CN108594730A - A kind of engineering construction Schedule monitoring system and method based on Internet of Things - Google Patents

A kind of engineering construction Schedule monitoring system and method based on Internet of Things Download PDF

Info

Publication number
CN108594730A
CN108594730A CN201810759910.6A CN201810759910A CN108594730A CN 108594730 A CN108594730 A CN 108594730A CN 201810759910 A CN201810759910 A CN 201810759910A CN 108594730 A CN108594730 A CN 108594730A
Authority
CN
China
Prior art keywords
positioning device
project
positioning
bim
mobile equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810759910.6A
Other languages
Chinese (zh)
Inventor
赵挺生
陈露
王腊
孔永华
蒋灵
徐凯
张淼
周炜
唐菁菁
张伟
杜婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong University of Science and Technology
CCCC First Highway Engineering Co Ltd
Original Assignee
Huazhong University of Science and Technology
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong University of Science and Technology, CCCC First Highway Engineering Co Ltd filed Critical Huazhong University of Science and Technology
Priority to CN201810759910.6A priority Critical patent/CN108594730A/en
Publication of CN108594730A publication Critical patent/CN108594730A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/042Programme control other than numerical control, i.e. in sequence controllers or logic controllers using digital processors
    • G05B19/0428Safety, monitoring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/20Pc systems
    • G05B2219/24Pc safety
    • G05B2219/24215Scada supervisory control and data acquisition

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

The engineering construction Schedule monitoring system based on Internet of Things that the invention discloses a kind of, including:Pairing device, data processor, BIM work stations are positioned, positioning pairing device is made of the main projects positioning device and positioning device for mobile equipment being placed on the permanent building or structures of project control partitioned project;The positioning device for mobile equipment is placed on the construction equipment of the permanent building or structures;The data processor exchanges data by public internet with the positioning pairing device, and the phasor difference for calculating the main projects positioning device and the positioning device for mobile equipment in positioning pairing device converts phasor difference to project progress information;The data processor is connect with the BIM station datas, and BIM work stations receive the project progress information of data processor transmission, and project progress information is shown in the BIM models of engineering.

Description

A kind of engineering construction Schedule monitoring system and method based on Internet of Things
Technical field:
The present invention relates to a kind of Schedule monitoring methods, more particularly, to a kind of engineering construction progress based on Internet of Things Monitoring system.
Background technology:
The Schedule monitoring of engineering construction contributes in control construction link to lead to the problem of, rationally transfers goods and materials, will be practical Construction speed and target advance comparison, can find out the factor for influencing construction speed, to ensure that engineering is completed as scheduled.
The acquisition mode of traditional construction speed is generally divided into two kinds:First, in-site measurement, craft are made a report on, i.e., by technology people It is made a report on by hand after going to scene to be checked;Second is that in-site measurement, software are made a report on, i.e., pass through software after being checked by technical staff scene It makes a report on.Aforesaid way is both needed to complete by manpower, takes time and effort, and existence information acquisition is not in time, progress data is inaccurate, works The drawbacks such as inefficiency.
To improve above-mentioned deficiency, there are scholar and technical staff to propose different Schedule monitoring methods:It installs at the construction field (site) Video camera, using monitoring host computer acquire construction site audio and video monitored automatically, this method data volume greatly, cost It is higher to be not easy to realize;Construction speed information is acquired by man-hour manually hand-held Schedule monitoring device at the scene, although this method cost is slightly lower But need to complete by manpower, thus, it still remains information collection not in time and the drawbacks such as takes time and effort, and can not achieve and apply The Full-automatic monitoring of work progress.
Invention content:
The purpose of the present invention is to overcome the above shortcomings and to provide a kind of engineering construction Schedule monitoring side based on Internet of Things Method, this method realized by Internet of things system and using GPS positioning technology to engineering level, vertical direction construction speed it is complete Automatic monitoring, support is provided for engineering construction informationization.
To achieve the above object, the present invention is realized using following scheme:A kind of engineering construction progress based on Internet of Things Monitoring system, including:Pairing device, data processor, BIM work stations are positioned, positioning pairing device includes being placed in project control The permanent building of property partitioned project processed or the main projects positioning device on structures and positioning device for mobile equipment;Institute Positioning device for mobile equipment is stated to be placed on the construction equipment of the permanent building or structures;The data processor passes through Public internet exchanges data with the positioning pairing device, for calculating the main projects positioning in positioning pairing device The phasor difference of device and the positioning device for mobile equipment converts phasor difference to project progress information;The data processor It is connect with the BIM station datas, BIM work stations receive the project progress information of data processor transmission, by project progress Information is shown in the BIM models of engineering;
More specifically, the main controlling partitioned project of project is also predefined, and it is k to be numbered1、k2、k3……kn, Middle k indicates main projects, in main projects knControlling work is disposed on the permanent building or structures of fixed position Journey positioning device kn d, positioning device for mobile equipment is disposed in the MOVING STRUCTURE equipment of the construction of permanent building or structuresAbove two device forms positioning pairing device, and wherein y indicates that travel engineering, d indicate location information;
A kind of monitoring method of the engineering construction progress based on Internet of Things, its step are as follows:
S1, the space coordinate (X acquired according to main projects positioning devicec,Yc,Zc) the structure main projects item Purpose BIM models;
S2, matching are placed in permanent building in same project controlling partitioned project or the main projects on structures Positioning device and positioning device for mobile equipment;
S3, the space coordinate (X acquired according to positioning device for mobile equipmentm,Ym,Zm), calculated by data processor described in Positioning device for mobile equipment and phasor difference between matched main projects positioning device, as the matched main projects of institute Project progress information;
Project progress information described in S4, BIM workstation collection, builds the project progress of the permanent building or structures Model;
Further, main projects positioning device of the invention includes GPS positioning module, information acquisition module, data Processing module, data disaply moudle, information storage module, power supply.
The positioning device for mobile equipment of the present invention includes GPS positioning module, information acquisition module, data processing module, number According to display module, information storage module, power supply.
Further, controlling partitioned project of the invention includes that engineering construction horizontal direction, vertical height change The partitioned project at place.
Further, the permanent building or structures of fixed position of the invention include column bottom or cantilever beam End, pillar, basis or the wall of completion of more specifically having constructed including engineering.
Further, construction equipment of the invention includes climbing formwork for construction frame or Hanging Basket, more specifically includes hoisting scaffold Or climbing formwork system.
Further, BIM work stations of the invention include BIM servers, BIM modeling modules, progress display module, information Memory module, statement management module.
Preferably, battery used in the present invention is solar cell.
The present invention based on Internet of Things engineering construction Schedule monitoring method, main projects positioning device is arranged in engineering On the permanent building or structures of fixed position, positioning device for mobile equipment is arranged in MOVING STRUCTURE equipment.Pass through Above two device is connect by public internet with data processor, is calculated and is analyzed its phasor difference, and is converted into project progress.Number It is connected with BIM work stations according to processor, project progress is shown in engineering BIM models, realizes the real-time letter of construction operation Breathization.What is generated has the beneficial effect that:
(1) present invention realizes full-automatic real time monitoring for the construction speed in engineering level, vertical direction, can be to engineering Further work such as material configuration, fund operation etc. is effectively instructed.
(2) apparatus structure that the present invention uses is simple, and cost is relatively low, convenient for laying, reduces hand labor waste, saves Engineering cost.
(3) present invention realizes the full-automatic construction speed monitoring data collection of prosthetic participation, avoids artificial acquisition The data relative distance of the human factor error that data generate, GPS positioning device acquisition is accurate, thus, data promptly and accurately, have Conducive to raising engineering construction efficiency.
(4) construction speed is monitored using internet and is combined with BIM by the present invention, improves engineering level, vertical direction The information system management level of upper construction speed monitoring.
Description of the drawings
Fig. 1 is the work flow diagram of the present invention;
Fig. 2 is the system structure diagram of the embodiment of the present invention 1;
Fig. 3 is the schematic diagram of the embodiment of the present invention 2;
Fig. 4 is the system structure diagram of the embodiment of the present invention 2.
Specific implementation mode
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.
Embodiment 1
Such as Fig. 2, a kind of monitoring system of the engineering construction progress based on Internet of Things, including:At positioning pairing device, data Device 3, BIM work stations 4 are managed, positioning pairing device is by being placed on the permanent building or structures of project control partitioned project Main projects positioning device (main projects GPS positioning device 1) and positioning device for mobile equipment (mobile equipment GPS is fixed Position device 2) composition;The positioning device for mobile equipment is placed on the construction equipment of the permanent building or structures;Institute It states data processor and data is exchanged with the positioning pairing device by public internet 5, for calculating in positioning pairing device The phasor difference of the main projects positioning device and the positioning device for mobile equipment converts phasor difference to project progress letter Breath;The data processor is connect with the BIM station datas, BIM work stations receive data processor transmission engineering into Information is spent, project progress information is shown in the BIM models of engineering;
As shown in Figure 1, the engineering construction Schedule monitoring method based on Internet of Things of the embodiment of the present invention includes the following steps:
S1, main controlling partitioned project of identifying project, and numbered property engineering k in order to control1, main projects k2, control Property engineering k processed3... controlling partitioned project includes that engineering construction horizontal direction, vertical height change branch's work at place Engineering construction route is divided into multiple and different horizontal, in vertical direction straight line construction access roads by journey.
S2, " main projects GPS is fixed for placement on the permanent building or structures of 1 fixed position of main projects Position device ", disposes " mobile equipment GPS positioning device ", above two device is formed in the MOVING STRUCTURE equipment constructed GPS positioning pairing device;The permanent building or structures of fixed position can be engineering construct the pillar of completion, basis or Wall etc., the MOVING STRUCTURE equipment with construction usage is on same direction line;MOVING STRUCTURE equipment can be Hanging Basket, promote foot hand Frame or climbing formwork system etc..
As shown in Fig. 2, main projects GPS positioning device 1 includes GPS positioning module 11, information acquisition module 12, data Processing module 13, data disaply moudle 14, information storage module 15, power supply 16.Mobile equipment GPS positioning device 2 is fixed including GPS Position module 21, information acquisition module 22, data processing module 23, data disaply moudle 24, information storage module 25, power supply 26. GPS positioning module 11 is connected with information acquisition module 15, and GPS positioning module 21 is connected with information acquisition module 25, can obtain institute Longitude and latitude and spatial data on ground.
S3, above-mentioned GPS positioning pairing device is connected using public internet with data processor, data processor point Analysis calculates the phasor difference of " main projects GPS positioning device 1 " and " mobile equipment GPS positioning device 2 ", and is converted For project progress information.
Such as main projects GPS positioning device 1, the coordinate of acquisition is (Xc, Yc, Zc), main projects GPS positioning dress It is on permanent works to set 1, and constant always, such as positioned at column bottom, mobility equipment GPS positioning device is set to pillar construction On climbing formwork for construction frame, the coordinate of acquisition is (XmH, YmH, ZmH), is raised with engineering progress, is variation, test two The phasor difference of person represents the pillar height that construction is completed:
H=SQRT [(XmH-Xc)2+(YmH-Yc)2+(ZmH-Zc)2];
The trueness error generated in the two space coordinate measurement process is offset while calculating phasor difference,
For another example, main projects are the constructions of beam, and main projects GPS positioning device 1 is located at cantilever beam-ends, the seat of acquisition Be designated as (Xc, Yc, Zc), mobile equipment GPS positioning device is disposed on the Hanging Basket on cantilever beam, the coordinate of acquisition be (XmL, YmL, ZmL), positioning device for mobile equipment movement with the extension of beam, is variation, and the phasor difference representative both tested is applied The beam length that work is completed:L=SQRT [(XmH-Xc)2+(YmH-Yc)2+(ZmH-Zc)2];
The trueness error generated in the two space coordinate measurement process is offset while calculating phasor difference.
As shown in Fig. 2, public internet connection main projects GPS positioning device 1,2 and of mobile equipment GPS positioning device Data processor is connect by connecting data processor with BIM work stations.It is fixed that data processor receives main projects GPS Position device 1 and mobile equipment GPS positioning device 2 longitude and latitude and spatial data that respectively obtain, by longitude and latitude and spatial data into Row analysis can be calculated the relative distance L of stream oriented device, this relative distance L is the air line distance of 2 points of device.Final data processing Device converts calculated range data L to corresponding project progress information.
S4, data processor is connected with BIM work stations, BIM work stations receive data processor transmission engineering into Information is spent, progress msg is shown in the BIM models of engineering.
As shown in Fig. 2, BIM work stations include BIM servers 31, BIM modeling modules 32, progress display module 33, information Memory module 34 and statement management module 35.After BIM servers receive the incoming project progress information of data processor, by it Import BIM modeling modules.Finally, project progress can be shown in engineering threedimensional model.Related management personnel and supervisor can Check project progress in detail in BIM models, it is easy to operate, it is intuitive and easy to understand.Statement management module and BIM modeling modules and progress Display module is connected, and produces project progress electronic document, facilitates printing.Information storage module can will real-time monitor into Degree information is preserved, convenient to check at any time.
S5, " main projects GPS is fixed for placement on the permanent building or structures of 2 fixed position of main projects Position device 1 " then exists if the MOVING STRUCTURE equipment of construction usage is different from the MOVING STRUCTURE equipment used at main projects 1 " mobile equipment GPS positioning device 2 " is disposed in MOVING STRUCTURE equipment.If not, then it still uses at a upper main projects The mobile equipment GPS positioning device of MOVING STRUCTURE equipment.Remaining step same S3, S4.
Device placement at S6, remaining main projects and the same S5 of project progress supervisory control and data acquisition (SCADA).It needs to illustrate It is that the GPS positioning device at main projects arranges to be arranged on demand successively according to construction speed, mobile equipment GPS positioning device root It is arranged according to the using flexible arrangement of site operation facilities and equipment.All GPS positioning devices are all connect with public internet, data Processor is finally translated into according to that can reflect that the position data of two GPS positioning devices of project progress calculates its relative distance Corresponding project progress information.
Embodiment 2
Such as Fig. 4, a kind of monitoring system of the engineering construction progress based on Internet of Things, including:At positioning pairing device, data Device 3, BIM work stations 4 are managed, positioning pairing device includes being placed in the permanent building or structures of project control partitioned project On main projects positioning device (main projects GPS positioning device 1), (mobile equipment GPS is fixed for positioning device for mobile equipment Position device 2) and ground control point positioning device 7;The positioning device for mobile equipment is placed in the permanent building or constructs On the construction equipment of object;The ground control point positioning device is placed in ground, and the data processor passes through public internet 5 Exchange data with the positioning pairing device, for calculate positioning pairing device in the main projects positioning device with it is described The phasor difference of positioning device for mobile equipment converts phasor difference to project progress information;The data processor and the BIM works Make station data connection, BIM work stations receive the project progress information of data processor transmission, by project progress information in engineering It is shown in BIM models;Main projects positioning device includes GPS positioning module for measuring latitude and longitude coordinates, laser range finder Spacing between acquisition and ground control point is for compensating at the height error, information acquisition module, data that GPS positioning module measures Manage module, data disaply moudle, information storage module, power supply.Positioning device for mobile equipment includes GPS positioning module for measuring Spacing between latitude and longitude coordinates, the acquisition of laser range finder 17 and ground control point is for compensating the height that GPS positioning module measures Error, information acquisition module, data processing module, data disaply moudle, information storage module, power supply.Ground control point positions Device 7 includes that GPS positioning module shows mould for measuring latitude and longitude coordinates, information acquisition module, data processing module, data Block, information storage module, power supply.Positioning device for mobile equipment includes GPS positioning module for measuring latitude and longitude coordinates, Laser Measuring Distance meter 27 acquire the spacing between ground control point be used to compensate height error, information acquisition module that GPS positioning module measures, Data processing module, data disaply moudle, information storage module, power supply.
Controlling partitioned project includes that engineering construction horizontal direction, vertical height change the partitioned project at place.
Such as the permanent building or structures of Fig. 3 fixed positions be column bottom 51 when, construction equipment is applied for creeping formwork The movements and postures of actors 52, main projects GPS positioning device are located at point O, and ground control point is point B, and mobility equipment GPS positioning device is located at Point A.The latitude and longitude coordinates of three can be measured by GPS module, and precision is higher, and the height of A points can be measured by laser range finder The distance of AB is measured, and the height of B points and O points is 0, and longitude and latitude is it is known that A points on climbing formwork for construction frame 52 move to A ' points because of construction When, the distance of known AB and A ' B are measured by laser range finder, while knowing A and A ' subpoint C latitude and longitude coordinates, i.e., The distance of known CB can be calculated the height for the right angled triangle being made of ACB by Pythagorean theorem and is made of A ' CB The height of right angled triangle, the point A height being calculated can compensate for the height error that GPS positioning module measures.
BIM work stations include BIM servers, BIM modeling modules, progress display module, information storage module, report management Module.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, not to The limitation present invention, all within the spirits and principles of the present invention made by all any modification, equivalent and improvement etc., should all include Within protection scope of the present invention.

Claims (6)

1. a kind of monitoring system of the engineering construction progress based on Internet of Things, including:Position pairing device, data processor, BIM Work station, positioning pairing device includes the permanent building for being placed in project control partitioned project or the controlling on structures Engineering positioning device and positioning device for mobile equipment;The positioning device for mobile equipment is placed in the permanent building or structure It builds on the construction equipment of object;The data processor exchanges data by public internet with the positioning pairing device, is used for The phasor difference for calculating the main projects positioning device and the positioning device for mobile equipment in positioning pairing device, by vector Difference is converted into project progress information;The data processor is connect with the BIM station datas, and BIM work stations receive data The project progress information of processor transmission, project progress information is shown in the BIM models of engineering;
A kind of monitoring method of the engineering construction progress based on Internet of Things, its step are as follows:
S1, the space coordinate (X acquired according to main projects positioning devicec,Yc,Zc) the structure main projects project BIM models;
S2, matching are placed in permanent building in same project controlling partitioned project or the positioning of the main projects on structures Device and positioning device for mobile equipment;
S3, the space coordinate (X acquired according to positioning device for mobile equipmentm,Ym,Zm), the movement is calculated by data processor Equipment positioning device and phasor difference between matched main projects positioning device, as matched main projects work Journey progress msg;
Project progress information described in S4, BIM workstation collection builds the project progress mould of the permanent building or structures Type.
2. monitoring system according to claim 1, which is characterized in that the main projects positioning device includes GPS fixed Position module, information acquisition module, data processing module, data disaply moudle, power supply and information storage module.
3. monitoring system according to claim 1, which is characterized in that the positioning device for mobile equipment includes GPS positioning Module, information acquisition module, data processing module, data disaply moudle, power supply and information storage module.
4. monitoring system according to claim 1, which is characterized in that the controlling partitioned project includes engineering construction Horizontal direction, vertical height change the partitioned project at place.
5. monitoring system according to claim 1, which is characterized in that the permanent building or structures include column bottom Portion or cantilever beam end.
6. monitoring system according to claim 1, which is characterized in that the construction equipment includes climbing formwork for construction frame or hangs Basket.
CN201810759910.6A 2018-07-11 2018-07-11 A kind of engineering construction Schedule monitoring system and method based on Internet of Things Pending CN108594730A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810759910.6A CN108594730A (en) 2018-07-11 2018-07-11 A kind of engineering construction Schedule monitoring system and method based on Internet of Things

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810759910.6A CN108594730A (en) 2018-07-11 2018-07-11 A kind of engineering construction Schedule monitoring system and method based on Internet of Things

Publications (1)

Publication Number Publication Date
CN108594730A true CN108594730A (en) 2018-09-28

Family

ID=63615361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810759910.6A Pending CN108594730A (en) 2018-07-11 2018-07-11 A kind of engineering construction Schedule monitoring system and method based on Internet of Things

Country Status (1)

Country Link
CN (1) CN108594730A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109413161A (en) * 2018-09-30 2019-03-01 温州锦丽斯企业有限公司 A kind of guideboard installation progress monitoring system
CN109709889A (en) * 2019-01-14 2019-05-03 江西集银科技有限公司 A kind of bridge hanging basket construction parameter intelligent monitor system and control method
CN111321902A (en) * 2020-02-26 2020-06-23 浙江锐博科技工程有限公司 System and method for hoisting components on assembly building construction site
CN114282909A (en) * 2022-01-04 2022-04-05 中广核工程有限公司 Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130155058A1 (en) * 2011-12-14 2013-06-20 The Board Of Trustees Of The University Of Illinois Four-dimensional augmented reality models for interactive visualization and automated construction progress monitoring
CN103226752A (en) * 2013-04-10 2013-07-31 中铁建设集团有限公司 Automatic real-time tracking method and automatic real-time tracking system for construction progress of house building
CN103455878A (en) * 2013-08-28 2013-12-18 哈尔滨工业大学 Method and device for construction progress network diagram real-time adjustment based on internet of things technology
CN106897453A (en) * 2017-03-08 2017-06-27 朱海涛 Engineering BIM progresses model and on-site supervision control methods
CN107818430A (en) * 2017-12-15 2018-03-20 武汉理工大学 A kind of building engineering construction progress msg management method and system based on BIM

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130155058A1 (en) * 2011-12-14 2013-06-20 The Board Of Trustees Of The University Of Illinois Four-dimensional augmented reality models for interactive visualization and automated construction progress monitoring
CN103226752A (en) * 2013-04-10 2013-07-31 中铁建设集团有限公司 Automatic real-time tracking method and automatic real-time tracking system for construction progress of house building
CN103455878A (en) * 2013-08-28 2013-12-18 哈尔滨工业大学 Method and device for construction progress network diagram real-time adjustment based on internet of things technology
CN106897453A (en) * 2017-03-08 2017-06-27 朱海涛 Engineering BIM progresses model and on-site supervision control methods
CN107818430A (en) * 2017-12-15 2018-03-20 武汉理工大学 A kind of building engineering construction progress msg management method and system based on BIM

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109413161A (en) * 2018-09-30 2019-03-01 温州锦丽斯企业有限公司 A kind of guideboard installation progress monitoring system
CN109413161B (en) * 2018-09-30 2021-07-27 温州锦丽斯企业有限公司 Guideboard installation progress monitoring system
CN109709889A (en) * 2019-01-14 2019-05-03 江西集银科技有限公司 A kind of bridge hanging basket construction parameter intelligent monitor system and control method
CN111321902A (en) * 2020-02-26 2020-06-23 浙江锐博科技工程有限公司 System and method for hoisting components on assembly building construction site
CN114282909A (en) * 2022-01-04 2022-04-05 中广核工程有限公司 Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method

Similar Documents

Publication Publication Date Title
CN108594730A (en) A kind of engineering construction Schedule monitoring system and method based on Internet of Things
CN105843228B (en) A kind of the map sharing method and system of clean robot
CN109782225B (en) Method for positioning coordinates of base station
CN109640256A (en) Layered stereoscopic monitoring method and system based on UWB positioning
CN105467359B (en) The method, apparatus and system of bluetooth positioning
CN108090959A (en) Indoor and outdoor one modeling method and device
CN110006424B (en) High-flux crop phenotype robot based on field and control system thereof
CN206772257U (en) A kind of bridge section model system based on High Performance Unmanned Aerial Vehicle
CN106447182A (en) Survey and design system generating chart uploading information automatically
CN107506724A (en) Inclination angle detection method and detection terminal
CN106384380A (en) 3D human body scanning, modeling and measuring method and system
CN110516304B (en) Indoor space modeling method
CN112287053A (en) System and method for collecting and processing surveying and mapping operation data in real time
CN209142388U (en) A kind of UAV system for BIM
CN107328416A (en) A kind of smart mobile phone real-time location method based on earth magnetism
CN112504236A (en) Unmanned aerial vehicle aerial photography power distribution network area surveying and mapping method
CN209250894U (en) Layered stereoscopic based on UWB positioning monitors system
CN109858184B (en) Sunlight simulation analysis system by means of oblique photography technology
CN206321246U (en) The general surveying instrument of distributed interactive
CN206132070U (en) Ally oneself with with three -dimensional gesture system of formula
CN115096266A (en) High-precision underground pipeline obvious point positioning and mapping device and method
CN206369811U (en) A kind of high-precision deformation monitoring device positioned based on the Big Dipper
CN206470405U (en) A kind of high-precision RTK satellite surveying and mappings system for being used to measure Target space position coordinate
TW469392B (en) Computer-aided synchronous measuring method
CN108519051A (en) A kind of box beam measurement method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928