemic circulations cooling system includes:E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, the A9 valves, The G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, the Z6 filters, C5 valves, the Z2 are exchanged Device connects to form A systemic circulations cooling circuit by pipeline;
The B systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described A9 valves, G2 pumps, the Z4 filters, the C3 valves, F1 valves, the Z2 exchangers connect to form B systemic circulations by pipeline Cool down circuit;
The C systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 exchangers connect that form C big by pipeline Circulation temperature lowering circuit;
The A freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, institute State Z6 filters, the C5 valves, the Z2 exchangers, G4 pumps, the Z7 filters, F4 valves, C6 valves are connected by pipeline Form A freezing and filterings circuit;
The B freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the F1 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form B freezing and filterings circuit by pipeline;
The C freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form C freezing and filterings circuit by pipeline;
The normal feed liquor systems of D include:The Z1 shields filter, D1 valves, the D2 valves, the A9 valves, G2 pumps, the Z4 mistakes Filter, the C3 valves, the E5 valves, the Z5 agitator tanks, the C4 valves, G3 pumps, the Z6 filters are connected by pipeline It connects to form the normal feed liquor circuits D;
The normal feed liquor systems of E include:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, the G2 are pumped, are described Z4 filters, the C3 valves, the E5 valves, the Z5 agitator tanks piping connect to form the normal feed liquor circuits E;
The normal feed liquor systems of F include:Z1 shield filter, the D1 valves, the M7 valves, G3 pumps, the Z6 filters, The D5 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits F by pipeline;
The normal feed liquor systems of G include:It is Z1 shield filter, the D1 valves, F2 valves, G4 pumps, the Z7 filters, described F4 valves, the E4 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits G by pipeline;
The D room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, the C3 valves, the C4 valves, G3 pumps, the Z6 filters, D4 valves connect to form D room temperature by pipeline Filtration circuit;
The E room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, D3 valves connect to form E room temperature filtration circuits by pipeline;
The F room temperature filtration system includes:The Z1 shields filter, the D1 valves, the M7 valves, G3 pumps, Z6 filterings Machine, the D4 valves connect to form F room temperature filtration circuits by pipeline;
The G room temperature filtration system includes:The Z1 shields filter, the D1 valves, the F2 valves, G4 pumps, Z7 filterings Machine, the F4 valves, the C6 valves connect to form G room temperature filtration circuits by pipeline;
The A add-on systems include:The Z5 agitator tanks, G5 additions pump, D6 valves, the Z4 filters connect to be formed by pipeline A adds circuit;
The B add-on systems include:The Z5 agitator tanks, G5 additions pump, D7 valves, the Z6 filters are connected by pipeline It forms B and adds circuit;
The A solid-liquid separation systems include:M1 valves, G11 pumps, Z14 centrifuges, G12 pump, M6 valves, the D2 valves, the A9 valves, The G2 pumps, the Z4 filters connect to form A separation of solid and liquid circulation loops by pipeline;
The B solid-liquid separation systems include:M2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M6 valves, institute M7 valves, G3 pumps, the Z6 filters is stated to connect to form B separation of solid and liquid circulation loops by pipeline;
The C solid-liquid separation systems include:F3 valves, the E4 valves, M3 valves, G11 pumps, the Z14 centrifuges, the G12 Pump, the M6 valves, the F2 valves, the G4 pump, the Z7 filters connect to form C separation of solid and liquid circulation loops by pipeline;
The cold liquid of A extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the D5 valves, the Z6 mistakes It is filter, the M2 valves, the C4 valves, the M7 valves, the D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, described Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 valves, the Z7 filters, the F3 valves, the F4 valves, The E4 valves, the F1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, M5 valves are connected by pipeline It forms the cold liquid of A and extracts circuit out;
The cold liquid of B extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 Valve, the C1 valves, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 pump, the Z14 from Scheming, G12 pumps, the M5 valves connect to form B cold liquid extractions circuit by pipeline;
The cold liquid of C extracts system out and includes:The D5 valves, the Z6 filters, the M2 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 Valve, the Z7 filters, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 are pumped, are described Z14 centrifuges, G12 pumps, the M5 valves connect to form C cold liquid extractions circuit by pipeline;
The normal liquid of D extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the A9 valves, the D1 valves, the Z6 filters, the D5 valves, the M2 valves, the M3 valves, the G11 pump, The Z14 centrifuges, G12 pumps, the M5 valves connect to form D normal liquid extractions circuit by pipeline;
The E liquid extracts system out:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, institute State D2 valves, the A9 valves, the D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form E liquid extraction circuit by pipeline;
The F liquid extracts system out:The Z6 filters, the M2 valves, the D5 valves, the C4 valves, the M7 valves, institute D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves is stated to connect to form F liquid by pipeline Body extracts circuit out;
The G liquid extracts system out:The Z7 filters, the F3 valves, the F4 valves, the E4 valves, the M3 valves, institute State C4 valves, the M7 valves, the D1 valves, the F2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form G liquid extraction circuit by pipeline;
Above system is not put into if any valve, is added according to demand in actual fabrication and operation, can not achieve unified instruction Valve using manual opening-closing cooperation realize.
The present invention can realize that freezing and filtering, room temperature filtering, quickly cooling are handed over automated and semi-automatic operating procedure respectively Change, speed heat exchange etc. processes use be to select according to demand, operating procedure is described below, before executing each single item system, own System is all that closed state has reached and waits for service requirement, and the pump element in execution system is opened and closed according to designer's design requirement (Pump belongs to closed state into pipe path individually in some execution systems), all elements, which have not represented, opens and closes function as exchanged Device, filter etc..Because equipment operating procedures is more, is not written in patent if any individual links known technology, is solved by designer It releases, example exhaust valve pipeline gets rid of native device etc..
Similarly, the Z8 refrigeration is for the Z8 refrigeration systems and adaption system and the Z8Z refrigeration systems and adaption system System and the Z8Z refrigeration systems category the using and the reserved principle.
Execute a speed heat swap operation:Start the B cooling water recirculation systems, the A coolant circulating systems (or the B Coolant circulating system), start the Z8 refrigeration systems later, the liquid exchanged later starts G10 by pipeline and is pumped into institute It states Z11 exchangers to swap, realizes a speed heat exchange process.
Execute two speed heat swap operations:It is (or described to start the BB cooling water recirculation systems, the AA coolant circulating systems BB coolant circulating systems), start the Z8Z refrigeration systems later, the liquid exchanged later starts the G10 by pipeline and pumps It is sent into the Z11 exchangers to swap, realizes two speed heat exchange process.
Execute a quickly cooling swap operation:Start the A cooling water recirculation systems and the B coolant circulating systems, Zhi Houqi The Z8 refrigeration systems are moved, the liquid exchanged later is pumped into the Z10 exchangers by pipeline startup G8 and swaps, real An existing quickly cooling exchange process.
Execute two quickly cooling swap operations:Start the AA cooling water recirculation systems(Or the BB cooling water recirculation systems)With The BB coolant circulating systems, start the Z8Z refrigeration systems later, and the liquid exchanged later starts the G8 by pipeline It is pumped into the Z10 exchangers to swap, realizes two quickly cooling exchange process.
Execute the A freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the A to be turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the B filters extension soil later System carries out precoating drainage to the Z6 filters and is situated between, completes and closes;Start A cooling water recirculation systems and described simultaneously A coolant circulating systems start the Z8 refrigeration systems and carry out cold energy energy storage later(Or start AA cooling water circulations system simultaneously System and the AA coolant circulating systems start the Z8Z refrigeration systems and carry out cold energy energy storage later);Later when cold energy energy storage reaches To the A systemic circulations cooling system is started when requiring, later when cooling reaches filtering requirement, the A systemic circulations cooling is closed System, starts the A freezing and filtering systems later and the A add-on systems carry out normal filtration.
Execute the B freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the B to be turned off, it is right later The A filters hang soil series system and carry out precoating drainage Jie, complete and close;Start the A cooling water recirculation systems simultaneously and the A is cold Matchmaker's circulatory system starts the Z8 refrigeration systems and carries out cold energy energy storage later(Or start the AA cooling water recirculation systems simultaneously With the AA coolant circulating systems, starts the Z8Z refrigeration systems later and carry out cold energy energy storage);Later when cold energy energy storage reaches It is required that when start the B systemic circulations cooling system, later when cooling reaches filtering requirement, close B systemic circulations cooling system System, starts the B freezing and filtering systems later and the A add-on systems carry out normal filtration.
Execute the C freezing and filtering systems operation:Start the cold feed liquor system completion feed liquors of the C to be turned off, it is right later The B filters hang soil series system and carry out precoating drainage Jie, complete and close;Start the A cooling water recirculation systems simultaneously and the A is cold Matchmaker's circulatory system starts the Z8 refrigeration systems and carries out cold energy energy storage later(Or start the AA cooling water recirculation systems simultaneously With the AA coolant circulating systems, starts the Z8Z refrigeration systems later and carry out cold energy energy storage);Later when cold energy energy storage reaches It is required that when start the C systemic circulations cooling system, later when cooling reaches filtering requirement, close C systemic circulations cooling system System, starts the C freezing and filtering systems later and the B add-on systems carry out normal filtration.
Execute the D room temperature filtration system operation:Start the normal feed liquor systems of the D, completion feed liquor is turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the B filters extension soil later System carries out precoating drainage to the Z6 filters and is situated between, completes and closes, and starts the D room temperature filtration system and the A later Add-on system, into normal filtration.
Execute the E room temperature filtration system operation:Start the normal feed liquor systems of the E, completion feed liquor is turned off, Zhi Houqi The dynamic A filters extension soil series system carries out precoating drainage to the Z4 filters and is situated between, completes and closes, and starts the E room temperature mistake later Filter system and the A add-on systems, into normal filtration.
Execute the F room temperature filtration system operation:Start the normal feed liquor systems of the F, completion feed liquor is turned off, Zhi Houqi The dynamic B filters extension soil series system carries out precoating drainage to the Z6 filters and is situated between, completes and closes, and starts the F room temperature mistake later Filter system and the B add-on systems, into normal filtration.
Execute the G room temperature filtration system operation:Start the normal feed liquor systems of the G, completion feed liquor is turned off, Zhi Houqi The dynamic C filters extension soil series system carries out precoating drainage to the Z7 filters and is situated between, completes and closes, and starts the G room temperature mistake later Filter system, into normal filtration.
It after filtering, selects according to demand, adaptation starts the A solid-liquid separation systems, the B is separated by solid-liquid separation system System, the C solid-liquid separation systems, the A liquid extraction system, B liquid extraction system, described C liquid extraction system etc., It completes to be separated by solid-liquid separation and liquid extracts technique etc. out.
Coordinate manual operation two-in-one system, to it is cumbersome and can unified instruction devise modularization but need to coordinate Personnel's gathered data carrys out compounding practice, because the pressure difference and flow of filtering flow change all in lasting variation and diatomite additive amount It requires, also need to the requirements such as the temperature difference to freezing and filtering, the implementation half of artificial detection data is needed to instruction cannot be completely unified Automation or manualization cooperation, the cooling tower can design using in circulating water temperature adjustable extent voluntarily auto-control unlatching with It closes, the cooling tower on the water tank, do not mark in view by display touch screen, control power distribution cabinet, module etc. Go out;Two-in-one control manually is added using automatically controlled and part is automatically controlled to valve portion used, carries out Regulating Pressure of Relief Values automatic protection dress It sets, the outlet of pump power source is connect with the high pressure port of safety valve, brought with preventing the failure of electric control valve and its violating operation Big pressure difference bring the possibility of damage to partial devices, the row pressure port connection of safety valve can liquid storage container, to prevent row pressure liquid The hidden danger that body is lost in and its splash zone comes!Feed liquor and go out at liquid can to design multi-pipeline to valve control, meet a variety of liquid Transform filter cleaning of body etc..My existing several patented technologies are additionally used simultaneously:Patent of invention title:A kind of automation Freezing filtration device and its operating method, patent of invention number:201110433647.X patent of invention title:A kind of modularization is low Warm filter device and its operating method, patent of invention number:201110433715.2 to ensure scientific and technological content and its city of the invention Field, practical value.

Claims (2)

1. a kind of freezing and filtering equipment of double refrigeration systems, which is characterized in that including:Z8 refrigeration systems, Z8Z refrigeration systems, A are cold But water circulation system, AA cooling water recirculation systems, B cooling water recirculation systems, BB cooling water recirculation systems, A coolant circulating systems, The cold feed liquor system of AA coolant circulating systems, B coolant circulating systems, BB coolant circulating systems, A, the cold feed liquor systems of B, the cold feed liquor systems of C System, A filters hang soil series system, soil series system is hung in B filters, soil series system is hung in C filters, A systemic circulations cooling system, B systemic circulations cooling system, C are followed greatly The normal feed liquor system of ring cooling system, A freezing and filtering systems, B freezing and filtering systems, C freezing and filtering systems, D, the normal feed liquor systems of E, The normal feed liquor systems of F, the normal feed liquor systems of G, D room temperature filtration system, E room temperature filtration system, F room temperature filtration system, G room temperature filtering system The cold liquid extraction of system, A add-on systems, B add-on systems, A solid-liquid separation systems, B solid-liquid separation systems, C solid-liquid separation systems, A The cold liquid extraction system of system, B, the cold liquid extraction systems of C, the normal liquid extraction systems of D, the normal liquid extraction systems of E, the normal liquid of F The normal liquid of extraction system, G extracts system out.
2. a kind of freezing and filtering equipment of double refrigeration systems according to claim 1, which is characterized in that the A cooling waters follow Loop system includes:B2 valves, Z12 cooling towers, B1 valves, G6 cooling pumps, T3 valves, T4 valves are cold by pipeline and the Z8 refrigeration systems Condenser inlet and outlet connection forms A cooling water circulation loops;
The AA cooling water recirculation systems include:The B2 valves, the Z12 cooling towers, the B1 valves, the G6 cooling pumps, T3T Valve, T4T valves form AA cooling water circulation loops by pipeline and the inlet and outlet connection of the condenser of the Z8Z refrigeration systems;
The B cooling water recirculation systems include:B3 valves, Z11 exchangers, E6 valves, the Z12 cooling towers, the B1 valves, the G6 Cooling pump, the T3 valves, the T4 valves form B cooling waters by pipeline and the inlet and outlet connection of the condenser of the Z8 refrigeration systems Circulation loop;
The BB cooling water recirculation systems include:The B3 valves, the Z11 exchangers, the E6 valves, the Z12 cooling towers, institute B1 valves, the G6 cooling pumps, the T3T valves, the T4T valves is stated to pass in and out by pipeline and the condenser of the Z8Z refrigeration systems Mouth connection forms BB cooling water circulation loops;
The A coolant circulating systems include:A1 valves, Z9 refrigerant tanks, A2 valves, G7 refrigerant pumps, A3 valves, Z3 exchangers, A4 valves, T1 Valve, T2 valves connect to form A refrigerant circulation circuits by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems;
The AA coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A3 Valve, the Z3 exchangers, the A4 valves, T1T valves, T2T valves are connected by pipeline and the evaporator inlet-outlet of the Z8Z refrigeration systems It connects to form AA refrigerant circulation circuits;
The B coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, A5 valves, Z10 exchangers, A6 valves, the T1 valves, the T2 valves connect shape by pipeline with the evaporator inlet-outlet of the Z8 refrigeration systems At B refrigerant circulation circuits;
The BB coolant circulating systems include:The A1 valves, the Z9 refrigerant tanks, the A2 valves, the G7 refrigerant pumps, the A5 The evaporation that valve, the Z10 exchangers, the A6 valves, the T1T valves, the T2T valves pass through pipeline and the Z8Z refrigeration systems Device inlet and outlet connection forms BB refrigerant circulation circuits;
The cold feed liquor systems of A include:Z1 protects filter, C1 valves, G1 pumps, Z2 exchangers, the Z3 exchangers, C2 valves, A9 valves, G2 Pump, Z4 filters, C3 valves, E5 valves, Z5 agitator tanks, C4 valves, G3 pump, Z6 filters connect to form the cold feed liquor circuits A by pipeline;
The cold feed liquor systems of B include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, the A9 valves, G2 pumps, the Z4 filters connect to form the cold feed liquor circuits B by pipeline;
The cold feed liquor systems of C include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 are handed over Parallel operation, the C2 valves, D2 valves, M7 valves, G3 pumps, the Z6 filters connect to form the cold feed liquor circuits C by pipeline;
Soil series system is hung in the A filters:C8 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the E5 Valve, the Z5 agitator tanks connect to form the Z4 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the B filters:D8 valves, G3 pumps, the Z6 filters, D5 valves, the E5 valves, the Z5 agitator tanks It connects to form the Z6 filters precoating filter aid circulation loop by pipeline;
Soil series system is hung in the C filters:C7 valves, G4 pumps, Z7 filters, E4 valves, the E5 valves, the Z5 agitator tanks pass through pipeline Connection forms the Z7 filters precoating filter aid circulation loop;
The A systemic circulations cooling system includes:E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, the A9 valves, The G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, the Z6 filters, C5 valves, the Z2 are exchanged Device connects to form A systemic circulations cooling circuit by pipeline;
The B systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described A9 valves, G2 pumps, the Z4 filters, the C3 valves, F1 valves, the Z2 exchangers connect to form B systemic circulations by pipeline Cool down circuit;
The C systemic circulations cooling system includes:It is the E1 valves, the Z2 exchangers, the Z3 exchangers, the C2 valves, described D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 exchangers connect that form C big by pipeline Circulation temperature lowering circuit;
The A freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the C4 valves, the G3 pump, institute State Z6 filters, the C5 valves, the Z2 exchangers, G4 pumps, the Z7 filters, F4 valves, C6 valves are connected by pipeline Form A freezing and filterings circuit;
The B freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the A9 valves, G2 pumps, the Z4 filters, the C3 valves, the F1 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form B freezing and filterings circuit by pipeline;
The C freezing and filtering systems include:The Z1 shields filter, the C1 valves, G1 pumps, the Z2 exchangers, the Z3 Exchanger, the C2 valves, the D2 valves, the M7 valves, G3 pumps, the Z6 filters, the C5 valves, the Z2 are exchanged Device, G4 pumps, the Z7 filters, the F4 valves, the C6 valves connect to form C freezing and filterings circuit by pipeline;
The normal feed liquor systems of D include:The Z1 shields filter, D1 valves, the D2 valves, the A9 valves, G2 pumps, the Z4 mistakes Filter, the C3 valves, the E5 valves, the Z5 agitator tanks, the C4 valves, G3 pumps, the Z6 filters are connected by pipeline It connects to form the normal feed liquor circuits D;
The normal feed liquor systems of E include:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, the G2 are pumped, are described Z4 filters, the C3 valves, the E5 valves, the Z5 agitator tanks piping connect to form the normal feed liquor circuits E;
The normal feed liquor systems of F include:Z1 shield filter, the D1 valves, the M7 valves, G3 pumps, the Z6 filters, The D5 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits F by pipeline;
The normal feed liquor systems of G include:It is Z1 shield filter, the D1 valves, F2 valves, G4 pumps, the Z7 filters, described F4 valves, the E4 valves, the E5 valves, the Z5 agitator tanks connect to form the normal feed liquor circuits G by pipeline;
The D room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, the C3 valves, the C4 valves, G3 pumps, the Z6 filters, D4 valves connect to form D room temperature by pipeline Filtration circuit;
The E room temperature filtration system includes:The Z1 shields filter, the D1 valves, the D2 valves, the A9 valves, G2 pumps, institute State Z4 filters, D3 valves connect to form E room temperature filtration circuits by pipeline;
The F room temperature filtration system includes:The Z1 shields filter, the D1 valves, the M7 valves, G3 pumps, Z6 filterings Machine, the D4 valves connect to form F room temperature filtration circuits by pipeline;
The G room temperature filtration system includes:The Z1 shields filter, the D1 valves, the F2 valves, G4 pumps, Z7 filterings Machine, the F4 valves, the C6 valves connect to form G room temperature filtration circuits by pipeline;
The A add-on systems include:The Z5 agitator tanks, G5 additions pump, D6 valves, the Z4 filters connect to be formed by pipeline A adds circuit;
The B add-on systems include:The Z5 agitator tanks, G5 additions pump, D7 valves, the Z6 filters are connected by pipeline It forms B and adds circuit;
The A solid-liquid separation systems include:M1 valves, G11 pumps, Z14 centrifuges, G12 pump, M6 valves, the D2 valves, the A9 valves, The G2 pumps, the Z4 filters connect to form A separation of solid and liquid circulation loops by pipeline;
The B solid-liquid separation systems include:M2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M6 valves, institute M7 valves, G3 pumps, the Z6 filters is stated to connect to form B separation of solid and liquid circulation loops by pipeline;
The C solid-liquid separation systems include:F3 valves, the E4 valves, M3 valves, G11 pumps, the Z14 centrifuges, the G12 Pump, the M6 valves, the F2 valves, the G4 pump, the Z7 filters connect to form C separation of solid and liquid circulation loops by pipeline;
The cold liquid of A extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the D5 valves, the Z6 mistakes It is filter, the M2 valves, the C4 valves, the M7 valves, the D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, described Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 valves, the Z7 filters, the F3 valves, the F4 valves, The E4 valves, the F1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, M5 valves are connected by pipeline It forms the cold liquid of A and extracts circuit out;
The cold liquid of B extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the A9 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 Valve, the C1 valves, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 pump, the Z14 from Scheming, G12 pumps, the M5 valves connect to form B cold liquid extractions circuit by pipeline;
The cold liquid of C extracts system out and includes:The D5 valves, the Z6 filters, the M2 valves, the C4 valves, the M7 valves, The D2 valves, the C2 valves, the Z3 exchangers, the Z2 exchangers, the F2 valves, the E1 valves, the D1 valves, the C1 Valve, the Z7 filters, the F3 valves, the F4 valves, the E4 valves, the F1 valves, the M3 valves, the G11 are pumped, are described Z14 centrifuges, G12 pumps, the M5 valves connect to form C cold liquid extractions circuit by pipeline;
The normal liquid of D extracts system out and includes:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, The D2 valves, the A9 valves, the D1 valves, the Z6 filters, the D5 valves, the M2 valves, the M3 valves, the G11 pump, The Z14 centrifuges, G12 pumps, the M5 valves connect to form D normal liquid extractions circuit by pipeline;
The E liquid extracts system out:The Z4 filters, the M1 valves, the C3 valves, the C4 valves, the M7 valves, institute State D2 valves, the A9 valves, the D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form E liquid extraction circuit by pipeline;
The F liquid extracts system out:The Z6 filters, the M2 valves, the D5 valves, the C4 valves, the M7 valves, institute D1 valves, the M3 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves is stated to connect to form F liquid by pipeline Body extracts circuit out;
The G liquid extracts system out:The Z7 filters, the F3 valves, the F4 valves, the E4 valves, the M3 valves, institute State C4 valves, the M7 valves, the D1 valves, the F2 valves, G11 pumps, the Z14 centrifuges, the G12 pump, the M5 valves It connects to form G liquid extraction circuit by pipeline.
CN201810780147.5A 2018-07-16 2018-07-16 A kind of freezing and filtering equipment of double refrigeration systems Pending CN108744712A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810780147.5A CN108744712A (en) 2018-07-16 2018-07-16 A kind of freezing and filtering equipment of double refrigeration systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810780147.5A CN108744712A (en) 2018-07-16 2018-07-16 A kind of freezing and filtering equipment of double refrigeration systems

Publications (1)

Publication Number Publication Date
CN108744712A true CN108744712A (en) 2018-11-06

Family

ID=63973905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810780147.5A Pending CN108744712A (en) 2018-07-16 2018-07-16 A kind of freezing and filtering equipment of double refrigeration systems

Country Status (1)

Country Link
CN (1) CN108744712A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109663407A (en) * 2019-02-22 2019-04-23 高云芝 A kind of method that liquid cryogen segmentation intercepts extract

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212091271U (en) * 2018-07-16 2020-12-08 高云芝 Freezing filtration equipment of two refrigerating system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212091271U (en) * 2018-07-16 2020-12-08 高云芝 Freezing filtration equipment of two refrigerating system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109663407A (en) * 2019-02-22 2019-04-23 高云芝 A kind of method that liquid cryogen segmentation intercepts extract

Similar Documents

Publication Publication Date Title
CN108759201A (en) A kind of freezing filtration device of double refrigeration systems
CN108654206A (en) A kind of freezing filtration device
CN108654197A (en) A kind of low-temperature filter
CN108619784A (en) A kind of freezing and filtering equipment
CN108854239A (en) It is a kind of to freeze double filter devices
CN108889022A (en) It is a kind of to freeze double filter plants
CN108771910A (en) A kind of double filter devices of double refrigeration
CN108993024A (en) A kind of quickly cooling technique in freezing and filtering unit
CN108744712A (en) A kind of freezing and filtering equipment of double refrigeration systems
CN109331540A (en) A kind of extraction raffinate treatment process of freezing and filtering unit
CN105154224B (en) Heat reclaim unit and recovery method in a kind of oil and fat refining process
CN108722011A (en) A kind of filter at low temperature equipment
CN108889026A (en) A kind of filtering technique of freezing and filtering unit
CN108827053A (en) A kind of thermal energy recycling technique of freezing and filtering unit
CN108939660A (en) A kind of dual system refrigeration process of freezing and filtering unit
CN108722010A (en) A kind of integrated form freezing and filtering unit
CN108722012A (en) A kind of technique of integrated form freezing and filtering unit
CN212091271U (en) Freezing filtration equipment of two refrigerating system
CN212091270U (en) Freezing filter equipment
CN212091232U (en) Low-temperature filtering device
CN212067995U (en) Freezing filtration equipment
CN108686421A (en) A kind of double filter plants of double refrigeration
CN212091216U (en) Freezing double-filter device
CN212067983U (en) Double-refrigeration double-filtering equipment
CN212091209U (en) Freezing double-filtering equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination