CN108547463A - Tall and big autoclaved aerated concrete batten installation equipment and installation method - Google Patents

Tall and big autoclaved aerated concrete batten installation equipment and installation method Download PDF

Info

Publication number
CN108547463A
CN108547463A CN201810546763.4A CN201810546763A CN108547463A CN 108547463 A CN108547463 A CN 108547463A CN 201810546763 A CN201810546763 A CN 201810546763A CN 108547463 A CN108547463 A CN 108547463A
Authority
CN
China
Prior art keywords
wallboard
steel plate
motor
equipment
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810546763.4A
Other languages
Chinese (zh)
Inventor
王雪峰
樊志鸿
姚东
庞磊
陈贺朝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201810546763.4A priority Critical patent/CN108547463A/en
Publication of CN108547463A publication Critical patent/CN108547463A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • E04G21/168Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements used for tilting, e.g. from horizontal to vertical position or vice versa

Abstract

The present invention relates to technical field of building construction, specifically a kind of tall and big autoclaved aerated concrete batten installation equipment and installation method.The equipment includes holder and jack machinism, jack machinism includes motor, pulley and fixture, motor is arranged on holder, pulley is arranged in cantilever tip lower position, fixture includes first assembly, second component, first assembly includes the first steel plate and threaded rod, threaded rod, which hangs down, to be arranged on the first steel plate, second component includes the second steel plate and U-shaped ring, the circular hole with shaft is provided on second steel plate, U-shaped ring is vertically set on the second steel plate, the steel wire penetrating pulley of motor, its end sleeve is on U-shaped ring, wallboard is pulled up to installation site by the steel wire rope and fixture of motor.Equipment peace of the present invention is torn open fast, and equipment is easy to operate, and wallboard installation speed is fast, is reduced labour's input, is improved speed of application, ensure that construction quality, improve working security, construction cost greatly reduces.

Description

Tall and big autoclaved aerated concrete batten installation equipment and installation method
Technical field
The present invention relates to technical field of building construction, specifically a kind of tall and big autoclaved aerated concrete batten installation equipment and peace Dress method.
Background technology
Internal partition wall in concrete frame structure mostly uses autoclaved aerated concrete batten(Hereinafter referred to as wallboard), common floor height Plank installation in, wallboard generally withstood using manpower by upper layer beam upwards, the installation method held out against below with scotch block works as layer It is only highly difficult or wallboard can not be installed to design position, Er Qieyi with manpower since monolithic wallboard weight is larger when high excessively high Manually to install, labor intensive power is larger, two blocks of short wallboards are vertically spliced growth wallboard by the method for generally use splicing, The connection type of this splicing is needed according to floor height to plate cutting, and wallboard cutting causes labour's input and waste of material, peace Dress mode danger is larger, needs to clog dedicated mortar, cumbersome for installation, the globality poor of board wall, construction quality difficulty control between wallboard System.
Invention content
Present invention seek to address that the above problem, throws to provide one kind simple in structure, simple and quick construction, reduce labour Tall and big autoclaved aerated concrete batten installation equipment and the installation side enter, accelerate speed of application, ensureing construction quality and construction safety Method.
The present invention solves described problem, the technical solution adopted is that:
A kind of tall and big autoclaved aerated concrete batten installation equipment, including holder and jack machinism, jack machinism include motor, cunning Wheel and fixture;Motor is arranged on holder, and pulley is arranged in cantilever tip lower position, and fixture includes first assembly, second Component;First assembly includes the first steel plate and threaded rod, and threaded rod, which hangs down, to be arranged on the first steel plate;Second component includes the second steel Plate and U-shaped ring, the circular hole with shaft is provided on the second steel plate, and U-shaped ring is vertically set on the second steel plate;Motor Steel wire penetrating pulley, end sleeve is on the U-shaped ring.
Preferably, holder includes upright bar and cross bar, and upright bar is formed by welding the frame body of holder with cross bar, and motor is fixedly mounted On the cross bar of holder.
Preferably, threaded rod hangs down and is welded on the first steel plate, and U-shaped ring is vertically welded on the second steel plate.
A kind of tall and big autoclaved aerated concrete method of plate installation, carries out in accordance with the following steps:
(One)Equipment is made, equipment includes holder and jack machinism, and jack machinism includes motor, pulley and fixture, motor It is arranged on holder, pulley is arranged in cantilever tip lower position, and fixture includes first assembly, the second component;First assembly packet The first steel plate and threaded rod are included, threaded rod, which hangs down, to be arranged on the first steel plate;Second component include the second steel plate and U-shaped ring, second The circular hole with shaft is provided on steel plate, U-shaped ring is vertically set on the second steel plate;The steel wire penetrating of motor is slided Wheel, end sleeve is on U-shaped ring;
(Two)The engaging portion of partition plate and roof of storied building, ground, metope is cleared up, mortar, concrete block of all protrusion metopes etc. are necessary It rejects and sweeps only, engaging portion uses mortar levelling;
(Three)In ground, metope and top surface according to design position, the good wallboard pre-installed position sideline of bullet and door and window hole sideline, according to room Between clear height size prepare wallboard, as possible select same size wallboard, when wallboard does not meet modulus can scene according to practical ruler Little progress row makes;
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with;
(Five)Equipment, which is placed on, need to install the side of position of wallboards;
(Six)The cradle top of equipment is leaned against on Vierendeel girder, ensures that holder and ground angle between 60o-75o, ensure construction Personnel can normally climb operation;
(Seven)300mm height and positions bore circular hole at the top of wallboard medium spacing;
(Eight)Wallboard is transported to installation site, installation site is to need to install position of wallboards and do not place equipment side, wallboard Short side is towards equipment;
(Nine)The circular hole on wallboard is passed through with the threaded rod of fixture first assembly, with the second steel with circular hole of the second component of fixture Sleeve-board fastens on threaded rod, and with nut;
(Ten)Start the switch of motor, steel wire rope is pulled up wallboard by pulley and fixture;
(11)Gradually lifting closes opening for motor to wallboard to wallboard design position after wallboard is lifted to wallboard design position It closes;
(12)Wallboard verticality and flatness are manually adjusted to code requirement, wallboard fixed frame, the gap between wallboard are installed Fixture is extractd after processing;
(13)Next block of wallboard is installed, is repeated the above steps.
Preferably, L-type card is fixed on wallboard top surface with nailing gun, L-type card is to help out, and when preventing lifting, is hung Dress dynamics is bigger than normal, and wallboard is caused to deviate pre-installed position, and wallboard is caused to topple hidden danger.
Using the present invention of above-mentioned technical proposal, compared with prior art, the feature protruded is:
Equipment peace is torn open fast, and equipment is easy to operate, and wallboard installation speed is fast, is reduced labour's input, is improved speed of application, It ensure that construction quality, improve working security, construction cost greatly reduces so that tall and big autoclaved aerated concrete batten Installation meets the quality requirement of " node is secured, wall stability, swift to operate, is adapted with frame-shear-wall structure ".
Description of the drawings
Schematic view of facade structure when Fig. 1 is installation of the embodiment of the present invention;
Fig. 2 is A-A cross-sectional views in Fig. 1;
Fig. 3 is the partial enlargement structural representation of A in Fig. 2;
Fig. 4 is the partial enlargement structural representation that circular hole is bored on wallboard of the embodiment of the present invention;
Fig. 5 is the partial enlargement structural representation that fixture of the embodiment of the present invention is connect with wallboard;
Fig. 6 is the structural schematic diagram of first assembly of the embodiment of the present invention;
Fig. 7 is the side structure schematic view of Fig. 6;
Fig. 8 is the structural schematic diagram of the second component of the embodiment of the present invention;
Fig. 9 is the present invention looks up structural representation of Fig. 8;
Figure 10 is the structural schematic diagram of multifunctional wrench of the embodiment of the present invention;
Figure 11 is the overlooking structure diagram of Figure 10;
In figure:Upright bar 1;Cross bar 2;Holder 3;Motor 4;Pulley 5;Fixture 6;First steel plate 7;Threaded rod 8;Second steel plate 9;U Type ring 10;Nut 11;Steel wire rope 12;Circular hole 13;Wallboard 14;Sawdust 15;L-type card 16;Multifunctional wrench 17.
Specific implementation mode:
With reference to embodiment, the invention will be further described, and purpose, which is only that, more fully understands the content of present invention, therefore, institute The example of act is not intended to limit protection scope of the present invention.
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11, a kind of tall and big autoclaved aerated concrete Batten installation equipment, including holder 3 and jack machinism, jack machinism include motor 4, pulley 5 and fixture 6;Motor 4 is solid Dingan County is on holder 3, and pulley 5 is fixedly mounted on 3 top lower position of holder, and fixture includes first assembly, the second component;The One component includes the first steel plate 7 and threaded rod 8, and threaded rod 8, which hangs down, to be welded on the first steel plate 7;Second component includes the second steel plate 9 With U-shaped ring 10, the circular hole coordinated with threaded rod 8 is machined on the second steel plate 9, U-shaped ring 10 is vertically welded on the second steel plate 9; The steel wire rope 12 of motor 4 passes through pulley 5, and for end sleeve on U-shaped ring 10, holder 3 includes upright bar 1 and cross bar 2, upright bar 1 The frame body of holder 3 is formed by welding with cross bar 2, upright bar 1 and cross bar 2 are all made of the steel pipe manufacturing of a diameter of 50mm, the length of cross bar 2 For 0.8m, motor 4 is fixedly mounted on the cross bar 2 of holder 3.
Tall and big autoclaved aerated concrete method of plate installation, carries out in accordance with the following steps:
(One)Equipment is made, equipment includes holder 3 and jack machinism, and jack machinism includes motor 4, pulley 5 and fixture 6, electricity Motivation 4 is fixedly mounted on holder 3, and pulley 5 is fixedly mounted on 3 top lower position of holder, and fixture 6 includes first assembly, the Two components;First assembly includes the first steel plate 7 and threaded rod 8, and threaded rod 8, which hangs down, to be welded on the first steel plate 7;Second component includes Second steel plate 9 and U-shaped ring 10 are machined with the circular hole coordinated with threaded rod 8 on second steel plate 9, and U-shaped ring 10 is vertically welded in second On steel plate 9;The steel wire rope 12 of motor 4 passes through pulley 5, and end sleeve is on U-shaped ring 10.
(Two)Clear up the engaging portion of partition plate and roof of storied building, ground, metope, mortar, the concrete block etc. of all protrusion metopes It must reject and sweep only, engaging portion uses mortar levelling.
(Three)In ground, metope and top surface according to design position, the pre-installed position sideline and door and window hole side of the good wallboard of bullet 14 Line prepares wallboard 14 according to stud size, selects the wallboard 14 of same size as possible, can when wallboard 14 does not meet modulus Scene is made according to actual size.
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with.
(Five)Fixed L-type card 16:L-type card 16 is fixed on 14 top surface of wallboard with nailing gun, L-type card 16 has been that auxiliary is made With when preventing lifting, lifting dynamics is bigger than normal, and wallboard 14 is caused to deviate pre-installed position, and wallboard 14 is caused to topple hidden danger.
(Six)Equipment, which is placed on, need to install the side of 14 position of wallboard.
(Seven)3 top of holder of equipment is leaned against on Vierendeel girder, ensures that holder 3 and ground angle between 60o-75o, are protected Card construction personnel can normally climb operation, 3 bottom of holder is lined with sawdust 15, ensure stability and the construction personnel of holder 3 Personal safety.
(Eight)300mm height and positions bore circular hole 13 at the top of 14 medium spacing of wallboard.
(Nine)By the transport of wallboard 14 to installation site, installation site is to need to install 14 position of wallboard and do not place equipment one Side, 14 short side of wallboard is towards equipment.
(Ten)The circular hole 13 on wallboard 14 is passed through with the threaded rod 8 of fixture first assembly, is justified with the band of the second component of fixture Second steel plate 9 in hole is sleeved on threaded rod 8, and is fastened with nut 11.
(11)Start the switch of motor 4, steel wire rope 12 is pulled up wallboard 14 by pulley 5 and fixture.
(12)Gradually lifting waits for the lifting of wallboard 14 to the design position of wallboard 14 to wallboard 14 to the design position of wallboard 14 The switch of motor 4 is closed afterwards.
(13)By multifunctional wrench 17 manually adjust wallboard 14 verticality and flatness to code requirement, wall is installed The fixed frame of plate 14 extracts fixture between wallboard 14 after the processing of gap.
(14)Next block of wallboard 14 is installed, is repeated the above steps.
The equipment peace of the present invention is torn open fast, and equipment is easy to operate, and the installation speed of wallboard 14 is fast, reduces labour's throwing Enter, improve speed of application, ensure that construction quality, improve working security, construction cost greatly reduces so that is high The installation of big autoclaved aerated concrete batten meets " node is secured, wall stability, swift to operate, is adapted with frame-shear-wall structure " Quality requirement.
The foregoing is merely preferably feasible embodiments of the invention, not thereby limit to the interest field of the present invention, It is all to use equivalence changes made by description of the invention and its accompanying drawing content, it is both contained within the interest field of the present invention.

Claims (5)

1. a kind of tall and big autoclaved aerated concrete batten installation equipment, including holder and jack machinism, it is characterised in that:Jack machinism Including motor, pulley and fixture;Motor is arranged on holder, and pulley is arranged in cantilever tip lower position, and fixture includes First assembly, the second component;First assembly includes the first steel plate and threaded rod, and threaded rod, which hangs down, to be arranged on the first steel plate;Second Component includes the second steel plate and U-shaped ring, is provided with the circular hole with shaft on the second steel plate, and U-shaped ring is vertically set on the On two steel plates;The steel wire penetrating pulley of motor, end sleeve is on U-shaped ring.
2. tall and big autoclaved aerated concrete batten installation equipment according to claim 1, it is characterised in that:Holder includes upright bar And cross bar, upright bar are formed by welding the frame body of holder with cross bar, motor is fixedly mounted on the cross bar of holder.
3. tall and big autoclaved aerated concrete batten installation equipment according to claim 1, it is characterised in that:Threaded rod, which hangs down, to be welded On the first steel plate, U-shaped ring is vertically welded on the second steel plate.
4. a kind of tall and big autoclaved aerated concrete method of plate installation, which is characterized in that carry out in accordance with the following steps:
(One)Equipment is made, equipment includes holder and jack machinism, and jack machinism includes motor, pulley and fixture, motor It is arranged on holder, pulley is arranged in cantilever tip lower position, and fixture includes first assembly, the second component;First assembly packet The first steel plate and threaded rod are included, threaded rod, which hangs down, to be arranged on the first steel plate;Second component include the second steel plate and U-shaped ring, second The circular hole with shaft is provided on steel plate, U-shaped ring is vertically set on the second steel plate;The steel wire penetrating of motor is slided Wheel, end sleeve is on U-shaped ring;
(Two)The engaging portion of partition plate and roof of storied building, ground, metope is cleared up, mortar, concrete block of all protrusion metopes etc. are necessary It rejects and sweeps only, engaging portion uses mortar levelling;
(Three)In ground, metope and top surface according to design position, the good wallboard pre-installed position sideline of bullet and door and window hole sideline, according to room Between clear height size prepare wallboard, as possible select same size wallboard, when wallboard does not meet modulus can scene according to practical ruler Little progress row makes;
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with;
(Five)Equipment, which is placed on, need to install the side of position of wallboards;
(Six)The cradle top of equipment is leaned against on Vierendeel girder, ensures that holder and ground angle between 60o-75o, ensure construction Personnel can normally climb operation;
(Seven)300mm height and positions bore circular hole at the top of wallboard medium spacing;
(Eight)Wallboard is transported to installation site, installation site is to need to install position of wallboards and do not place equipment side, wallboard Short side is towards equipment;
(Nine)The circular hole on wallboard is passed through with the threaded rod of fixture first assembly, with the second steel with circular hole of the second component of fixture Sleeve-board fastens on threaded rod, and with nut;
(Ten)Start the switch of motor, steel wire rope is pulled up wallboard by pulley and fixture;
(11)Gradually lifting closes opening for motor to wallboard to wallboard design position after wallboard is lifted to wallboard design position It closes;
(12)Wallboard verticality and flatness are manually adjusted to code requirement, wallboard fixed frame, the gap between wallboard are installed Fixture is extractd after processing;
(13)Next block of wallboard is installed, is repeated the above steps.
5. tall and big autoclaved aerated concrete method of plate installation according to claim 4, it is characterised in that:With nailing gun in wallboard L-type card is fixed on top surface.
CN201810546763.4A 2018-05-31 2018-05-31 Tall and big autoclaved aerated concrete batten installation equipment and installation method Pending CN108547463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810546763.4A CN108547463A (en) 2018-05-31 2018-05-31 Tall and big autoclaved aerated concrete batten installation equipment and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810546763.4A CN108547463A (en) 2018-05-31 2018-05-31 Tall and big autoclaved aerated concrete batten installation equipment and installation method

Publications (1)

Publication Number Publication Date
CN108547463A true CN108547463A (en) 2018-09-18

Family

ID=63511536

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810546763.4A Pending CN108547463A (en) 2018-05-31 2018-05-31 Tall and big autoclaved aerated concrete batten installation equipment and installation method

Country Status (1)

Country Link
CN (1) CN108547463A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114191737A (en) * 2021-11-30 2022-03-18 上海宝冶集团有限公司 Safety rope fastening device and using method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000001904A1 (en) * 1998-07-03 2000-01-13 Sarremejeanne Guy Robert Mobile horizontal platform for prefabrication on building site and for successively placing masonry parts
CN204983692U (en) * 2015-07-29 2016-01-20 中建八局第四建设有限公司 Concrete panel's hoist device
CN205151516U (en) * 2015-11-10 2016-04-13 河北晶通建筑科技有限公司 Simple and easy hoist and mount of prefabricated wallboard
CN106968442A (en) * 2017-04-20 2017-07-21 中冶建工集团有限公司 A kind of construction method of autoclaved lightweight sand aerated concrete batten partition wall
CN208347322U (en) * 2018-05-31 2019-01-08 中国二十二冶集团有限公司 Equipment is used in tall and big autoclaved aerated concrete batten installation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2000001904A1 (en) * 1998-07-03 2000-01-13 Sarremejeanne Guy Robert Mobile horizontal platform for prefabrication on building site and for successively placing masonry parts
CN204983692U (en) * 2015-07-29 2016-01-20 中建八局第四建设有限公司 Concrete panel's hoist device
CN205151516U (en) * 2015-11-10 2016-04-13 河北晶通建筑科技有限公司 Simple and easy hoist and mount of prefabricated wallboard
CN106968442A (en) * 2017-04-20 2017-07-21 中冶建工集团有限公司 A kind of construction method of autoclaved lightweight sand aerated concrete batten partition wall
CN208347322U (en) * 2018-05-31 2019-01-08 中国二十二冶集团有限公司 Equipment is used in tall and big autoclaved aerated concrete batten installation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114191737A (en) * 2021-11-30 2022-03-18 上海宝冶集团有限公司 Safety rope fastening device and using method thereof

Similar Documents

Publication Publication Date Title
US6082058A (en) Lifting method of building construction from top to bottom
US9631379B2 (en) Building construction method and lifting device
CN107100358B (en) Cantilever bracket and bracket body special for unloading-free industrialized safety protection and construction method of cantilever bracket and bracket body
CN113090019A (en) Construction method and construction device for high-rise structure
WO2023208250A1 (en) Curtain wall construction platform
CN113818562A (en) Construction method of assembled frame structure
CN211775640U (en) Modular staircase regularization steel protection passageway
CN107142954B (en) Steel hanging box lifting system for integral lifting and lifting method thereof
CN110485752B (en) High-rise building dismantling method and machine
CN116607795A (en) Steel column hoisting and positioning aid and positioning method
CN108547463A (en) Tall and big autoclaved aerated concrete batten installation equipment and installation method
CN202945798U (en) Overhanging type scaffold corner device
CN208347322U (en) Equipment is used in tall and big autoclaved aerated concrete batten installation
CN110259087B (en) Scaffold support structure and scaffold support system
CN109235871B (en) Construction method of variable cross-section structure aluminum alloy template
CN112227814B (en) Method for dismantling straight-barrel type concrete tower body
CN215670929U (en) Shear force wall elevator shaft assembled operation platform
CN113833312A (en) Combined temporary construction stair used in assembly type stair
CN109707152B (en) Aluminum alloy formwork system and construction method thereof
CN111847272A (en) Supporting method of tower crane for reconstruction of existing building
CN104947925A (en) Elevator shaft protecting operation platform
AU2018247335A1 (en) Lift shaft assembly and construction and installation thereof
KR20210068283A (en) Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing
CN115217319B (en) High-altitude replacement construction method for attached lifting scaffold
CN219732312U (en) BIM-based residential apartment AAC outer wall slat angle steel inverted installation structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180918

RJ01 Rejection of invention patent application after publication