CN108708266A - A kind of anchoring process of landscape suspension bridge and its decorative cable - Google Patents
A kind of anchoring process of landscape suspension bridge and its decorative cable Download PDFInfo
- Publication number
- CN108708266A CN108708266A CN201810505268.9A CN201810505268A CN108708266A CN 108708266 A CN108708266 A CN 108708266A CN 201810505268 A CN201810505268 A CN 201810505268A CN 108708266 A CN108708266 A CN 108708266A
- Authority
- CN
- China
- Prior art keywords
- longeron
- anchorage
- towing rope
- sunpender
- main push
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/02—Suspension bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of landscape suspension bridge and its anchoring process of decorative cable, main push-towing rope is set up in by cable saddle on bridge tower, main push-towing rope end is anchored on the anchorage structures of Abutment, anchoring structure includes inside side wall above abutment cushion cap, the anchorage of cushion cap upper outer and cushion cap, and cushion cap, anchorage and side wall formed by integrally casting are completed;Sunpender upper end is fixed on design position by cord clip and main push-towing rope, and the lower end of sunpender is anchored by longitudinal and cross beam, and crossbeam is I-steel, and one end is embedded in pier cap beam, and other end welding steel is bolted with longeron main body;Longeron is made of two panels channel steel, and sunpender is fixed between two channel steels by upper padding plate, lower bolster and bolt, and longeron is cast in concrete therewith at Abutment, bridge tower.It the invention avoids sunpender to be fixed on side bar flange plate, reduces to structure detrimental effect, and there is certain landscape and economic sexual clorminance, operation maintenance is simple, is used convenient for people.
Description
Technical field
The invention belongs to science of bridge building fields, and in particular to the anchoring side of a kind of landscape suspension bridge and its decorative cable
Method.
Background technology
Since ancient times, significant Landscape Architecture just occupies spatial position outstanding, will be easier to be identified, be taken as weight
The things wanted.With the development of the social economy, the spiritual enjoyment level demand of people is higher and higher, Urban Landscape Bridge can give people
Bring visual experience.The decorative suspension cable of landscape suspension bridge is simultaneously not involved in main body bridge structure stress, in work progress
Usually first construction bridges agent structure, bridge tower of then constructing, main push-towing rope are erected at by the cable saddle on bridge tower on bridge tower, main push-towing rope
End is anchored on anchorage, finally carries out the construction of sunpender.
In some built at present landscape suspension bridges, sunpender is fixed on the edge of a wing Board position of side bar, sunpender fixation side
Formula may have an adverse effect to beam body by influences such as various loads such as wind load, carload, reduce bridge security
Quality;And built Bridge anchorage structure is huger, and the structure gravity of abutment itself is not utilized to go to offset the drawing of main push-towing rope
Power causes the problems such as construction is complicated, quantities is big, of high cost.
Invention content
For problems of the prior art, the present invention provides the anchoring of a kind of landscape suspension bridge and its decorative cable
Method resists the pulling force of main push-towing rope using abutment self structure gravity, while the fixed form of sunpender will not generate not beam body
Profit influences, to make suspended-cable structure only play decoration function.
In order to solve the above technical problems, the present invention provides the following technical solutions:
A kind of landscape suspension bridge, including bridge tower, the main push-towing rope 1 being set up on bridge tower, bent cap 4, the master being set up on bent cap 4
Beam, anchorage system 3 and sunpender 9;The longeron 2 parallel with girder longitudinal central axis line is arranged in 1 lower section of main push-towing rope, and passes through more sunpenders 9
It is connect with longeron 2;5 vertical connection of crossbeam longeron 2 middle part and extend horizontally away from 4 tail end of bent cap, longeron 2 pass through the portion of bridge tower
Divide and be embedded in bridge tower, 2 both ends of longeron and anchorage system 3 are poured and integrally connect afterwards with 1 both ends of main push-towing rope;The anchorage system
3 include abutment cushion cap 15, positioned at the anchorage block 18 of 15 upper outer of abutment cushion cap and positioned at abutment cushion cap 15 above on the inside of bridge
Platform side wall 14.
Longeron 2 include two open ends backwards to and the channel steel that is mutually parallel, sunpender 9 pass through positioned at 2 left and right sides of longeron
Steel plate 11 and bolt 8 are fixed between two channel steels, and pass through the upper padding plate 6, lower bolster 7 and nut positioned at 2 upper and lower of longeron
10 fixed derrick, 9 lower end;5 one end of crossbeam and 11 vertical welding of steel plate, the other end are passed perpendicularly through through reinforcing bar 1, run through steel
Muscle 1 is poured by pre-buried in bent cap 4.
The bolt 8 passes perpendicularly through 9 axis of sunpender.
The tail end of longeron 2 is passed through through reinforcing bar 2 13, is poured in anchorage system 3 by pre-buried through reinforcing bar 2 13.
The crossbeam 5 is made of multigroup I-steel.
The anchorage block 18 includes anchorage block body, anchorage 16, bellows 17 and is located at anchorage block body internal reservation
Through hole 19, the anchorage 16 is used to be secured across the main push-towing rope 1 of through hole 19 and bellows 17, and the bellows 17 is used
In package main push-towing rope 1.
9 upper end of sunpender is fixed on by cord clip on main push-towing rope 1.
A method of decorative suspended-cable structure is installed on above-mentioned landscape suspension bridge, is included the following steps:
S1:It pours 5 one end of crossbeam is pre-buried in bent cap 4, it is another that the side channel steel of longeron 2 is then welded on crossbeam 5
End installs the other side channel steel of longeron 2, sunpender 9 is stuck between two channel steels;
S2:Construct bridge tower and anchorage structures, longeron 2 be partially embedded in by bridge tower in bridge tower, by longeron 2 both ends with
Anchorage system 3 pours integrally;
S3:Main push-towing rope 1 is erected on bridge tower, in place, 1 both ends of main push-towing rope are anchored on anchorage system 3 for tensioning main push-towing rope 1;
S4:It is symmetrically installed sunpender 9, and 9 lower end of fixed derrick from bridge tower toward both ends.
Technical scheme of the present invention has the following advantages and technique effect:
(1) in the present invention, sunpender need not be fixed on the flange plate of girder, be brought to agent structure to reduce
Adverse effect;
(2) present invention reduces the structure sizes of main push-towing rope anchorage, and abutment its own gravity is made full use of to resist produced by main push-towing rope
Pulling force;
(3) the invention enables light structures, and construction is convenient, at low cost, have certain landscape dominance.
Description of the drawings
Fig. 1 is the general arrangement of landscape suspension bridge of the present invention.
Fig. 2 is the connection diagram of sunpender 9, longeron 2, crossbeam 5, bent cap 4.
Fig. 3 is the connection diagram of longeron 2 and anchorage system 3.
Fig. 4 is the elevation of anchorage system 3.
Fig. 5 is the side view of anchorage system 3.
Wherein, 1-main push-towing rope, 2-longerons, 3-anchorage systems, 4-bent caps, 5-crossbeams, 6-upper padding plates, 7-lower bolsters,
8-bolts, 9-sunpenders, 10-nuts, 11-steel plates, 12-run through reinforcing bar one, 13-run through reinforcing bar two, 14-abutment sidewalls,
15-abutment cushion caps, 16-anchorages, 17-bellowss, 18-anchorage blocks, 19-through holes.
Specific implementation mode
Technical scheme of the present invention is described in further detail below in conjunction with the accompanying drawings.
As shown in fig. 1~fig. 5, a kind of landscape suspension bridge, including bridge tower, the main push-towing rope 1 being set up on bridge tower, bent cap 4, erection
In girder, anchorage system 3 and sunpender 9 on bent cap 4;The longeron 2 parallel with girder longitudinal central axis line is arranged in 1 lower section of main push-towing rope, and
It is connect with longeron 2 by more sunpenders 9;2 middle part of longeron and 5 vertical connection of crossbeam being extend horizontally away from 4 tail end of bent cap, longeron
2 being partially embedded in bridge tower by bridge tower, 2 both ends of longeron and anchorage system 3 are connect after pouring integrally with 1 both ends of main push-towing rope;
The anchorage system 3 includes abutment cushion cap 15, positioned at the anchorage block 18 of 15 upper outer of abutment cushion cap and positioned at abutment cushion cap
The abutment sidewall 14 of 15 tops inside.
Longeron 2 include two open ends backwards to and the channel steel that is mutually parallel, sunpender 9 pass through positioned at 2 left and right sides of longeron
Steel plate 11 and bolt 8 are fixed between two channel steels, and pass through the upper padding plate 6, lower bolster 7 and nut positioned at 2 upper and lower of longeron
10 fixed derrick, 9 lower end;5 one end of crossbeam and 11 vertical welding of steel plate, the other end are passed perpendicularly through through reinforcing bar 1, run through steel
Muscle 1 is poured by pre-buried in bent cap 4.
The bolt 8 passes perpendicularly through 9 axis of sunpender.
The tail end of longeron 2 is passed through through reinforcing bar 2 13, is poured in anchorage system 3 by pre-buried through reinforcing bar 2 13.
The crossbeam 5 is made of multigroup I-steel.
The anchorage block 18 includes anchorage block body, anchorage 16, bellows 17 and is located at anchorage block body internal reservation
Through hole 19, the anchorage 16 is used to be secured across the main push-towing rope 1 of through hole 19 and bellows 17, and the bellows 17 is used
In package main push-towing rope 1.
9 upper end of sunpender is fixed on by cord clip on main push-towing rope 1.
A method of decorative suspended-cable structure is installed on above-mentioned landscape suspension bridge, is included the following steps:
S1:It pours 5 one end of crossbeam is pre-buried in bent cap 4, it is another that the side channel steel of longeron 2 is then welded on crossbeam 5
End installs the other side channel steel of longeron 2, sunpender 9 is stuck between two channel steels;
S2:Construct bridge tower and anchorage structures, longeron 2 be partially embedded in by bridge tower in bridge tower, by longeron 2 both ends with
Anchorage system 3 pours integrally;
S3:Main push-towing rope 1 is erected on bridge tower, in place, 1 both ends of main push-towing rope are anchored on anchorage system 3 for tensioning main push-towing rope 1;
S4:It is symmetrically installed sunpender 9, and 9 lower end of fixed derrick from bridge tower toward both ends.
Anchorage system 3 and abutment sidewall 14, the steel bar overall binding in construction work of abutment cushion cap 15, one-piece casting coagulation
The bellows 17 of earth forming, package main push-towing rope 1 passes through through hole 19,1 end of main push-towing rope to anchor and fix by anchorage 16, final main push-towing rope
1 pulling force is undertaken by 3 its own gravity of anchorage system.
Since the suspended-cable structure of the present invention belongs to main bridge decorative parts, be not involved in the main stress of main bridge, suspended-cable structure with
The separation of main bridge is individually designed, and for 9 anchoring lower ends of sunpender on longeron 2, longeron 2 is partially embedded in bridge tower, anchor by bridge tower, abutment
In ingot structure, crossbeam 5, which is supported in, to be embedded on 4 beam-ends of bent cap.It need to be accurately controlled in bridge tower, abutment, pier cap beam construction vertical
The embedding absolute altitude of beam 2, crossbeam 5,2 upper hanger 9 of longeron reserve hole site and also answer setting-out accurate.It is needed in the production process in main push-towing rope
Accurate marker is carried out on 1, then calculates the absolute altitude at each control point, and jack can be used in anchorage zone tensioning in the adjustment of main push-towing rope 1.
The vertical distribution for first adjusting main span span centre cable is completed to fix at cable saddle.The label on main push-towing rope 1 be should refer to when adjustment to ensure rope
Adjusting range.Main span adjust after, end bay according to design provide Suo Li by 1 tensioning of main push-towing rope in place.Sunpender is in installing Cable-clamp
It installs immediately after the completion.Small-sized sunpender is using manually installed, and large-scale sunpender is using crane cooperation installation.9 in-site installation of sunpender needs
Want tensioning.The installation and tensioning of sunpender 9 carry out successively from bridge tower toward both sides, and both sides bridge tower hanger erection tensioning needs symmetrical equilibrium to apply
Work ensures 9 apparent perpendicular shape of sunpender and main cable alignment.First time tensioning applies 1/4 design power by each sunpender 9
Temporary locking, second of sequence is identical as first time, complete by design power tensioning, then detects the actual loading of each sunpender 9,
Finally specifically each sunpender 9 is finely adjusted according to design power.For two sunpenders 9 close to 1 anchor point of main push-towing rope, due to hanging
Pole length is shorter, using push-and-pull rod.The theoretical anchor point of anchorage block 18 answers setting-out accurate, and absolute altitude must accurately control.It waits mixing
Solidifying soil intensity reaches 100%, can install main push-towing rope.It is pre-buried accurate that anchorage 16 etc. at 1 anchoring of main push-towing rope is answered, and ensures in stretching process
Cable is always positioned at the center of reserved bellows 17, and with bar-mat reinforcement spot welding around.
Sunpender 9 is fixed on longeron 2 and crossbeam 5 by anchoring process through the invention, rather than sunpender 9 is directly fixed
In on beam body flange plate, to reduce the adverse effect to beam body, abutment cushion cap 15, anchorage block 18 and abutment sidewall 14 are designed
It is structure as a whole, 1 pulling force of main push-towing rope is passed to by entire anchor system 3 by anchorage block 18, anchor system 3 again passes entire load
It is handed to abutment sidewall 14 and abutment cushion cap 15, abutment sidewall 14 and abutment cushion cap 15 provide sufficiently large resistance to balance main push-towing rope
1 huge pulling force prevents bridge tower from tilting and even collapses, to play the anchorage effect of balance 1 pulling force of main push-towing rope, makes full use of and finish
Its own gravity of structure avoids construction large volume anchorage structures from improving the stability and durability of structure to save cost.
Claims (8)
1. a kind of landscape suspension bridge, including bridge tower, the main push-towing rope (1) being set up on bridge tower, bent cap (4), it is set up on bent cap (4)
Girder, anchorage system (3) and sunpender (9);It is characterized in that:Parallel with girder longitudinal central axis line indulge is set below main push-towing rope (1)
Beam (2), and connect with longeron (2) by more sunpenders (9);The cross extending horizontally away in the middle part of longeron (2) and from bent cap (4) tail end
Beam (5) vertical connection, longeron (2) are partially embedded in by bridge tower in bridge tower, and longeron (2) both ends and anchorage system (3) pour
It is connect with main push-towing rope (1) both ends after integral;The anchorage system (3) includes abutment cushion cap (15), is located at abutment cushion cap (15)
The anchorage block (18) of upper outer and the abutment sidewall (14) on the inside of abutment cushion cap (15) top.
2. landscape suspension bridge according to claim 1, it is characterised in that:Longeron (2) include two open ends backwards to and phase
Mutually parallel channel steel, sunpender (9) are fixed on two channel steels by being located at steel plate (11) at left and right sides of longeron (2) and bolt (8)
Between, and upper padding plate (6), lower bolster (7) and nut (10) fixed derrick (9) lower end by being located at longeron (2) upper and lower;It is horizontal
Beam (5) one end and steel plate (11) vertical welding, the other end are passed perpendicularly through through reinforcing bar one (12), pre- through reinforcing bar one (12)
It buries and pours in bent cap (4).
3. landscape suspension bridge according to claim 2, it is characterised in that:The bolt (8) passes perpendicularly through sunpender (9) axis
Line.
4. landscape suspension bridge according to claim 1, it is characterised in that:The tail end of longeron (2) is by through reinforcing bar two (13)
It passes through, is poured in anchorage system (3) by pre-buried through reinforcing bar two (13).
5. landscape suspension bridge according to claim 1, it is characterised in that:The crossbeam (5) is made of multigroup I-steel.
6. landscape suspension bridge according to claim 1, it is characterised in that:The anchorage block (18) includes anchorage block sheet
Body, anchorage (16) and the through hole (19) positioned at anchorage block body internal reservation, bellows (17) are placed in through hole (19)
In, the main push-towing rope (1) of through hole (19) and bellows (17) that the anchorage (16) is used to be secured across, the bellows (17)
For wrapping up main push-towing rope (1).
7. landscape suspension bridge according to claim 1, it is characterised in that:Sunpender (9) upper end is fixed on main push-towing rope by cord clip
(1) on.
8. a kind of method for installing decorative suspended-cable structure on landscape suspension bridge described in claim 1, which is characterized in that packet
Include following steps:
S1:It pours crossbeam (5) one end is pre-buried in the bent cap (4), the side channel steel of longeron (2) is then welded on crossbeam (5)
The other end, the other side channel steel of installation longeron (2), sunpender (9) is stuck between two channel steels;
S2:Construct bridge tower and anchorage structures, longeron (2) be partially embedded in by bridge tower in bridge tower, by longeron (2) both ends with
Anchorage system (3) pours integrally;
S3:Main push-towing rope (1) is erected on bridge tower, tensioning main push-towing rope (1) is anchored at anchorage system (3) in place, by main push-towing rope (1) both ends
On;
S4:It is symmetrically installed sunpender (9), and fixed derrick (9) lower end from bridge tower toward both ends.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810505268.9A CN108708266B (en) | 2018-05-24 | 2018-05-24 | A kind of anchoring process of landscape suspension bridge and its decorative cable |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810505268.9A CN108708266B (en) | 2018-05-24 | 2018-05-24 | A kind of anchoring process of landscape suspension bridge and its decorative cable |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108708266A true CN108708266A (en) | 2018-10-26 |
CN108708266B CN108708266B (en) | 2019-09-17 |
Family
ID=63869516
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810505268.9A Active CN108708266B (en) | 2018-05-24 | 2018-05-24 | A kind of anchoring process of landscape suspension bridge and its decorative cable |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108708266B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201386252Y (en) * | 2009-02-19 | 2010-01-20 | 西南交通大学 | Temporary connecting device of girder section bottom plates of steel box girders of suspension bridge |
CN202744951U (en) * | 2012-06-28 | 2013-02-20 | 中铁十三局集团第一工程有限公司 | Light anchorage structure |
CN104233962A (en) * | 2014-08-11 | 2014-12-24 | 王双其 | Method for reinforcing and strengthening main cable of suspension bridge |
KR101664989B1 (en) * | 2016-05-17 | 2016-10-11 | (주)신흥이앤지 | Structure for suspension bridge without constructing anchor block |
CN106884371A (en) * | 2017-04-25 | 2017-06-23 | 安徽省交通控股集团有限公司 | A kind of non-uniform beam and suspension cable combined bridge structural system |
-
2018
- 2018-05-24 CN CN201810505268.9A patent/CN108708266B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201386252Y (en) * | 2009-02-19 | 2010-01-20 | 西南交通大学 | Temporary connecting device of girder section bottom plates of steel box girders of suspension bridge |
CN202744951U (en) * | 2012-06-28 | 2013-02-20 | 中铁十三局集团第一工程有限公司 | Light anchorage structure |
CN104233962A (en) * | 2014-08-11 | 2014-12-24 | 王双其 | Method for reinforcing and strengthening main cable of suspension bridge |
KR101664989B1 (en) * | 2016-05-17 | 2016-10-11 | (주)신흥이앤지 | Structure for suspension bridge without constructing anchor block |
CN106884371A (en) * | 2017-04-25 | 2017-06-23 | 安徽省交通控股集团有限公司 | A kind of non-uniform beam and suspension cable combined bridge structural system |
Also Published As
Publication number | Publication date |
---|---|
CN108708266B (en) | 2019-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106120568B (en) | The construction method of cross a river Main Bridge bridge pier secondary locking temporary consolidation structure | |
JP3177157U (en) | A simple tower instrument in a high-rise bridge. | |
CN101117795A (en) | Mounting method for steel case basket arch single-frame segment | |
CN105568870B (en) | For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction | |
CN106012851B (en) | Steel box-girder and performance of concrete column confined method for synchronously constructing | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN102277836B (en) | Construction method of tilting concrete tower base | |
CN109440634A (en) | The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off | |
CN110644371A (en) | Prefabricated capping beam installation method and system | |
CN102134832A (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
CN205242278U (en) | A triangle string basket method is hanged and is watered device for deck bridge construction | |
CN103835238B (en) | A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing | |
CN211472207U (en) | Suspension beam system for hoisting prefabricated section box girder | |
CN108708266B (en) | A kind of anchoring process of landscape suspension bridge and its decorative cable | |
CN215482366U (en) | Double-line continuous beam bracket structure | |
CN208328660U (en) | The U-shaped girder construction of the Two bors d's oeuveres of combined bridge | |
CN215593730U (en) | Hanging basket for parasitic support with beam plate on wide body of cable-stayed bridge with cantilever pouring double-side box | |
CN110424243A (en) | A kind of Long span Tied-Arch Bridge Main Bridge jack-up system and jack-up construction method | |
CN214328478U (en) | Three-tower self-anchored suspension bridge | |
CN109778717A (en) | A kind of passive method of adjustment of the mechanical state of cantilever beam | |
CN211772868U (en) | Pier temporary consolidation device in large-span continuous beam | |
CN107142830A (en) | Steel pipe web prestressing force steel reinforced concrete combines main beam structure and construction method | |
CN209619836U (en) | The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off | |
CN108332983B (en) | Antiknock test pedestal of cable-stayed bridge | |
CN111172863A (en) | Bridge pier column reinforcing bar location placenta |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |