CN108708536A - Console mode scaffold building construction method - Google Patents

Console mode scaffold building construction method Download PDF

Info

Publication number
CN108708536A
CN108708536A CN201810569285.9A CN201810569285A CN108708536A CN 108708536 A CN108708536 A CN 108708536A CN 201810569285 A CN201810569285 A CN 201810569285A CN 108708536 A CN108708536 A CN 108708536A
Authority
CN
China
Prior art keywords
scaffold
bar
upright bar
rod
horizontal rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810569285.9A
Other languages
Chinese (zh)
Inventor
胡长亮
谷橙
徐开伟
张也
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc Northeast Construction (shenyang) Engineering Technology Co Ltd
Original Assignee
Mcc Northeast Construction (shenyang) Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mcc Northeast Construction (shenyang) Engineering Technology Co Ltd filed Critical Mcc Northeast Construction (shenyang) Engineering Technology Co Ltd
Priority to CN201810569285.9A priority Critical patent/CN108708536A/en
Publication of CN108708536A publication Critical patent/CN108708536A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/02Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means
    • E04G1/04Scaffolds primarily resting on the ground composed essentially of members elongated in one dimension only, e.g. poles, lattice masts, with or without end portions of special form, connected together by any means the members being exclusively poles, rods, beams, or other members of similar form and simple cross-section

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

A kind of console mode scaffold building construction method, pass sequentially through that ground is built with basis, the building of upright bar, the building of longitudinal horizontal rod, the building of horizontal rod, the building of bridging, the building of scaffold board, wall-connecting piece are built, and the processing of privileged sites, solve the technical issues of corner caused by the big scaffold construction in building abnormity existing in the prior art, polygon, angle of inclination, cornice with other protruding parts scaffold constructions.

Description

Console mode scaffold building construction method
Technical field
The invention belongs to construction, relate generally to a kind of console mode scaffold building construction method.
Background technology
It builds in citizen, Fang Jian, setting up and removing for scaffold will be related to.Scaffold is set up with Demolition Construction at this Proportion is very big in the engineering of a little industries, and the erection construction method and quality of scaffold, directly affects corresponding engineering Safety.Existing console mode scaffold, which is set up, generally uses the general method set up layer by layer, when meeting special-shaped building, Set up structure cannot in time according to construction need be adjusted, set up stability and cannot be guaranteed, and set up take it is longer, cause Whole claim for eot.
Invention content
The purpose of the present invention is to provide a kind of console mode scaffold building construction methods, pass sequentially through ground and are taken with basis It builds, the building of upright bar, the building of longitudinal horizontal rod, the building of horizontal rod, the building of bridging, scaffold board are built, even Wall part build and the processing of privileged sites.It solves in the prior art due to building abnormity, polygon, angle of inclination Corner caused by big scaffold construction, the technical issues of cornicing with other protruding parts scaffold constructions.
The technical solution adopted by the present invention is:
Console mode scaffold building construction method, which is characterized in that its step is:
1) ground is built with basis:Scaffold basic foundation backfill compaction in layers, in scaffold upright rod bottom feet hand Plate, gutter is arranged in surrounding on the outside of scaffold;
2) upright bar is built:
2.1) longitudinal bar of sweeping the floor is fixed on using right-angle coupler in the upright bar being not more than at 200mm away from steel pipe bottom end, laterally Bar of sweeping the floor is fixed on using right-angle coupler in the upright bar below longitudinal bar of sweeping the floor;When scaffold upright rod basis is not in same height When on degree, the longitudinal direction of eminence bar of sweeping the floor is extended to lower and two fixed across with upright bar;
2.2) in addition to top layer, remaining each layer is respectively walked connector and is connected using sleeve couple scaffold upright rod, the docking in upright bar Fastener answers interlaced arrangement, and two adjacent upright bar connectors, which must not be located at, to be synchronized with across interior, and scaffold upright rod top railing is higher by female Youngster's wall upper end 1m is higher by cornice upper end 1.5m;
3) longitudinal horizontal rod:Longitudinal horizontal rod should be arranged in the inside of upright bar, be fastened using right-angle coupler and column;Two The connector of adjacent longitudinal horizontal rod should not be arranged in synchronization or with across interior;Asynchronous difference is wrong in the horizontal direction across two adjacent heads The distance opened is more than or equal to 500mm;The distance of connector center to nearest host node is not more than the 1/3 of advance;
4) horizontal rod:Horizontal rod in work layer at non-master, according between needs of support scaffold board etc. Away from setting, horizontal rod both ends are all made of right-angle coupler and are fixed in longitudinal horizontal rod, and horizontal rod is set at host node, adopt With right-angle coupler fastening in longitudinal horizontal rod;
5) bridging:Bridging is arranged in the outside of scaffold, by scaffold end, left and right is continuously set from bottom to top It sets, is fixed with fastener mutually with the crosspoint of other rod pieces when setting;
6) scaffold board:Setting is fixed in three horizontal rods, and by its both ends with iron wire and horizontal rod;
7) wall-connecting piece:It is started setting up from bottom first step longitudinal horizontal rod, wall-connecting piece, across arrangement, is preferentially adopted by two steps three It is arranged with diamond shape, square arrangement, rectangular arrangement can also be used, and drawknot node is encrypted in corner and top portion;
8) guardrail and foot guard plate:One of guard rail rod is arranged away from/2 positions in Walk, and foot guard plate height is 200mm;
9) special parts treatment:
9.1) scaffold chute is set up:
9.1.1), the load of upright bar is maximum at chute, takes the measure for increasing upright bar or local off-load;
9.1.2) chute is wider than equal to 1m, and the gradient is preferably 1:3, chute uses zig-zag type, attachment external scaffolding setting;Tiltedly Road both sides and platform periphery are respectively provided with railing and foot guard plate, rail height 1.2m;
9.1.3) chute both sides, end and platform periphery are provided with bridging;
9.1.4) scaffold board is by the way of horizontal paving, adds longitudinal supporting bar under horizontal rod, between longitudinal supporting bar Away from draw runner of less than or equal to 500mm, setting up defences on chute scaffold board, tread plate is smaller than equal to 300mm;
9.2) hole is handled:
9.2.1) door opening of scaffold is using rising brace, parallel-chord truss structure type, the inclination angle of brace and ground For 60 ° of 45-;
9.2.2) diagonal web member is fixed on using rotary buckle on the external part of intersecting therewith horizontal rod, rotary buckle The distance of center line to host node is less than or equal to 150mm;Diagonal web member uses elongated bar, is stretched out in diagonal web member and door opening truss The end of lower boom increases an anti-skid fastener, fastener of the fastener at host node;
9.2.3) diagonal web member uses elongated rod piece, and the both sides upright bar under door opening truss is two-tube upright bar, and auxiliary pole height is answered Higher than 2 step of door opening;
9.3) it cornices or the processing of other protruding parts:
When scaffold binds, in order to ensure that the safety of construction, outer row's upright bar height must be over the height of house cornice, and Twice flak jacket column foot guard plate with together with is set, safety vertical net is hung;When cornicing or the width of other protruding parts is more than 800mm, Any type in following two modes may be used:
9.3.1), scaffold building height when the width that cornices is more than 800mm, increases by row's scaffold outside less than 15m Way
9.3.2), scaffold building height is more than 15m, when the width that cornices is more than 800mm, is cornicing or protruding parts, is adopting The way overhang with shaped steel is set up.
The beneficial effects of the invention are as follows:
1), speed of application is fast, a survival rate height, and operation difficulty is small.
2), construction operability is strong, safety coefficient is high, can ensure construction speed requirement.
3), engineering construction quality is guaranteed, and disclosure satisfy that design and the requirement of technical specification..
Description of the drawings
Fig. 1:Increase upright bar in embodiment 1 at external corner sets up schematic diagram.
Fig. 2:Construction schematic diagram at basic and gutter in embodiment 1.
Fig. 3:In embodiment 1 in length and breadth it is horizontal should and upright bar organigram.
Fig. 4 a:Longitudinal horizontal rod is not synchronizing interior banjo fixing butt jointing arrangement schematic diagram in embodiment 1.
Fig. 4 b:Longitudinal horizontal rod is not the same as across interior banjo fixing butt jointing arrangement schematic diagram in embodiment 1.
Fig. 5:Bridging arrangement schematic diagram in embodiment 1.
Fig. 6:Connection diagram is overlapped in embodiment 1.
Fig. 7:Wall-connecting piece arrangement schematic diagram in embodiment 1.
Fig. 8:Schematic diagram is arranged in foot guard plate in embodiment 1.
Fig. 9 a:Chute sets up schematic diagram in embodiment 1.
Fig. 9 b:For Fig. 9 a along 1-1 to structural schematic diagram.
Fig. 9 c:For Fig. 9 a along 2-2 to structural schematic diagram.
Fig. 9 d:For the elevation of Fig. 9 a.
Figure 10:To set up schematic diagram at all middle hole of embodiment 1.
Figure 11:To cornice in embodiment 1 or protruding parts detail drawing.
Figure 12:Elevator shaft mouth construction schematic diagram in embodiment 1.
Figure 13:Stair, floor and balcony provisional protection schematic diagram in embodiment 1.
Specific implementation mode
Console mode scaffold building construction method, step are:
1) ground is built with basis:Scaffold basic foundation backfill compaction in layers, in scaffold upright rod bottom feet hand Plate, gutter is arranged in surrounding on the outside of scaffold.
2) upright bar is built:
2.1) longitudinal bar of sweeping the floor is fixed on using right-angle coupler in the upright bar being not more than at 200mm away from steel pipe bottom end, laterally Bar of sweeping the floor is fixed on using right-angle coupler in the upright bar below longitudinal bar of sweeping the floor;When scaffold upright rod basis is not in same height When on degree, the longitudinal direction of eminence bar of sweeping the floor is extended to lower and two fixed across with upright bar;
2.2) in addition to top layer, remaining each layer is respectively walked connector and is connected using sleeve couple scaffold upright rod, the docking in upright bar Fastener answers interlaced arrangement, and two adjacent upright bar connectors, which must not be located at, to be synchronized with across interior, and scaffold upright rod top railing is higher by female Youngster's wall upper end 1m is higher by cornice upper end 1.5m.
3) longitudinal horizontal rod:Longitudinal horizontal rod should be arranged in the inside of upright bar, be fastened using right-angle coupler and column;Two The connector of adjacent longitudinal horizontal rod should not be arranged in synchronization or with across interior;Asynchronous difference is wrong in the horizontal direction across two adjacent heads The distance opened is more than or equal to 500mm;The distance of connector center to nearest host node is not more than the 1/3 of advance.
4) horizontal rod:Horizontal rod in work layer at non-master, according between needs of support scaffold board etc. Away from setting, horizontal rod both ends are all made of right-angle coupler and are fixed in longitudinal horizontal rod, and horizontal rod is set at host node, adopt With right-angle coupler fastening in longitudinal horizontal rod.
5) bridging:Bridging is arranged in the outside of scaffold, by scaffold end, left and right is continuously set from bottom to top It sets, is fixed with fastener mutually with the crosspoint of other rod pieces when setting.
6) scaffold board:Setting is fixed in three horizontal rods, and by its both ends with iron wire and horizontal rod.
7) wall-connecting piece:It is started setting up from bottom first step longitudinal horizontal rod, wall-connecting piece, across arrangement, is preferentially adopted by two steps three It is arranged with diamond shape, square arrangement, rectangular arrangement can also be used, and drawknot node is encrypted in corner and top portion.
8) guardrail and foot guard plate:One of guard rail rod is arranged away from/2 positions in Walk, and foot guard plate height is 200mm.
9) special parts treatment:
9.1) scaffold chute is set up:
9.1.1), the load of upright bar is maximum at chute, takes the measure for increasing upright bar or local off-load;
9.1.2) chute is wider than equal to 1m, and the gradient is preferably 1:3, chute uses zig-zag type, attachment external scaffolding setting;Tiltedly Road both sides and platform periphery are respectively provided with railing and foot guard plate, rail height 1.2m;
9.1.3) chute both sides, end and platform periphery are provided with bridging;
9.1.4) scaffold board is by the way of horizontal paving, adds longitudinal supporting bar under horizontal rod, between longitudinal supporting bar Away from draw runner of less than or equal to 500mm, setting up defences on chute scaffold board, tread plate is smaller than equal to 300mm;
9.2) hole is handled:
9.2.1) door opening of scaffold is using rising brace, parallel-chord truss structure type, the inclination angle of brace and ground For 60 ° of 45-;
9.2.2) diagonal web member is fixed on using rotary buckle on the external part of intersecting therewith horizontal rod, rotary buckle The distance of center line to host node is less than or equal to 150mm;Diagonal web member uses elongated bar, is stretched out in diagonal web member and door opening truss The end of lower boom increases an anti-skid fastener, fastener of the fastener at host node;
9.2.3) diagonal web member uses elongated rod piece, and the both sides upright bar under door opening truss is two-tube upright bar, and auxiliary pole height is answered Higher than 2 step of door opening;
9.3) it cornices or the processing of other protruding parts:
When scaffold binds, in order to ensure that the safety of construction, outer row's upright bar height must be over the height of house cornice, and Twice flak jacket column foot guard plate with together with is set, safety vertical net is hung;When cornicing or the width of other protruding parts is more than 800mm, Any type in following two modes may be used:
9.3.1), scaffold building height when the width that cornices is more than 800mm, increases by row's scaffold outside less than 15m Way
9.3.2), scaffold building height is more than 15m, when the width that cornices is more than 800mm, is cornicing or protruding parts, is adopting The way overhang with shaped steel is set up.
Embodiment 1:
Tongliao City's filial piety Zhuanghe cultural industry band folk culture shop-Mongolian medicine shop engineering is located at Tongliao City Xincheng District Huolin Gol road West side, filial piety Zhuanghe's bank landscape belt, boundary of works area include building shown in the drawings such as civil engineering and installation, decorate, electrical, discharge The full content of the construction drawings design code such as water, HVAC, fire-fighting, ventilation, elevator, light current.This engineering is multilayer public building. Main body is basement one, and function is open type exhibition room.It is equipped with 5 independent building elevator towers on the ground.2690 squares of overall floorage Rice, wherein 1818 square metres of basement, 872 square metres of building elevator tower.Building includes 1 layer of basement and 5 stair towers, and building is high Up to 16 meters of degree, embedded depth of foundation is about 8.5 meters.A height of 7.2 meters of basement floor, base form is raft foundation, sole plate Thickness is 800, concrete grade C40, seepage-resistant grade P6, and upper structure type is frame-shear-wall structure, beam slab concrete Grade is C30, floor thickness be basement roof 200,150 ㎜ of upper floor plate.
One, integral construction:
1, technological process is set up
→ → positioning is arranged elongated chock → putting bar of sweeping the floor → and is established by root for foundation bearing capacity experiment for levelling of the land, compacting Upright bar, pacify immediately with bar fastening of sweeping the floor → installing sweep the floor cross bar and fastened with upright bar or bar of sweeping the floor → first step leger (with it is each Upright bar fastens) → peace the first step small cross bar → second step leger → the small cross bar of second step → add interim hound (upper end with Second step leger fastens, dismountable after install twice wall connecting rod) → third and fourth walk leger and small cross bar → wall connecting rod → Connect upright bar → add bridging → paving scaffold board.
2, erection construction method
(1), according to construction and building plan-position is set up, inside and outside upright bar is measured from metope in building quadrangle first Distance, and mark.It this time is evenly arranged upright bar position with 50m steel tapes, the spacing of upright bar is not more than 1500mm, and use is red Paint marks, and then puts chock, and chock must be parallel to metope.
(2), during setting up first floor scaffold, one of bearing diagonal is set along the every frame lattice of surrounding, corner is double To adding, wait for that the reliable drawknot rear of the wall-connecting piece of the position scaffold and agent structure is dismountable.
(3), double-pole scaffold arranges upright bar in first standing, and rear vertical outer row's upright bar often arranges upright bar and first stands both ends, after drawing logical line, Stand intermediate upright bar again, the line of inside and outside two upright bar is vertical with metope, when upright bar spreading, first stands outer row, it is rear it is vertical in row.
(4), the first floor and work layer must take hard isolation, completely spread scaffold board between upright bar and metope in scaffold.It applies Every being closed using Dense mesh screen or other measures between upright bar and building (in 10m) in 3 step frame bodies below work layer.
(5), the guard rail of 0.9m high and the skirting board of 180mm high be must be provided with from second step on the outside of scaffold, pushed up Row's guard rail sets three guard rails, and height is respectively 1.3m, 0.9m, 0.3m.(door and window at the large span standard width of a room in an old-style house is met in interior upright bar Hole) guard rail of 0.9m high and the skirt bar of 300mm high need to be added.
(6), it is gone along with sb. to guard him since the scaffolding structure construction period of this engineering only serves, the laying of scaffold board is with work layer Boundary completely spreads three layers and bottom top layer is completely spread, and the stage to be decorated is laid with layer by layer again.The scaffold board main reinforcement of full laying should be perpendicular to vertical To horizon bar, docking tiling is completely taped against position, and position of not leaving a blank, there is not allowed that taking the lead, four angles are fixed on support rod with 18# galvanized wires On, it is desirable that it is smooth to bind secured infall.Scaffold board is accomplished to stand intact, and damaged will replace in time.
(7), scaffold must coordinative construction progress set up, one time adjacent wall-connecting piece or more two is not to be exceeded in scaffolding height Step.After often having taken a step scaffold, correction step pitch, advance, transfer and the verticality of upright bar should be provided according to specification.
(8), safety net is fixed on the inboard of scaffold outer vertical rod, is used in combination and is hanged up tightly, on the corner not less than 18# galvanized wires The inside of safety net increases a upright bar, ensures that the straight of safety net, safe Dense mesh screen are increased with construction layer, is higher by construction layer 1m or more.In scaffold negative and positive corner, vertically and horizontally horizon bar necessarily is formed intersecting parallels, refers to Fig. 1.
3, technological process is removed
Safety net → foot guard plate and scaffold board → guard rail → bridging → hound → small cross bar → leger → vertical Bar.
4, it removes and requires
(1), preparation is removed
1. marking work distinctive emblem, pedestrian is forbidden to enter;
2. checking whether the fastener connection of scaffold, wall-connecting piece, support system etc. meet detailing requiments comprehensively;
3. the sequence of the dismounting in Design of Construction Organization and measure are improved according to inspection result supplement, after authorities ratify It can implement;
4. carrying out safe demolition technique by Project Technical responsible person to tell somebody what one's real intentions are, and fulfil signature formality;
5. removing the sundries and ground obstacle on scaffold.
(2), dismounting sequence is strictly observed, from top to bottom, that props up afterwards first tears open, is torn open after propping up afterwards, usually first tears railing, foot open Palm, Crossing brace then tear small cross bar, leger, upright bar etc. open;
(3), it assumes unified command of, echoes up and down, coordination should be informed first pair when unlocking knot related with another people Side, with fall arrest;
(4), material working tool is transported with pulley rope, must not be thrown out without care.In dismounting, special messenger should be sent to keep an eye on, it must not arbitrarily disorderly Material is thrown down from high-altitude.All kinds of component and fittings forbid throwing to ground.
(5), removing operation from top to bottom must successively carry out, and forbid to be carried out at the same time up and down;
(6), the stability for removing back frame body is not destroyed, and before wall attaching rod is removed, should add temporary support prevents from deforming, Wall-connecting piece must successively be removed with scaffold, forbid to tear scaffold open again after first removing wall-connecting piece flood or several layers;Segmentation is removed Height difference should not exceed two steps;If height difference is more than two steps, wall-connecting piece reinforcing should be added;
(7), it when being torn open when scaffold to the height of last root long upright bar of lower part (about 6.5 meters), first in place should take If after interim throwing support is reinforced, then removing wall-connecting piece;
(8), when scaffold takes segmentation, discrete faces are removed, reinforcement measure should be taken to the scaffold both ends that do not remove.
Two, construction is set up
1, ground and basis
The compacting factor of scaffold basic foundation backfill compaction in layers, backfill is not less than 0.94, and compactness uses ring Skill in using a kitchen knife in cookery experiment is determined, and foundation bearing capacity standard value is 135KN/m2, and surface pours 100 thickness C15 concrete cushions.In foot hand Frame bottom of upright rod pads the elongated scaffold board of 50*500, carries out gutter at surrounding 500 on the outside of the scaffold, prevents ponding from impregnating ground Base.Forbid to cut the earth within the scope of 2 meters on the outside of scaffold.Basis and gutter detail drawing are as shown in Figure 2.
2, upright bar
(1), scaffold must be provided with bar of vertically and horizontally sweeping the floor.Bar of longitudinally sweeping the floor should be fixed on using right-angle coupler away from steel pipe bottom End no more than at 200mm in upright bar, it is vertical below longitudinal bar of sweeping the floor that bar of laterally sweeping the floor should use right-angle coupler be fixed on On bar.
(2), scaffold upright rod basis is not when on sustained height, it is necessary to by the longitudinal direction of eminence sweep the floor bar to lower extend two It is fixed across with upright bar, difference of height is not more than 1m.The distance of upright bar axis to side slope above side slope is no less than 500mm, in detail See Fig. 3.
(3), scaffold upright rod is in addition to top layer, remaining each layer, which respectively walks connector, to use sleeve couple to connect, in upright bar Sleeve couple answers interlaced arrangement, and two adjacent upright bar connectors, which must not be located at, to be synchronized with across interior, and two adjacent upright bar connectors are in height side It is not less than 500mm to the distance being staggered, the distance between each connector center and host node should not exceed 600mm;The overlap joint of upright bar Length is not less than 1m, and 3 rotary buckles are fixed, and end fastener edge is not less than 100mm far from rod end distance;.
(4), scaffold upright rod top railing is higher by parapet upper end 1m, is higher by cornice upper end 1.5m.
3, longitudinal horizontal rod
(1), longitudinal horizontal rod should be arranged in the inside of upright bar, be fastened using right-angle coupler and column, single pole length is not Less than 3 across (4.5m).
(2), the connector of two adjacent longitudinal horizontal rods should not be arranged in synchronization or with across interior;Asynchronous difference is adjacent across two The distance that connector is staggered in the horizontal direction is not less than 500mm;The distance of a connector center to nearest host node is not more than advance 1/3, refer to Fig. 4 a, Fig. 4 b.
(3), the horizontal departure of same row's leger is not more than the 1/250 of the piece scaffold total length, and is not more than 50mm.
(4), on the outside of scaffold from second step 1/2 Walk away from must be provided with one of longitudinal horizontal rod at (0.9m).
4, horizontal rod
(1), horizontal rod is obtained in work layer at non-master, spaced set is preferably needed according to support scaffold board, Maximum spacing should not exceed the 1/2 of advance.
(2), horizontal rod both ends should all be fixed on using right-angle coupler in longitudinal horizontal rod, and cross must be set at host node To horizon bar, using right-angle coupler fastening in longitudinal horizontal rod, axis offset host node distance is not more than 150mm;
(3) horizontal rod end stretches out outer vertical rod length and cannot be less than 100mm, and as possible one shows and ensures that alien invasion is macro Effect is seen, distance of the inside away from metope is not more than 100mm.
5, bridging setting requirements
(1), bridging is arranged in the outside of scaffold, and by scaffold end, it is 5~7 that per pass bridging, which crosses over upright bar, Root, per pass bridging width are no less than 4 across and being not less than 6m, the inclination angle on brace and ground is 45 °~60 °, left from bottom to top Fight continuity is arranged, and is fixed with fastener mutually with the crosspoint of other rod pieces when setting.The bridging lap of splice is no less than 1m and use No less than 3 rotary buckles are fixed, and edge to the rod end distance of end fastener cover board is no less than 100mm, and it is big should to extend to top It is more than cross bar.Structure refers to Fig. 5.
(2), the connector of bridging brace is connected using overlap joint, and the lap of splice is not less than 1m, is equidistantly positioned 3 turn buckles Part is fixed, and end fastener edge is not less than 100mm far from rod end, refers to lower Fig. 6.
(3), bridging brace is fixed on rotary buckle in external part or the upright bar of intersecting therewith horizontal rod, rotation Turn fastener center line and is not more than 150mm away from host node distance.
6, scaffold board
The wooden scaffold board should be generally arranged in three horizontal rods, and its both ends iron wire is consolidated with horizontal rod It is fixed.3 horizontal rods are at least set under every piece of scaffold board;Scaffold board is using tiling, and joint must be double when docking connects Horizontal rod, 200~250mm of gap;Scaffold board both ends must be tied with horizontal rod, to prevent from tumbling.
7, wall-connecting piece
(1), the arrangement of wall-connecting piece is preferably arranged close to host node, and the distance for deviateing host node should not exceed 300mm.When more than Brace must be increased when 300mm.
(2), wall-connecting piece should start setting up from bottom first step longitudinal horizontal rod, when setting is had any problem at this, Ying Cai It is fixed with other responsible measures.
(3), wall-connecting piece preferentially should use diamond shape to arrange, square arrangement, rectangular cloth can also be used by two steps three across arrangement It sets.Drawknot node is encrypted in corner and top portion.Horizontal direction spacing 4.5m, vertical direction spacing 3.6m.Structure refers to Fig. 7.
8, guardrail and foot guard plate
One of guard rail rod is arranged away from/2 positions (0.9m) in Walk, and foot guard plate height is 200mm, and structure refers to Fig. 8.
Three, special parts treatment
1, scaffold chute is set up
(1), the load of upright bar is often maximum at chute, because have scaffold board and foot guard plate layer by layer, therefore the upright bar of chute Its stability is calculated, if being unsatisfactory for requiring, the measure for increasing upright bar or local off-load can be taken.
(2), chute width is not preferably less than 1m, and the gradient is preferably 1:3, chute uses zig-zag type, attachment external scaffolding setting to turn Platform is arranged in crook, and half space width is not less than 1.2m.Chute both sides and platform periphery are respectively provided with railing and foot guard plate.Railing Height should be 1.2m.
(3), chute both sides, end and platform periphery, it is necessary to which bridging is set.
(4), scaffold board adds longitudinal supporting bar, longitudinal rest distance between tie rods by the way of horizontal paving under horizontal rod No more than 500mm, must set up defences draw runner on chute scaffold board, and anti-skidding stripe pitch is not more than 300mm, and batten thickness should be 20mm- 30mm.Structure refers to Fig. 9 a-9d.
2, hole is handled
(1), the door opening of scaffold, which uses, rises brace, parallel-chord truss structure type, and the inclination angle on brace and ground is answered In 45-60.
(2), diagonal web member should be fixed on using rotary buckle on the external part of intersecting therewith horizontal rod, rotary buckle The distance of center line to host node is not more than 150mm.Diagonal web member uses elongated bar, is stretched out up and down in diagonal web member and door opening truss The end of chord member increases an anti-skid fastener, fastener of the fastener at host node.
(3) diagonal web member should use elongated rod piece, and the both sides upright bar under door opening truss is two-tube upright bar, and auxiliary pole height answers height In 2 step of door opening.
Structure refers to Figure 10.
3, it cornices or the processing of other protruding parts
When scaffold binds, in order to ensure that the safety of construction, outer row's upright bar height must be over the height of house cornice.And Twice flak jacket column foot guard plate with together with is set, safety vertical net is hung.The height of scaffold outer vertical rod exceeds 1 meter of parapet, to slope Roofing must be over 1.5 meters of cornice, and when the width that cornices is less than 800mm, interior row's upright bar is less than cornice bottom 150-200mm, and outer row is most The free height on upper row wall-connecting piece top is not more than 4m.
When cornicing or the width of other protruding parts is more than 800mm, forbid to be set up from by the way of choosing using steel pipe Any type in following two modes may be used in external scaffolding.
(1), scaffold building height is less than 15m can increase by row's scaffold outside when the width that cornices is more than 800mm Way
(2), scaffold building height is more than 15m, when the width that cornices is more than 800mm, is cornicing or protruding parts, using type The way of steel overhanging is set up, and Figure 11 is referred to.
4, escape way is set up
First floor channel must fix exit and entrance, and non-channel should all be shut, while set up protection canopy, depth of building It is 3 × 2.5m when 20m or less, is 6 × 2.5m when depth of building 20m or more, both sides should be closed, and safety is hung above entrance Gap marker board and safety warning-panel.100mm thickness C15 concrete hardenings must be used into the ground of escape way.
5, elevator shaft
Elevator shaft mouth uses upper-turn-type door.Height is 1.2m, and width exceeds well head both sides 200m (one side 100mm), used Material is that 12 reinforcing bars of Φ are welded, and brushes the black alternate warning coloration (paint) of Huang of 40cm.The first floor sets one of double-layer horizontal in elevator Safety net more than the first floor sets one of horizontal safety net every 3 layers and no more than 10m, and safety net all round closure is tight.Refer to Fig. 1.
6, the edge protections railing such as stair is set up
(1), all kinds of holes of construction site passage proximate and pit slot etc., in addition to setting protective equipment and safety sign, Night should also set red light and warn.
(2), at stair step and half space.The secured guard rail of twice must be set or protected with vertical linked network.Revolution Formula staircase should install first floor horizontal safety net and set one of horizontal safety net every four layers.Refer to Figure 13.

Claims (1)

1. console mode scaffold building construction method, which is characterized in that its step is:
1) ground is built with basis:Scaffold basic foundation backfill compaction in layers, in scaffold upright rod bottom feet palm, Gutter is arranged in surrounding on the outside of scaffold;
2) upright bar is built:
2.1) longitudinal bar of sweeping the floor is fixed on away from steel pipe bottom end using right-angle coupler no more than in the upright bar at 200mm, is laterally swept the floor Bar is fixed on using right-angle coupler in the upright bar below longitudinal bar of sweeping the floor;When scaffold upright rod basis is not on sustained height When, the longitudinal direction of eminence bar of sweeping the floor is extended to lower and two fixed across with upright bar;
2.2) in addition to top layer, remaining each layer is respectively walked connector and is connected using sleeve couple scaffold upright rod, the sleeve couple in upright bar Answer interlaced arrangement, two adjacent upright bar connectors, which must not be located at, to be synchronized with across interior, and scaffold upright rod top railing is higher by parapet Upper end 1m is higher by cornice upper end 1.5m;
3) longitudinal horizontal rod:Longitudinal horizontal rod should be arranged in the inside of upright bar, be fastened using right-angle coupler and column;Two adjacent The connector of longitudinal horizontal rod should not be arranged in synchronization or with across interior;What asynchronous difference was staggered in the horizontal direction across two adjacent heads Distance is more than or equal to 500mm;The distance of connector center to nearest host node is not more than the 1/3 of advance;
4) horizontal rod:Horizontal rod in work layer at non-master is equidistantly set according to the needs of support scaffold board It sets, horizontal rod both ends are all made of right-angle coupler and are fixed in longitudinal horizontal rod, and horizontal rod is set at host node, using straight Angle fastener fastening is in longitudinal horizontal rod;
5) bridging:Bridging is arranged in the outside of scaffold, by scaffold end, the continuous setting in left and right from bottom to top, if It is fixed with fastener mutually with the crosspoint of other rod pieces when setting;
6) scaffold board:Setting is fixed in three horizontal rods, and by its both ends with iron wire and horizontal rod;
7) wall-connecting piece:It is started setting up from bottom first step longitudinal horizontal rod, wall-connecting piece, across arrangement, preferentially uses water chestnut by two steps three Shape is arranged, square arrangement, rectangular arrangement can also be used, and drawknot node is encrypted in corner and top portion;
8) guardrail and foot guard plate:One of guard rail rod is arranged away from/2 positions in Walk, and foot guard plate height is 200mm;
9) special parts treatment:
9.1) scaffold chute is set up:
9.1.1), the load of upright bar is maximum at chute, takes the measure for increasing upright bar or local off-load;
9.1.2) chute is wider than equal to 1m, and the gradient is preferably 1:3, chute uses zig-zag type, attachment external scaffolding setting;Chute two Side and platform periphery are respectively provided with railing and foot guard plate, rail height 1.2m;
9.1.3) chute both sides, end and platform periphery are provided with bridging;
9.1.4) scaffold board adds longitudinal supporting bar by the way of horizontal paving under horizontal rod, and longitudinal rest distance between tie rods is small In draw runner of equal to 500mm, setting up defences on chute scaffold board, tread plate is smaller than equal to 300mm;
9.2) hole is handled:
9.2.1) door opening of scaffold, which uses, rises brace, parallel-chord truss structure type, and the inclination angle on brace and ground is 45- 60°;
9.2.2) diagonal web member is fixed on using rotary buckle on the external part of intersecting therewith horizontal rod, rotary buckle center The distance of line to host node is less than or equal to 150mm;Diagonal web member uses elongated bar, and upper lower edge is stretched out in diagonal web member and door opening truss The end of bar increases an anti-skid fastener, fastener of the fastener at host node;
9.2.3) diagonal web member uses elongated rod piece, and the both sides upright bar under door opening truss is two-tube upright bar, and auxiliary pole height should be higher than that Door opening 40cm;
9.3) it cornices or the processing of other protruding parts:
When scaffold binds, in order to ensure the safety of construction, outer row's upright bar height must be over the height of house cornice, and be arranged Twice flak jacket column foot guard plate with together with hangs safety vertical net;It, can be with when cornicing or the width of other protruding parts is more than 800mm Using any type in following two modes:
9.3.1), scaffold building height when the width that cornices is more than 800mm, increases doing for row's scaffold outside less than 15m Method
9.3.2), scaffold building height is more than 15m, when the width that cornices is more than 800mm, is cornicing or protruding parts, using type The way of steel overhanging is set up.
CN201810569285.9A 2018-06-05 2018-06-05 Console mode scaffold building construction method Withdrawn CN108708536A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810569285.9A CN108708536A (en) 2018-06-05 2018-06-05 Console mode scaffold building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810569285.9A CN108708536A (en) 2018-06-05 2018-06-05 Console mode scaffold building construction method

Publications (1)

Publication Number Publication Date
CN108708536A true CN108708536A (en) 2018-10-26

Family

ID=63870500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810569285.9A Withdrawn CN108708536A (en) 2018-06-05 2018-06-05 Console mode scaffold building construction method

Country Status (1)

Country Link
CN (1) CN108708536A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565928A (en) * 2019-07-26 2019-12-13 江苏兴厦建设工程集团有限公司 Fast-assembling, quick detach formula scaffold frame for construction of building outer wall
CN110670867A (en) * 2019-10-16 2020-01-10 陕西建工第三建设集团有限公司 Construction method of scaffold for improving outer vertical surface of existing building
CN110820942A (en) * 2019-11-14 2020-02-21 浙江勤业建工集团有限公司 Construction method for roof overlong overhanging lotus flower modeling steel structure
CN111005547A (en) * 2019-12-31 2020-04-14 广东省第一建筑工程有限公司 Construction method of external scaffold with two-way twist staggered floor vertical face
CN112144558A (en) * 2020-10-10 2020-12-29 广州市水电建设工程有限公司 Replacement type open caisson construction method suitable for soft foundation
CN112227682A (en) * 2020-09-16 2021-01-15 飞帆集团有限公司 Scaffold structure and scaffold erection process
CN113358068A (en) * 2021-04-26 2021-09-07 福建数博讯信息科技有限公司 Floor type scaffold correcting method and device
CN113914589A (en) * 2021-10-14 2022-01-11 北京益汇达清水建筑工程有限公司 Construction method of clear water sample plate wall bottom support filling frame body
CN114855828A (en) * 2021-02-03 2022-08-05 贵州建工集团第三建筑工程有限责任公司 Construction method for high slope management of hidden danger of geological features of land
CN114961197A (en) * 2022-06-15 2022-08-30 广州盈德建筑工程有限公司 Safe and reliable building outer double-row scaffold and building method thereof
CN115217318A (en) * 2022-07-06 2022-10-21 中国二十冶集团有限公司 Material lifting device for installing and detaching floor scaffold of plate buckle and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205330133U (en) * 2015-10-16 2016-06-22 河北中建工程有限公司 Overhanging scaffold
CN106437172A (en) * 2016-07-27 2017-02-22 中国能源建设集团安徽电力建设第工程有限公司 Putting-up method of scaffold for building of booster station of wind power plant
CN206091244U (en) * 2016-05-11 2017-04-12 中国建筑第八工程局有限公司 Double scaffold frame of console mode

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205330133U (en) * 2015-10-16 2016-06-22 河北中建工程有限公司 Overhanging scaffold
CN206091244U (en) * 2016-05-11 2017-04-12 中国建筑第八工程局有限公司 Double scaffold frame of console mode
CN106437172A (en) * 2016-07-27 2017-02-22 中国能源建设集团安徽电力建设第工程有限公司 Putting-up method of scaffold for building of booster station of wind power plant

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
湖北天宇建设有限公司: "曙光村还建楼B地块5#、7#楼落地式脚手架施工方案", 《HTTPS://JZ.DOCIN.COM/P-1872298421.HTML》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565928A (en) * 2019-07-26 2019-12-13 江苏兴厦建设工程集团有限公司 Fast-assembling, quick detach formula scaffold frame for construction of building outer wall
CN110670867A (en) * 2019-10-16 2020-01-10 陕西建工第三建设集团有限公司 Construction method of scaffold for improving outer vertical surface of existing building
CN110820942A (en) * 2019-11-14 2020-02-21 浙江勤业建工集团有限公司 Construction method for roof overlong overhanging lotus flower modeling steel structure
CN111005547A (en) * 2019-12-31 2020-04-14 广东省第一建筑工程有限公司 Construction method of external scaffold with two-way twist staggered floor vertical face
CN111005547B (en) * 2019-12-31 2023-10-31 广东省第一建筑工程有限公司 Construction method of outer scaffold of two-way bending and twisting staggered floor elevation
CN112227682B (en) * 2020-09-16 2022-01-25 飞帆集团有限公司 Scaffold structure and scaffold erection process
CN112227682A (en) * 2020-09-16 2021-01-15 飞帆集团有限公司 Scaffold structure and scaffold erection process
CN112144558A (en) * 2020-10-10 2020-12-29 广州市水电建设工程有限公司 Replacement type open caisson construction method suitable for soft foundation
CN114855828A (en) * 2021-02-03 2022-08-05 贵州建工集团第三建筑工程有限责任公司 Construction method for high slope management of hidden danger of geological features of land
CN114855828B (en) * 2021-02-03 2024-04-19 贵州建工集团第三建筑工程有限责任公司 Construction method for land block geological hidden danger high slope treatment
CN113358068A (en) * 2021-04-26 2021-09-07 福建数博讯信息科技有限公司 Floor type scaffold correcting method and device
CN113914589A (en) * 2021-10-14 2022-01-11 北京益汇达清水建筑工程有限公司 Construction method of clear water sample plate wall bottom support filling frame body
CN114961197A (en) * 2022-06-15 2022-08-30 广州盈德建筑工程有限公司 Safe and reliable building outer double-row scaffold and building method thereof
CN114961197B (en) * 2022-06-15 2024-03-29 广州盈德建筑工程有限公司 Safe and reliable building outer double-row scaffold and erecting method thereof
CN115217318A (en) * 2022-07-06 2022-10-21 中国二十冶集团有限公司 Material lifting device for installing and detaching floor scaffold of plate buckle and construction method

Similar Documents

Publication Publication Date Title
CN108708536A (en) Console mode scaffold building construction method
CN105019639B (en) Overhead cantilever formwork and its construction method
CN104074349B (en) A kind of new-type protection type attachment type raise scaffold
CN202324571U (en) Overhanging type double-row scaffold
CN103362297B (en) A kind of attached lift scaffold constructure scheme
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN206174437U (en) Be applied to gallows of super high overlength cantilevered member construction
CN102400470B (en) Construction method for multi-platform deep foundation of hillside high-rise building
CN106013750A (en) Disc buckle direct insertion type support frame capable of being rapidly assembled and disassembled and construction method thereof
CN110259090A (en) A kind of construction method of novel pull-up builder's jack
CN105088979B (en) Demolition blasting method for large bridge
CN105350760A (en) Edge-beam-supporting steel-rod-inclined-pulling and wire-rope-unloading overhanging scaffold construction method
CN112554208B (en) Cantilever support platform, supporting and retaining wall and construction method
CN105544562A (en) Jet anchor net protection construction process for renovating rock heaps on high and steep slope
CN103243912B (en) Multilayer is without plate framework construction method
CN201236489Y (en) Roof edge protection railing for preventing high altitude falling
CN111236603B (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
CN106013755A (en) Cantilever frame for existing building and construction method
CN111608376B (en) Comprehensive construction method for shaping component
CN202788017U (en) Horizontally-overhung rigid hermetic section steel protective shed for high-rise buildings
CN205894723U (en) Convertible curtain stereoplasm protective screen
CN106760530B (en) A kind of operating platform and its construction method for the dismounting of tower crane wall attaching rod
CN114855828B (en) Construction method for land block geological hidden danger high slope treatment
CN105781134B (en) A kind of horizontal hole protective construction and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20181026

WW01 Invention patent application withdrawn after publication