CN108677739A - 斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 - Google Patents
斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 Download PDFInfo
- Publication number
- CN108677739A CN108677739A CN201810802040.6A CN201810802040A CN108677739A CN 108677739 A CN108677739 A CN 108677739A CN 201810802040 A CN201810802040 A CN 201810802040A CN 108677739 A CN108677739 A CN 108677739A
- Authority
- CN
- China
- Prior art keywords
- measuring point
- coordinate
- prism
- denoted
- point
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/02—Suspension bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/04—Cable-stayed bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统,本发明通过两个棱镜点可以确定温度变化影响量的修正的任意空间位置,可以有效地回避温度对桥梁塔柱立模坐标的影响,无需在高温时段停止放样工作。
Description
技术领域
本发明涉及桥梁索塔施工中温度影响的修正,特别是一种斜拉桥和悬索桥索塔施工过程温度变形修正方法。
背景技术
由于塔身温度场变化(相对于设计基准温度)导致塔身空间位置发生偏移,这种偏移随塔身高度的增加而增大,随温度变化的增大而增大。对于高度较高的索塔结构,温度变化的影响不能忽视,需要采取可靠的方法进行处理。处理方法有两种:(1)在温度变化不大和塔身施工高度不是高时主要采用回避温度变化的方法进行控制点坐标的放样和竣工验收。(2)当温度影响较大且无法采用回避温度影响办法时,采用计算温度影响并修正的方法处理。在塔身施工时的放样和竣工测量时,根据计算出的影响量对控制点坐标进行调整(调整量的计算在现场可完成)。如果选择回避温度方法,模板的放样只能在晚上特定的气温条件下进行,对主体工程的工期十分不利。传统的单个棱镜的追踪棱镜法只能确定一个点,仅仅以该点的变化量来替代立模时的修正量,忽略了立模点和棱镜点的空间差,这是不准确的。
发明内容
本发明所要解决的技术问题是,针对现有技术不足,提供一种斜拉桥和悬索桥索塔施工过程温度变形修正方法,使索塔结构立模与理论值接近。
为解决上述技术问题,本发明所采用的技术方案是:一种斜拉桥和悬索桥索塔施工过程温度变形修正方法,包括以下步骤:
1)在索塔爬模上安装第一棱镜和第二棱镜,两个棱镜高度差为3m~8m;
2)在准备调模前对两个棱镜点进行观测,此时测量数据即称为“零点坐标”,测点1(第一棱镜的测点)坐标记为(x01,y01,z01),测点2(第二棱镜的测点)坐标记为(x02,y02,z02);
3)对模板进行放样时,测量两个棱镜,此时测点1’(对应(第一棱镜的测点))坐标记为(x11,y11,z11),测点2’(对应(第二棱镜的测点))坐标记为(x12,y12,z12);测点3’(放样点)坐标记为(x13,y13,z13);
4)通过零点坐标推算测点3(立模点)真实坐标,再利用立模点真实坐标对测点3’坐标进行实时修正。
步骤2)中,在准备调模前的凌晨3时~5时对两个棱镜点进行观测,此时因环境温度较均匀而产生的塔偏很小。
步骤4)中,推算后的测点3坐标(x03,y03,z03)为:z03=z01+l·cosα;x03=x01+l·sinα·sinβ;y03=y01+l·sinα·cosβ;其中,l为测点3与测点1之间的距离,α为测点1和2构成的空间直线与z轴形成的夹角;β为该直线投影到xoy平面与y轴形成的夹角。修正后的测点3’坐标(x13,y13,z13)为:z13=z11+l·cosα′;x13=x11+l·sinα'·sinβ';y13=y11+l·sinα'·cosβ',其中,α’为测点1’和2’构成的空间直线与z轴形成的夹角;β’为该直线投影到xoy平面与y轴形成的夹角。
相应的,本发明还提供了一种斜拉桥和悬索桥索塔施工过程温度变形修正系统,其包括:
安装于索塔爬模上的第一棱镜和第二棱镜,两个棱镜高度差为3m~8m;
第一观测单元,在准备调模前对两个棱镜点进行观测,此时测量数据即称为“零点坐标”,测点1坐标记为(x01,y01,z01),测点2坐标记为(x02,y02,z02);
第二观测单元,在对模板放样时测量两个棱镜,此时测点1’坐标记为(x11,y11,z11),测点2’坐标记为(x12,y12,z12);测点3’坐标记为(x13,y13,z13);
修正单元,用于通过零点坐标推算测点3真实坐标,再利用立模点真实坐标对测点3’坐标进行实时修正。
与现有技术相比,本发明所具有的有益效果为:本发明通过两个棱镜点可以确定温度变化影响量修正后的任意空间位置,可以有效地回避温度对桥梁塔柱立模坐标的影响,无需在高温等温度影响较大时段停止放样工作。
附图说明
图1为本发明温度变形修正方法流程图;
图2为本发明计算修正值示意图;
图3为本发明实施例索塔偏位示意图。
具体实施方式
1、在索塔爬模上焊接两个棱镜支座(棱镜支座相对位置要求不会发生改变)棱镜1和棱镜2,两个棱镜高差为3m~8m即可(当爬模无法保证安装后棱镜的稳固时,应考虑将焊接位置调整到塔柱上,提前预埋焊接件);
2、在准备调模的前一天晚上环境温度比较均匀(一般在凌晨3小时~5小时环境温度比较均匀),此时因环境温度均匀而产生的塔偏很小,安装上棱镜并对两个棱镜测点进行观测,此时测量数据即称为“零点坐标”,此时测点1的坐标记为(x01,y01,z01),测点2坐标记为(x02,y02,z02);
3、在对模板进行放样时,首先测量两个棱镜测点,此时测点1’的坐标记为(x11,y11,z11),测点2’的坐标记为(x12,y12,z12);测点3’的坐标记为(x13,y13,z13)
4、通过零点坐标推算立模点真实坐标,再利用实时观测值对放样点坐标进行实时修正。
测点1和2构成的空间直线与z轴形成的夹角记为α,其投影到xoy平面与y轴形成角度记为β。同理测点1’和2’构成的空间直线与z轴形成的夹角记为α’,其投影到xoy平面与y轴形成角度记为β’,则
同理可得sinα'、cosα'、sinβ'和cosβ'。
测点3与测点1两点间的距离记为l,有
则推算后的立模点坐标为:
z03=z01+l·cosα;x03=x01+l·sinα·sinβ;y03=y01+l·sinα·cosβ
(1-6)
设测点3’与测点1’两点间的距离为l',有l'=l,则修正后的放样点坐标为:
z13=z11+l·cosα′;x13=x11+l·sinα'·sinβ';y13=y11+l·sinα'·cosβ'
(1-7)
为了便于实际应用过程的方便性,可以利用以上公式编制Excel公式在模板放样过程中进行实时计算。
5依据上式(1-7)获得放样点的实时位置(x13,y13,z13),然后利用该实时位置进行放样。本发明将有效地回避温度对桥梁塔柱立模坐标的影响,无需在高温等温度影响较大的时段停止放样工作。
实例分析
将此方法应用于嘉鱼长江大桥索塔施工控制中,取得良好效果。
为了了解嘉鱼桥北索塔塔柱在温度影响下的偏位情况,在距离承台85.1m高度中塔柱上布置两个棱镜测点,进行24小时观测,根据当天气温显示凌晨5:00左右气温较均匀,以该时刻为“基准点”,塔柱偏位情况统计如表1所示,其中△X表示顺桥向偏位,△Y表示横桥向偏位,△Z表示高程方向偏差。
表1塔柱24小时塔偏情况
表1可知,塔柱在温度影响作用下发生较大偏移,最大偏移量△Y达到15.7mm,出现在下午14:30左右。1号点的高程偏差△Z较2号点稍大,这是由于1号点布置位置较2号点高,在温度作用下变形更大。塔柱在横桥向偏位△Y比顺桥向△X大,这是因为横桥向为东西走向受太阳直射方向影响,塔柱阴阳面产生的温差较大。
在嘉鱼长江公路大桥塔柱施工前期并未采用追踪棱镜法对立模坐标进行修正,进行节段成品验收时横桥向最大偏位达到22mm,超出规范和施工控制允许规定的10mm以内,应用追踪棱镜法后索塔偏位基本控制在在10mm以内,索塔偏位如图3所示。
Claims (5)
1.一种斜拉桥和悬索桥索塔施工过程温度变形修正方法,其特征在于,包括以下步骤:
1)在索塔爬模上安装第一棱镜和第二棱镜,两个棱镜高度差为3m~8m;
2)在准备调模前对两个棱镜点进行观测,此时测量数据即称为“零点坐标”,第一棱镜的测点,即测点1坐标记为(x01,y01,z01),第二棱镜的测点,即测点2坐标记为(x02,y02,z02);
3)对模板进行放样时,测量两个棱镜,此时第一棱镜的测点,即测点1’坐标记为(x11,y11,z11),第二棱镜的测点,即测点2’坐标记为(x12,y12,z12);放样点,即测点3’的坐标记为(x13,y13,z13);
4)通过零点坐标推算立模点,即测点3的真实坐标,再利用立模点真实坐标对放样点坐标进行实时修正。
2.根据权利要求1所述的斜拉桥和悬索桥索塔施工过程温度变形修正方法,其特征在于,步骤2)中,在准备调模前的凌晨3时~5时对两个棱镜点进行观测。
3.根据权利要求1所述的斜拉桥和悬索桥索塔施工过程温度变形修正方法,其特征在于,步骤2)中,推算后的立模点坐标(x03,y03,z03)为:z03=z01+l·c oαs;x03=x01+l·sinα·sinβ;y03=y01+l·sinα·cosβ。其中,l为测点3与测点1之间的距离,α为测点1和2构成的空间直线与z轴形成的夹角;β为该直线投影到xoy平面与y轴形成的夹角。
4.根据权利要求3所述的斜拉桥和悬索桥索塔施工过程温度变形修正方法,其特征在于,步骤4)中,修正后的放样点坐标(x13,y13,z13)为:z13=z11+l·coαs′;x13=x11+l·sinα'·sinβ';y13=y11+l·sinα'·cosβ',其中,α’为测点1’和2’构成的空间直线与z轴形成的夹角;β’为该直线投影到xoy平面与y轴形成的夹角。
5.一种斜拉桥和悬索桥索塔施工过程温度变形修正系统,其特征在于,包括:
安装于索塔爬模上的第一棱镜和第二棱镜,两个棱镜高度差为3m~8m;
第一观测单元,用于在准备调模前对两个棱镜点进行观测,此时测量数据即称为“零点坐标”,测点1坐标记为(x01,y01,z01),测点2坐标记为(x02,y02,z02);
第二观测单元,用于对模板进行放样时,测量两个棱镜,此时测点1’坐标记为(x11,y11,z11),测点2’坐标记为(x12,y12,z12);
测点3’坐标记为(x13,y13,z13);
修正单元,用于通过零点坐标推算测点3真实坐标,再利用测点3真实坐标对测点3’坐标进行实时修正。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810802040.6A CN108677739B (zh) | 2018-07-20 | 2018-07-20 | 斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810802040.6A CN108677739B (zh) | 2018-07-20 | 2018-07-20 | 斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108677739A true CN108677739A (zh) | 2018-10-19 |
CN108677739B CN108677739B (zh) | 2021-04-16 |
Family
ID=63814604
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810802040.6A Active CN108677739B (zh) | 2018-07-20 | 2018-07-20 | 斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108677739B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110184936A (zh) * | 2019-06-10 | 2019-08-30 | 中南大学 | 基于温度监控的大跨度曲线刚构桥变形控制方法及系统 |
CN111305039A (zh) * | 2020-01-22 | 2020-06-19 | 长沙理工大学 | 一种改善转体斜拉桥应力分布的装置及其安装方法 |
CN112818444A (zh) * | 2021-01-15 | 2021-05-18 | 中铁二院工程集团有限责任公司 | 基于运营行车安全的铁路混凝土桥梁线形实时控制方法 |
CN113483810A (zh) * | 2021-06-10 | 2021-10-08 | 上海铁路北斗测量工程技术有限公司 | 一种桥梁上轨道的变形监测方法及其系统 |
CN113884056A (zh) * | 2021-10-14 | 2022-01-04 | 中铁大桥局第九工程有限公司 | 一种大跨度连续梁挂篮悬臂现浇梁测量方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1869585A (zh) * | 2006-06-13 | 2006-11-29 | 中铁宝桥股份有限公司 | 钢索塔节段三维跟踪测量划线方法 |
CN101799276A (zh) * | 2010-02-26 | 2010-08-11 | 中铁大桥局股份有限公司 | 斜拉桥塔梁同步施工时塔柱及索道管的测量控制方法 |
CN103966942A (zh) * | 2013-01-24 | 2014-08-06 | 中交公路规划设计院有限公司 | 一种用于控制三塔斜拉桥主梁和桥塔纵向响应的结构体系 |
JP2016003475A (ja) * | 2014-06-16 | 2016-01-12 | 前田建設工業株式会社 | 上げ越し量修正方法、上げ越し量修正装置、及びプログラム |
CN207032055U (zh) * | 2017-07-27 | 2018-02-23 | 中铁大桥局集团有限公司 | 斜拉桥塔梁同步施工测量装置 |
-
2018
- 2018-07-20 CN CN201810802040.6A patent/CN108677739B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1869585A (zh) * | 2006-06-13 | 2006-11-29 | 中铁宝桥股份有限公司 | 钢索塔节段三维跟踪测量划线方法 |
CN101799276A (zh) * | 2010-02-26 | 2010-08-11 | 中铁大桥局股份有限公司 | 斜拉桥塔梁同步施工时塔柱及索道管的测量控制方法 |
CN103966942A (zh) * | 2013-01-24 | 2014-08-06 | 中交公路规划设计院有限公司 | 一种用于控制三塔斜拉桥主梁和桥塔纵向响应的结构体系 |
JP2016003475A (ja) * | 2014-06-16 | 2016-01-12 | 前田建設工業株式会社 | 上げ越し量修正方法、上げ越し量修正装置、及びプログラム |
CN207032055U (zh) * | 2017-07-27 | 2018-02-23 | 中铁大桥局集团有限公司 | 斜拉桥塔梁同步施工测量装置 |
Non-Patent Citations (2)
Title |
---|
第5期: "苏通大桥超高塔施工控制技术", 《中外公路》 * |
陈永奇主编: "《工程测量学(第四版)》", 31 May 2016, 测绘出版社 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110184936A (zh) * | 2019-06-10 | 2019-08-30 | 中南大学 | 基于温度监控的大跨度曲线刚构桥变形控制方法及系统 |
CN111305039A (zh) * | 2020-01-22 | 2020-06-19 | 长沙理工大学 | 一种改善转体斜拉桥应力分布的装置及其安装方法 |
CN111305039B (zh) * | 2020-01-22 | 2021-06-01 | 长沙理工大学 | 一种改善转体斜拉桥应力分布的装置及其安装方法 |
CN112818444A (zh) * | 2021-01-15 | 2021-05-18 | 中铁二院工程集团有限责任公司 | 基于运营行车安全的铁路混凝土桥梁线形实时控制方法 |
CN113483810A (zh) * | 2021-06-10 | 2021-10-08 | 上海铁路北斗测量工程技术有限公司 | 一种桥梁上轨道的变形监测方法及其系统 |
CN113483810B (zh) * | 2021-06-10 | 2022-12-02 | 上海铁路北斗测量工程技术有限公司 | 一种桥梁上轨道的变形监测方法及其系统 |
CN113884056A (zh) * | 2021-10-14 | 2022-01-04 | 中铁大桥局第九工程有限公司 | 一种大跨度连续梁挂篮悬臂现浇梁测量方法 |
CN113884056B (zh) * | 2021-10-14 | 2024-05-14 | 中铁大桥局第九工程有限公司 | 一种大跨度连续梁挂篮悬臂现浇梁测量方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108677739B (zh) | 2021-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108677739A (zh) | 斜拉桥和悬索桥索塔施工过程温度变形修正方法及系统 | |
US11112270B2 (en) | Attitude self-compensation method to the transmitters of wMPS based on inclinometer | |
CN107063119B (zh) | 管道内壁形貌和中心轴直线度测量装置和方法 | |
CN108981665B (zh) | 一种基于坐标测量的基坑顶部水平位移监测方法 | |
CN101700527B (zh) | 厚壁大口径管轧机找正方法 | |
CN106123776B (zh) | 一种顶管智能顶进测量系统以及测量方法 | |
WO2022262571A1 (zh) | 一种隧道管环端面平整度自动测量系统 | |
CN106223201B (zh) | 梁段桥梁线形监控的纠偏方法 | |
CN110440743B (zh) | 一种基于基线的隧道变形监测方法、系统、介质及设备 | |
CN114120785B (zh) | 一种煤矿掘进设备与地质模型、巷道设计模型的耦合系统 | |
CN106441112B (zh) | 一种可变量程的激光三角法位移测量装置与方法 | |
CN108316363B (zh) | 基坑水平位移自动监测系统及方法 | |
CN104048605B (zh) | 激光扫描测量标靶平差方程式构建方法 | |
CN112000135B (zh) | 基于人脸最高温点特征反馈的三轴云台视觉伺服控制方法 | |
CN111380519B (zh) | 一种超短基线/捷联惯性导航松组合的导航误差校正方法 | |
CN107891228B (zh) | 一种核电站主管道安装焊接变形监控方法 | |
CN113738390A (zh) | 一种矩形顶管机的分时迁移空间姿态微调纠偏方法 | |
CN105241434B (zh) | 基于wMPS系统的移动发射站快速定向方法 | |
CN111721260B (zh) | 基于水准仪i角误差修正的高精度光束法沉降测量方法 | |
CN110130903B (zh) | 盾构隧道施工纠偏的稳态目标偏置系统及方法 | |
CN112902845B (zh) | 轨迹式顶管自动导向方法 | |
CN110542396B (zh) | 一种异形钢塔节段姿态快速定位测量方法 | |
CN111174790B (zh) | 一种地形剖面跟踪路径的形成方法 | |
CN104908030A (zh) | 基于粒度模型的scara机器人精准定位方法 | |
Sun et al. | Line shape monitoring of longspan concrete-filled steel tube arches based on three-dimensional laser scanning |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |