CN108505553B - The method for correcting error of strip footing brick-concrete building - Google Patents

The method for correcting error of strip footing brick-concrete building Download PDF

Info

Publication number
CN108505553B
CN108505553B CN201810347608.XA CN201810347608A CN108505553B CN 108505553 B CN108505553 B CN 108505553B CN 201810347608 A CN201810347608 A CN 201810347608A CN 108505553 B CN108505553 B CN 108505553B
Authority
CN
China
Prior art keywords
cushion cap
concrete
jacking
building
bar shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810347608.XA
Other languages
Chinese (zh)
Other versions
CN108505553A (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Chuangming Architectural Design Consulting Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810347608.XA priority Critical patent/CN108505553B/en
Publication of CN108505553A publication Critical patent/CN108505553A/en
Application granted granted Critical
Publication of CN108505553B publication Critical patent/CN108505553B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of method for correcting error of strip footing brick-concrete building, it is characterized in that construction procedure includes: that (1) determines forced landing area and jacking area;The center of gravity that building is calculated according to load assignment situation divides forced landing area and jacking area after determining the center of gravity of building;(2) load wall is reinforced;(3) concrete bar shaped cushion cap is reinforced;(4) building is jacked;(5) it force-lands to building;Structure of the invention performance is good, securely and reliably.

Description

The method for correcting error of strip footing brick-concrete building
Technical field
The present invention relates to a kind of method for correcting error, in particular to a kind of method for correcting error of strip footing brick-concrete building.
Background technique
It to rectify a deviation after the inclination of strip footing brick-concrete building, but construction risk is larger during rectifying a deviation.Tradition side Method is using single forced landing or jack-up construction method, and the stress no matter generated in the construction of that method is all very big, it is necessary to right Conventional method is adjusted.Since the load wall stiffness and strength of brick mix structure want far short of what is expected relative to frame structure, force-landing Or biggish secondary stress can be generated during jack-up construction, and if do not reinforced to it, it is possible to it will cause structure destruction, Generate safety problem.Biggish secondary stress can be generated during building forced landing or jack-up construction to concrete foundation, it is also right Concrete bar shaped cushion cap may cause destruction.
Summary of the invention
The present invention is to provide a kind of method for correcting error of strip footing brick-concrete building, solves the problems, such as Deviation Correction Construction safety.
Construction procedure of the present invention includes:
(1) forced landing area and jacking area are determined;
The center of gravity that building is calculated according to load assignment situation divides forced landing area and jacking after determining the center of gravity of building Area;Forced landing or jack-up construction are using laterally basic axis as operating unit, and laterally basis axis refers to short side basis axis, In The forced landing amount or jacking amount of same lateral basis axis be it is identical, forced landing amount or jacking amount are according to every lateral basic axis Average correction amount determine;8~10 settlement observation points are arranged in every lateral basic axis, according to 8-10 settlement observation The average value of point determines average correction amount.
(2) load wall is reinforced;
Step is reinforced using as follows: removing the painting of load wall first, then the brick surface of load wall hangs rinforcement bar again, Rinforcement bar diameter is 14~16mm, and rinforcement bar spacing is 350~400mm, and rinforcement bar welds anchor rib, anchor every 400~500mm Gu muscle diameter is 14~16mm, the brick dust seam that anchor rib protrudes into load wall is anchored;Rinforcement bar is carried out after anchoring pre- Stress tension;Rinforcement bar after prestressed stretch-draw becomes fold-line-shaped;Adjacent rinforcement bar is fixed with fixing muscle.
(3) concrete bar shaped cushion cap is reinforced;
Strengthening of foundation is using as follows: concrete bar shaped cushion cap side is implanted into reinforcing bar, and implantation bar diameter is 25~32mm, plants Entering reinforcing bar distribution spacing is 400~450mm;It is implanted into reinforcing bar specific steps are as follows: it is drilled with preformed hole in concrete bar shaped cushion cap side, Reserved hole depth is 300~350mm, and reserving bore dia is 27~34mm, is then inserted into reinforcing bar, preformed hole and reinforcing bar in preformed hole Between gap closed using high strength epoxy resin glue;Concrete bar shaped cushion cap is added after implantation reinforcement construction Gu concrete bar shaped cushion cap ruggedized construction uses rectangular cushion cap, rectangular cushion cap is widened and is increased to concrete bar shaped cushion cap, Concrete bar shaped cushion cap is wrapped in the inside by rectangular cushion cap, and Widening is determined according to forced landing amount or jacking amount, when forced landing amount or top Rising amount is less than or equal to 30mm, and 200mm is widened on the every side of concrete bar shaped cushion cap, and the concrete bar shaped cushion cap amount of increasing is 100mm;When Forced landing amount or jacking amount are greater than 30mm and are less than or equal to 50mm, and 400mm, concrete bar shaped are widened in the every side of concrete bar shaped cushion cap The cushion cap amount of increasing is 200mm;When forced landing amount or jacking amount are greater than 50mm and are less than or equal to 70mm, the every side of concrete bar shaped cushion cap Widen 600mm, the concrete bar shaped cushion cap amount of increasing is 300mm;When forced landing amount or jacking amount are greater than 70mm, concrete bar shaped cushion cap 800mm is widened on every side, and the concrete bar shaped cushion cap amount of increasing is 400mm.Rectangular cushion cap concrete strength uses C30 or more.
(4) building is jacked;
It raw on structure foundation local products can disturb to influence to jack effect when due to force-landing on building, thus it is first right Building is jacked, and is then force-landed again to building.
Minimum Jacking point quantity determines according to the following formula: n=kP/N, n are Jacking point quantity;K is safety coefficient, and value is 1.5;P is top total load head;N is the design load for jacking supporting-point, takes 0.8 times of jack nominal operation load.It determines Out after minimum Jacking point quantity, Jacking point is configured further according to building load deployment scenarios, Jacking point spacing is 0.8~ 1.5m increases Jacking point quantity when minimum Jacking point quantity is not enough arranged.Jacking point arrangement will avoid door-window opening, work as door Increase concrete lintel when window hole width is greater than 1.2m, below door-window opening to be reinforced.
(5) it force-lands to building;
From vertical drilling at concrete bar shaped cushion cap edge 200mm, drilling depth is 20~30m, bore diameter is 150~ 200mm.Drilling rod is connected with high-pressure rubber pipe with high-pressure pump, clear water is conveyed into hole by high-pressure pump.Clear water is from sprayer body Sprayed in the form of high-pressure water jet in nozzle, cutting damage effect formed to foundation soil, high-pressure water pressure control 1.5~ 2.5MPa, flow control is in 40~45L/min.The foundation soil cut mixes together with water, returns to ground after forming mud.Through After high pressure jer cutting, a mud column is just formd under basis.
Structure of the invention performance is good, securely and reliably.
Detailed description of the invention
Fig. 1 is that load wall reinforces schematic diagram, and Fig. 2 is that concrete bar shaped cushion cap reinforces schematic diagram.
In each attached drawing: 1, rinforcement bar, 2, the rinforcement bar after prestressed stretch-draw, 3, fixing muscle, 4, implantation reinforcing bar, 5, rectangular hold Platform, 6, concrete bar shaped cushion cap.
Specific embodiment
The present embodiment construction procedure includes:
(1) forced landing area and jacking area are determined;
The center of gravity that building is calculated according to load assignment situation divides forced landing area and jacking after determining the center of gravity of building Area;Forced landing or jack-up construction are using laterally basic axis as operating unit, and laterally basis axis refers to short side basis axis, In The forced landing amount or jacking amount of same lateral basis axis be it is identical, forced landing amount or jacking amount are according to every lateral basic axis Average correction amount determine;8~10 settlement observation points are arranged in every lateral basic axis, according to 8-10 settlement observation The average value of point determines average correction amount.
(2) load wall is reinforced;
Step is reinforced using as follows: removing the painting of load wall first, then the brick surface of load wall hangs rinforcement bar again, Rinforcement bar diameter is 14~16mm, and rinforcement bar spacing is 350~400mm, and rinforcement bar welds anchor rib, anchor every 400~500mm Gu muscle diameter is 14~16mm, the brick dust seam that anchor rib protrudes into load wall is anchored;Rinforcement bar is carried out after anchoring pre- Stress tension;Rinforcement bar after prestressed stretch-draw becomes fold-line-shaped;Adjacent rinforcement bar is fixed with fixing muscle.
(3) concrete bar shaped cushion cap is reinforced;
Strengthening of foundation is using as follows: concrete bar shaped cushion cap side is implanted into reinforcing bar, and implantation bar diameter is 25~32mm, plants Entering reinforcing bar distribution spacing is 400~450mm;It is implanted into reinforcing bar specific steps are as follows: it is drilled with preformed hole in concrete bar shaped cushion cap side, Reserved hole depth is 300~350mm, and reserving bore dia is 27~34mm, is then inserted into reinforcing bar, preformed hole and reinforcing bar in preformed hole Between gap closed using high strength epoxy resin glue;Concrete bar shaped cushion cap is added after implantation reinforcement construction Gu concrete bar shaped cushion cap ruggedized construction uses rectangular cushion cap, rectangular cushion cap is widened and is increased to concrete bar shaped cushion cap, Concrete bar shaped cushion cap is wrapped in the inside by rectangular cushion cap, and Widening is determined according to forced landing amount or jacking amount, when forced landing amount or top Rising amount is less than or equal to 30mm, and 200mm is widened on the every side of concrete bar shaped cushion cap, and the concrete bar shaped cushion cap amount of increasing is 100mm;When Forced landing amount or jacking amount are greater than 30mm and are less than or equal to 50mm, and 400mm, concrete bar shaped are widened in the every side of concrete bar shaped cushion cap The cushion cap amount of increasing is 200mm;When forced landing amount or jacking amount are greater than 50mm and are less than or equal to 70mm, the every side of concrete bar shaped cushion cap Widen 600mm, the concrete bar shaped cushion cap amount of increasing is 300mm;When forced landing amount or jacking amount are greater than 70mm, concrete bar shaped cushion cap 800mm is widened on every side, and the concrete bar shaped cushion cap amount of increasing is 400mm.Here the concrete bar shaped cushion cap amount of increasing is exactly in attached drawing Dash area height.Rectangular cushion cap concrete strength uses C30 or more.
(4) building is jacked;
Minimum Jacking point quantity determines according to the following formula: n=kP/N, n are Jacking point quantity;K is safety coefficient, and value is 1.5;P is top total load head;N is the design load for jacking supporting-point, takes 0.8 times of jack nominal operation load.It determines Out after minimum Jacking point quantity, Jacking point is configured further according to building load deployment scenarios, Jacking point spacing is 0.8~ 1.5m increases Jacking point quantity when minimum Jacking point quantity is not enough arranged.Jacking point arrangement will avoid door-window opening, work as door Increase concrete lintel when window hole width is greater than 1.2m, below door-window opening to be reinforced.
(5) it force-lands to building;
From vertical drilling at concrete bar shaped cushion cap edge 200mm, drilling depth is 20~30m, bore diameter is 150~ 200mm.Drilling rod is connected with high-pressure rubber pipe with high-pressure pump, clear water is conveyed into hole by high-pressure pump.Clear water is from sprayer body Sprayed in the form of high-pressure water jet in nozzle, cutting damage effect formed to foundation soil, high-pressure water pressure control 1.5~ 2.5MPa, flow control is in 40~45L/min.The foundation soil cut mixes together with water, returns to ground after forming mud.Through After high pressure jer cutting, a mud column is just formd under basis.

Claims (1)

1. a kind of method for correcting error of strip footing brick-concrete building, it is characterized in that construction procedure includes:
(1) forced landing area and jacking area are determined;
The center of gravity that building is calculated according to load assignment situation divides forced landing area and jacking area after determining the center of gravity of building;Compel Drop or jack-up construction are using laterally basic axis as operating unit, and laterally basis axis refers to short side basis axis, identical cross Be to the forced landing amount or jacking amount of basic axis it is identical, forced landing amount or jacking amount be according to every laterally basic axis be averaged Correction amount determines;Every laterally basic axis 8~10 settlement observation points are set, according to putting down for 8-10 settlement observation point Mean value determines average correction amount;
(2) load wall is reinforced;
Load wall reinforces step using as follows: removing the rendering layer of load wall first, then hangs and add on the brick surface of load wall Gu muscle, rinforcement bar diameter is 14~16mm, and rinforcement bar spacing is 350~400mm, and rinforcement bar is welded every 400~500mm and anchored Muscle, anchor rib diameter are 14~16mm, and the brick dust seam that anchor rib protrudes into load wall is anchored;After anchoring to rinforcement bar into Row prestressed stretch-draw;Rinforcement bar after prestressed stretch-draw becomes fold-line-shaped;Adjacent rinforcement bar is fixed with fixing muscle;
(3) concrete bar shaped cushion cap is reinforced;
Strengthening of foundation is using as follows: in concrete bar shaped cushion cap side, implantation reinforcing bar is set, implantation bar diameter is 25~32mm, Being implanted into reinforcing bar distribution spacing is 400~450mm;It is implanted into reinforcing bar specific steps are as follows: be drilled in concrete bar shaped cushion cap side reserved Hole, reserve hole depth be 300~350mm, reserve bore dia be 27~34mm, then preformed hole be inserted into reinforcing bar, preformed hole and Gap is closed using high strength epoxy resin glue between reinforcing bar;Be implanted into reinforcement construction after to concrete bar shaped cushion cap into Row reinforce, concrete bar shaped cushion cap ruggedized construction use rectangular cushion cap, rectangular cushion cap concrete bar shaped cushion cap is widened and Increase, concrete bar shaped cushion cap is wrapped in the inside by rectangular cushion cap, and rectangular cushion cap concrete strength uses C30 or more;
(4) building is jacked;
Minimum Jacking point quantity determines according to the following formula: n=kP/N, n are Jacking point quantity;K is safety coefficient, value 1.5; P is top total load head;N is the design load of Jacking point, takes 0.8 times of jack nominal operation load;It determines at least to push up After rising point quantity, it is configured Jacking point further according to building load deployment scenarios, Jacking point spacing is 0.8~1.5m, when most When few Jacking point quantity is not enough arranged, increase Jacking point quantity;
(5) it force-lands to building;
From vertical drilling at concrete bar shaped cushion cap edge 200mm, drilling depth is 20~30m, bore diameter is 150~ 200mm;Drilling rod is connected with high-pressure rubber pipe with high-pressure pump, clear water is conveyed into hole by high-pressure pump;Clear water is from sprayer body Sprayed in the form of high-pressure water jet in nozzle, cutting damage effect formed to foundation soil, high-pressure water pressure control 1.5~ 2.5MPa, flow control is in 40~45L/min;The foundation soil cut mixes together with water, returns to ground after forming mud;Through After high pressure jer cutting, a mud column is just formd under basis;
Jacking point arrangement will avoid door-window opening, when door-window opening width is greater than 1.2m, increase concrete below door-window opening Lintel is reinforced.
CN201810347608.XA 2017-01-21 2017-01-21 The method for correcting error of strip footing brick-concrete building Active CN108505553B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810347608.XA CN108505553B (en) 2017-01-21 2017-01-21 The method for correcting error of strip footing brick-concrete building

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201810347608.XA CN108505553B (en) 2017-01-21 2017-01-21 The method for correcting error of strip footing brick-concrete building
CN201710072383.7A CN106836323B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of strip footing brick-concrete building

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710072383.7A Division CN106836323B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of strip footing brick-concrete building

Publications (2)

Publication Number Publication Date
CN108505553A CN108505553A (en) 2018-09-07
CN108505553B true CN108505553B (en) 2019-12-03

Family

ID=59122296

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201810347651.6A Active CN108532655B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of brick-concrete building
CN201710072383.7A Expired - Fee Related CN106836323B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of strip footing brick-concrete building
CN201810347608.XA Active CN108505553B (en) 2017-01-21 2017-01-21 The method for correcting error of strip footing brick-concrete building

Family Applications Before (2)

Application Number Title Priority Date Filing Date
CN201810347651.6A Active CN108532655B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of brick-concrete building
CN201710072383.7A Expired - Fee Related CN106836323B (en) 2017-01-21 2017-01-21 The deviation rectification construction method of strip footing brick-concrete building

Country Status (1)

Country Link
CN (3) CN108532655B (en)

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3455861B2 (en) * 1995-03-03 2003-10-14 清水建設株式会社 Foundation structure and foundation construction method
JPH0913416A (en) * 1995-06-27 1997-01-14 Daito Kogyo Kk Correcting method for sunk building
CN1099515C (en) * 1998-07-16 2003-01-22 赵启 Integral building-translating equipment and method
JP3804063B2 (en) * 2001-10-15 2006-08-02 株式会社佐藤住建 Reinforcement structure and reinforcement method of foundation structure in building
CN100386781C (en) * 2005-07-12 2008-05-07 范晓征 Intercom remote control device with identity code function
CN101725258B (en) * 2008-10-30 2012-09-19 上海天演建筑物移位工程有限公司 Integral jacking method of heritage buildings
CN101691765B (en) * 2009-09-21 2011-01-26 唐业清 Double-ash well pole stress relief coordination and rectification method for complex foundation
CN101994325B (en) * 2010-12-22 2012-11-28 建研地基基础工程有限责任公司 Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN107165436B (en) * 2016-02-17 2020-01-07 朱奎 Brick wall reinforcing structure
CN106120811A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 A kind of foundation ditch periphery distortion preventing and deviation rectification construction method
CN106320403A (en) * 2016-09-20 2017-01-11 武汉理工大学 Inclination rectification and reinforcement method for existing building

Also Published As

Publication number Publication date
CN106836323B (en) 2018-09-18
CN108505553A (en) 2018-09-07
CN108532655A (en) 2018-09-14
CN106836323A (en) 2017-06-13
CN108532655B (en) 2019-11-29

Similar Documents

Publication Publication Date Title
CN108343260B (en) Inclined building deviation rectifying and reinforcing structure and construction method thereof
CN107435346A (en) A kind of grouting and reinforcing method for correcting error suitable for high building structure
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN104195911A (en) Widened embankment structure with beside-water cliff high retaining wall fill section and construction method of widened embankment structure
CN103541352B (en) A kind of at ground, sandy soil stratum major diameter Vertical spots underground continuous construction method
CN101250878A (en) Method for supporting deep building pit using non bulit-in end pile anchor in combination with anchor slab wall
CN105040712A (en) High-pressure washing anchor planting and recharging comprehensive biological protection structure of soft and hard smashing interbedding type composite rock slope and construction method of structure
CN106812153A (en) Beam and slab type construction elevator foundation construction engineering method in a kind of backfill
CN112411610A (en) Pile foundation underpinning construction method
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN108797323B (en) Steel trestle suitable for hard stratum
CN108505553B (en) The method for correcting error of strip footing brick-concrete building
CN110387886A (en) Civil air defense constructions and installations foundation pit supporting construction and its construction method
CN112012747B (en) Tunnel inclined shaft construction method for V-level surrounding rock soil texture
CN105386462A (en) Integral construction type small and medium-sized basement and construction method thereof
CN107604940A (en) A kind of steel pipe grid Expansive Soils Retaining Wall and its construction method
CN104711981B (en) A kind of foundation pit soil nailing structures and methods
CN211448697U (en) Single-line tunnel supporting device for soft rock slight large deformation in plateau area
CN111893994A (en) Pile casing-free pore-forming method for foundation pile of aeolian dune steep slope
CN110565709A (en) Method for correcting inclination of composite foundation building by taking soil from mattress layer and forcing to land
CN110924404A (en) Construction method for deep backfill filling wall foundation
CN105756078B (en) One kind extends out lamination type and draws digging spread foundation and its construction method
JP6345328B1 (en) Original position building method and original position structure
CN108396794B (en) Deviation rectifying method for building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230524

Address after: Room 410, 4th Floor, No. 31 Tiyuan Road, Yuhua District, Changsha City, Hunan Province, 410000

Patentee after: Hunan Chuangming Architectural Design Consulting Co.,Ltd.

Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Patentee before: Ye Changqing

TR01 Transfer of patent right