CN108625885A - A kind of semi-automatic duct piece assembling machine and its assembling method - Google Patents

A kind of semi-automatic duct piece assembling machine and its assembling method Download PDF

Info

Publication number
CN108625885A
CN108625885A CN201810693894.5A CN201810693894A CN108625885A CN 108625885 A CN108625885 A CN 108625885A CN 201810693894 A CN201810693894 A CN 201810693894A CN 108625885 A CN108625885 A CN 108625885A
Authority
CN
China
Prior art keywords
jurisdiction
section
snatch
assembling machine
oil cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810693894.5A
Other languages
Chinese (zh)
Inventor
李龙飞
叶蕾
程永龙
高博
胡燕伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Ningbo Rail Transit Group Co Ltd
Original Assignee
China Railway Engineering Equipment Group Co Ltd CREG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Equipment Group Co Ltd CREG filed Critical China Railway Engineering Equipment Group Co Ltd CREG
Priority to CN201810693894.5A priority Critical patent/CN108625885A/en
Publication of CN108625885A publication Critical patent/CN108625885A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Automatic Assembly (AREA)

Abstract

The invention discloses a kind of semi-automatic duct piece assembling machine and its assembling method, solve the problems, such as that pipe sheet assembling the degree of automation is low in the prior art, assembled efficiency is low.The present invention includes section of jurisdiction propulsion device and section of jurisdiction hanging apparatus, the section of jurisdiction propulsion device includes propelling cylinder, the section of jurisdiction hanging apparatus includes rotary support, rotary support side corresponding with cutterhead is equipped with assembling machine driving and reel assembly, the other side of rotary support is equipped with reversing frame, reversing frame is connected with assembling machine driving, it is horizontal on reversing frame to be equipped with guide beam, guide beam is equipped with sliding rack, sliding rack is equipped with the elevating mechanism being vertically arranged and horizontally disposed axial movement oil cylinder, the fixing end of axial movement oil cylinder is connected with reversing frame, the lower end of elevating mechanism is equipped with grasping mechanism.Main movement link of the present invention is acted using automation, is eliminated a large amount of human intervention operation and is saved the time of pipe sheet assembling link transhipment section of jurisdiction, improves assembled speed and working efficiency.

Description

A kind of semi-automatic duct piece assembling machine and its assembling method
Technical field
The present invention relates to technical field of tunnel construction, a kind of semi-automatic duct piece assembling machine and its assembling method are particularly related to.
Background technology
Construction of Urban Rail Traffic and Urban Underground piping lane development are swift and violent in recent years.Shield construction is excellent with its construction More property is grown rapidly.Built tunnel piping link is the important link in shield-tunneling construction, manual operation duct piece assembling machine Assembled tunnel duct piece is the current major way for carrying out tunnel-liner.The artificial excessive equipment operation that carries out increases faulty operation Possibility, it is larger and higher to personnel requirement to expend energy, causes the waste of manpower and materials, it is low to work at the same time efficiency, influences to apply Work progress.
Invention content
For the deficiency in above-mentioned background technology, a kind of semi-automatic duct piece assembling machine of present invention proposition and its assembling method, Solve the problems, such as that pipe sheet assembling the degree of automation is low in the prior art, assembled efficiency is low.
The technical proposal of the invention is realized in this way:A kind of semi-automatic duct piece assembling machine, including be installed on inside shield body Section of jurisdiction propulsion device and section of jurisdiction hanging apparatus, section of jurisdiction propulsion device and section of jurisdiction hanging apparatus be connected with controller;It is described Section of jurisdiction propulsion device includes several propelling cylinders being arranged along shield body circumference, propelling cylinder and the propulsion being arranged on trailer Pump is connected, and the section of jurisdiction hanging apparatus includes the rotary support being arranged inside shield body, and rotary support is corresponding with cutterhead Side be equipped with assembling machine driving and reel assembly, the other side of rotary support is equipped with reversing frame, and reversing frame drives with assembling machine It is connected, horizontal on reversing frame to be equipped with guide beam, guide beam is equipped with sliding rack, and sliding rack is equipped with the elevator being vertically arranged Structure and horizontally disposed axial movement oil cylinder, the fixing end for moving axially oil cylinder are connected with reversing frame, move axially oil cylinder Telescopic end is connected with sliding rack, and axial movement oil cylinder is connected with the assembled pump being arranged in shield body, under elevating mechanism End is equipped with the grasping mechanism for grasping pipe piece.
The elevating mechanism includes the guide sleeve and lift cylinder being connected with sliding rack, and guide post is equipped in guide sleeve, The fixing end of lift cylinder is fixedly connected with sliding rack, and the telescopic end of lift cylinder is connected with guide post, the lower end of guide post with Grasping mechanism is fixedly connected, and lift cylinder is connected with assembled pump.
The grasping mechanism includes snatch holder and snatch head, and snatch head is arranged on snatch holder, is set on snatch holder There are two the snatch hair oil cylinder for adjusting snatch head direction, the telescopic end of snatch hair oil cylinder is connected with snatch head, snatch head The fixing end of oil cylinder is connected with snatch holder.
Assembling machine driving includes drive motor and retarder, and retarder is connected with drive motor, retarder it is defeated Shaft is connected with reversing frame, and reversing frame is rotatablely connected with rotary support.
A kind of assembling method of semi-automatic duct piece assembling machine, includes the following steps:S0:Semi-automatic assembled pattern is selected, is opened Dynamic assembly pump and propulsion pump, S1:Controller controls section of jurisdiction hanging apparatus, makes snatch hair oil cylinder, lift cylinder and axial shifting Dynamic oil cylinder is recycled to zero-bit;S2:Controller controls assembling machine driving and opens, and assembling machine driving drives reversing frame rotation, makes to grab Mechanism is taken to rotate to capture area, while propelling cylinder stretching holds out against assembled section of jurisdiction;S3:Controller control axial movement Oil cylinder stretches out, and sliding rack is made to be moved to the upper area for waiting for grasping pipe piece;S4:Controller controls lift cylinder and stretches out, and makes crawl Mechanism is in suitable position with grasping pipe piece is waited for, adjusts snatch hair oil cylinder, makes snatch head and waits for that grasping pipe piece is in suitable position And direction, manually section of jurisdiction is fixed on snatch head;S5:Controller control lift cylinder is recycled to zero-bit, makes grasping mechanism band Section of jurisdiction to be raised above;S6:The axial Shift cylinder of controller control is recycled to zero-bit, makes sliding rack with grasping mechanism to Forward It is dynamic;S7:Assembling machine driving drives reversing frame rotation, so that grasping mechanism is rotated to assembled region, while propelling cylinder is recycled to zero Position;S8:Controller controls lift cylinder and stretches out setting length, and section of jurisdiction is made to be in appropriate location with assembled position;S9:It is accomplished manually Section of jurisdiction fine tuning is completed at the same time section of jurisdiction connection;S10:The propelling cylinder in the assembled region of controller control stretches out the pipe held out against in assembly Piece;S11:Grasping mechanism unclamps section of jurisdiction;S12:The action of S1-S11 is repeated, until completing last block on current tunnel anchor ring The assembly of section of jurisdiction;S13:Section of jurisdiction propulsion device and section of jurisdiction hanging apparatus restPose.
Before carrying out step S0, need the position of assembled section of jurisdiction it is known that can by being manually entered in controller or It is input in controller by guidance system.
Reversing frame drive grasping mechanism of the present invention realizes positive 200 degree and reversed 200 degree rotations, moves axially oil cylinder and carries Oil-lifting jar realizes that comprehensive installation of section of jurisdiction is realized in movement of the grasping mechanism in horizontal and vertical face, flexible movements respectively.This hair Bright main movement link is acted using automation, is eliminated a large amount of human intervention operation and is saved pipe sheet assembling link transhipment pipe The time of piece, improve assembled speed and working efficiency.
Description of the drawings
In order to illustrate the embodiments of the present invention more clearly, attached drawing makees letter needed in being described below to embodiment Singly introduce, it should be apparent that, drawings in the following description are only some embodiments of the invention, for the common skill in this field For art personnel, without creative efforts, other drawings may also be obtained based on these drawings.
Fig. 1 is overall structure of the present invention.
Fig. 2 is pipe sheet assembling control flow chart of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of not making the creative labor Embodiment shall fall within the protection scope of the present invention.
As shown in Figs. 1-2, a kind of semi-automatic duct piece assembling machine, including be installed on section of jurisdiction propulsion device inside shield body 1 and Section of jurisdiction hanging apparatus, section of jurisdiction propulsion device are used to support assembled section of jurisdiction, and section of jurisdiction hanging apparatus is used for the handling and installation of section of jurisdiction; Section of jurisdiction propulsion device and section of jurisdiction hanging apparatus are connected with controller, realize automation mechanized operation.The section of jurisdiction propulsion device packet Several propelling cylinders 6 being arranged along 1 circumference of shield body are included, for holding out against assembled section of jurisdiction.Propelling cylinder 6 is with setting rear Propulsion pump on trailer is connected, and pump is promoted to provide the power needed for propelling cylinder, realizes the flexible of propelling cylinder.The pipe Piece hanging apparatus includes the rotary support 4 being arranged inside shield body 1, and the side corresponding with cutterhead 20 of rotary support 4, which is equipped with, spells The other side of installation driving 2 and reel assembly 3, rotary support 4 is equipped with reversing frame 5, and reversing frame 5 is connected with assembling machine driving 2, Assembling machine driving 2 includes drive motor and retarder, and retarder is connected with drive motor, the output shaft of retarder with time Pivoted frame 5 is connected, and reversing frame 5 is rotatablely connected with rotary support 4, and assembling machine driving drives reversing frame rotation.It is horizontal on reversing frame 5 Equipped with guide beam 10, guide beam 10 is equipped with sliding rack 8, and sliding rack can slide on guide beam.Sliding rack 8 is equipped with and sets vertically The fixing end of the elevating mechanism and horizontally disposed axial movement oil cylinder 10 set, axial movement oil cylinder 10 is connected with reversing frame 5, The telescopic end of axial movement oil cylinder 10 is connected with sliding rack 8, axial movement oil cylinder 10 and the assembled pump being arranged in shield body 1 It is connected, assembled pump is that axial movement the flexible of oil cylinder provides power, moves axially the flexible drive sliding rack and liter of oil cylinder Descending mechanism is moved horizontally along guide beam, and the lower end of elevating mechanism is equipped with the grasping mechanism 12 for grasping pipe piece, elevating mechanism band Dynamic grasping mechanism moves up and down, and realizes the movement that grasping mechanism drives section of jurisdiction in vertical direction.
Further, the elevating mechanism includes the guide sleeve 11 being connected with sliding rack 8 and lift cylinder 7, lift cylinder It is vertically arranged with guide sleeve.Guide post 13 is equipped in guide sleeve 11, the fixing end of lift cylinder 7 is fixedly connected with sliding rack 8, The telescopic end of lift cylinder 7 is connected with guide post 13, and the lower end of guide post 13 is fixedly connected with grasping mechanism 12, lift cylinder 7 It is connected with assembled pump, assembled pump is that the flexible of lift cylinder provides power, the telescopic band action-oriented column edge of lift cylinder Guide sleeve moves up and down, and realizes the lifting of grasping mechanism.The grasping mechanism 12 includes snatch holder 14 and snatch head 15, snatch First 15 are arranged on snatch holder 14, set that there are two for adjusting the snatch hair oil cylinder in 15 direction of snatch head on snatch holder 14 16, the telescopic end of snatch hair oil cylinder 16 is connected with snatch head 15, and the fixing end of snatch hair oil cylinder 16 is connected with snatch holder 14 It connects.Two snatch hair oil cylinders are separately positioned on the both sides of snatch head, for adjusting snatch head angle during grasping pipe piece Adjusting, so that snatch head and section of jurisdiction is in suitable position.
A kind of assembling method of semi-automatic duct piece assembling machine, includes the following steps:S0:Semi-automatic assembled pattern is selected, is opened Dynamic assembly pump and propulsion pump, S1:Controller controls section of jurisdiction hanging apparatus, makes snatch hair oil cylinder, lift cylinder and axial shifting Dynamic oil cylinder is recycled to zero-bit;S2:Controller controls assembling machine driving and opens, and assembling machine driving drives reversing frame rotation, makes to grab Mechanism is taken to rotate to capture area, while propelling cylinder stretching holds out against assembled section of jurisdiction;S3:Controller control axial movement Oil cylinder stretches out, and sliding rack is made to be moved to the upper area for waiting for grasping pipe piece;S4:Controller controls lift cylinder and stretches out, and makes crawl Mechanism is in suitable position with grasping pipe piece is waited for, adjusts snatch hair oil cylinder, makes snatch head and waits for that grasping pipe piece is in suitable position And direction, manually section of jurisdiction is fixed on snatch head;S5:Controller control lift cylinder is recycled to zero-bit, makes grasping mechanism band Section of jurisdiction to be raised above;S6:The axial Shift cylinder of controller control is recycled to zero-bit, makes sliding rack with grasping mechanism to Forward It is dynamic;S7:Assembling machine driving drives reversing frame rotation, so that grasping mechanism is rotated to assembled region, while propelling cylinder is recycled to zero Position;S8:Controller controls lift cylinder and stretches out setting length, and section of jurisdiction is made to be in appropriate location with assembled position;S9:It is accomplished manually Section of jurisdiction fine tuning is completed at the same time section of jurisdiction connection;S10:The propelling cylinder in the assembled region of controller control stretches out the pipe held out against in assembly Piece;S11:Grasping mechanism unclamps section of jurisdiction;S12:The action of S1-S11 is repeated, until completing last block on current tunnel anchor ring The assembly of section of jurisdiction;S13:Section of jurisdiction propulsion device and section of jurisdiction hanging apparatus restPose.
Before carrying out step S0, need the position of assembled section of jurisdiction it is known that can by being manually entered in controller or It is input in controller by guidance system.Such as:Provided by artificial or guidance system need the position of assembled section of jurisdiction to The assembled angle that first piece of section of jurisdiction is calculated by PLC operations drives reversing frame rotation according to this assembled angle assembly driving Corresponding angle reaches capture area, manual operation assembling machine grasping pipe piece.After the completion of manual operation assembling machine grasping pipe piece, PLC calculates reversing frame rotation angle according to known section of jurisdiction position and assembling machine is rotated to assembled region, is carried out to section of jurisdiction assembled.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention god.

Claims (6)

1. a kind of semi-automatic duct piece assembling machine, it is characterised in that:Including being installed on shield body(1)Internal section of jurisdiction propulsion device and pipe Piece hanging apparatus, section of jurisdiction propulsion device and section of jurisdiction hanging apparatus are connected with controller;The section of jurisdiction propulsion device includes edge Shield body(1)Several propelling cylinders of circumference setting(6), propelling cylinder(6)It is connected with the propulsion pump being arranged on trailer It connects, the section of jurisdiction hanging apparatus includes being arranged in shield body(1)Internal rotary support(4), rotary support(4)With cutterhead(20)Phase Corresponding side drives equipped with assembling machine(2)With reel assembly(3), rotary support(4)The other side be equipped with reversing frame(5), return Pivoted frame(5)It is driven with assembling machine(2)It is connected, reversing frame(5)It is upper horizontal equipped with guide beam(10), guide beam(10)It is equipped with and slides Moving frame(8), sliding rack(8)It is equipped with the elevating mechanism being vertically arranged and horizontally disposed axial movement oil cylinder(10), axial to move Dynamic oil cylinder(10)Fixing end and reversing frame(5)It is connected, moves axially oil cylinder(10)Telescopic end and sliding rack(8)It is connected It connects, moves axially oil cylinder(10)With setting in shield body(1)Interior assembled pump is connected, and the lower end of elevating mechanism is equipped with for grabbing Take the grasping mechanism of section of jurisdiction(12).
2. semi-automatic duct piece assembling machine according to claim 1, it is characterised in that:The elevating mechanism includes and sliding rack (8)The guide sleeve being connected(11)And lift cylinder(7), guide sleeve(11)In be equipped with guide post(13), lift cylinder(7)Consolidate Fixed end and sliding rack(8)It is fixedly connected, lift cylinder(7)Telescopic end and guide post(13)It is connected, guide post(13)Lower end With grasping mechanism(12)It is fixedly connected, lift cylinder(7)It is connected with assembled pump.
3. semi-automatic duct piece assembling machine according to claim 1 or 2, it is characterised in that:The grasping mechanism(12)Including Snatch holder(14)With snatch head(15), snatch head(15)It is arranged in snatch holder(14)On, snatch holder(14)It is equipped with two It is a to be used to adjust snatch head(15)The snatch hair oil cylinder in direction(16), snatch hair oil cylinder(16)Telescopic end and snatch head(15)Phase Connection, snatch hair oil cylinder(16)Fixing end and snatch holder(14)It is connected.
4. semi-automatic duct piece assembling machine according to claim 3, it is characterised in that:The assembling machine driving(2)Including driving Dynamic motor and retarder, retarder are connected with drive motor, the output shaft and reversing frame of retarder(5)It is connected, reversing frame (5)With rotary support(4)Rotation connection.
5. a kind of assembling method of semi-automatic duct piece assembling machine as described in claim 1, it is characterised in that:Including following step Suddenly:S0:Semi-automatic assembled pattern is selected, assembled pump is started and promotes pump, S1:Controller controls section of jurisdiction hanging apparatus, makes Snatch hair oil cylinder, lift cylinder and axial movement oil cylinder are recycled to zero-bit;S2:Controller controls assembling machine driving and opens, and spells Installation driving drives reversing frame rotation, and grasping mechanism is made to rotate to capture area, at the same propelling cylinder stretching hold out against it is assembled Section of jurisdiction;S3:The axial Shift cylinder of controller control stretches out, and sliding rack is made to be moved to the upper area for waiting for grasping pipe piece;S4:Control Device control lift cylinder processed stretches out, and makes grasping mechanism and waits for that grasping pipe piece is in suitable position, adjusts snatch hair oil cylinder, make snatch Head with wait for that grasping pipe piece is in suitable position and direction, manually section of jurisdiction is fixed on snatch head;S5:Controller control promotes oil Cylinder is recycled to zero-bit, and grasping mechanism is made to be raised above with section of jurisdiction;S6:The axial Shift cylinder of controller control is recycled to zero-bit, Sliding rack is set to be moved forward with grasping mechanism;S7:Assembling machine driving drives reversing frame rotation, and grasping mechanism is made to rotate to assembly Region, while propelling cylinder is recycled to zero-bit;S8:Controller controls lift cylinder and stretches out setting length, makes section of jurisdiction and assembled position It sets and is in appropriate location;S9:It is accomplished manually section of jurisdiction fine tuning and is completed at the same time section of jurisdiction connection;S10:The controller assembled region of control pushes away The section of jurisdiction held out against in assembly is stretched out into oil cylinder;S11:Grasping mechanism unclamps section of jurisdiction;S12:The action of S1-S11 is repeated, until complete At the assembly of last block section of jurisdiction on current tunnel anchor ring;S13:Section of jurisdiction propulsion device and section of jurisdiction hanging apparatus restPose .
6. the assembling method of semi-automatic duct piece assembling machine according to claim 5, it is characterised in that:Carry out step S0 it Before, need the position of assembled section of jurisdiction it is known that control can be input in controller or by guidance system by being manually entered In device.
CN201810693894.5A 2018-06-29 2018-06-29 A kind of semi-automatic duct piece assembling machine and its assembling method Pending CN108625885A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810693894.5A CN108625885A (en) 2018-06-29 2018-06-29 A kind of semi-automatic duct piece assembling machine and its assembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810693894.5A CN108625885A (en) 2018-06-29 2018-06-29 A kind of semi-automatic duct piece assembling machine and its assembling method

Publications (1)

Publication Number Publication Date
CN108625885A true CN108625885A (en) 2018-10-09

Family

ID=63689418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810693894.5A Pending CN108625885A (en) 2018-06-29 2018-06-29 A kind of semi-automatic duct piece assembling machine and its assembling method

Country Status (1)

Country Link
CN (1) CN108625885A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209435A (en) * 2018-11-27 2019-01-15 江苏凯宫隧道机械有限公司 The automatic detection tunnel duct piece of band spells the assembling machine of ring circularity
CN110552708A (en) * 2019-09-24 2019-12-10 中国重型机械研究院股份公司 Pipe piece assembling machine and assembling method
CN110847922A (en) * 2019-12-13 2020-02-28 中国铁建重工集团股份有限公司 Operation control device and heading equipment

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09125893A (en) * 1995-10-31 1997-05-13 Ishikawajima Harima Heavy Ind Co Ltd Automatic segment assembly device and segment positioning method
JP2001082093A (en) * 1999-09-10 2001-03-27 Taisei Corp Lining assembly device for rectangular shield machine
CN1837578A (en) * 2006-03-29 2006-09-27 上海隧道工程股份有限公司 Shield segment splicing machine with six-freedom degree
JP2010070998A (en) * 2008-09-19 2010-04-02 Ihi Corp Shield machine
CN102733819A (en) * 2012-03-29 2012-10-17 江苏凯宫隧道机械有限公司 Shield pipe segment erector formed by splicing six-degree-of-freedom double arms in staggered way
CN103195445A (en) * 2013-04-15 2013-07-10 辽宁北方重工机器制造有限公司 Self-positioning quick segment erector
CN204552749U (en) * 2015-02-04 2015-08-12 海瑞克(广州)隧道设备有限公司 A kind of small-sized shield machine segment erector
CN204783064U (en) * 2015-07-06 2015-11-18 中铁工程装备集团有限公司 It assembles machine to be applicable to major diameter section of jurisdiction vacuum chuck formula section of jurisdiction
CN107989632A (en) * 2017-12-28 2018-05-04 辽宁三三工业有限公司 A kind of duct piece assembling machine section of jurisdiction device for adjusting posture
CN108035721A (en) * 2017-12-07 2018-05-15 徐工集团凯宫重工南京有限公司 A kind of miniature shield six degree of freedom duct piece assembling machine

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09125893A (en) * 1995-10-31 1997-05-13 Ishikawajima Harima Heavy Ind Co Ltd Automatic segment assembly device and segment positioning method
JP2001082093A (en) * 1999-09-10 2001-03-27 Taisei Corp Lining assembly device for rectangular shield machine
CN1837578A (en) * 2006-03-29 2006-09-27 上海隧道工程股份有限公司 Shield segment splicing machine with six-freedom degree
JP2010070998A (en) * 2008-09-19 2010-04-02 Ihi Corp Shield machine
CN102733819A (en) * 2012-03-29 2012-10-17 江苏凯宫隧道机械有限公司 Shield pipe segment erector formed by splicing six-degree-of-freedom double arms in staggered way
CN103195445A (en) * 2013-04-15 2013-07-10 辽宁北方重工机器制造有限公司 Self-positioning quick segment erector
CN204552749U (en) * 2015-02-04 2015-08-12 海瑞克(广州)隧道设备有限公司 A kind of small-sized shield machine segment erector
CN204783064U (en) * 2015-07-06 2015-11-18 中铁工程装备集团有限公司 It assembles machine to be applicable to major diameter section of jurisdiction vacuum chuck formula section of jurisdiction
CN108035721A (en) * 2017-12-07 2018-05-15 徐工集团凯宫重工南京有限公司 A kind of miniature shield six degree of freedom duct piece assembling machine
CN107989632A (en) * 2017-12-28 2018-05-04 辽宁三三工业有限公司 A kind of duct piece assembling machine section of jurisdiction device for adjusting posture

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李文福;: "盾构管片拼装机的结构分析" *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209435A (en) * 2018-11-27 2019-01-15 江苏凯宫隧道机械有限公司 The automatic detection tunnel duct piece of band spells the assembling machine of ring circularity
CN110552708A (en) * 2019-09-24 2019-12-10 中国重型机械研究院股份公司 Pipe piece assembling machine and assembling method
CN110847922A (en) * 2019-12-13 2020-02-28 中国铁建重工集团股份有限公司 Operation control device and heading equipment

Similar Documents

Publication Publication Date Title
CN108625885A (en) A kind of semi-automatic duct piece assembling machine and its assembling method
CN109667605A (en) A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh
CN211393616U (en) Lifting beam frame for manure leaking plate front traveling crane
CN217844755U (en) Multifunctional drill rod robot for industrial silicon furnace
CN107553687A (en) 3D houses printer
CN213745213U (en) Efficient pipe laying device
CN115744618B (en) Hoisting method for tower type boiler girder
CN209704593U (en) A kind of manual imitation is laid with the laying rack of tunnel double-lining steel mesh
CN107287376B (en) Molten iron pretreatment assists blowing slag-removing device of skimming
CN108001701A (en) Movable unmanned helicopter catapult-launching gear
CN213061952U (en) Mechanism is salvaged in flexible interception of floater on water
CN208502804U (en) A kind of semi-automatic duct piece assembling machine
CN211816261U (en) Lifting device for concrete pouring guide pipe
CN1367559A (en) Method for paying-off by utilizing overhead line and equipment for implementing said method
CN210103322U (en) Self-driven urban underground prefabricated comprehensive pipe gallery laying and hoisting machine
CN209892249U (en) Portal type duct piece assembling equipment
CN202578567U (en) Petroleum well drilling tool receiving and dismantling device
CN115263378A (en) Arch frame installation trolley and use method thereof
CN107999510A (en) A kind of bridge construction completion water blockoff sandbag processing unit
CN2846474Y (en) Vertical digging device
CN218624125U (en) Well drilling machine with winch system
CN216912727U (en) Lifting and rotating roller frame device of automatic seam welder
CN218292852U (en) Crawler-type full-automatic steel bar binding machine
CN218324863U (en) Multi-angle hole leading equipment in subway tunnel
CN217921077U (en) Green building elevation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20221214

Address after: 450016 No. 99 Sixth Avenue, Zhengzhou economic and Technological Development Zone, Henan

Applicant after: CHINA RAILWAY ENGINEERING EQUIPMENT GROUP Co.,Ltd.

Applicant after: Ningbo Rail Transit Group Co.,Ltd.

Address before: 450016 No. 99 Sixth Avenue, Zhengzhou economic and Technological Development Zone, Henan

Applicant before: CHINA RAILWAY ENGINEERING EQUIPMENT GROUP Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009

RJ01 Rejection of invention patent application after publication