CN108547463A - Tall and big autoclaved aerated concrete batten installation equipment and installation method - Google Patents
Tall and big autoclaved aerated concrete batten installation equipment and installation method Download PDFInfo
- Publication number
- CN108547463A CN108547463A CN201810546763.4A CN201810546763A CN108547463A CN 108547463 A CN108547463 A CN 108547463A CN 201810546763 A CN201810546763 A CN 201810546763A CN 108547463 A CN108547463 A CN 108547463A
- Authority
- CN
- China
- Prior art keywords
- wallboard
- steel plate
- motor
- equipment
- fixture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/167—Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
- E04G21/168—Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements used for tilting, e.g. from horizontal to vertical position or vice versa
Abstract
The present invention relates to technical field of building construction, specifically a kind of tall and big autoclaved aerated concrete batten installation equipment and installation method.The equipment includes holder and jack machinism, jack machinism includes motor, pulley and fixture, motor is arranged on holder, pulley is arranged in cantilever tip lower position, fixture includes first assembly, second component, first assembly includes the first steel plate and threaded rod, threaded rod, which hangs down, to be arranged on the first steel plate, second component includes the second steel plate and U-shaped ring, the circular hole with shaft is provided on second steel plate, U-shaped ring is vertically set on the second steel plate, the steel wire penetrating pulley of motor, its end sleeve is on U-shaped ring, wallboard is pulled up to installation site by the steel wire rope and fixture of motor.Equipment peace of the present invention is torn open fast, and equipment is easy to operate, and wallboard installation speed is fast, is reduced labour's input, is improved speed of application, ensure that construction quality, improve working security, construction cost greatly reduces.
Description
Technical field
The present invention relates to technical field of building construction, specifically a kind of tall and big autoclaved aerated concrete batten installation equipment and peace
Dress method.
Background technology
Internal partition wall in concrete frame structure mostly uses autoclaved aerated concrete batten(Hereinafter referred to as wallboard), common floor height
Plank installation in, wallboard generally withstood using manpower by upper layer beam upwards, the installation method held out against below with scotch block works as layer
It is only highly difficult or wallboard can not be installed to design position, Er Qieyi with manpower since monolithic wallboard weight is larger when high excessively high
Manually to install, labor intensive power is larger, two blocks of short wallboards are vertically spliced growth wallboard by the method for generally use splicing,
The connection type of this splicing is needed according to floor height to plate cutting, and wallboard cutting causes labour's input and waste of material, peace
Dress mode danger is larger, needs to clog dedicated mortar, cumbersome for installation, the globality poor of board wall, construction quality difficulty control between wallboard
System.
Invention content
Present invention seek to address that the above problem, throws to provide one kind simple in structure, simple and quick construction, reduce labour
Tall and big autoclaved aerated concrete batten installation equipment and the installation side enter, accelerate speed of application, ensureing construction quality and construction safety
Method.
The present invention solves described problem, the technical solution adopted is that:
A kind of tall and big autoclaved aerated concrete batten installation equipment, including holder and jack machinism, jack machinism include motor, cunning
Wheel and fixture;Motor is arranged on holder, and pulley is arranged in cantilever tip lower position, and fixture includes first assembly, second
Component;First assembly includes the first steel plate and threaded rod, and threaded rod, which hangs down, to be arranged on the first steel plate;Second component includes the second steel
Plate and U-shaped ring, the circular hole with shaft is provided on the second steel plate, and U-shaped ring is vertically set on the second steel plate;Motor
Steel wire penetrating pulley, end sleeve is on the U-shaped ring.
Preferably, holder includes upright bar and cross bar, and upright bar is formed by welding the frame body of holder with cross bar, and motor is fixedly mounted
On the cross bar of holder.
Preferably, threaded rod hangs down and is welded on the first steel plate, and U-shaped ring is vertically welded on the second steel plate.
A kind of tall and big autoclaved aerated concrete method of plate installation, carries out in accordance with the following steps:
(One)Equipment is made, equipment includes holder and jack machinism, and jack machinism includes motor, pulley and fixture, motor
It is arranged on holder, pulley is arranged in cantilever tip lower position, and fixture includes first assembly, the second component;First assembly packet
The first steel plate and threaded rod are included, threaded rod, which hangs down, to be arranged on the first steel plate;Second component include the second steel plate and U-shaped ring, second
The circular hole with shaft is provided on steel plate, U-shaped ring is vertically set on the second steel plate;The steel wire penetrating of motor is slided
Wheel, end sleeve is on U-shaped ring;
(Two)The engaging portion of partition plate and roof of storied building, ground, metope is cleared up, mortar, concrete block of all protrusion metopes etc. are necessary
It rejects and sweeps only, engaging portion uses mortar levelling;
(Three)In ground, metope and top surface according to design position, the good wallboard pre-installed position sideline of bullet and door and window hole sideline, according to room
Between clear height size prepare wallboard, as possible select same size wallboard, when wallboard does not meet modulus can scene according to practical ruler
Little progress row makes;
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with;
(Five)Equipment, which is placed on, need to install the side of position of wallboards;
(Six)The cradle top of equipment is leaned against on Vierendeel girder, ensures that holder and ground angle between 60o-75o, ensure construction
Personnel can normally climb operation;
(Seven)300mm height and positions bore circular hole at the top of wallboard medium spacing;
(Eight)Wallboard is transported to installation site, installation site is to need to install position of wallboards and do not place equipment side, wallboard
Short side is towards equipment;
(Nine)The circular hole on wallboard is passed through with the threaded rod of fixture first assembly, with the second steel with circular hole of the second component of fixture
Sleeve-board fastens on threaded rod, and with nut;
(Ten)Start the switch of motor, steel wire rope is pulled up wallboard by pulley and fixture;
(11)Gradually lifting closes opening for motor to wallboard to wallboard design position after wallboard is lifted to wallboard design position
It closes;
(12)Wallboard verticality and flatness are manually adjusted to code requirement, wallboard fixed frame, the gap between wallboard are installed
Fixture is extractd after processing;
(13)Next block of wallboard is installed, is repeated the above steps.
Preferably, L-type card is fixed on wallboard top surface with nailing gun, L-type card is to help out, and when preventing lifting, is hung
Dress dynamics is bigger than normal, and wallboard is caused to deviate pre-installed position, and wallboard is caused to topple hidden danger.
Using the present invention of above-mentioned technical proposal, compared with prior art, the feature protruded is:
Equipment peace is torn open fast, and equipment is easy to operate, and wallboard installation speed is fast, is reduced labour's input, is improved speed of application,
It ensure that construction quality, improve working security, construction cost greatly reduces so that tall and big autoclaved aerated concrete batten
Installation meets the quality requirement of " node is secured, wall stability, swift to operate, is adapted with frame-shear-wall structure ".
Description of the drawings
Schematic view of facade structure when Fig. 1 is installation of the embodiment of the present invention;
Fig. 2 is A-A cross-sectional views in Fig. 1;
Fig. 3 is the partial enlargement structural representation of A in Fig. 2;
Fig. 4 is the partial enlargement structural representation that circular hole is bored on wallboard of the embodiment of the present invention;
Fig. 5 is the partial enlargement structural representation that fixture of the embodiment of the present invention is connect with wallboard;
Fig. 6 is the structural schematic diagram of first assembly of the embodiment of the present invention;
Fig. 7 is the side structure schematic view of Fig. 6;
Fig. 8 is the structural schematic diagram of the second component of the embodiment of the present invention;
Fig. 9 is the present invention looks up structural representation of Fig. 8;
Figure 10 is the structural schematic diagram of multifunctional wrench of the embodiment of the present invention;
Figure 11 is the overlooking structure diagram of Figure 10;
In figure:Upright bar 1;Cross bar 2;Holder 3;Motor 4;Pulley 5;Fixture 6;First steel plate 7;Threaded rod 8;Second steel plate 9;U
Type ring 10;Nut 11;Steel wire rope 12;Circular hole 13;Wallboard 14;Sawdust 15;L-type card 16;Multifunctional wrench 17.
Specific implementation mode:
With reference to embodiment, the invention will be further described, and purpose, which is only that, more fully understands the content of present invention, therefore, institute
The example of act is not intended to limit protection scope of the present invention.
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11, a kind of tall and big autoclaved aerated concrete
Batten installation equipment, including holder 3 and jack machinism, jack machinism include motor 4, pulley 5 and fixture 6;Motor 4 is solid
Dingan County is on holder 3, and pulley 5 is fixedly mounted on 3 top lower position of holder, and fixture includes first assembly, the second component;The
One component includes the first steel plate 7 and threaded rod 8, and threaded rod 8, which hangs down, to be welded on the first steel plate 7;Second component includes the second steel plate 9
With U-shaped ring 10, the circular hole coordinated with threaded rod 8 is machined on the second steel plate 9, U-shaped ring 10 is vertically welded on the second steel plate 9;
The steel wire rope 12 of motor 4 passes through pulley 5, and for end sleeve on U-shaped ring 10, holder 3 includes upright bar 1 and cross bar 2, upright bar 1
The frame body of holder 3 is formed by welding with cross bar 2, upright bar 1 and cross bar 2 are all made of the steel pipe manufacturing of a diameter of 50mm, the length of cross bar 2
For 0.8m, motor 4 is fixedly mounted on the cross bar 2 of holder 3.
Tall and big autoclaved aerated concrete method of plate installation, carries out in accordance with the following steps:
(One)Equipment is made, equipment includes holder 3 and jack machinism, and jack machinism includes motor 4, pulley 5 and fixture 6, electricity
Motivation 4 is fixedly mounted on holder 3, and pulley 5 is fixedly mounted on 3 top lower position of holder, and fixture 6 includes first assembly, the
Two components;First assembly includes the first steel plate 7 and threaded rod 8, and threaded rod 8, which hangs down, to be welded on the first steel plate 7;Second component includes
Second steel plate 9 and U-shaped ring 10 are machined with the circular hole coordinated with threaded rod 8 on second steel plate 9, and U-shaped ring 10 is vertically welded in second
On steel plate 9;The steel wire rope 12 of motor 4 passes through pulley 5, and end sleeve is on U-shaped ring 10.
(Two)Clear up the engaging portion of partition plate and roof of storied building, ground, metope, mortar, the concrete block etc. of all protrusion metopes
It must reject and sweep only, engaging portion uses mortar levelling.
(Three)In ground, metope and top surface according to design position, the pre-installed position sideline and door and window hole side of the good wallboard of bullet 14
Line prepares wallboard 14 according to stud size, selects the wallboard 14 of same size as possible, can when wallboard 14 does not meet modulus
Scene is made according to actual size.
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with.
(Five)Fixed L-type card 16:L-type card 16 is fixed on 14 top surface of wallboard with nailing gun, L-type card 16 has been that auxiliary is made
With when preventing lifting, lifting dynamics is bigger than normal, and wallboard 14 is caused to deviate pre-installed position, and wallboard 14 is caused to topple hidden danger.
(Six)Equipment, which is placed on, need to install the side of 14 position of wallboard.
(Seven)3 top of holder of equipment is leaned against on Vierendeel girder, ensures that holder 3 and ground angle between 60o-75o, are protected
Card construction personnel can normally climb operation, 3 bottom of holder is lined with sawdust 15, ensure stability and the construction personnel of holder 3
Personal safety.
(Eight)300mm height and positions bore circular hole 13 at the top of 14 medium spacing of wallboard.
(Nine)By the transport of wallboard 14 to installation site, installation site is to need to install 14 position of wallboard and do not place equipment one
Side, 14 short side of wallboard is towards equipment.
(Ten)The circular hole 13 on wallboard 14 is passed through with the threaded rod 8 of fixture first assembly, is justified with the band of the second component of fixture
Second steel plate 9 in hole is sleeved on threaded rod 8, and is fastened with nut 11.
(11)Start the switch of motor 4, steel wire rope 12 is pulled up wallboard 14 by pulley 5 and fixture.
(12)Gradually lifting waits for the lifting of wallboard 14 to the design position of wallboard 14 to wallboard 14 to the design position of wallboard 14
The switch of motor 4 is closed afterwards.
(13)By multifunctional wrench 17 manually adjust wallboard 14 verticality and flatness to code requirement, wall is installed
The fixed frame of plate 14 extracts fixture between wallboard 14 after the processing of gap.
(14)Next block of wallboard 14 is installed, is repeated the above steps.
The equipment peace of the present invention is torn open fast, and equipment is easy to operate, and the installation speed of wallboard 14 is fast, reduces labour's throwing
Enter, improve speed of application, ensure that construction quality, improve working security, construction cost greatly reduces so that is high
The installation of big autoclaved aerated concrete batten meets " node is secured, wall stability, swift to operate, is adapted with frame-shear-wall structure "
Quality requirement.
The foregoing is merely preferably feasible embodiments of the invention, not thereby limit to the interest field of the present invention,
It is all to use equivalence changes made by description of the invention and its accompanying drawing content, it is both contained within the interest field of the present invention.
Claims (5)
1. a kind of tall and big autoclaved aerated concrete batten installation equipment, including holder and jack machinism, it is characterised in that:Jack machinism
Including motor, pulley and fixture;Motor is arranged on holder, and pulley is arranged in cantilever tip lower position, and fixture includes
First assembly, the second component;First assembly includes the first steel plate and threaded rod, and threaded rod, which hangs down, to be arranged on the first steel plate;Second
Component includes the second steel plate and U-shaped ring, is provided with the circular hole with shaft on the second steel plate, and U-shaped ring is vertically set on the
On two steel plates;The steel wire penetrating pulley of motor, end sleeve is on U-shaped ring.
2. tall and big autoclaved aerated concrete batten installation equipment according to claim 1, it is characterised in that:Holder includes upright bar
And cross bar, upright bar are formed by welding the frame body of holder with cross bar, motor is fixedly mounted on the cross bar of holder.
3. tall and big autoclaved aerated concrete batten installation equipment according to claim 1, it is characterised in that:Threaded rod, which hangs down, to be welded
On the first steel plate, U-shaped ring is vertically welded on the second steel plate.
4. a kind of tall and big autoclaved aerated concrete method of plate installation, which is characterized in that carry out in accordance with the following steps:
(One)Equipment is made, equipment includes holder and jack machinism, and jack machinism includes motor, pulley and fixture, motor
It is arranged on holder, pulley is arranged in cantilever tip lower position, and fixture includes first assembly, the second component;First assembly packet
The first steel plate and threaded rod are included, threaded rod, which hangs down, to be arranged on the first steel plate;Second component include the second steel plate and U-shaped ring, second
The circular hole with shaft is provided on steel plate, U-shaped ring is vertically set on the second steel plate;The steel wire penetrating of motor is slided
Wheel, end sleeve is on U-shaped ring;
(Two)The engaging portion of partition plate and roof of storied building, ground, metope is cleared up, mortar, concrete block of all protrusion metopes etc. are necessary
It rejects and sweeps only, engaging portion uses mortar levelling;
(Three)In ground, metope and top surface according to design position, the good wallboard pre-installed position sideline of bullet and door and window hole sideline, according to room
Between clear height size prepare wallboard, as possible select same size wallboard, when wallboard does not meet modulus can scene according to practical ruler
Little progress row makes;
(Four)It is transported with balance car, in strict accordance with material cutting plan by conveying sheet to installation site, avoids colliding with;
(Five)Equipment, which is placed on, need to install the side of position of wallboards;
(Six)The cradle top of equipment is leaned against on Vierendeel girder, ensures that holder and ground angle between 60o-75o, ensure construction
Personnel can normally climb operation;
(Seven)300mm height and positions bore circular hole at the top of wallboard medium spacing;
(Eight)Wallboard is transported to installation site, installation site is to need to install position of wallboards and do not place equipment side, wallboard
Short side is towards equipment;
(Nine)The circular hole on wallboard is passed through with the threaded rod of fixture first assembly, with the second steel with circular hole of the second component of fixture
Sleeve-board fastens on threaded rod, and with nut;
(Ten)Start the switch of motor, steel wire rope is pulled up wallboard by pulley and fixture;
(11)Gradually lifting closes opening for motor to wallboard to wallboard design position after wallboard is lifted to wallboard design position
It closes;
(12)Wallboard verticality and flatness are manually adjusted to code requirement, wallboard fixed frame, the gap between wallboard are installed
Fixture is extractd after processing;
(13)Next block of wallboard is installed, is repeated the above steps.
5. tall and big autoclaved aerated concrete method of plate installation according to claim 4, it is characterised in that:With nailing gun in wallboard
L-type card is fixed on top surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810546763.4A CN108547463A (en) | 2018-05-31 | 2018-05-31 | Tall and big autoclaved aerated concrete batten installation equipment and installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810546763.4A CN108547463A (en) | 2018-05-31 | 2018-05-31 | Tall and big autoclaved aerated concrete batten installation equipment and installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108547463A true CN108547463A (en) | 2018-09-18 |
Family
ID=63511536
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810546763.4A Pending CN108547463A (en) | 2018-05-31 | 2018-05-31 | Tall and big autoclaved aerated concrete batten installation equipment and installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108547463A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114191737A (en) * | 2021-11-30 | 2022-03-18 | 上海宝冶集团有限公司 | Safety rope fastening device and using method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000001904A1 (en) * | 1998-07-03 | 2000-01-13 | Sarremejeanne Guy Robert | Mobile horizontal platform for prefabrication on building site and for successively placing masonry parts |
CN204983692U (en) * | 2015-07-29 | 2016-01-20 | 中建八局第四建设有限公司 | Concrete panel's hoist device |
CN205151516U (en) * | 2015-11-10 | 2016-04-13 | 河北晶通建筑科技有限公司 | Simple and easy hoist and mount of prefabricated wallboard |
CN106968442A (en) * | 2017-04-20 | 2017-07-21 | 中冶建工集团有限公司 | A kind of construction method of autoclaved lightweight sand aerated concrete batten partition wall |
CN208347322U (en) * | 2018-05-31 | 2019-01-08 | 中国二十二冶集团有限公司 | Equipment is used in tall and big autoclaved aerated concrete batten installation |
-
2018
- 2018-05-31 CN CN201810546763.4A patent/CN108547463A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2000001904A1 (en) * | 1998-07-03 | 2000-01-13 | Sarremejeanne Guy Robert | Mobile horizontal platform for prefabrication on building site and for successively placing masonry parts |
CN204983692U (en) * | 2015-07-29 | 2016-01-20 | 中建八局第四建设有限公司 | Concrete panel's hoist device |
CN205151516U (en) * | 2015-11-10 | 2016-04-13 | 河北晶通建筑科技有限公司 | Simple and easy hoist and mount of prefabricated wallboard |
CN106968442A (en) * | 2017-04-20 | 2017-07-21 | 中冶建工集团有限公司 | A kind of construction method of autoclaved lightweight sand aerated concrete batten partition wall |
CN208347322U (en) * | 2018-05-31 | 2019-01-08 | 中国二十二冶集团有限公司 | Equipment is used in tall and big autoclaved aerated concrete batten installation |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114191737A (en) * | 2021-11-30 | 2022-03-18 | 上海宝冶集团有限公司 | Safety rope fastening device and using method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6082058A (en) | Lifting method of building construction from top to bottom | |
US9631379B2 (en) | Building construction method and lifting device | |
CN107100358B (en) | Cantilever bracket and bracket body special for unloading-free industrialized safety protection and construction method of cantilever bracket and bracket body | |
CN113090019A (en) | Construction method and construction device for high-rise structure | |
WO2023208250A1 (en) | Curtain wall construction platform | |
CN113818562A (en) | Construction method of assembled frame structure | |
CN211775640U (en) | Modular staircase regularization steel protection passageway | |
CN107142954B (en) | Steel hanging box lifting system for integral lifting and lifting method thereof | |
CN110485752B (en) | High-rise building dismantling method and machine | |
CN116607795A (en) | Steel column hoisting and positioning aid and positioning method | |
CN108547463A (en) | Tall and big autoclaved aerated concrete batten installation equipment and installation method | |
CN202945798U (en) | Overhanging type scaffold corner device | |
CN208347322U (en) | Equipment is used in tall and big autoclaved aerated concrete batten installation | |
CN110259087B (en) | Scaffold support structure and scaffold support system | |
CN109235871B (en) | Construction method of variable cross-section structure aluminum alloy template | |
CN112227814B (en) | Method for dismantling straight-barrel type concrete tower body | |
CN215670929U (en) | Shear force wall elevator shaft assembled operation platform | |
CN113833312A (en) | Combined temporary construction stair used in assembly type stair | |
CN109707152B (en) | Aluminum alloy formwork system and construction method thereof | |
CN111847272A (en) | Supporting method of tower crane for reconstruction of existing building | |
CN104947925A (en) | Elevator shaft protecting operation platform | |
AU2018247335A1 (en) | Lift shaft assembly and construction and installation thereof | |
KR20210068283A (en) | Structural Systems and Methods for Floor Structural Work in Elevator Machine Room of Apartment Housing | |
CN115217319B (en) | High-altitude replacement construction method for attached lifting scaffold | |
CN219732312U (en) | BIM-based residential apartment AAC outer wall slat angle steel inverted installation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180918 |
|
RJ01 | Rejection of invention patent application after publication |