CN108547327A - A kind of construction method of prefabricated piping lane seam waterproof - Google Patents

A kind of construction method of prefabricated piping lane seam waterproof Download PDF

Info

Publication number
CN108547327A
CN108547327A CN201810288123.8A CN201810288123A CN108547327A CN 108547327 A CN108547327 A CN 108547327A CN 201810288123 A CN201810288123 A CN 201810288123A CN 108547327 A CN108547327 A CN 108547327A
Authority
CN
China
Prior art keywords
piping lane
waterproof
prefabricated piping
prefabricated
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810288123.8A
Other languages
Chinese (zh)
Other versions
CN108547327B (en
Inventor
孟繁奇
赵世东
王寒
刘洋
刘鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201810288123.8A priority Critical patent/CN108547327B/en
Publication of CN108547327A publication Critical patent/CN108547327A/en
Application granted granted Critical
Publication of CN108547327B publication Critical patent/CN108547327B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Sewage (AREA)
  • Road Paving Structures (AREA)

Abstract

The construction method of specifically a kind of prefabricated piping lane seam waterproof of the present invention;It is characterized in that:Groove is reserved in the seaming position of prefabricated piping lane agent structure when constructing including fish tail and waterproof layer, the bar shaped gas cell of unaerated is overlay in the bottom of reserved groove, self-adhering-type rubber fastening band is overlay on bar shaped gas cell;Prefabricated piping lane is inflated strip shaped air sac, self-adhering-type rubber fastening band is securely affixed to the seam crossing of prefabricated piping lane agent structure using air pressure after installation is complete;It is detached after air-impulse bag is deflated;It is laid with Grouting Pipe in the side of reserved groove, exhaust pipe is set in the other side of reserved groove simultaneously, high-performance waterproofing coiled material is pasted securely from the plate outer side anti-package to side wall of prefabricated piping lane, makes to form enclosure space under bottom plate, then waterproof mortar, filling bottom plate gap are noted.It can so avoid body of groundwater from penetrating into piping lane by socket joint seam along gap, improve waterproof quality.

Description

A kind of construction method of prefabricated piping lane seam waterproof
Technical field
The present invention relates to the realm of building construction, the construction method of specifically a kind of prefabricated piping lane seam waterproof.
Background technology
For pipe gallery as underground long range linear building, how to effectively prevent Groundwater infiltration is global problem.It is comprehensive It closes piping lane and waterproof is generally carried out by outer patch waterproof roll, water-tight concrete self waterproofing, interior painting water-repellent paint.Pipe gallery The outer waterproof of bottom plate usually first overlays one layer of waterproof roll, pea gravel concreten construction waterproof protective layer is used above, then in waterproof It constructs on protective layer agent structure.Such way is more applicable in the construction of cast-in-place pipe gallery, but in the construction of prefabricated piping lane, Since there are gaps, the leakage of any one place's waterproof roll can lead to underground water between prefabricated piping lane bottom surface and fish tail and waterproof layer The probability that prefabricated piping lane seam infiltration is substantially increased to each seam is flowed freely between entire bottom plate.
Invention content
The object of the present invention is to provide one kind can avoid body of groundwater along gap by socket joint seam penetrate into piping lane from And improve the integral waterproofing quality of prefabricated piping lane.
In order to achieve the above object, the invention is realized in this way:
A kind of construction method of prefabricated piping lane seam waterproof, including
Concrete cushion is first implemented in step 1, piping lane bottom surface, by surveying and locating, is reserved in prefabricated pipe gallery seaming position recessed Slot;
Step 2 overlays high-performance waterproofing coiled material on bed course, and groove is close to that bed course is recessed, and 1m wide extra plays are arranged in seam crossing To enhance waterproof effect, foam rubber stick is then placed in groove to increase extension of the seam crossing waterproof roll in deformation Property.
Step 3 uses pea gravel concreten to be laid with fish tail and waterproof layer on waterproof roll, when fish tail and waterproof layer is constructed, pre- The seaming position of tubulation corridor agent structure reserves groove,
Step 4 overlays the bar shaped gas cell of unaerated in the bottom of reserved groove,
Step 5 overlays self-adhering-type rubber fastening band on bar shaped gas cell;
Step 6, prefabricated piping lane are inflated strip shaped air sac after installation is complete, using air pressure by self-adhering-type rubber fastening band jail Adhere the seam crossing for being labelled to prefabricated piping lane agent structure;
Step 7 detaches after air-impulse bag is deflated;
Step 8 is laid with Grouting Pipe in the side of reserved groove, while exhaust pipe is arranged in the other side of reserved groove;
Step 9 pastes high-performance waterproofing coiled material securely from the plate outer side anti-package to side wall of prefabricated piping lane, makes shape under bottom plate At enclosure space, waterproof mortar, filling bottom plate gap are then noted.
Using this prefabricated piping lane waterproof construction method for bottom plate, prefabricated pipe corridor bottom plate seam crossing external labeling type waterproof roll can be made It is close to water-tight concrete setting, while piping lane bottom plate gap is filled up by slip casting, body of groundwater is avoided to be connect by socket joint along gap Seam penetrates into piping lane, improves waterproof quality.
Description of the drawings
Fig. 1 is the construction schematic diagram one of this construction method.
Fig. 2 is the construction schematic diagram two of this construction method.
Specific implementation mode
It is further illustrated the present invention below by way of specific embodiment.
As shown in Figure 1, a kind of construction method of prefabricated piping lane seam waterproof, includes the following steps:
Concrete cushion 1 is first implemented in step 1, piping lane bottom surface, by surveying and locating, is reserved in prefabricated pipe gallery seaming position recessed Slot 2;
Step 2 overlays high-performance waterproofing coiled material 3 on bed course 1, and it is recessed to be close to bed course at groove 2, and it is additional that 1m wide is arranged in seam crossing Layer to enhance waterproof effect, then in groove 2 places foam rubber stick 4 to increase seam crossing waterproof roll 3 in deformation Ductility;
Step 3 uses pea gravel concreten to be laid with fish tail and waterproof layer 5 on waterproof roll 3, and seaming position reserves the ditch that width is B Slot is not implemented, and the size of B is determined according to self-adhering-type rubber water-proof bandwidth;
Step 4 overlays unaerated bar shaped gas cell 6 in channel bottom, overlays self-adhering-type rubber fastening band 7 on gas cell 6, then Prefabricated piping lane is installed;
Step 5, liquidate airbag aeration, and self-adhering-type rubber fastening band is made to be tightly attached to prefabricated piping lane seam crossing;
As shown in Fig. 2,
Step 6, after self-adhering-type rubber fastening band 7 pastes jail, air-impulse bag deflate take out.Groove side is reserved in fish tail and waterproof layer to spread If Grouting Pipe 8 and slip casting, exhaust pipe is arranged in the other side, by high-performance waterproofing coiled material by pasting jail in plate outer side anti-package to side wall Gu.
Using this prefabricated piping lane waterproof construction method for bottom plate, prefabricated pipe corridor bottom plate seam crossing external labeling type waterproof roll can be made It is close to water-tight concrete setting, while piping lane bottom plate gap is filled up by slip casting, body of groundwater is avoided to be connect by socket joint along gap Seam penetrates into piping lane, improves waterproof quality.

Claims (1)

1. a kind of construction method of prefabricated piping lane seam waterproof, it is characterized in that:Including
Concrete cushion is first implemented in step 1, piping lane bottom surface, by surveying and locating, is reserved in prefabricated pipe gallery seaming position recessed Slot;
Step 2 overlays high-performance waterproofing coiled material on bed course, and groove is close to that bed course is recessed, and 1m wide extra plays are arranged in seam crossing To enhance waterproof effect, foam rubber stick is then placed in groove to increase extension of the seam crossing waterproof roll in deformation Property;
Step 3 uses pea gravel concreten to be laid with fish tail and waterproof layer on waterproof roll, when fish tail and waterproof layer is constructed, in prefabricated pipe The seaming position of corridor agent structure reserves groove,
Step 4 overlays the bar shaped gas cell of unaerated in the bottom of reserved groove,
Step 5 overlays self-adhering-type rubber fastening band on bar shaped gas cell;
Step 6, prefabricated piping lane are inflated strip shaped air sac after installation is complete, using air pressure by self-adhering-type rubber fastening band jail Adhere the seam crossing for being labelled to prefabricated piping lane agent structure;
Step 7 detaches after air-impulse bag is deflated;
Step 8 is laid with Grouting Pipe in the side of reserved groove, while exhaust pipe is arranged in the other side of reserved groove;
Step 9 pastes high-performance waterproofing coiled material securely from the plate outer side anti-package to side wall of prefabricated piping lane, makes shape under bottom plate At enclosure space, waterproof mortar, filling bottom plate gap are then noted.
CN201810288123.8A 2018-03-30 2018-03-30 Waterproof construction method for prefabricated pipe gallery joints Active CN108547327B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810288123.8A CN108547327B (en) 2018-03-30 2018-03-30 Waterproof construction method for prefabricated pipe gallery joints

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810288123.8A CN108547327B (en) 2018-03-30 2018-03-30 Waterproof construction method for prefabricated pipe gallery joints

Publications (2)

Publication Number Publication Date
CN108547327A true CN108547327A (en) 2018-09-18
CN108547327B CN108547327B (en) 2020-05-26

Family

ID=63513875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810288123.8A Active CN108547327B (en) 2018-03-30 2018-03-30 Waterproof construction method for prefabricated pipe gallery joints

Country Status (1)

Country Link
CN (1) CN108547327B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364517A (en) * 2020-04-21 2020-07-03 中铁第四勘察设计院集团有限公司 Waterproof connection structure for prefabricated comprehensive pipe gallery connector
CN111809658A (en) * 2020-06-16 2020-10-23 青建集团股份公司 Prefabricated pipe gallery structure
CN113605446A (en) * 2021-08-17 2021-11-05 深圳市天健坪山建设工程有限公司 Prefabricated assembly for underground comprehensive pipe gallery construction and construction method thereof
CN113969649A (en) * 2021-12-06 2022-01-25 湖北淇源新材料科技有限公司 Waterproof layer fixing device
CN114718123A (en) * 2022-04-28 2022-07-08 中国一冶集团有限公司 Prefabricated pipe jacking gallery and cast-in-place pipe gallery butt joint construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003328381A (en) * 2002-05-10 2003-11-19 Sumitomo Rubber Ind Ltd Flexible rubber joint and its mounting structure and its constructing method
CN104846784A (en) * 2015-05-14 2015-08-19 吉林省银河水利水电新技术设计有限公司 Gravity dam telescopic joint water stop failure backwater fast closing treating method
CN107489435A (en) * 2017-09-30 2017-12-19 济南市市政工程设计研究院(集团)有限责任公司 A kind of changeable type inflatable waterstop for Tunneling by mining method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003328381A (en) * 2002-05-10 2003-11-19 Sumitomo Rubber Ind Ltd Flexible rubber joint and its mounting structure and its constructing method
CN104846784A (en) * 2015-05-14 2015-08-19 吉林省银河水利水电新技术设计有限公司 Gravity dam telescopic joint water stop failure backwater fast closing treating method
CN107489435A (en) * 2017-09-30 2017-12-19 济南市市政工程设计研究院(集团)有限责任公司 A kind of changeable type inflatable waterstop for Tunneling by mining method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364517A (en) * 2020-04-21 2020-07-03 中铁第四勘察设计院集团有限公司 Waterproof connection structure for prefabricated comprehensive pipe gallery connector
CN111809658A (en) * 2020-06-16 2020-10-23 青建集团股份公司 Prefabricated pipe gallery structure
CN113605446A (en) * 2021-08-17 2021-11-05 深圳市天健坪山建设工程有限公司 Prefabricated assembly for underground comprehensive pipe gallery construction and construction method thereof
CN113969649A (en) * 2021-12-06 2022-01-25 湖北淇源新材料科技有限公司 Waterproof layer fixing device
CN114718123A (en) * 2022-04-28 2022-07-08 中国一冶集团有限公司 Prefabricated pipe jacking gallery and cast-in-place pipe gallery butt joint construction method
CN114718123B (en) * 2022-04-28 2023-10-24 中国一冶集团有限公司 Butt joint construction method for prefabricated top pipe gallery and cast-in-situ pipe gallery

Also Published As

Publication number Publication date
CN108547327B (en) 2020-05-26

Similar Documents

Publication Publication Date Title
CN108547327A (en) A kind of construction method of prefabricated piping lane seam waterproof
CN105089044B (en) A kind of construction method of horizontal pushing tow compression type coercion underground continuous wall system
CN110878700B (en) Tunnel waterproof structure and construction method thereof
CN209742914U (en) Backfill grouting rubber and inflate plugging device behind underground construction
RU2014103551A (en) WATERED FABRIC
CN209339169U (en) A kind of precipitation well in foundation pit plugging device
CN104947700B (en) Well sealing method for dewatering well
CN204530780U (en) The water proof structure of underground-structure deformation joint
CN100419210C (en) Waterproof device for entrance of shield tunnel
CN112376620A (en) Waterproof treatment method for side wall of underground building structure by reverse construction joint
CN107524174A (en) A kind of diaphragm wall I-shaped steel joint provided with water expandable waterstop
CN208763072U (en) A kind of submerged tunnel side wall waterproof structure for deformation seams
CN110863502B (en) Construction method for dynamically adjusting foundation pit precipitation and plugging precipitation well and plugging structure
CN207714386U (en) A kind of interface position and its waterproof construction of seabed tunnel and open cut accessory structure
CN208379645U (en) The waterproof system of anti-float anchor rod
CN207863323U (en) A kind of roof seepage preventing structure
CN203247838U (en) Fully-buried basement side wall post-pouring belt advance water stop formwork
CN204532382U (en) Be suitable for the open-cut tunnel structure of extremely frigid zones
CN208201896U (en) A kind of underground engineering dewatering well waterproof construction
CN202580321U (en) Waterproof structure of through-wall pipe
CN208763073U (en) A kind of submerged tunnel roof deformation seam waterproof construction
CN108521097A (en) A kind of prefabricated tunnel of electric power and its installation method
CN209228392U (en) Subway station circular construction joint water proof structure
CN212453367U (en) Plant roof height movement joint department and prevent root thorn connected node structure
CN209568552U (en) A kind of concrete joint water stop structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant