CN108515611A CN201810393109.4A CN201810393109A CN108515611A CN 108515611 A CN108515611 A CN 108515611A CN 201810393109 A CN201810393109 A CN 201810393109A CN 108515611 A CN108515611 A CN 108515611A
Authority
CN
China
Prior art keywords
sleeper
mechanisms
crossbeam
gearbox
fang zhang
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810393109.4A
Other languages
Chinese (zh)
Inventor
谢志钦
谢志峰
田桂华
谢志礼
谢志安
郝连虎
孙佳户
王伟星
艾紫光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Silvery Dragon Prestressed Materials Co Ltd
Original Assignee
Tianjin Silvery Dragon Prestressed Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Silvery Dragon Prestressed Materials Co Ltd filed Critical Tianjin Silvery Dragon Prestressed Materials Co Ltd
Priority to CN201810393109.4A priority Critical patent/CN108515611A/en
Publication of CN108515611A publication Critical patent/CN108515611A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/043Wire anchoring or tensioning means for the reinforcements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/046Post treatment to obtain pre-stressed articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention belongs to sleepers to put a field, provide a kind of sleeper Fang Zhang mechanisms, put a device and a device is put in sleeper tensioning.A kind of sleeper Fang Zhang mechanisms, including two columns, column inside install vertical line guide rail, are equipped with crossbeam between two vertical line guide rails, crossbeam moves vertically between two columns above and below vertical line guide rail respectively;Crossbeam is equipped with the gearbox moved in the horizontal direction, and gearbox provides power by variable-frequency motor, and the output shaft of gearbox is connected with a multiple connectors of putting.A kind of flowing water unit method sleeper puts a device, including two sets of above-mentioned sleepers put a device.A device is put and sleeper tensioning puts a device and solves existing sleeper and puts a device to put a unit efficiency relatively low and to being put when multigroup Synchronous Radio of single deformed bar suddenly the problems such as in sleeper Fang Zhang of the present invention mechanisms.

Description

A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms
Technical field
The invention belongs to sleepers to put a field, more particularly, to a kind of sleeper Fang Zhang mechanisms, put a device and sleeper tensioning Put a device.
Background technology
In the production of flowing water unit method sleeper, steel strand prestress must be loosened before sleeper demoulding, it is existing to put a device Efficiency is relatively low and to being put when multigroup Synchronous Radio of single deformed bar suddenly, and it is existing that sleeper end is also easy to produce splitting As the quality of sleeper substantially reduces, and also seriously affects the service life of sleeper.
Invention content
In view of this, the present invention is directed to propose a kind of sleeper Fang Zhang mechanisms, put a device and a device is put in sleeper tensioning, with Existing sleeper is solved to put a device to put a unit efficiency relatively low and when to multigroup Synchronous Radio of single deformed bar Put the problems such as opening suddenly.
In order to achieve the above objectives, the technical proposal of the invention is realized in this way:
Vertical line guide rail is installed in a kind of sleeper Fang Zhang mechanisms, including two columns, the column inside respectively, and two hang down It is equipped with crossbeam between straight the linear guide, the crossbeam moves vertically between two columns above and below vertical line guide rail;The crossbeam It is equipped with the gearbox moved in the horizontal direction, the gearbox provides power, the output shaft of the gearbox by variable-frequency motor It is connected with a multiple connectors of putting.
As a kind of further technical solution, the crossbeam is by sagging on vertical hydraulic cylinder drives edge vertical line guide rail Straight movement.
As a kind of further technical solution, the vertical hydraulic cylinder is separately positioned on the crossbeam two there are two setting End.
As a kind of further technical solution, the vertical hydraulic cylinder is separately positioned below the crossbeam both ends.
As a kind of further technical solution, the gearbox is by horizontal hydraulic cylinder drives edge horizontal motion;Institute The one end for stating horizontal hydraulic cylinder couples crossbeam, and the other end couples gearbox.
As a kind of further technical solution, the crossbeam suspended on gearbox below by horizontal linear guide rail.
As a kind of further technical solution, the horizontal linear guide rail is located at horizontal hydraulic cylinder there are two setting Both sides.
As a kind of further technical solution, the horizontal hydraulic cylinder is located at the middle part of the crossbeam.
As a kind of further technical solution, the variable-frequency motor is located at the different of the gearbox with a connector is put Side.
Compared with the existing technology, sleeper Fang Zhang of the present invention mechanisms have the advantage that:
After sleeper Fang Zhang of the present invention mechanisms are exclusively used in sleeper deformed bar using screw thread connection Tension Forming It puts, the present apparatus can realize multigroup synchronous slow release stress of single deformed bar, avoid sleeper when putting suddenly The generation of end splitting phenomena can ensure sleeper quality, extend sleeper service life.
A kind of flowing water unit method sleeper puts a device, including two sets of above-mentioned sleeper Fang Zhang mechanisms.This flowing water unit as a result, It includes above-mentioned sleeper Fang Zhang mechanisms usefulness that method sleeper, which puts a device, and details are not described herein
A device is put in a kind of sleeper tensioning, including above-mentioned sleeper puts a device and sleeper pre-stress stretching device.As a result, It includes above-mentioned sleeper Fang Zhang mechanisms usefulness that a device is put in the tensioning of this sleeper, and details are not described herein.
Description of the drawings
The attached drawing for constituting the part of the present invention is used to provide further understanding of the present invention, schematic reality of the invention Example and its explanation are applied for explaining the present invention, is not constituted improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the sleeper Fang Zhang mechanisms described in the embodiment of the present invention;
Fig. 2 is the schematic side view of the sleeper Fang Zhang mechanisms described in the embodiment of the present invention;
Fig. 3 is the schematic rear view of the sleeper Fang Zhang mechanisms described in the embodiment of the present invention;
Fig. 4 is the schematic top plan view of the sleeper Fang Zhang mechanisms described in the embodiment of the present invention.
Reference sign:
1- columns;2- vertical line guide rails;3- vertical hydraulic cylinders;4- crossbeams;5- horizontal linear guide rails;6- horizontal hydraulic pressures Cylinder;7- gearboxes;8- variable-frequency motors;9- puts a connector.
Specific implementation mode
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
In the description of the present invention, it is to be understood that, term "center", " longitudinal direction ", " transverse direction ", "upper", "lower", The orientation or positional relationship of the instructions such as "front", "rear", "left", "right", " vertical ", "horizontal", "top", "bottom", "inner", "outside" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description of the present invention and simplification of the description, rather than instruction or dark Show that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore should not be understood as pair The limitation of the present invention.In addition, term " first ", " second " etc. are used for description purposes only, it is not understood to indicate or imply phase To importance or implicitly indicate the quantity of indicated technical characteristic.The feature for defining " first ", " second " etc. as a result, can To express or implicitly include one or more this feature.In the description of the present invention, unless otherwise indicated, " multiple " It is meant that two or more.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood by concrete condition Concrete meaning in the present invention.
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
Embodiment one
A kind of sleeper Fang Zhang mechanisms, as Figure 1-Figure 4, including two columns 1, installation is vertical straight respectively for 1 inside of column Line guide rail 2, crossbeam 4 is equipped between two vertical line guide rails 2, and crossbeam 4 is sagging along vertical line guide rail 2 between two columns 1 Straight movement;Crossbeam 4 is equipped with the gearbox 7 moved in the horizontal direction, and gearbox 7 provides power by variable-frequency motor 8, can pass through change Frequency modulation section puts a rate, and the output shaft of gearbox 7 is connected with multiple connectors 9 of putting.
In the optional technical solution of the present embodiment, crossbeam 4 is by sagging on 3 drives edge vertical line guide rail 2 of vertical hydraulic cylinder Straight movement.
In the optional technical solution of the present embodiment, there are two vertical hydraulic cylinder 3 is set, it is separately positioned on 4 both ends of crossbeam.It utilizes Two 3 synchronization liftings of vertical hydraulic cylinder allow crossbeam 4 to prolong about 2 vertical line guide rail between two columns 1 and move vertically, with Ensure put a connector and need to put open compressor wire it is corresponding.
In the optional technical solution of the present embodiment, vertical hydraulic cylinder 3 is separately positioned below 4 both ends of crossbeam.
In the optional technical solution of the present embodiment, gearbox 7 is by 6 drives edge horizontal motion of horizontal hydraulic cylinder;It is horizontal One end of hydraulic cylinder 6 couples crossbeam 4, and the other end couples gearbox 7.The flexible of horizontal hydraulic cylinder 6 can be such that gearbox prolongs Horizontal linear guide rail direction horizontal movement, to ensure to put contact and disengaging of the connector with tension rod.
In the optional technical solution of the present embodiment, crossbeam 4 suspended on gearbox 7 below by horizontal linear guide rail 5.
In the optional technical solution of the present embodiment, there are two horizontal linear guide rail 5 is set, it is located at horizontal hydraulic cylinder 6 Both sides.
In the optional technical solution of the present embodiment, horizontal hydraulic cylinder 6 is located at the middle part of crossbeam 4.
In the optional technical solution of the present embodiment, variable-frequency motor 8 and the heteropleural that a connector 9 is located at gearbox 7 is put.
The course of work of this example:
The present apparatus is respectively arranged a set of in the Zhang Gong position both sides of putting of flowing water unit method sleeper production line, variable-frequency motor 8 is located at Far from put Zhang Gong position side, to gearbox 7 provide power support, when sleeper steel mould go out curing pool run to put Zhang Gong position when, profit It is opened with put slow to sleeper implementation of a device of putting of station both sides.Specifically, after sleeper steel mould runs to and puts Zhang Gong position, first The tension rod of a connector 9 and sleeper steel mould is put on a horizontal line by the lift adjustment of vertical hydraulic cylinder 3, then horizontal liquid Cylinder pressure 6 extends forward, makes to put a connector 9 and couples with tension rod or ratcheting, finally starts variable-frequency motor 8, put 9 band of a connector Dynamic tension rod slowly rotates 1~3 week, so that sleeper stress is released, then quickly rotate several weeks, reaches the mesh of tension rod dismantling Rear stopping variable-frequency motor 8, horizontal hydraulic cylinder 6 bounces back, makes to put a connector 9 and be detached from tension rod, and sleeper, which is put, to be finished, sleeper Punching block can enter next process.
Embodiment two
A kind of flowing water unit method sleeper puts a device, including two sets of above-mentioned sleeper Fang Zhang mechanisms, is arranged in sleeper The both sides of punching block operation.It includes above-mentioned sleeper Fang Zhang mechanisms usefulness that this flowing water unit method sleeper, which puts a device, as a result, herein It repeats no more.
Embodiment three
A device is put in a kind of sleeper tensioning, including above-mentioned sleeper puts a device and sleeper pre-stress stretching device.Sleeper Pre-stress stretching device does not specifically describe the concrete structure of the device using existing herein.This sleeper tensioning as a result, is put It includes above-mentioned sleeper Fang Zhang mechanisms usefulness to open device, and details are not described herein.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention With within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention god.

Claims (10)

1. a kind of sleeper Fang Zhang mechanisms, it is characterised in that:Including two columns (1), installation is vertical respectively on the inside of the column (1) The linear guide (2) is equipped with crossbeam (4) between two vertical line guide rails (2), and the crossbeam (4) is between two columns (1) along vertical The linear guide (2) moves vertically up and down;The crossbeam (4) is equipped with the gearbox (7) moved in the horizontal direction, the gearbox (7) power is provided by variable-frequency motor (8), the output shaft of the gearbox (7) is connected with a multiple connectors (9) of putting.
2. sleeper Fang Zhang according to claim 1 mechanisms, it is characterised in that:The crossbeam (4) is driven by vertical hydraulic cylinder (3) It is dynamic to move vertically up and down along vertical line guide rail (2).
3. Fang Zhang mechanisms according to claim 2, it is characterised in that:The vertical hydraulic cylinder (3) sets respectively there are two setting It sets below the crossbeam (4) both ends.
4. sleeper Fang Zhang according to claim 1 mechanisms, it is characterised in that:The gearbox (7) is by horizontal hydraulic cylinder (6) Drives edge horizontal motion;One end of the horizontal hydraulic cylinder (6) couples crossbeam (4), and the other end couples gearbox (7)。
5. sleeper Fang Zhang according to claim 4 mechanisms, it is characterised in that:The crossbeam (4) is below by horizontal linear Guide rail (5) suspended on gearbox (7).
6. sleeper Fang Zhang according to claim 5 mechanisms, it is characterised in that:There are two the horizontal linear guide rail (5) sets, It is located at the both sides of horizontal hydraulic cylinder (6).
7. sleeper Fang Zhang according to claim 6 mechanisms, it is characterised in that:The horizontal hydraulic cylinder (6) is located at the cross The middle part of beam (4).
8. sleeper Fang Zhang according to claim 1 mechanisms, it is characterised in that:The variable-frequency motor (8) and put a connector (9) it is located at the heteropleural of the gearbox (7).
9. a kind of flowing water unit method sleeper puts a device, it is characterised in that:Including two sets of claim 1-8 any one of them rails Zhen Fangzhang mechanisms.
10. a device is put in a kind of sleeper tensioning, it is characterised in that:A device and sleeper are put including the sleeper described in claim 9 Pre-stress stretching device.
CN201810393109.4A 2018-04-27 2018-04-27 A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms Pending CN108515611A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810393109.4A CN108515611A (en) 2018-04-27 2018-04-27 A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810393109.4A CN108515611A (en) 2018-04-27 2018-04-27 A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms

Publications (1)

Publication Number Publication Date
CN108515611A true CN108515611A (en) 2018-09-11

Family

ID=63429357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810393109.4A Pending CN108515611A (en) 2018-04-27 2018-04-27 A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms

Country Status (1)

Country Link
CN (1) CN108515611A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109795029A (en) * 2019-03-01 2019-05-24 河间市银龙轨道有限公司 A kind of pre-stress rail plate puts a device
CN110978261A (en) * 2019-12-25 2020-04-10 河间市银龙轨道有限公司 Synchronous slow release control device
CN114953166A (en) * 2022-05-10 2022-08-30 中铁十四局集团房桥有限公司 Automatic tensioning and releasing method for single tensioning and releasing prestressed tendon of sleeper

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102357929A (en) * 2011-10-21 2012-02-22 中铁十二局集团有限公司 Rail slab stress tensioning system
CN105619600A (en) * 2014-11-05 2016-06-01 天津银龙预应力材料股份有限公司 Synchronous tensioning and releasing control system for pre-tensioned track boards
CN106079068A (en) * 2016-08-08 2016-11-09 中国铁道科学研究院铁道建筑研究所 One is first opened precast track plate Synchronous Radio and is opened device and its implementation
CN106808581A (en) * 2017-01-23 2017-06-09 山西高行液压股份有限公司 High-speed railway track plate pre-tensioning system flowing water unit production line puts an equipment
CN106903791A (en) * 2017-01-23 2017-06-30 山西高行液压股份有限公司 Track plates reinforcing bar Synchronous Radio equipment
WO2018028555A1 (en) * 2016-08-08 2018-02-15 中国铁道科学研究院铁道建筑研究所 Tensioning device for prefabricated track slab and synchronous relaxation device for pre-tensioned prefabricated track slab
CN208305365U (en) * 2018-04-27 2019-01-01 天津银龙预应力材料股份有限公司 Fang Zhang mechanism, flowing water unit method sleeper puts a device and a device is put in sleeper tensioning

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102357929A (en) * 2011-10-21 2012-02-22 中铁十二局集团有限公司 Rail slab stress tensioning system
CN105619600A (en) * 2014-11-05 2016-06-01 天津银龙预应力材料股份有限公司 Synchronous tensioning and releasing control system for pre-tensioned track boards
CN106079068A (en) * 2016-08-08 2016-11-09 中国铁道科学研究院铁道建筑研究所 One is first opened precast track plate Synchronous Radio and is opened device and its implementation
WO2018028555A1 (en) * 2016-08-08 2018-02-15 中国铁道科学研究院铁道建筑研究所 Tensioning device for prefabricated track slab and synchronous relaxation device for pre-tensioned prefabricated track slab
CN106808581A (en) * 2017-01-23 2017-06-09 山西高行液压股份有限公司 High-speed railway track plate pre-tensioning system flowing water unit production line puts an equipment
CN106903791A (en) * 2017-01-23 2017-06-30 山西高行液压股份有限公司 Track plates reinforcing bar Synchronous Radio equipment
CN208305365U (en) * 2018-04-27 2019-01-01 天津银龙预应力材料股份有限公司 Fang Zhang mechanism, flowing water unit method sleeper puts a device and a device is put in sleeper tensioning

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109795029A (en) * 2019-03-01 2019-05-24 河间市银龙轨道有限公司 A kind of pre-stress rail plate puts a device
CN109795029B (en) * 2019-03-01 2024-03-29 河间市银龙轨道有限公司 Tension releasing device for prestressed track slab
CN110978261A (en) * 2019-12-25 2020-04-10 河间市银龙轨道有限公司 Synchronous slow release control device
CN114953166A (en) * 2022-05-10 2022-08-30 中铁十四局集团房桥有限公司 Automatic tensioning and releasing method for single tensioning and releasing prestressed tendon of sleeper
CN114953166B (en) * 2022-05-10 2023-06-20 中铁十四局集团房桥有限公司 Automatic sleeper prestressed tendon stretching and releasing method capable of stretching and releasing single sleeper

Similar Documents

Publication Publication Date Title
CN108515611A (en) A device is put and a device is put in sleeper tensioning in a kind of sleeper Fang Zhang mechanisms
CN205325920U (en) Vibrating device
CN100586682C (en) Advanced tension method bi-directional prestress concrete track board steel model
CN209408814U (en) A kind of PC track beam form system
CN204844405U (en) Fixed mould platform is used in synchronous vibration device and production of PC component
CN208305365U (en) Fang Zhang mechanism, flowing water unit method sleeper puts a device and a device is put in sleeper tensioning
CN204060722U (en) A kind of trestle trolley adjusting mechanism
CN103015276A (en) Host machine of track-laying machine improved based on replacement structure, and assembly method thereof
CN204566337U (en) A kind of production die for manufacturing fabricated member
CN202037711U (en) Driving device of lifting frame for demoulding of aerated concrete block green body
CN2933805Y (en) Pretensioned bidirectional prestressing concrete rail plate steel mould
CN106166796B (en) A kind of stretching bed seat for the production of no tiny fragments of stone, coal, etc. formula high-speed railway track plate
CN104772815A (en) Production die for prefabricated part
CN202202260U (en) Constructing device for bridge body
CN209579949U (en) A kind of production equipment of precast beam
CN108274597A (en) Poling core pulling equipment and wallboard laminator
CN208303649U (en) A kind of guide rail stamping die
CN204414326U (en) A kind of novel fixing cast-type material-feeding mechanism
CN114474306A (en) Large-scale prefabricated component integral vibration table without manual vibration
CN209665731U (en) A kind of production equipment of precast beam
CN109967715A (en) A kind of rotor aluminum die casting equipment based on motor manufacturing production line
CN202291146U (en) Bending mechanism for steel bar truss web bar
CN202202872U (en) Railway tunnel lining jacking frame
CN207616856U (en) A kind of track plates galling device
CN112037549A (en) Traffic safety is with portable interim signal lamp

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination