CN108632566A CN201710155764.1A CN201710155764A CN108632566A CN 108632566 A CN108632566 A CN 108632566A CN 201710155764 A CN201710155764 A CN 201710155764A CN 108632566 A CN108632566 A CN 108632566A
Authority
CN
China
Prior art keywords
data collector
collector
informationization
built
project supervision
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710155764.1A
Other languages
Chinese (zh)
Inventor
朱宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Tianshi Construction Supervision Co Ltd
Original Assignee
Suzhou Tianshi Construction Supervision Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Tianshi Construction Supervision Co Ltd filed Critical Suzhou Tianshi Construction Supervision Co Ltd
Priority to CN201710155764.1A priority Critical patent/CN108632566A/en
Publication of CN108632566A publication Critical patent/CN108632566A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W84/00Network topologies
    • H04W84/18Self-organising networks, e.g. ad-hoc networks or sensor networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Signal Processing (AREA)
  • Multimedia (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Selective Calling Equipment (AREA)

Abstract

The invention discloses a kind of informationizations suitable for project supervision to build pipe device, the control device being connected including data collector and with data collector, the data collector includes video collector and is used for transmission the transmission device of the video information of video collector, the transmission device includes ZigBee chips, the ZigBee chips are connected by wireless ad hoc network with control device, it further include the battery module powered for data collector, it is provided with electrostatic discharge protection circuit on the connectivity port of the data collector and battery module, it builds at low cost, and the cumbersome of wiring can be simplified, networking flexibility.

Description

Pipe device is built in a kind of informationization suitable for project supervision
Technical field
The present invention relates to construction management device fields, and in particular, to a kind of informationization suitable for project supervision Build pipe device.
Background technology
Supervisor is needed to supervise to scene in the process of construction of one architectural engineering in China, so as in time Processing work progress in every affairs, ensure being smoothed out for engineering.In some large-scale construction engineerings, not only put more Wide, environment is complicated and changeable, technical standard is more, quality safety requires high, supervisor that need to ceaselessly run in each setting Between, and contacted using liaison mode mostly to the supervision and management of each setting.For ease of supervisor to the prison at scene The mode of remote monitoring can be used in work, and existing remote monitoring is generally basede on video monitoring, for the engineering built, Wiring trouble, and to construction, there is also certain influences sometimes.
Invention content
In order to solve the above-mentioned technical problem the present invention provides a kind of informationization suitable for project supervision and builds pipe device, take It builds at low cost, and the cumbersome of wiring, networking flexibility can be simplified.
Technical solution is used by the present invention solves the above problems:
Pipe device is built in a kind of informationization suitable for project supervision, including data collector and the control that is connected with data collector Device, the data collector include video collector and are used for transmission the transmission device of the video information of video collector, institute It includes ZigBee chips to state transmission device, and the ZigBee chips are connected by wireless ad hoc network with control device, further include For the battery module of data collector power supply, electrostatic protection is provided on the connectivity port of the data collector and battery module Circuit.The present invention improves on the basis of existing technology, is acquired to the video information at scene using video collector, By transmission device to the video information teletransmission, the remote management to field data is realized.Shape is being built since project is in State is not easy to the operations such as wiring.The transmission device of this programme uses ZigBee chips, ZigBee chips to carry out data transmission having It is cheap, the characteristics of low-power consumption, it can save and build cost.The ZigBee chips of multiple data collectors pass through wireless ad hoc network It is connected with control device, wireless ad hoc network does not need the support of fixed equipment, and voluntarily networking between each node is avoided in engineering It is connected up in project, reduces the cumbersome of wiring, networking flexibility, and it is of low cost.Data collector will realize work, and power supply is needed to supply Electricity is converted according to alternating current and is powered, and there is also the problems of wiring trouble;This programme realizes that data pass using ZigBee chips Defeated, low in energy consumption, electric current does not exceed 50mA when operating at full capacity, and this programme directly uses battery powered, both meets data The power demands of collector also further eliminate the trouble for electrical wiring.In building engineering construction, especially summer, Dry weather, dirt is husky all over the sky, extremely easy to produce static electricity, and the components rapid wear such as ZigBee chips in data collector, using electrostatic Protection circuit protects electrostatic, is protected to chip in data collector.
Preferably, being also associated with hardware firewall on the control device.Due to wireless ad hoc network safety not It is good, therefore hardware firewall is connected on control device, to enhance the safety of control device.
Preferably, the ZigBee chips are CC2430RF.
Preferably, the control device includes controller, display device, loud speaker and signal receiving device, it is described aobvious Showing device, loud speaker and signal receiving device are all connected on the controller.
To sum up, the beneficial effects of the invention are as follows:
1, the characteristics of present invention realizes the teletransmission of data using ZigBee chips, cheap, low-power consumption, can save and take Build up this.
2, it is connected with control device by wireless ad hoc network between transmission device of the invention, does not need fixed equipment Support, voluntarily networking between each node avoids connecting up in engineering project, reduces the cumbersome of wiring, networking flexibility, and cost It is cheap.
3, data collector of the invention uses battery powered, further eliminates the trouble of wiring.
Description of the drawings
Fig. 1 is the principle of the present invention block diagram.
Specific implementation mode
With reference to embodiment and attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, shows So, described embodiment is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the implementation in the present invention Example, every other embodiment obtained by those of ordinary skill in the art without making creative efforts belong to The scope of protection of the invention.
Embodiment:Pipe device is built in a kind of informationization suitable for project supervision as shown in Figure 1, including data collector and The control device being connected with data collector, the data collector include video collector and are used for transmission video collector The transmission device of video information, the transmission device include ZigBee chips, and the ZigBee chips pass through wireless ad hoc network It is connected with control device, further includes the battery module powered for data collector, the company of the data collector and battery module It connects and is provided with electrostatic discharge protection circuit on port.The realization of electrostatic discharge protection circuit is the very ripe technology in this field, therefore not right Its structure is repeated.
It is also associated with hardware firewall on the control device.
The ZigBee chips are CC2430RF.CC2430RF advocates CMOS solutions, and low cost, low-power consumption can Effectively reduce power consumption.Certainly, other models also can be used in ZigBee chips.
The control device includes controller, display device, loud speaker and signal receiving device, and the display device is raised Sound device and signal receiving device are all connected on the controller.Signal receiving device realizes that the reception to data, display device are realized Display to video information, loud speaker report the voice messaging of reception, convenient for supervisor to the information of construction site Change management.
It is enlightenment with the above-mentioned desirable embodiment according to this patent, through the above description, relevant staff is complete Various changes and amendments can be carried out in the range of without departing from this item patented technology thought entirely.The technology of this item patent Property range is not limited to the contents of the specification, it is necessary to determine its technical scope according to right.

Claims (4)

1. pipe device is built in a kind of informationization suitable for project supervision, including data collector and the control that is connected with data collector Device processed, it is characterised in that:The data collector includes video collector and is used for transmission the video information of video collector Transmission device, the transmission device includes ZigBee chips, the ZigBee chips pass through wireless ad hoc network with control fill It sets connected, further includes the battery module powered for data collector, on the connectivity port of the data collector and battery module It is provided with electrostatic discharge protection circuit.
2. pipe device is built in a kind of informationization suitable for project supervision according to claim 1, it is characterised in that:The control It is also associated with hardware firewall on device processed.
3. pipe device is built in a kind of informationization suitable for project supervision according to claim 1, it is characterised in that:It is described ZigBee chips are CC2430RF.
4. pipe device is built in a kind of informationization suitable for project supervision according to claim 1, it is characterised in that:The control Device processed includes controller, display device, loud speaker and signal receiving device, and the display device, loud speaker and signal receive Device is all connected on the controller.
CN201710155764.1A 2017-03-16 2017-03-16 Pipe device is built in a kind of informationization suitable for project supervision Pending CN108632566A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710155764.1A CN108632566A (en) 2017-03-16 2017-03-16 Pipe device is built in a kind of informationization suitable for project supervision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710155764.1A CN108632566A (en) 2017-03-16 2017-03-16 Pipe device is built in a kind of informationization suitable for project supervision

Publications (1)

Publication Number Publication Date
CN108632566A true CN108632566A (en) 2018-10-09

Family

ID=63687564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710155764.1A Pending CN108632566A (en) 2017-03-16 2017-03-16 Pipe device is built in a kind of informationization suitable for project supervision

Country Status (1)

Country Link
CN (1) CN108632566A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105812740A (en) * 2016-03-28 2016-07-27 成都晨越建设项目管理股份有限公司 Information construction and management device suitable for project supervision

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105812740A (en) * 2016-03-28 2016-07-27 成都晨越建设项目管理股份有限公司 Information construction and management device suitable for project supervision

Similar Documents

Publication Publication Date Title
CN201893783U (en) Homeplug
CN103543731A (en) Remote intelligent monitoring system of wave crest welding machine
CN104750077A (en) Water quality monitoring system of offshore cage based on ZigBee and GPRS (General Packet Radio Service) technologies
CN107809358A (en) A kind of intelligent home control system based on radio frequency control
CN105812740A (en) Information construction and management device suitable for project supervision
CN105184450A (en) Wireless communication based personnel management system for hydropower generation
CN202931563U (en) Power environment monitoring system based on ZigBee wireless communication technology
CN103546565A (en) Remote intelligent monitoring system for chip mounters
CN205212878U (en) Novel charge stake intelligent network deployment equipment
CN204514997U (en) A kind of multifunction power system cloud gray model monitoring system
CN108632566A (en) Pipe device is built in a kind of informationization suitable for project supervision
CN206906471U (en) A kind of aerator monitoring system
CN206640394U (en) A kind of monitoring system based on power bus information
CN204578552U (en) Serial server
CN210776299U (en) Comprehensive pipe rack area control system and control cabinet
CN208689422U (en) A kind of narrowband internet of things net controller
CN203118207U (en) Data acquisition device for microgrid system
CN111311896A (en) Convenient low-power consumption analog acquisition wireless transmission system
CN205810094U (en) Solar powered peculiar to vessel wireless combined type trans assembly
CN103543732A (en) Slicing machine remote intelligent monitoring system
CN214626367U (en) Intelligent power supply and distribution system for observation field
CN203661300U (en) Wireless sensor network node system
CN204539174U (en) A kind of simple and easy external power supply POE electric power system
CN205540891U (en) Project management informatization manages device
CN218512816U (en) Intelligent Internet of things lightning protection visual management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009