CN108532450B - A kind of continuous bridge preloaded spring temporary consolidation device - Google Patents

A kind of continuous bridge preloaded spring temporary consolidation device Download PDF

Info

Publication number
CN108532450B
CN108532450B CN201810376956.XA CN201810376956A CN108532450B CN 108532450 B CN108532450 B CN 108532450B CN 201810376956 A CN201810376956 A CN 201810376956A CN 108532450 B CN108532450 B CN 108532450B
Authority
CN
China
Prior art keywords
fixed
block
substructure
preloaded spring
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810376956.XA
Other languages
Chinese (zh)
Other versions
CN108532450A (en
Inventor
周应新
刘延芳
汪永林
鲍卫刚
张晓锋
涂金平
钱正富
李文
曾维成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Infrastructure Maintenance Group Co Ltd
Yunnan Traffic Investment And Construction Group Co Ltd
Yunnan Wu Yi Expressway Co Ltd
Construction Headquarters Of Yunnan Wu Yi Expressway
Original Assignee
China Communications Infrastructure Maintenance Group Co Ltd
Yunnan Traffic Investment And Construction Group Co Ltd
Yunnan Wu Yi Expressway Co Ltd
Construction Headquarters Of Yunnan Wu Yi Expressway
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Communications Infrastructure Maintenance Group Co Ltd, Yunnan Traffic Investment And Construction Group Co Ltd, Yunnan Wu Yi Expressway Co Ltd, Construction Headquarters Of Yunnan Wu Yi Expressway filed Critical China Communications Infrastructure Maintenance Group Co Ltd
Priority to CN201810376956.XA priority Critical patent/CN108532450B/en
Publication of CN108532450A publication Critical patent/CN108532450A/en
Application granted granted Critical
Publication of CN108532450B publication Critical patent/CN108532450B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • E01D19/048Bearings being adjustable once installed; Bearings used in incremental launching
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Abstract

The present invention relates to a kind of continuous bridge preloaded spring temporary consolidation devices, including upper steel plate, it is permanently fixed block, it is fixed temporarily block, preloaded spring, fixed pin, rotating block, connecting shaft and substructure, the horizontal steel plate of substructure is fixed on above bridge pier, rotating block is symmetrically distributed in inside between substructure two blocks of vertical steel plates positioned opposite, rotating block one end is connected and fixed pin by connecting shaft, fixed pin is fixed on substructure two blocks of vertical steel plates positioned opposite, two pieces of rotating blocks are separately connected preloaded spring one end, the preloaded spring other end is fixed on substructure two blocks of vertical steel plates positioned opposite, it is permanently fixed block top and is fixed on upper steel plate bottom, block is fixed temporarily to be fixed on rotating block and be permanently fixed between block.The configuration of the present invention is simple, low in cost, installation maintenance is easy, is easy to repair;Continuous beam hold-down support moment " unlock " can be made anchor block and each sliding pier cooperate with loaded, shared seismic force according to the shock resistance of itself by earthquake when occurring.

Description

A kind of continuous bridge preloaded spring temporary consolidation device
Technical field
The present invention relates to a kind of continuous bridge preloaded spring temporary consolidation devices, are suitable for railway bridge, highway bridge, city height The newly-built or seismic hardening of bridge formation and various beam structures, can make structure cooperative bearing under the geological process that happens suddenly, mention High structure entirety anti-seismic performance.
Background technique
For the seismic response for reducing continuous bridge, the anti-seismic performance of continuous bridge is improved, usually continuous bridge use is subtracted, Shock isolating pedestal and viscous damper etc. subtract isolation measure, such as lead core rubber support, viscous damper.But current conventional scheme All individually loaded without changing continuous bridge anchor block, other existing shock resistances for respectively sliding pier are not played and benefit State.In recent years, there is scholar to propose Lock-up device, consider from technical standpoint, each pier cooperative bearing may be implemented, On the one hand not only initial stage is with high costs for such device, but also the inspection in later period and maintenance are miscellaneous, and operation and maintenance cost are high;It is another Aspect, it is loaded that such device realizes that each bridge pier is cooperateed with by increasing structure overall stiffness, with the conventional design concept for subtracting shock insulation It runs counter to, therefore applicable elements have certain limitation, the example for being applied to bridge earthquake resistance is less.
Summary of the invention
The purpose of the present invention is to provide a kind of continuous bridge preloaded spring temporary consolidation devices.
The present invention can open the Function Decomposition for the hold-down support that continuous bridge is arranged, and be realized by the present apparatus normal It is fixed temporarily function under working load effect, under seismic loading, block is fixed temporarily and falls off, the present apparatus " failure ", branch Seat is worked in the form of movable bearing support.On the one hand: it is fixed temporarily falling off for block, the rigidity of structural system changes, Natural vibration period extends, to play isolating affection;On the other hand, full-bridge is respectively provided with movable bearing support, the earthquake inertia of superstructure Power is allocated according to the composite rigidity of bridge pier, support, and the stress of each bridge pier can tend to be average.It overcomes foregoing continuous Beam bridge anchor block is individually loaded, the state that other existing shock resistances for respectively sliding pier are not played and utilized.
The technical scheme is that a kind of continuous bridge preloaded spring temporary consolidation device, including it is upper steel plate, permanent solid Determine block, be fixed temporarily block, adjustable preloaded spring, fixed pin, rotating block, connecting shaft and substructure, in which: substructure is by four The rectangular parallelepiped structure of the vertical steel plate of block and one piece of horizontal steel plate connection composition, the horizontal steel plate of substructure are fixed on bridge pier Side, rotating block are symmetrically distributed in inside between substructure two blocks of vertical steel plates positioned opposite, and rotating block one end passes through connection Axis connection fixed pin, the fixed pin are fixed on substructure two blocks of vertical steel plates positioned opposite, two pieces of rotating block difference Preloaded spring one end is connected, the preloaded spring other end is fixed on substructure two blocks of vertical steel plates positioned opposite, forever Upper steel plate bottom is fixed on long fixed block top, is fixed temporarily block both ends and is separately connected two pieces of rotating blocks, one side connection is permanent Fixed block is fixed temporarily block and is fixed on rotating block and is permanently fixed between block.
In the present invention, for the buckling for preventing the vertical steel plate of substructure, ribbed stiffener 8 is provided on four blocks of vertical steel plates.
In the present invention, in normal state, temporary consolidation block can be fixed on and be permanently fixed by preloaded spring described device Between block and rotating block, by being fixed temporarily block and being permanently fixed between block and be fixed temporarily rubbing between block and rotating block It wipes power and meets the longitudinally fixed needs of support.
In the present invention, in earthquake burst, earthquake ground motion acceleration activates described device, under seismic acceleration effect, if It sets the preloaded spring after rotating block to deform, so that being fixed temporarily block leaves home position, fall off, rotating block and permanent The movable function of the device is realized in relative displacement between fixed block.
The working principle of device of the present invention is as follows:
1, normal use load (or earthquake of setting up defences) can be realized by the way that rigidity, deflection and the number of preloaded spring is arranged Function is fixed temporarily under effect;
2, after seismic loading is more than the elastic restoring force that set preloaded spring provides, rotating block occurs to turn It is dynamic, so that the preloaded spring of side is occurred compressive deformation, other side preloaded spring recoverable force causes to be fixed temporarily block and falls off, from And realize the movable function of the device;
3, after device activity, movable bearing support set by bridge pier can be made to play one's part to the full, on the one hand change structure Rigidity, plays isolating affection at the natural vibration period of extending structure;On the other hand, it is played by the frictional resistance of the movable bearing support of setting Damping effect.
4, by the setting of movable bearing support, the bridge pier stress in every may make to tend to be average, it is ensured that bridge pier structure has Identical seismic safety degree.
The beneficial effects of the present invention are:
The configuration of the present invention is simple, low in cost, installation maintenance is easy, is easy to repair;Earthquake can be by continuous beam when occurring Hold-down support moment " unlock " makes anchor block and each sliding pier cooperate with loaded, shared earthquake according to the shock resistance of itself Power;It can achieve the purpose that improve continuous bridge entirety anti-seismic performance in the case where not increasing the existing shock resistance of anchor block;If There is adjustable preloaded spring, realizes that normal use load (or sets up defences against ground by the way that rigidity, deflection and the number of preloaded spring is arranged Shake) effect under be fixed temporarily function, it is ensured that the use function under normal condition.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
Figure label: 1 is upper steel plate, and 2 is are permanently fixed block, and 3 is are fixed temporarily block, and 4 be preloaded spring, and 5 be fixed pin, 6 be rotating block, and 7 be connecting shaft, and 8 be ribbed stiffener, and 9 be substructure, and 10 be bridge pier.
Specific embodiment
The present invention is further illustrated below by embodiment combination attached drawing.
Embodiment 1:
With reference to embodiments and attached drawing is described in further detail, but not as a limitation of the invention.
Embodiment 1: the structure of the present embodiment as shown in Figure 1, a kind of continuous bridge preloaded spring temporary consolidation device, including Upper steel plate 1, be permanently fixed block 2, be fixed temporarily block 3, preloaded spring 4, fixed pin 5, rotating block 6, connecting shaft 7, ribbed stiffener 8 and under Portion's structure 9 is mounted on bridge pier 10.Block 3 is fixed temporarily by preloaded spring 4, be fixed on be permanently fixed block 2 and rotating block 6 it Between.Rotating block 6 is connect by connecting shaft 7 with the fixed pin 5 being fixed in substructure 9.Substructure 9 is one perpendicular by four pieces The rectangular configuration of straight steel plate and one piece of horizontal steel plate composition is arranged ribbed stiffener 8, passes through bottom steel for the buckling for preventing vertical steel plate Plate is attached with bridge pier.

Claims (4)

1. a kind of continuous bridge preloaded spring temporary consolidation device, including upper steel plate, it is permanently fixed block, is fixed temporarily block, preloads Spring, fixed pin, rotating block, connecting shaft and substructure, it is characterised in that: substructure is by four blocks of vertical steel plates and one block of water The rectangular parallelepiped structure of plain plate connection composition, the horizontal steel plate of substructure are fixed on above bridge pier, and rotating block is symmetrically distributed in Inside between substructure two blocks of vertical steel plates positioned opposite, rotating block one end is connected and fixed pin by connecting shaft, described solid Rationed marketing is fixed on substructure two blocks of vertical steel plates positioned opposite, and two pieces of rotating blocks are separately connected preloaded spring one end, institute It states the preloaded spring other end to be fixed on substructure two blocks of vertical steel plates positioned opposite, is permanently fixed block top and is fixed on Steel plate bottom is fixed temporarily block both ends and is separately connected two pieces of rotating blocks, and one side connection is permanently fixed block, that is, it is solid to be fixed temporarily block Due to rotating block and it is permanently fixed between block.
2. continuous bridge preloaded spring temporary consolidation device according to claim 1, it is characterised in that four blocks of vertical steel plates On be provided with ribbed stiffener, to prevent the buckling of the vertical steel plate of substructure.
3. continuous bridge preloaded spring temporary consolidation device according to claim 1, it is characterised in that described device is just Under normal state, being fixed temporarily block can be fixed on and be permanently fixed between block and rotating block, by being fixed temporarily block by preloaded spring Meet the longitudinally fixed needs of support with the frictional force for being permanently fixed between block and being fixed temporarily between block and rotating block.
4. continuous bridge preloaded spring temporary consolidation device according to claim 1, it is characterised in that in earthquake burst, Earthquake ground motion acceleration activates described device, under seismic acceleration effect, the preloaded spring after rotating block is arranged in and becomes Shape falls off so that being fixed temporarily block leaves home position, and the dress is realized in rotating block and the relative displacement being permanently fixed between block The movable function set.
CN201810376956.XA 2018-04-25 2018-04-25 A kind of continuous bridge preloaded spring temporary consolidation device Active CN108532450B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810376956.XA CN108532450B (en) 2018-04-25 2018-04-25 A kind of continuous bridge preloaded spring temporary consolidation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810376956.XA CN108532450B (en) 2018-04-25 2018-04-25 A kind of continuous bridge preloaded spring temporary consolidation device

Publications (2)

Publication Number Publication Date
CN108532450A CN108532450A (en) 2018-09-14
CN108532450B true CN108532450B (en) 2019-07-23

Family

ID=63477595

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810376956.XA Active CN108532450B (en) 2018-04-25 2018-04-25 A kind of continuous bridge preloaded spring temporary consolidation device

Country Status (1)

Country Link
CN (1) CN108532450B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555009B (en) * 2019-01-24 2023-08-15 湖南中腾土木工程技术有限公司 Support and beam body shock absorption and insulation structure system and application thereof
CN109853370B (en) * 2019-01-25 2020-07-03 石家庄铁道大学 Negative stiffness seismic isolation and reduction device for continuous beam

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3046929B2 (en) * 1995-06-16 2000-05-29 三菱重工業株式会社 Bridge seismic isolation structure
JP3038343B2 (en) * 1997-03-05 2000-05-08 株式会社ダイナミックデザイン Damping device and mounting method
US20030099413A1 (en) * 2001-11-26 2003-05-29 Lee George C. Seismic isolation bearing
KR100647523B1 (en) * 2006-08-19 2006-11-29 주식회사 도화종합기술공사 Fall down prevent apparatus for rail road bridge
KR101504617B1 (en) * 2013-06-04 2015-03-20 한국수력원자력 주식회사 The isolating device with seismic isolators against wind
CN104695323A (en) * 2013-12-04 2015-06-10 汪穹立 Bridge damping support
CN204780635U (en) * 2015-05-13 2015-11-18 中建六局土木工程有限公司 Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures

Also Published As

Publication number Publication date
CN108532450A (en) 2018-09-14

Similar Documents

Publication Publication Date Title
US5599106A (en) Ball-in-cone seismic isolation bearing
CN106368115B (en) A kind of shock isolation system suitable for medium and small span beam bridge
CN103850358A (en) Three-dimensional seism isolation system
CN108532450B (en) A kind of continuous bridge preloaded spring temporary consolidation device
CN201554141U (en) Shock isolating support for self-adaptive bispherical steel spring plate
CN202913344U (en) Seismic mitigation and isolation system applied to seismic resistance of long-span continuous beam of single-track railway
KR20110019587A (en) Damper separting type seismic isolation device lead
CN108679158A (en) Earthquake isolating equipment and cultural relics display case
CN107165041B (en) Shock-absorbing and isolating steel support
CN201053103Y (en) Ball-type vibration reducing obstructing support base
Constantinou et al. Experimental and theoretical study of a sliding isolation system for bridges
CN101892624B (en) Bridge shock absorption and isolation structure
CN101718077A (en) Bridge girder anti-seismic bearing
CN111827098A (en) Trigger type limited negative stiffness high-strength spring damping support
Ikonomou Alexisismon isolation engineering for nuclear power plants
CN103696358B (en) The multiple span bridge beam bridge damping device that a kind of earthquake acceleration activates
CN203238538U (en) Flat spring plate type rubber expansion joint
CN206784159U (en) A kind of bridge girder anti-seismic bearing
CN109027677A (en) A kind of LNG storage tank shock isolating pedestal and installation method
JP3854108B2 (en) Bridge seismic isolation device
CN201310071Y (en) Bridge earthquake-proof support seat
Castellano et al. Seismic isolation of continuous bridges through curved surface sliders combined with shock transmission units
CN110616937B (en) Variable-frequency curved-surface ball shock insulation support with viscous damper
Matsushita et al. Studies on mechanisms to decrease earthquake force applied to buildings
CN207659849U (en) Shock isolating pedestal and bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant