CN108555129A - Aluminium foil equipment for wrapping and system - Google Patents
Aluminium foil equipment for wrapping and system Download PDFInfo
- Publication number
- CN108555129A CN108555129A CN201810568798.8A CN201810568798A CN108555129A CN 108555129 A CN108555129 A CN 108555129A CN 201810568798 A CN201810568798 A CN 201810568798A CN 108555129 A CN108555129 A CN 108555129A
- Authority
- CN
- China
- Prior art keywords
- slide rail
- aluminium foil
- cylinder
- horizontal slide
- pressure mechanism
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000005030 aluminium foil Substances 0.000 title claims abstract description 116
- 230000007246 mechanism Effects 0.000 claims abstract description 82
- 238000001179 sorption measurement Methods 0.000 claims abstract description 60
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 25
- 239000011248 coating agent Substances 0.000 claims abstract description 10
- 238000000576 coating method Methods 0.000 claims abstract description 10
- 239000011230 binding agent Substances 0.000 claims description 36
- 238000009434 installation Methods 0.000 claims description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 2
- 238000000034 method Methods 0.000 abstract description 7
- 230000008569 process Effects 0.000 abstract description 6
- 241000209140 Triticum Species 0.000 description 9
- 235000021307 Triticum Nutrition 0.000 description 9
- 230000001276 controlling effect Effects 0.000 description 8
- 238000010586 diagram Methods 0.000 description 8
- 210000004276 hyalin Anatomy 0.000 description 7
- 239000012528 membrane Substances 0.000 description 7
- 238000010521 absorption reaction Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 3
- 238000011161 development Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 239000004744 fabric Substances 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 230000001105 regulatory effect Effects 0.000 description 3
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000012545 processing Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 239000002390 adhesive tape Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 235000013361 beverage Nutrition 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 235000019504 cigarettes Nutrition 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 239000003814 drug Substances 0.000 description 1
- 229940079593 drug Drugs 0.000 description 1
- 235000013305 food Nutrition 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 239000011810 insulating material Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000005022 packaging material Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D33/00—Special measures in connection with working metal foils, e.g. gold foils
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D43/00—Feeding, positioning or storing devices combined with, or arranged in, or specially adapted for use in connection with, apparatus for working or processing sheet metal, metal tubes or metal profiles; Associations therewith of cutting devices
- B21D43/003—Positioning devices
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Basic Packing Technique (AREA)
Abstract
The invention discloses a kind of aluminium foil equipment for wrapping, the aluminium foil equipment for wrapping includes a pedestal, a positioning adsorption jig, a horizontal sliding equipment, one first feeding pressure mechanism and one second feeding pressure mechanism.The horizontal sliding equipment includes two horizontal slide rails being divided at the positioning adsorption jig both ends, a sliding block that can be slided on the horizontal slide rail is respectively provided at the rear and front end of each horizontal slide rail, the both ends of first feeding pressure mechanism are respectively arranged on the sliding block of horizontal slide rail front end, and the both ends of second feeding pressure mechanism are respectively arranged on the sliding block of horizontal slide rail rear end.Aluminium foil equipment for wrapping of the present invention is by positioning adsorption jig to fix the aluminium foil for needing bound edge to process, pass through the cooperation of the first feeding pressure mechanism and the second feeding pressure mechanism, realize the operation of aluminium foil bound edge, without manual operations, reduce artificial input, it is easy to operate succinct, and be conducive to improve working efficiency and product quality.The invention also discloses a kind of aluminium foil edge-coating systems.
Description
Technical field
The present invention relates to aluminium foil manufacture field of mechanical technique more particularly to a kind of aluminium foil equipment for wrapping and systems.
Background technology
Aluminium foil is widely used in food, beverage, cigarette, drug, photographic plate, family daily necessity because of its excellent characteristic
Deng being typically used as its packaging material.And in order to make preferably to meet customer need in aluminium foil process, production is improved, is needed
Bound edge processing is carried out to aluminium foil, wherein aluminium foil bound edge is to coat aluminium foil using insulating materials.
Current aluminium foil bound edge process uses manually operated mode, and artificial aluminium foil bound edge has artificial input big but work
Make the low problem of efficiency, and employee's long working is easy fatigue, product quality is unable to get guarantee so that yields is low,
To limit the development of aluminium foil production industry.
In consideration of it, it is necessary to provide a kind of aluminium foil equipment for wrapping solving drawbacks described above and system, to reduce artificial throw
Enter and aluminium foil bound edge difficulty of construction, raising working efficiency and yields.
Invention content
A technical problem to be solved by this invention is to provide a kind of aluminium foil equipment for wrapping and system to reduce Aluminium Foil Package
The artificial input and difficulty of construction of side work, improve working efficiency and product yield.
In order to solve the above technical problems, the present invention uses technical solution as described below:A kind of aluminium foil equipment for wrapping, it is described
Aluminium foil equipment for wrapping includes a pedestal, a positioning adsorption jig, a horizontal sliding equipment, one first feeding pressure mechanism and one second
Feeding pressure mechanism.Wherein, the positioning adsorption jig is set on the pedestal, to adsorb fixed aluminium foil;The horizontal skate machine
Structure includes two horizontal slide rails being divided at the positioning adsorption jig both ends, is respectively set at the rear and front end of each horizontal slide rail
There is a sliding block that can be slided on the horizontal slide rail;The both ends of first feeding pressure mechanism are respectively arranged at positioned at horizontal slide rail
On the sliding block of front end, to be set at the top of the positioning adsorption jig side and be slided along the horizontal slide rail;Described
The both ends of two feeding pressure mechanisms are respectively arranged on the sliding rail of horizontal slide rail rear end, are arranged with correspondence first feeding pressure mechanism
It is slided at the top of the positioning adsorption jig other side and along the horizontal slide rail.
Its further technical solution is:The horizontal sliding equipment further includes having the first cylinder and the second cylinder, and described
The piston rod of one cylinder is connect with first feeding pressure mechanism or the sliding block positioned at horizontal slide rail front end to drive described
One feeding pressure mechanism is slided along the horizontal slide rail, the piston rod and the second feeding pressure mechanism of second cylinder or described positioned at level
The sliding block of sliding rail rear end is connected to drive second feeding pressure mechanism to be slided along the horizontal slide rail.
Its further technical solution is:First feeding pressure mechanism includes the first binder component and the first vertical shift group
Part, the first vertical shift component connect with the first binder component and is set to the top of the positioning adsorption jig, with control
The first binder component is made vertically to move;Second feeding pressure mechanism includes the second binder component and the second vertical shift group
Part, the second vertical shift component is connected with the second binder component and corresponding first feeding pressure mechanism is set to the positioning
The top of adsorption jig is vertically moved with controlling the second binder component.
Its further technical solution is:The first binder component include one first connecting plate, one first squeegee base and
One is fixedly installed in the first scraper plate in first squeegee base, and first scraper plate is installed on first squeegee base and leans on
The side of nearly positioning adsorption jig, first connecting plate are set to the other side of first squeegee base, and described first connects
The both ends of fishplate bar are set to by one first cushion block described on the sliding block of horizontal slide rail front end respectively;The second binder group
Part includes one second connecting plate, one second squeegee base and one is fixedly installed in the second scraper plate in second squeegee base,
Second scraper plate is installed on second squeegee base close to the side of positioning adsorption jig, and second connecting plate is set to
The both ends of the other side of second squeegee base, second connecting plate are set to described be located at by one second cushion block respectively
On the sliding block of horizontal slide rail rear end.
Its further technical solution is:The number of first cylinder is one, and the cylinder barrel of first cylinder passes through one
Fixed frame is installed on the pedestal and the piston rod of first cylinder is connect with the first squeegee base;Second cylinder
Number is two, and every 1 second cylinder is installed on the side of the horizontal slide rail and the work of second cylinder by positioning piece
Stopper rod is connect with the sliding block positioned at horizontal slide rail rear end.
Its further technical solution is:The first vertical shift component includes the first upright slide rail and is set to described the
The first top shoe on one upright slide rail, first upright slide rail are set on the cushion block of the horizontal slide rail front end,
First top shoe is connect with the first squeegee base, is moved along the first upright slide rail track for the first binder component;Institute
It includes the second upright slide rail and the second top shoe for being set on second upright slide rail to state the second vertical shift component, described
Second upright slide rail is set on the cushion block of the horizontal slide rail rear end, and second top shoe and the second squeegee base connect
It connects, is moved along the second upright slide rail track for the second binder component.
Its further technical solution is:The first vertical shift component further includes having third cylinder, the third cylinder
Piston rod connect with the first squeegee base to drive the first binder component to be slided along first upright slide rail;Described
Two vertical shift components further include having the 4th cylinder, and the piston rod of the 4th cylinder is connect with the second squeegee base to drive
The second binder component is stated to slide along second upright slide rail.
Its further technical solution is:The positioning adsorption jig upper surface is provided along its length locating slot, described
The bottom surface for positioning adsorption jig is equipped with a through-hole, and the through-hole surrounding is downwardly extending an interface, and the pedestal, which is equipped with one, to be held
The perforation that the interface passes through.
In order to solve the above technical problems, the present invention also provides a kind of aluminium foil edge-coating system, the aluminium foil edge-coating system includes
Have an aluminium foil equipment for wrapping, a pressure vacuum tank and a vacuum pump, the pressure vacuum tank respectively with the aluminium foil bound edge
Equipment and vacuum pump connection.
The beneficial technical effect of the present invention lies in:Aluminium foil equipment for wrapping of the present invention is adsorbed solid by a positioning adsorption jig
Determine aluminium foil, by the cooperation of the first feeding pressure mechanism and the second feeding pressure mechanism, realizes the bound edge operation of aluminium foil, without hand-manipulated,
Artificial input is reduced, working efficiency and product quality are improved.Meanwhile aluminium foil edge-coating system provided by the invention also has above-mentioned work(
Can, be conducive to the development for accelerating aluminium foil technology, bring good economic benefit.
Description of the drawings
Fig. 1 is the structural schematic diagram of one specific embodiment of aluminium foil equipment for wrapping of the present invention.
Fig. 2 is the vertical view of aluminium foil equipment for wrapping shown in Fig. 1.
Fig. 3 is the front view of aluminium foil equipment for wrapping shown in Fig. 1.
Fig. 4 is the structure schematic diagram of aluminium foil equipment for wrapping shown in Fig. 1.
Fig. 5 is the bottom surface structure schematic diagram of aluminium foil equipment for wrapping shown in Fig. 1.
Fig. 6 is the structural schematic diagram of the positioning adsorption jig of aluminium foil equipment for wrapping shown in Fig. 1.
Fig. 7 is the enlarged diagram of part A shown in Fig. 6.
Fig. 8 is the structural schematic diagram of the aluminium foil cutting part of embodiment illustrated in fig. 1.
Fig. 9 is the side layered structure schematic diagram of aluminium foil cutting part shown in Fig. 8.
Figure 10 is the structural schematic diagram of one specific embodiment of aluminium foil edge-coating system of the present invention.
Specific implementation mode
To make those skilled in the art that the object, technical solutions and advantages of the present invention be more clearly understood, with
Under the present invention is further elaborated in conjunction with the accompanying drawings and embodiments, similar reference numerals represent similar component in attached drawing.
Obviously, will be described below embodiment is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the present invention
In embodiment, every other implementation obtained by those of ordinary skill in the art without making creative efforts
Example, shall fall within the protection scope of the present invention.
Referring to figs. 1 to Fig. 4, in the present embodiment, aluminium foil equipment for wrapping 10 includes that a pedestal 100, one positions adsorption jig
110, a horizontal sliding equipment 140, one first feeding pressure mechanism 120 and one second feeding pressure mechanism 130.Wherein, the positioning absorption
Jig 110 is set on the pedestal 100, with the fixed aluminium foil for needing bound edge to process of absorption.
In the present embodiment, horizontal sliding equipment 140 includes two water being divided at 110 both ends of positioning adsorption jig
Smooth base of the rail seat 141 and two is divided into the horizontal slide rail 142 on the horizontal slide rail pedestal 141, before each horizontal slide rail 142
Both ends are respectively provided with a sliding block 143 that can be slided on the horizontal slide rail 142 afterwards.The both ends of first feeding pressure mechanism 120 point
It is not set on the sliding block 143 of 142 front end of horizontal slide rail, to be set at the top of 110 side of positioning adsorption jig simultaneously
It is slided along the track of the horizontal slide rail 142;The both ends of second feeding pressure mechanism 130 are respectively arranged at positioned at horizontal slide rail
On the sliding block 143 of 142 rear ends, 110 other side of positioning adsorption jig is set to correspond to first feeding pressure mechanism 120
Top at and along the track of the horizontal slide rail 142 slide.Preferably, the sliding block 143 is equipped with cushion block 148, and described the
The both ends of one feeding pressure mechanism 120 and the both ends of the second feeding pressure mechanism 130 are respectively arranged on corresponding cushion block 148.
Certainly, in other embodiments, the horizontal slide rail 142 can be not necessarily to be installed on horizontal slide rail pedestal 141, and straight
It connects and is set on the pedestal 100 at 110 both ends of the positioning adsorption jig.The horizontal sliding equipment 140 uses two horizontal slide rails
142 setting, it can be ensured that the first feeding pressure mechanism 120 and the second feeding pressure mechanism 130 sliding steady and smooth, improve working efficiency and
Processing effect.
Wherein, the horizontal sliding equipment 140 further include it is at least one connect with first feeding pressure mechanism 120 or with institute
Rheme in 142 front end of horizontal slide rail sliding block 143 connect with drive the first feeding pressure mechanism 120 along the track of horizontal slide rail 142
First cylinder 144 of sliding and it is at least one connect with second feeding pressure mechanism 130 or with described positioned at horizontal slide rail 142
The second cylinder 145 to drive the second feeding pressure mechanism 130 to be slided along the track of horizontal slide rail 142 that the sliding block 143 of rear end connects.
In conjunction with Fig. 1 to Fig. 4, in the present embodiment, the horizontal sliding equipment 140 is set to first feeding pressure mechanism 120 including one
The first cylinder 144 and two on the pedestal 100 in front is divided into the second cylinder 145 on the horizontal slide rail 142, and described first
The cylinder barrel of cylinder 144 is installed on the pedestal 100 by a fixed frame 1441 and the piston rod of the first cylinder 144 and described the
One feeding pressure mechanism 120 connects so that the first feeding pressure mechanism 120 is according to the working condition of piston rod along the horizontal slide rail 142
Track is slided, and the cylinder barrel of second cylinder 145 is installed on side and the second cylinder of horizontal slide rail 142 by locating piece 146
145 piston rod is connect by a connection piece 147 with the cushion block 148 on the sliding block 143 of 142 rear end of horizontal slide rail,
So that the second feeding pressure mechanism 130 is slided according to the working condition of piston rod along the track of the horizontal slide rail 142.Preferably, institute
Stating the first cylinder 144 uses CDJ2B16-75 cylinders, second cylinder 145 to use CDU16-20 cylinders.
Certainly, in some embodiments, the number of first cylinder 144 can be two, and two first cylinders 144 divide
It is not installed on the side of two horizontal slide rails 142 and its piston rod is connect with the sliding block 143 positioned at 142 front end of horizontal slide rail.
In other embodiments, the number of first cylinder 144 can be multiple, and the cylinder barrel of first cylinder 144 passes through fixation
Frame 1441 is installed on the pedestal 100 along the length direction of positioning adsorption jig 110 and the piston rod of first cylinder 144
It is connect with the first feeding pressure mechanism 120.In some embodiments, the number of second cylinder 145 can be one, described second
The cylinder barrel of cylinder 145 is installed on the pedestal 100 by fixed frame 1441 and its piston rod and second feeding pressure mechanism 130
Connection.In other embodiments, the number of second cylinder 145 can be multiple, and the cylinder barrel of second cylinder 145 passes through
Fixed frame 1441 is installed on the pedestal 100 along the length direction of positioning adsorption jig 110 and the work of second cylinder 145
Stopper rod is connect with the second feeding pressure mechanism 130.
With continued reference to Fig. 1 to Fig. 4, specifically, in the present embodiment, first feeding pressure mechanism 120 includes the first binder
Component 121 and two first vertical shift components 122, the two first vertical shift components 122 with the first binder component
121 connect and are set at the top of the positioning adsorption jig 110, are vertically slided with controlling the first binder component 121
It is dynamic.Wherein, the first binder component 121 includes one first connecting plate 1211, one first squeegee base 1212 and one fixation peace
Loaded on the first scraper plate 1213 in first squeegee base 1212, first scraper plate 1213 is installed on the first scraper plate base
The side of the close positioning adsorption jig 110 of seat 1212, first connecting plate 1211 are set to first squeegee base
1212 other side, the both ends of first connecting plate 1211 are set to the level that is located at by the cushion block 148 respectively and slide
On the sliding block 143 of 142 front end of rail, the piston rod of first cylinder 144 is connect with the first squeegee base 1212, is realized and is utilized the
One cylinder 144 drives first feeding pressure mechanism 120 to be slided along the track of the horizontal slide rail 142.
The first vertical shift component 122 include one perpendicular to the horizontal slide rail 142 the first upright slide rail 1221
And one be set to the first top shoe 1222 on first upright slide rail 1221, first upright slide rail 1221 is by one
Sliding rail pedestal 1224 is set on the cushion block 148 of 142 front end of the horizontal slide rail, specifically, the upper sliding rail pedestal
1224 bottom surface is installed on the cushion block 148, and side is provided with first upright slide rail 1221, first top shoe
1222 are set on first upright slide rail 1221 and are connect with the other side of the first squeegee base 1212, for first pressure
Expect that component 121 is slided along the track of the first upright slide rail 1221, to be carried out to adsorbing fixed aluminium foil in positioning adsorption jig 110
Bound edge operates.Preferably, in the present embodiment, the first vertical shift component 122 further includes for driving first pressure
Expect the third cylinder 1223 that component 121 is slided along the track of the first upright slide rail 1221, the cylinder barrel bottom of the third cylinder 1223
Portion is set on the first connecting plate 1211 and the piston rod of third cylinder 1223 passes through a drive connection portion 124 and the first scraper plate base
Seat 1212 connects so that the first squeegee base 1212 can be vertical along first according to the working condition of the piston rod of third cylinder 1223
The track of sliding rail 1221 is slided, and to drive the sliding of the first scraper plate 1213, realizes the operation of aluminium foil bound edge.Certainly, in other implementations
In example, the cylinder barrel of the third cylinder 1223 is mountable on the cushion block 148 of 142 front end of the horizontal slide rail and its piston
Bar is connect with the first squeegee base 1212.
In some embodiments, the number of the first vertical shift component 122 can be one or more, and described first is perpendicular
Straight moving assembly 122 may be disposed on first connecting plate 1211 and uniformly be arranged along the length direction of the first connecting plate 1211
Cloth.
With continued reference to Fig. 1 to Fig. 4, specifically, in the present embodiment, second feeding pressure mechanism 130 includes the second binder
Component 131 and two second vertical shift components 132, the two second vertical shift components 132 with the second binder component
131 connect and are set at the top of the positioning adsorption jig 110, are vertically slided with controlling the second binder component 131
It is dynamic.Wherein, the second binder component 131 includes one second connecting plate 1311, one second squeegee base 1312 and one fixation peace
Loaded on the second scraper plate 1313 in second squeegee base 1312, second scraper plate 1313 is installed on the second scraper plate base
The side of the close positioning adsorption jig 110 of seat 1312, second connecting plate 1311 are set to second squeegee base
1312 other side, the both ends of second connecting plate 1311 are set to the level that is located at by the cushion block 148 respectively and slide
On the sliding block 143 of 142 rear end of rail, realize that second feeding pressure mechanism 130 is slided along the track of horizontal slide rail 142.
The second vertical shift component 132 include one perpendicular to the horizontal slide rail 142 the second upright slide rail 1321
And one be set to the second top shoe 1322 on second upright slide rail 1321, second upright slide rail 1321 is set to position
In on the cushion block 148 of 142 rear end of the horizontal slide rail, second top shoe 1322 is set to second upright slide rail 1321
It above and with the other side of the second squeegee base 1312 connect, for the second binder component 131 along the second upright slide rail 1321
Track is slided, to carry out bound edge operation to adsorbing fixed aluminium foil in positioning adsorption jig 110.Preferably, in the present embodiment,
The second vertical shift component 132 further includes for driving the second binder component 131 along the second upright slide rail 1321
4th cylinder 1323 of track sliding, the cylinder barrel of the 4th cylinder 1323 are installed on by a fixing piece 125 positioned at the water
On the cushion block 148 of smooth 142 rear end of rail and the piston rod of the 4th cylinder 1323 passes through a drive connection part 134 and the second scraper plate base
Seat 1312 connects so that the second squeegee base 1312 can be vertical along second according to the working condition of the piston rod of the 4th cylinder 1323
The track of sliding rail 1321 is slided, and to drive the sliding of the second scraper plate 1313, realizes the operation of aluminium foil bound edge.Certainly, in other implementations
In example, the cylinder barrel bottom of the 4th cylinder 1323 can be fixedly installed on second connecting plate 1311 and its piston rod and the
Two squeegee bases 1312 connect.
In some embodiments, the number of the second vertical shift component 132 can be one or more, and described second is perpendicular
Straight moving assembly 132 may be disposed on second connecting plate 1311 and uniformly be arranged along the length direction of the second connecting plate 1311
Cloth.
Since first cylinder 144, the second cylinder 145, third cylinder 1223 and the 4th cylinder 1323 are cylinder, then
The aluminium foil equipment for wrapping 10 further includes the solenoid valve module 180 for having control cylinder operation switch, and the solenoid valve module 180 is set
It is placed on the pedestal 100, the solenoid valve module 180 includes that there are four solenoid valves, respectively the first solenoid valve 181, second
Solenoid valve 182, third solenoid valve 183 and the 4th solenoid valve 184.Wherein, first solenoid valve, 181 and first cylinder 144 connects
It connects, second solenoid valve 182 is connect with the third cylinder 1223, the aluminium foil bound edge work for controlling the first feeding pressure mechanism 120;
The third solenoid valve 183 is connect with second cylinder 145, and the 4th solenoid valve 184 is connect with the 4th cylinder 1323, is used
In the aluminium foil bound edge work for controlling the second feeding pressure mechanism 130.Each solenoid valve is connected with corresponding cylinder, for controlling each gas
The break-make of compressed air in cylinder, to which the work of the aluminium foil bound edge of the first feeding pressure mechanism 120 of control and the second feeding pressure mechanism 130 starts
And stopping, setting solenoid valve can facilitate installation in the form of solenoid valve module 180, while can save installation space.The aluminium
Foil equipment for wrapping 10 further includes having air source regulating valve 190, and the air source regulating valve 190 is installed on the pedestal 100 and difference
It is connect with each cylinder, the size for adjusting compressed air pressure in cylinder, so that cylinder is effectively run, prevents air pressure is too small from making
Product quality declines, while the damage for avoiding air pressure excessive to cylinder, improves the first feeding pressure mechanism 120 and the second feeding pressure mechanism
The accuracy of 130 aluminium foil bound edges operation.In the present embodiment, the air source regulating valve 190 is connect with each cylinder, to control cylinder
The pressure of interior compressed air is 0.5kgf/cm2。
With continued reference to Fig. 1 to Fig. 4, in the present embodiment, the time relay, the time are additionally provided on the pedestal 100
Relay is connect with solenoid valve module 180, for presetting the aluminium foil bound edge time and according to preset time to accurately control the first pressure
Expect the aluminium foil bound edge operation of mechanism 120 and the second feeding pressure mechanism 130.The time relay includes the first AH-3 time relays
161, the 2nd AH-3 time relays 162, the first H3Y time relays 163 and the 2nd H3Y time relays 164.Wherein, AH-
3 time relays and the H3Y time relays belong to the on-delay type time relay, immediately begin to prolong after obtaining input signal
When, it need to wait for that delay finishes, execution part ability output signal is with manipulation and control circuit;After input signal disappears, relay is vertical
The state being restored to before action.The first AH-3 time relays 161 and first solenoid valve 181 connection, described the
The two AH-3 time relays 162 and the second solenoid valve 182 connect, the first H3Y time relays 163 and the third
Solenoid valve 183 connects, the 2nd H3Y time relays 164 and the 4th solenoid valve 184 connection.
The 2nd AH-3 time relays 162 are connected to the first AH-3 time relays 161 and the first H3Y time relays
Between device 163, output signal for obtaining the first AH-3 time relays simultaneously outputs signal to the first H3Y time relays
163, the 2nd H3Y time relays 164 and the first H3Y time relays 163 are electrically connected, for obtaining described first
The output signal of the H3Y time relays 163 is sequentially worked between each time relay with realizing, i.e., when described first
The AH-3 time relays 161 work after the completion of, the 2nd AH-3 time relays 162 start to work, and the 2nd AH-3 times after
After the completion of electric appliance 162 works, the first H3Y time relays 163 are started to work, and the first H3Y time relays 163 have worked
Cheng Hou, the 2nd H3Y time relays 164 are started to work.
The aluminium foil equipment for wrapping 10 further includes having intermediate relay, and the intermediate relay is set on pedestal 100,
In the present embodiment, the number of the intermediate relay is two, respectively the first intermediate relay 171 and the second intermediate relay
172, first intermediate relay 171 is connected between the first AH-3 time relays 161 and first solenoid valve 181,
For when the first AH-3 time relays 161 receive electric signal, starting to control the start-up operation of the first solenoid valve 181,
It works to control first cylinder 144, is inhaled to positioning along the track of horizontal slide rail 142 with controlling the first feeding pressure mechanism 120
The time that attached jig 110 moves;First intermediate relay 171 is connected to the 2nd AH-3 time relays 162 and described
Between two solenoid valves 182, second solenoid valve is controlled for when the 2nd AH-3 time relays 162 receive electric signal, starting
182 start to work, and work to control the third cylinder 1223, to control the first feeding pressure mechanism 120 along the first upright slide rail
The time that 1221 track is moved to positioning adsorption jig 110, to accurately control the aluminium foil bound edge behaviour of the first feeding pressure mechanism 120
Make.Second intermediate relay 172 is connected between the first H3Y time relays 163 and the third solenoid valve 183, is used
It starts to work in when the first H3Y time relays 163 receive electric signal, starting control third solenoid valve 183, to control
Second cylinder 145 works, to control the second feeding pressure mechanism 130 along the track of horizontal slide rail 142 to positioning adsorption jig 110
The mobile time;Second intermediate relay 172 is connected to the 2nd H3Y time relays 164 and the 4th solenoid valve 184
Between, the start-up operation of the 4th solenoid valve 184 is controlled for when the 2nd H3Y time relays 164 receive electric signal, starting,
To control the 4th cylinder 1323 work, with control the second feeding pressure mechanism 130 along the track of the second upright slide rail 1321 to
The time that adsorption jig 110 moves is positioned, to accurately control the aluminium foil bound edge operation of the second feeding pressure mechanism 130.
Wherein, the intermediate relay is connected between the time relay and solenoid valve module 180, for detection time after
Electric appliance realizes circuit control self-locking function so that the electric current in circuit is more stable, and when intermediate relay test to time after
When electric appliance obtains electric, then corresponding electromagnetic valve work is controlled, time relay time-delay characteristics, realization is coordinated to accurately control aluminium foil bound edge
The time of operation improves working efficiency and product yield.
Specifically, in the present embodiment, the aluminium foil equipment for wrapping 10 further includes having power module 101 and start button
102, the start button 102 is connected between the power module 101 and the first AH-3 time relays 161, is used for
The conducting for controlling 161 working power of the first AH-3 time relays, to control the beginning of aluminium foil bound edge operation.
With reference to Fig. 5 to Fig. 7, in the present embodiment, the upper surface of the positioning adsorption jig 110 is provided along its length
Locating slot 111, the locating slot 111 and the aluminium foil for needing bound edge to process are same wide, and multiple suction holes are provided in the locating slot 111
1111, the suction hole 1111 is used to the aluminium foil for needing bound edge to process being adsorbed in locating slot 111.The positioning adsorption jig
110 bottom surface is equipped with a through-hole 112, and 112 surrounding of the through-hole is downwardly extending an interface 113, for connecting press device
To change the atmospheric pressure state in positioning adsorption jig 110, in conjunction with suction hole 111 to realize the absorption of aluminium foil, correspondingly, the bottom
Seat 100 is equipped with one and holds the perforation 150 that the interface 113 passes through.Preferably, 110 upper surface of positioning adsorption jig is grown along it
Degree direction is in being uniformly placed with positioning pin 115, for making aluminium foil preferably be adsorbed in positioning adsorption jig 110.
Specifically, as shown in Figure 8 and Figure 9, the area that posts on one side of aluminium foil draws 211 more than the wheat of aluminium foil, and formation needs bound edge
Aluminium foil 210, wherein it is 3M1318 adhesive tapes that wheat, which is drawn, and multiple another sides for needing bound edge aluminium foil 210 fix row by a hyaline membrane 220
Cloth, forms aluminium foil cutting part 20, and hyaline membrane 220 is equipped with and 115 the same number of location hole 221, Yong Huke of the positioning pin
By the way that location hole 221 is arranged in the positioning pin 115 so that aluminium foil cutting part 20 is accurately positioned over the positioning adsorption jig
In 110 locating slot 111.Preferably, the material of the hyaline membrane 220 is low viscous transparent PET.
In conjunction with Fig. 2, Fig. 6 and Fig. 8, in the present embodiment, there are five need bound edge aluminium foil for the arrangement of aluminium foil cutting part 20
210, the number of the positioning pin 115 is five.Certainly, in other embodiments, the number of the positioning pin 115 can be one
Or it is multiple.
Referring to Fig.1 0, the invention also discloses a kind of aluminium foil edge-coating system 30, the aluminium foil edge-coating system 30 includes one
The aluminium foil equipment for wrapping 10, a pressure vacuum tank 310 and a vacuum pump 320, the vacuum pump 320 and pressure vacuum tank 310
Connection, vacuum state is obtained for being evacuated to pressure vacuum tank 310.The pressure vacuum tank 310 passes through pipeline and institute
The interface 113 for stating positioning adsorption jig 110 connects, to realize the control of the internal air pressure of positioning adsorption jig 110.Its
In, it is provided with a vacuum solenoid 312 for being connected to floor push 313 on the pipeline, is controlled very for passing through floor push 313
The switch of empty solenoid valve 312, to control the break-make that positioning adsorption jig 110 is connect with 310 pipeline of pressure vacuum tank, it is fixed to realize
The control of the internal air pressure of position adsorption jig 110.
Based on above-mentioned design, the flow of aluminium foil bound edge operation may include following steps:
User by aluminium foil cutting part with hyaline membrane upward and wheat draws state directed downwardly to be positioned in positioning adsorption jig.Specifically
Location hole on the hyaline membrane of aluminium foil cutting part is arranged in the positioning pin of positioning adsorption jig, aluminium foil is die cut by ground, user
Part with hyaline membrane upward and wheat draws state directed downwardly to be accurately positioned in the locating slot.User steps on floor push so that true
Empty solenoid valve is opened, and the pipeline between pressure vacuum tank and positioning adsorption jig is connected, and vacuum pump is by pressure vacuum tank to fixed
Air in the adsorption jig of position is evacuated, and in conjunction with the suction hole on locating slot, aluminium foil cutting part is adsorbed in locating slot.
User takes the hyaline membrane of aluminium foil cutting part off so that the wheat at aluminium foil edge is drawn and holds up.
User presses start button, controls the first feeding pressure mechanism and the second feeding pressure mechanism by the Mai Labao holded up in aluminium foil
On.Specifically, user presses start button so that the first AH-3 time relays obtain working power, control the first AH-
3 time relays work, and start timing, coordinate intermediate relay, the piston rod movement of control CDJ2B16-75 cylinders so that the
One feeding pressure mechanism is moved along the track of horizontal slide rail to positioning adsorption jig, to draw in the horizontal direction the wheat holded up towards needing to wrap
Side aluminium foil folds, when the delay timing of the first AH-3 time relays terminates and outputs signal to the first solenoid valve, the first binder
Mechanism stopping moves horizontally, and the work of the 2nd AH-3 time relays starts timing, controls third cylinder operation so that the first pressure
Mechanism is expected vertically to positioning adsorption jig movement, thus by the wheat tension and compression of folding to bound edge aluminium foil is needed, as the 2nd AH-3
When time relay delay timing terminates and outputs signal to second solenoid valve, the first feeding pressure mechanism stops vertical shift, at this time
The Mai Layu of folding needs bound edge aluminium foil smooth, realizes the operation of aluminium foil bound edge;First feeding pressure mechanism resets;First H3Y time relays
Device obtains the output signal of the 2nd AH-3 time relays, controls the first H3Y time relays work, starts timing, match
Close intermediate relay, control CDU16-20 cylinders piston rod movement so that the second feeding pressure mechanism along the track of horizontal slide rail to
Adsorption jig movement is positioned, to draw the wheat holded up in the horizontal direction towards needing bound edge aluminium foil to fold, when the first H3Y time relays
When terminating and outputing signal to third solenoid valve, the stopping of the second feeding pressure mechanism moves horizontally for device delay timing, the 2nd H3Y times after
Electrical work starts timing, controls the 4th cylinder operation so that the second feeding pressure mechanism is vertically moved to positioning adsorption jig
It is dynamic, thus by the wheat tension and compression of folding to bound edge aluminium foil is needed, when the delay timing of the 2nd AH-3 time relays terminates simultaneously output signal
When to four solenoid valves, the second feeding pressure mechanism stops vertical shift, and the Mai Layu folded at this time needs bound edge aluminium foil smooth, realizes aluminium
Foil bound edge operates;Second feeding pressure mechanism resets, and completes the operation of aluminium foil bound edge.
User takes out the aluminium foil of bound edge.Specifically, user unclamps floor push, and control vacuum solenoid is stopped,
And the aluminium foil of bound edge is taken out.
In conclusion aluminium foil equipment for wrapping of the present invention positions adsorption jig to adsorb fixed aluminium foil by one, pass through first
The bound edge operation of aluminium foil is realized in the cooperation of feeding pressure mechanism and the second feeding pressure mechanism, without manual operations, reduces artificial input, knot
The time relay and intermediate relay are closed, the bound edge operating time is accurately controlled, improves working efficiency and product quality.Meanwhile
Aluminium foil edge-coating system provided by the invention also has above-mentioned function, is conducive to the development for accelerating aluminium foil technology, brings
Good economic benefit.
The foregoing is merely the preferred embodiment of the present invention, rather than do limitation in any form to the present invention.This field
Technical staff can impose various equivalent changes and improvement, all institutes within the scope of the claims on the basis of the above embodiments
The equivalent variations done or modification should all be fallen under the scope of the present invention.
Claims (9)
1. a kind of aluminium foil equipment for wrapping, which is characterized in that the aluminium foil equipment for wrapping includes:
One pedestal;
One positioning adsorption jig, is set on the pedestal, to adsorb fixed aluminium foil;
One horizontal sliding equipment comprising have two horizontal slide rails being divided at the positioning adsorption jig both ends, each level
A sliding block that can be slided on the horizontal slide rail is respectively provided at the rear and front end of sliding rail;
One first feeding pressure mechanism, both ends are respectively arranged on the sliding block of horizontal slide rail front end, to be set to the positioning
It is slided at the top of adsorption jig side and along the horizontal slide rail;
One second feeding pressure mechanism, both ends are respectively arranged on the sliding block of horizontal slide rail rear end, with correspondence first pressure
Material mechanism is set at the top of the positioning adsorption jig other side and is slided along the horizontal slide rail.
2. aluminium foil equipment for wrapping as described in claim 1, it is characterised in that:The horizontal sliding equipment further includes having the first gas
Cylinder and the second cylinder, the piston rod of first cylinder and first feeding pressure mechanism or the cunning positioned at horizontal slide rail front end
Block is connected to drive first feeding pressure mechanism to be slided along the horizontal slide rail, the piston rod of second cylinder and described second
Feeding pressure mechanism or the sliding block positioned at horizontal slide rail rear end are connected to drive second feeding pressure mechanism along the horizontal slide rail
Sliding.
3. aluminium foil equipment for wrapping as claimed in claim 2, it is characterised in that:First feeding pressure mechanism includes the first binder group
Part and the first vertical shift component, the first vertical shift component, which connect with the first binder component and is set to the positioning, to be inhaled
The top of attached jig is vertically moved with controlling the first binder component;Second feeding pressure mechanism includes the second binder group
Part and the second vertical shift component, the second vertical shift component is connected with the second binder component and corresponding first binder
Mechanism is set to the top of the positioning adsorption jig, is vertically moved with controlling the second binder component.
4. aluminium foil equipment for wrapping as claimed in claim 3, it is characterised in that:The first binder component includes one first connection
Plate, one first squeegee base and one are fixedly installed in the first scraper plate in first squeegee base, the first scraper plate installation
In the side of the close positioning adsorption jig of first squeegee base, first connecting plate is set to the first scraper plate base
The other side of seat, the both ends of first connecting plate are set to by one first cushion block described positioned at horizontal slide rail front end respectively
On sliding block;The second binder component is fixedly installed in described second including one second connecting plate, one second squeegee base and one
The second scraper plate in squeegee base, second scraper plate are installed on the one of the close positioning adsorption jig of second squeegee base
Side, second connecting plate are set to the other side of second squeegee base, and the both ends of second connecting plate pass through respectively
One second cushion block is set to described on the sliding block of horizontal slide rail rear end.
5. aluminium foil equipment for wrapping as claimed in claim 4, it is characterised in that:The number of first cylinder is one, described
The cylinder barrel of first cylinder is installed on the pedestal by a fixed frame and the piston rod of first cylinder and the first scraper plate base
Seat connection;The number of second cylinder is two, and every 1 second cylinder is installed on the horizontal slide rail by positioning piece
The piston rod of side and second cylinder is connect with the sliding block positioned at horizontal slide rail rear end.
6. aluminium foil equipment for wrapping as claimed in claim 4, it is characterised in that:The first vertical shift component includes first perpendicular
Straight sliding rail and the first top shoe being set on first upright slide rail, first upright slide rail are set to positioned at the water
On the cushion block of smooth rail front end, first top shoe is connect with the first squeegee base, for the first binder component along first
It moves upright slide rail track;The second vertical shift component is including the second upright slide rail and is set to second upright slide rail
On the second top shoe, second upright slide rail is set on the cushion block of the horizontal slide rail rear end, on described second
Sliding block is connect with the second squeegee base, is moved along the second upright slide rail track for the second binder component.
7. aluminium foil equipment for wrapping as claimed in claim 6, it is characterised in that:The first vertical shift component further includes having
The piston rod of three cylinders, the third cylinder is connect with the first squeegee base to drive the first binder component along described first
Upright slide rail slides;The second vertical shift component further includes having the 4th cylinder, the piston rod and second of the 4th cylinder
To drive, the second binder component is slided along second upright slide rail for squeegee base connection.
8. aluminium foil equipment for wrapping as described in claim 1, it is characterised in that:The positioning adsorption jig upper surface is along its length
Direction is equipped with locating slot, and the bottom surface of the positioning adsorption jig is equipped with a through-hole, and the through-hole surrounding is downwardly extending one and connects
Mouthful, the pedestal is equipped with one and holds the perforation that the interface passes through.
9. a kind of aluminium foil edge-coating system, which is characterized in that the aluminium foil edge-coating system includes a claims 1-8 any
Described in aluminium foil equipment for wrapping, a pressure vacuum tank and a vacuum pump, the pressure vacuum tank respectively with the aluminium foil bound edge
Equipment and vacuum pump connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810568798.8A CN108555129A (en) | 2018-06-05 | 2018-06-05 | Aluminium foil equipment for wrapping and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810568798.8A CN108555129A (en) | 2018-06-05 | 2018-06-05 | Aluminium foil equipment for wrapping and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108555129A true CN108555129A (en) | 2018-09-21 |
Family
ID=63552980
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810568798.8A Pending CN108555129A (en) | 2018-06-05 | 2018-06-05 | Aluminium foil equipment for wrapping and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108555129A (en) |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
BE892469A (en) * | 1982-03-12 | 1982-07-01 | Belgian Law Enforcement Agency | Wrapping machine which rotates the pack being wrapped - esp. for reducing compressible contents to constant volume or compressive stress |
JPH08119451A (en) * | 1994-10-24 | 1996-05-14 | Konan Denki Kk | Handling device for bottle of palletizer |
CN202028668U (en) * | 2010-12-27 | 2011-11-09 | 南通超达机械科技有限公司 | Aluminum foil automatic wrapping tool for automotive interior trim |
EP2394809A1 (en) * | 2010-06-09 | 2011-12-14 | Ilapak International S.A. | Packaging machine for forming envelopes |
CN103286240A (en) * | 2013-06-17 | 2013-09-11 | 王加龙 | Assembly equipment and method of heat exchanger |
CN103950573A (en) * | 2014-04-11 | 2014-07-30 | 深圳市思博克科技有限公司 | Full-automatic photo covering machine |
CN203806191U (en) * | 2014-02-24 | 2014-09-03 | 宁波长晟电子科技有限公司 | Automobile LOGO double sided tape gluing device |
CN203955819U (en) * | 2014-07-30 | 2014-11-26 | 浙江蓝宝石仪表科技有限公司 | A kind of double-deck taping machine of gas meter |
CN204276718U (en) * | 2014-10-31 | 2015-04-22 | 亿和精密金属制品(深圳)有限公司 | In a kind of mould, splicing transmits material stacking machine |
KR101547219B1 (en) * | 2014-12-31 | 2015-08-25 | (주)씨엘팜 | Method and apparatus for producing oral dispersible film with multi low and formulated drug |
CN104943900A (en) * | 2015-06-23 | 2015-09-30 | 广东韦达尔科技有限公司 | Automatic film attaching equipment |
CN105436273A (en) * | 2015-11-06 | 2016-03-30 | 无锡市金杨新型电源有限公司 | Full-automatic covering machine |
CN107413938A (en) * | 2017-06-06 | 2017-12-01 | 广东天机工业智能系统有限公司 | Apparatus for bending |
CN108058467A (en) * | 2016-11-07 | 2018-05-22 | 广州市科腾智能装备股份有限公司 | Taping machine and the automatic edge-coating system with the taping machine |
CN208408212U (en) * | 2018-06-05 | 2019-01-22 | 钜冠协创(深圳)科技有限公司 | Aluminium foil equipment for wrapping and system |
-
2018
- 2018-06-05 CN CN201810568798.8A patent/CN108555129A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
BE892469A (en) * | 1982-03-12 | 1982-07-01 | Belgian Law Enforcement Agency | Wrapping machine which rotates the pack being wrapped - esp. for reducing compressible contents to constant volume or compressive stress |
JPH08119451A (en) * | 1994-10-24 | 1996-05-14 | Konan Denki Kk | Handling device for bottle of palletizer |
EP2394809A1 (en) * | 2010-06-09 | 2011-12-14 | Ilapak International S.A. | Packaging machine for forming envelopes |
CN202028668U (en) * | 2010-12-27 | 2011-11-09 | 南通超达机械科技有限公司 | Aluminum foil automatic wrapping tool for automotive interior trim |
CN103286240A (en) * | 2013-06-17 | 2013-09-11 | 王加龙 | Assembly equipment and method of heat exchanger |
CN203806191U (en) * | 2014-02-24 | 2014-09-03 | 宁波长晟电子科技有限公司 | Automobile LOGO double sided tape gluing device |
CN103950573A (en) * | 2014-04-11 | 2014-07-30 | 深圳市思博克科技有限公司 | Full-automatic photo covering machine |
CN203955819U (en) * | 2014-07-30 | 2014-11-26 | 浙江蓝宝石仪表科技有限公司 | A kind of double-deck taping machine of gas meter |
CN204276718U (en) * | 2014-10-31 | 2015-04-22 | 亿和精密金属制品(深圳)有限公司 | In a kind of mould, splicing transmits material stacking machine |
KR101547219B1 (en) * | 2014-12-31 | 2015-08-25 | (주)씨엘팜 | Method and apparatus for producing oral dispersible film with multi low and formulated drug |
CN104943900A (en) * | 2015-06-23 | 2015-09-30 | 广东韦达尔科技有限公司 | Automatic film attaching equipment |
CN105436273A (en) * | 2015-11-06 | 2016-03-30 | 无锡市金杨新型电源有限公司 | Full-automatic covering machine |
CN108058467A (en) * | 2016-11-07 | 2018-05-22 | 广州市科腾智能装备股份有限公司 | Taping machine and the automatic edge-coating system with the taping machine |
CN107413938A (en) * | 2017-06-06 | 2017-12-01 | 广东天机工业智能系统有限公司 | Apparatus for bending |
CN208408212U (en) * | 2018-06-05 | 2019-01-22 | 钜冠协创(深圳)科技有限公司 | Aluminium foil equipment for wrapping and system |
Non-Patent Citations (1)
Title |
---|
付强;: "浅析直立锁边铝合金屋面施工", 铁道建筑技术, no. 08, 20 August 2009 (2009-08-20), pages 139 - 142 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109514916A (en) | A kind of carton automatic folding device and case binder | |
CN108638520A (en) | A kind of automation flanging heat pressing forming machines | |
CN208408212U (en) | Aluminium foil equipment for wrapping and system | |
CN102380468B (en) | Coating equipment | |
CN108555129A (en) | Aluminium foil equipment for wrapping and system | |
CN109537189B (en) | Material folding device of automatic waist plate sewing machine | |
CN206585021U (en) | A kind of Z-shaped laminated cell automatic laminating machine | |
CN202800259U (en) | Uniform pocket cloth edge folding and press ironing machine | |
CN209127626U (en) | Automatic patch top dome machine | |
KR100305298B1 (en) | Sheet separating method and apparatus | |
CN208979853U (en) | One kind being used for high-precision chip sorption separating mechanism | |
CN109129657A (en) | Battery core corner cut equipment | |
CN205052696U (en) | Cake cutting machine insert paper device | |
CN208497934U (en) | A kind of gold stamping tooling of panel of air conditioner cabinet | |
CN208413235U (en) | It is a kind of abnormity smallclothes for material separating device | |
CN211167614U (en) | Carton unpacking and opening device | |
CN103027417A (en) | Finished product taking and stacking-up device of hot-pressing machine of pocket cloth edgefolds of uniform clothes | |
CN207405396U (en) | The material pressing device of cloth cutting system | |
CN208896215U (en) | Battery core corner cut equipment | |
CN208759719U (en) | Cutting machine a kind of energy-efficient and with machine vision | |
CN106696284A (en) | Buffering and following mechanism of ultrasonic plastic welding machine pressing machine | |
CN207072463U (en) | Mobile phone color box separator | |
CN216443964U (en) | Packaging bag processing is with stacking equipment | |
CN108995198A (en) | A kind of plate face film sticking apparatus | |
CN111321581B (en) | Prevent fold cloth edge cutting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |