CN108691556A - A kind of shield synchronization slip casting and secondary grouting technique - Google Patents

A kind of shield synchronization slip casting and secondary grouting technique Download PDF

Info

Publication number
CN108691556A
CN108691556A CN201710216241.3A CN201710216241A CN108691556A CN 108691556 A CN108691556 A CN 108691556A CN 201710216241 A CN201710216241 A CN 201710216241A CN 108691556 A CN108691556 A CN 108691556A
Authority
CN
China
Prior art keywords
grouting
shield
stratum
slurries
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710216241.3A
Other languages
Chinese (zh)
Other versions
CN108691556B (en
Inventor
赵余夫
翁厚洋
傅珺
许文明
沈杰
翟羽佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongrun Construction Group Co Ltd
Original Assignee
Hongrun Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongrun Construction Group Co Ltd filed Critical Hongrun Construction Group Co Ltd
Priority to CN201710216241.3A priority Critical patent/CN108691556B/en
Publication of CN108691556A publication Critical patent/CN108691556A/en
Application granted granted Critical
Publication of CN108691556B publication Critical patent/CN108691556B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Abstract

A kind of shield synchronization slip casting of present invention offer and secondary grouting technique, include the following steps:(1) slurries are configured according to stratum monitoring data automatic blending system, (2) slurries configured are delivered to the slurry storage tank of shield machine, (3) slurries in the slurry storage tank are delivered to grouting at the tail of the shield machine pipe, (4) shield tail structure void synchronous grouting is carried out according to dynamic stratum monitoring data, (5) secondary grouting is carried out according to dynamic stratum monitoring data, surface grout injection measure can be taken when necessary, shield duct piece arrangement of reinforcement is suitably reinforced, and add reserved injected hole, to supplement slip casting according to dynamic monitoring situation in the construction process, the beneficial effects of the invention are as follows this section tunnel soil body whole process to be reinforced using tracking two fluid grouting, synchronous grouting is combined with secondary grouting according to dynamic stratum monitoring data, the needs of Different Strata situation can not only be met, and ground deformation amount and section of jurisdiction offset are small, it is safe.

Description

A kind of shield synchronization slip casting and secondary grouting technique
Technical field
The present invention relates to a kind of shield synchronization slip casting and secondary grouting techniques, belong to constructing tunnel field.
Background technology
The type of grouting at the tail of the shield machine is divided into subsequent slip casting, synchronous grouting, timely slip casting and secondary grouting.Wherein, synchronous grouting It is to work as shield driving, after shield tail is detached from section of jurisdiction, the gap backbreak occurs in the section of jurisdiction back side, to avoid making in Shield Construction Method Used At stratum deformation, destruction is caused to influence neighbouring structure, and after shield tail disengaging, fill concreteness slurries at the section of jurisdiction back side A kind of form of construction work.When the control of surface subsidence and tunnel upward floating are required it is relatively stringent in the case of generally noted using synchronous Slurry, and coordinate secondary grouting as supplement measure.
Synchronous grouting comes with some shortcomings in construction at present:Early strength is low, is easy to isolate, ground deformation amount and section of jurisdiction Offset is big, grouting quality stability difference etc..
Invention content
The object of the present invention is to provide a kind of shield synchronization slip casting and secondary grouting techniques, and intensity is high, is not easy to isolate, ground Facial disfigurement amount and section of jurisdiction offset are small, and grouting quality is good, safe.
In order to achieve the above object, the control method that the present invention uses includes the following steps:(1) automatic according to stratum monitoring data Stirring system configures slurries, and the slurries configured are delivered to the slurry storage tank of shield machine by (2), in (3) described slurry storage tank Slurries are delivered to grouting at the tail of the shield machine pipe, and (4) carry out shield tail structure void synchronous grouting, (5) basis according to dynamic stratum monitoring data Dynamic stratum monitoring data carry out secondary grouting.
Preferably, in the step (1), feedback data is monitored according to stratum, the grout coordinate ratio is adjusted, with The slurries for adapting to stratum condition are obtained, the wherein material of slurries used by synchronous grouting mainly has flyash, sand and water etc..Root According to stratum monitoring data, the proportioning of the slurry material is adjusted in due course, using optimal slurries are matched, increases the cohesive strength on stratum And internal friction angle, to improve stratum adhesion strength and compactness, to have the function that reinforcing.
Preferably, in the step (3), it is both provided with pressure sensor on the grouting at the tail of the shield machine pipe, convenient for prison in real time Grouting pressure is surveyed, slip casting process is preferably controlled in conjunction with grouting pressure and stratum monitoring data, can be made if grouting pressure is excessive It is damaged at the running pulp even shield duct piece, if grouting pressure deficiency it will cause grouting amounts few, structure void insufficient fill, from And ground deformation and the shield duct piece is caused to deviate.
Preferably, grouting amount is the 130%~180% of theoretical structure void, and extra large Rake earth pressure balanced shield, EPBS is per ring slip casting Amount is about 5.46~7.56m3, and Kawasaki earth pressure balanced shield, EPBS is about 5.59~7.74m3 per ring grouting amount, and grouting pressure is balance 1.5 times of soil pressure, specific mud jacking amount and mud jacking point optimize, slurries depending on pressure value and stratum deformation monitoring data when mud jacking Consistency is generally 9~12.
Preferably, the shield duct piece arrangement of reinforcement is suitably reinforced, and adds reserved injected hole, so as to root in the construction process Slip casting is supplemented according to dynamic monitoring situation, pressure injection dual slurry forms hoop around tunnel every 5~8 rings when necessary, keeps tunnel vertical To the intermittent sealing isolation strip of formation.
Preferably, in the step (4), due to the static lateral pressure coefficient and tunnel top buried depth of grouting pressure and stratum Linear correlation, grouting amount is also related to the infiltration coefficient on stratum, so, during shield crossing construction of railways, it is necessary in conjunction with dynamic State stratum monitoring data data carry out control slip casting, and injection phase of the fltting speed of shield machine, slurries etc. can also influence Grouting quality will be accomplished timely, uniform, enough, it is ensured that its structure void is able to timely and enough in entire work progress Ground deformation and section of jurisdiction offset control are arrived minimum by filling.
The beneficial effects of the invention are as follows:It is reinforced using tracking two fluid grouting, intensity is high, is not easy to isolate, according to dynamic stratum Synchronous grouting is combined by monitoring data with secondary grouting, can not only meet the needs of Different Strata situation, but also ground becomes Shape amount and section of jurisdiction offset are small, and grouting quality is good, safe.
Description of the drawings
Fig. 1 is the implementation steps figure of the present invention.
Specific implementation mode
Below against attached drawing, by the description of the embodiment, to the specific implementation mode of the present invention, such as involved each structure The works such as mutual alignment and connection relation, the effect of each section and operation principle between the shape of part, construction, each section are further Detailed description.
Referring to Fig. 1, a kind of shield synchronization slip casting of present invention offer and secondary grouting technique comprising following steps:(1) root Slurries are configured according to stratum monitoring data automatic blending system, the slurries configured are delivered to the slurry storage tank of shield machine by (2), (3) Slurries in slurry storage tank are delivered to grouting at the tail of the shield machine pipe, (4) carry out shield tail structure void synchronization according to dynamic stratum monitoring data Slip casting, (5) carry out secondary grouting according to dynamic stratum monitoring data.
Preferably, in step (1), feedback data is monitored according to stratum, adopts an effective measure controlled in time, to slurries Proportioning is adjusted, and to obtain the optimal slurries for adapting to stratum condition, the material for the slurries that synchronous grouting uses mainly has fine coal Ash, sand and water etc..Each ground local product manages mechanical index such as the following table 1, the slurry material proportioning such as the following table 2 of synchronous grouting along the line (1m3)。
Each ground local product manages mechanical index along table 1
2 slurry material of table matches
Material Sand Flyash Bentonite Cement Additive Water
Weight 800kg 380kg 80kg 80kg 3.0kg 380kg
According to stratum monitoring data, the proportioning of slurry material is adjusted in due course, using optimal slurries are matched, increases stratum Cohesive strength and internal friction angle, to improve stratum adhesion strength and compactness, to have the function that reinforcing.
In step (3), it is both provided with pressure sensor on grouting at the tail of the shield machine pipe, convenient for monitoring grouting pressure in real time, in conjunction with Grouting pressure and stratum monitoring data preferably control slip casting process, if grouting pressure is excessive, it will cause running pulp even shield pipes Piece is damaged, if grouting pressure deficiency it will cause grouting amounts few, structure void insufficient fill, so as to cause ground deformation and shield Section of jurisdiction deviates.
Grouting amount is the 130%~180% of theoretical structure void, and extra large Rake earth pressure balanced shield, EPBS is about per ring grouting amount 5.46~7.56m3, Kawasaki earth pressure balanced shield, EPBS are about 5.59~7.74m3 per ring grouting amount, and grouting pressure is balancing earth pressure power 1.5 times, specific mud jacking amount and mud jacking point optimize, slurry consistency one depending on pressure value and stratum deformation monitoring data when mud jacking As be 9~12.
Shield duct piece arrangement of reinforcement is suitably reinforced, and adds reserved injected hole, so as in the construction process according to dynamic monitoring Situation supplements slip casting, and every 5~8 rings, pressure injection dual slurry forms hoop around tunnel when necessary, and tunnel is made to be longitudinally formed interruption Sealing isolation strip.
This section tunnel soil body whole process is reinforced using tracking two fluid grouting.
Surface grout injection measure is taken when necessary in this section tunnel.
In step (4), since grouting pressure and the static lateral pressure coefficient and tunnel top buried depth on stratum are linearly related, note Slurry amount is also related to the infiltration coefficient on stratum, so, during shield crossing construction of railways, it is necessary to monitor number in conjunction with dynamic stratum According to data, control slip casting is carried out, and injection phase of the fltting speed of shield machine, slurries etc. can also influence grouting quality, To accomplish in entire work progress timely, uniform, enough, it is ensured that its structure void is able to timely and enough filling, by ground Minimum is arrived in deformation and section of jurisdiction offset control.
The present invention implementation process be:First according to stratum monitoring data, automatic blending system configures optimal slurries, so The slurries configured are delivered to by slurry feeding pump the slurry storage tank of shield machine afterwards, are further delivered to grouting at the tail of the shield machine pipe, The pressure value of detection is transmitted to control system, system combination dynamic stratum monitoring data by the pressure sensor in Grouting Pipe in real time Shield tail structure void synchronous grouting is carried out, feedback data is monitored according to earth's surface, adopts an effective measure controlled in time, to slurries Proportioning is adjusted, and assigns special messenger to be responsible in construction, detailed record, and base area are carried out to pushed position, intrusion, pressure value Layer deformation monitor information adjusts in time, it is ensured that the construction quality of mud jacking process, synchronous grouting are monitored further according to dynamic stratum later Data carry out secondary grouting, when secondary grouting, are made detailed records to pushed position, intrusion, pressure value, and become according to stratum Shape monitoring information adjusts in time, it is ensured that the construction quality of mud jacking process.According to the deformation monitoring situation in construction, adjustment at any time is noted Slurry amount and grouting parameter, secondary grouting adjust at any time according to ground monitoring situation, to make stratum deformation amount minimize, until Until ground deformation is stablized, to ensure the safety of railroad track.
The beneficial effects of the invention are as follows:It is reinforced using tracking two fluid grouting, intensity is high, is not easy to isolate, according to dynamic stratum Synchronous grouting is combined by monitoring data with secondary grouting, can not only meet the needs of Different Strata situation, but also ground becomes Shape amount and section of jurisdiction offset are small, and grouting quality is good, safe.
The embodiments of the present invention have been described in detail above, but content is only presently preferred embodiments of the present invention, cannot It is believed to be used to limit the scope of the invention.Any changes and modifications in accordance with the scope of the present application, should all Still fall within the scope of the patent of the present invention.

Claims (5)

1. a kind of shield synchronization slip casting and secondary grouting technique, include the following steps:
(1) slurries are configured according to stratum monitoring data automatic blending system;
(2) slurries configured are delivered to the slurry storage tank of shield machine;
(3) slurries in the slurry storage tank are delivered to grouting at the tail of the shield machine pipe;
(4) shield tail structure void synchronous grouting is carried out according to dynamic stratum monitoring data;And
(5) secondary grouting is carried out according to dynamic stratum monitoring data.
2. shield synchronization slip casting according to claim 1 and secondary grouting technique, it is characterised in that:In the step (1) In, feedback data is monitored according to stratum, the grout coordinate ratio is adjusted, to obtain the slurries for adapting to stratum condition, wherein The material of slurries used by synchronous grouting includes flyash, Sha Heshui.
3. shield synchronization slip casting according to claim 1 and secondary grouting technique, it is characterised in that:In the step (3) In, it is provided with pressure sensor on the grouting at the tail of the shield machine pipe.
4. shield synchronization slip casting according to claim 1 and secondary grouting technique, it is characterised in that:Grouting amount is built for theory The 130%~180% of gap is built, the every ring grouting amount of extra large Rake earth pressure balanced shield, EPBS is about 5.46~7.56m3, and Kawasaki soil pressure is flat Weighing apparatus shield is about 5.59~7.74m3 per ring grouting amount, and grouting pressure is 1.5 times of balancing earth pressure power, specific mud jacking amount and mud jacking Point optimizes depending on pressure value and stratum deformation monitoring data when mud jacking, and slurry consistency is 9~12.
5. shield synchronization slip casting according to claim 1 and secondary grouting technique, it is characterised in that:By shield duct piece arrangement of reinforcement Reinforce, and add reserved injected hole, to supplement slip casting according to dynamic monitoring situation in the construction process, and exists every 5~8 rings Pressure injection dual slurry forms hoop around tunnel, and tunnel is made to be longitudinally formed intermittent sealing isolation strip.
CN201710216241.3A 2017-04-05 2017-04-05 Shield synchronous grouting and secondary grouting process Active CN108691556B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710216241.3A CN108691556B (en) 2017-04-05 2017-04-05 Shield synchronous grouting and secondary grouting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710216241.3A CN108691556B (en) 2017-04-05 2017-04-05 Shield synchronous grouting and secondary grouting process

Publications (2)

Publication Number Publication Date
CN108691556A true CN108691556A (en) 2018-10-23
CN108691556B CN108691556B (en) 2020-11-03

Family

ID=63842553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710216241.3A Active CN108691556B (en) 2017-04-05 2017-04-05 Shield synchronous grouting and secondary grouting process

Country Status (1)

Country Link
CN (1) CN108691556B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110159307A (en) * 2019-05-16 2019-08-23 北京市政建设集团有限责任公司 A kind of tunnel multilayer grouting process
CN110454194A (en) * 2019-08-06 2019-11-15 中广核工程有限公司 Shield-tunneling construction secondary grouting method
CN111779494A (en) * 2020-07-29 2020-10-16 中建八局轨道交通建设有限公司 Grouting method for controlling upward floating of duct piece in shield construction
CN112901178A (en) * 2021-01-18 2021-06-04 中铁上海工程局集团第五工程有限公司 Thixotropic slurry anti-drag grouting system and grouting method for medium-long distance oversized-diameter jacking pipe
CN114961790A (en) * 2022-05-27 2022-08-30 中南大学 Shield synchronous grouting construction method and construction effect evaluation method thereof
CN115030733A (en) * 2022-06-17 2022-09-09 中建三局第三建设工程有限责任公司 Grouting method for preventing stratum soil loss or ground surface settlement

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174439A (en) * 2013-04-11 2013-06-26 上海隧道工程股份有限公司 Construction method for shield tunnel slow condensing type synchronous grouting
CN203960850U (en) * 2013-11-18 2014-11-26 北京建工土木工程有限公司 A kind of rich pigment fine sand stratum mobilism filling system
CN104847364A (en) * 2015-05-18 2015-08-19 中建交通建设集团有限公司 Construction method of shield and continuous cutting pile foundation for penetrating through residential building group
CN105257276A (en) * 2015-11-18 2016-01-20 中国华冶科工集团有限公司 Grouting monitoring system and monitoring method thereof
CN106121662A (en) * 2016-05-06 2016-11-16 同济大学 Backbreak region synchronous grouting dynamic compensation of shield digging local fills control method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174439A (en) * 2013-04-11 2013-06-26 上海隧道工程股份有限公司 Construction method for shield tunnel slow condensing type synchronous grouting
CN203960850U (en) * 2013-11-18 2014-11-26 北京建工土木工程有限公司 A kind of rich pigment fine sand stratum mobilism filling system
CN104847364A (en) * 2015-05-18 2015-08-19 中建交通建设集团有限公司 Construction method of shield and continuous cutting pile foundation for penetrating through residential building group
CN105257276A (en) * 2015-11-18 2016-01-20 中国华冶科工集团有限公司 Grouting monitoring system and monitoring method thereof
CN106121662A (en) * 2016-05-06 2016-11-16 同济大学 Backbreak region synchronous grouting dynamic compensation of shield digging local fills control method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110159307A (en) * 2019-05-16 2019-08-23 北京市政建设集团有限责任公司 A kind of tunnel multilayer grouting process
CN110454194A (en) * 2019-08-06 2019-11-15 中广核工程有限公司 Shield-tunneling construction secondary grouting method
CN111779494A (en) * 2020-07-29 2020-10-16 中建八局轨道交通建设有限公司 Grouting method for controlling upward floating of duct piece in shield construction
CN111779494B (en) * 2020-07-29 2022-07-12 中建八局轨道交通建设有限公司 Grouting method for controlling upward floating of duct piece in shield construction
CN112901178A (en) * 2021-01-18 2021-06-04 中铁上海工程局集团第五工程有限公司 Thixotropic slurry anti-drag grouting system and grouting method for medium-long distance oversized-diameter jacking pipe
CN112901178B (en) * 2021-01-18 2023-03-24 中铁上海工程局集团第五工程有限公司 Thixotropic slurry anti-drag grouting system and grouting method for medium-long distance oversized-diameter jacking pipe
CN114961790A (en) * 2022-05-27 2022-08-30 中南大学 Shield synchronous grouting construction method and construction effect evaluation method thereof
CN115030733A (en) * 2022-06-17 2022-09-09 中建三局第三建设工程有限责任公司 Grouting method for preventing stratum soil loss or ground surface settlement

Also Published As

Publication number Publication date
CN108691556B (en) 2020-11-03

Similar Documents

Publication Publication Date Title
CN108691556A (en) A kind of shield synchronization slip casting and secondary grouting technique
CN111396063B (en) Construction method for short-distance upward-crossing existing line downward-passing sewage jacking pipe of water-rich sand layer shield
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN104088647B (en) Shield tube push bench with super-large rectangular cross section
CN105804761B (en) Construction method suitable for liquefied sand stratum shield near-distance passing through building
CN102758635B (en) Construction method for tool changing under pressure in shield of water-rich silty soil and silty sand stratum under station tracks of railways
CN102080548B (en) Construction method of tunnel to cross airport runway by shield method
CN108625866B (en) Shield machine based on steel bushing device crosses ventilating shaft method
CN107842374B (en) The novel inert slurry of shield and combination grouting process for upper soft lower hard water rich strata
CN110924967B (en) Fine control construction method for shield proximity sensitive building in water-rich sandy gravel stratum
CN203905954U (en) Super-large shield pipe push bench with rectangular cross section
CN104343455A (en) Long-distance curved jacking pipe and pipe roof construction technique
CN111156010B (en) Construction method for shield of expansion soil layer to penetrate through existing train station house
CN104455726A (en) Pipe-jacking construction method for pipeline bottom grouting reinforcement
CN103603670A (en) Construction method of ultra-deep-earthed shield crossing complex formations
CN109681236A (en) Big cross section water-rich sand layer shield driving synchronous grouting method
CN104533432A (en) Construction method for shield to penetrate through buildings in old town of downtown in complex stratums
CN103498697A (en) Filling and construction method for goaf below tunnel
CN109779651A (en) A kind of sand ginger cohesive soil stratum low coverage Slurry Balanced Pipe Jacking Construction method
CN104389613A (en) Construction method of slurry balance shield crossing dangerous underground pipeline
CN112922616A (en) Method for controlling shield crossing construction
CN205576638U (en) Consolidate roadbed structure who handles newly -built railway karst foundation
CN108222954A (en) The construction method of shield crossing sand material back filled region
Maid Design features of the Botlek rail tunnel in the Betuweroute
Shin et al. TBM (Tunnel Boring Machine) tunneling in urban areas by EPB (Earth Pressure Balance): design consideration of Hanoi pilot light metro line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant