CN108487651A CN201810197430.5A CN201810197430A CN108487651A CN 108487651 A CN108487651 A CN 108487651A CN 201810197430 A CN201810197430 A CN 201810197430A CN 108487651 A CN108487651 A CN 108487651A
Authority
CN
China
Prior art keywords
mould bases
fixed
plate
wall
fixed border
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810197430.5A
Other languages
Chinese (zh)
Other versions
CN108487651B (en
Inventor
郭山河
张长雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Heyuan Environmental Protection Technology Co Ltd
Original Assignee
Fuzhou Heyuan Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Heyuan Environmental Protection Technology Co Ltd filed Critical Fuzhou Heyuan Environmental Protection Technology Co Ltd
Priority to CN201810197430.5A priority Critical patent/CN108487651B/en
Publication of CN108487651A publication Critical patent/CN108487651A/en
Application granted granted Critical
Publication of CN108487651B publication Critical patent/CN108487651B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/20Tools or apparatus for applying mortar

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Finishing Walls (AREA)

Abstract

It builds a wall the invention discloses one kind and using quickly plastering mould bases, including fix mould bases and movement side plate, the mobile side plate is slidably mounted on the fixed mould bases side, and the mobile side plate passes through locking member with the fixed mould bases and fixes locking;The fixed mould bases includes horizontally disposed fixed border, the fixed border is U-shaped, the outer edge of the fixed border is provided with enclosing, it is provided with waist-shaped hole on the two sides of the enclosing, the bottom of the fixed border is provided with the first lateral guide lip, and first guide lip vertically with the fixed border.Advantageous effect is:The laying height of mortar can be limited by the fixed border and the connecting plate, to ensure the flatness of spreading bricks;The laying width of mortar is limited using the padded plate of the fixation and the activity padded plate, to prevent when hammer presses brick body, mortar is fallen outward, ensures the aesthetics and flatness of built a wall body.

Description

One kind is built a wall with quickly plastering mould bases
Technical field
The present invention relates to building implement fields, and in particular to one kind is built a wall with quickly plastering mould bases.
Background technology
It is a kind of common construction technology in building construction process to build a wall.It is that brick is sticked together using mortar, To make the brick piled up form firm wall.During building a wall, the laying of mortar, which is often construction worker, will utilize watt Knife is laid on brick, in process of deployment, construction worker is needed skillfully to grasp the laying depth of mortar, thus by mortar It divides on the surface of brick, to ensure that it is smooth that same layer brick can be laid with.
Applicants have discovered that at least there is following technical problem in the prior art:After brick is placed on mortar, need Hammer pressure is carried out to brick, to make brick bottom be bonded completely with mortar, therefore mortar can be made by the extruding of brick and from It is squeezed out inside and outside wall, when the mortar of extrusion exceeds surface of wall, due to gravity, the mortar being extruded can be downward It falls, causes the waste of mortar, and protrude from wall but the mortar not fallen can make the aesthetics of surface of wall and flatness big It is big to reduce.
Invention content
The purpose of the present invention be that solve the above-mentioned problems and provide one kind build a wall with quickly plastering mould bases, with solve During building a wall in the prior art, mortar is easy to fall, and causes to waste, and protrudes U.S. that metope can be also reduced with the mortar of wall The technical problems such as the property seen.Preferred technical solution has in many technical solutions provided by the invention:Pass through the fixed mould bases Mould bases is formed with the mobile side, the laying width of mortar is limited, while controlling the laying height of mortar, to keep away Exempt from mortar to fall, and can avoid mortar and be extruded wall, ensures the technique effects such as the aesthetics of wall, elaboration as detailed below.
To achieve the above object, the present invention provides following technical schemes:
One kind provided by the invention is built a wall with quickly plastering mould bases, including fixed mould bases and mobile side plate, the mobile side Plate is slidably mounted on the fixed mould bases side, and the mobile side plate is fixed by locking member with the fixed mould bases and locked;
The fixed mould bases includes horizontally disposed fixed border, and the fixed border is U-shaped, outside the fixed border Edge is provided with enclosing, is provided with waist-shaped hole on the two sides of the enclosing, and the bottom of the fixed border is provided with lateral First guide lip, and first guide lip vertically with the fixed border, on the inside of first guide lip with it is described The angle of fixed border is provided with fixed padded plate, is provided with the first molgogger below the padded plate of fixation, and described the Handle is provided with above the side of one guide lip, and the handle is fixedly mounted on the outside of the enclosing;
The mobile side plate includes the flexible frame and sliding baffle of both sides, and connection is provided among the flexible frame Plate, and the connecting plate is horizontally disposed, the sliding baffle plate setting is in the flexible scuncheon, and two sliding baffles Between interior spacing and the outline border size of the enclosing match, olos and the fixation between two sliding baffles The U-shaped opening size of frame matches, and the flexible frame is provided with locking hole, and the locking member can be made through the locking hole It stretches into the waist-shaped hole, the mobile side plate and the fixed mould bases is linked together, the connecting plate bottom is provided with It is padded that the angle of the second guide lip straight down, the second guide lip inside and the connecting plate is provided with activity Plate, the padded plate lower section of activity are provided with the second molgogger.
It is built a wall using above-mentioned one kind and is adjusted described first according to the width of institute's brick masonary with quickly plastering mould bases and be oriented to gear Spacing between side and second guide lip enables first molgogger and second molgogger respectively along wall The interior outside of body freely slides, and when adjusting, only need to pull the connecting plate, so that the flexible frame is slid along the enclosing, i.e., The adjusting to mould bases inboard width can be achieved, after the completion of adjusting, the locking member is locked, to make the mobile side plate and institute It states fixed mould bases to be fixed together, in use, the padded plate of the fixation and the padded plate of activity is made to be fitted in lower layer's wall Surface makes first molgogger and second molgogger be fitted in the surfaces externally and internally of lower layer's wall, then by mortar Pour into the rectangle frame that the fixed border and the connecting plate surround, then mortar is shakeout, make the height of mortar with it is described solid Determine that bezel height is concordant, can so accurately control the laying depth of mortar, after laying, then passes through the handle and drag institute It states fixed mould bases to move forward along wall, continues to be laid with mortar, since the padded plate of the fixation and the activity are padded Plate blocks the edge inside and outside brick body, to make the mortar of laying still remain with a distance apart from wall edge, to Make brick body when hammering pressure into shape, reserves certain extension space for mortar, prevent mortar from falling, while also can avoid mortar protruding wall Body.
Preferably, the width of the fixed border is 1-2cm, thickness 0.5cm.
Preferably, the enclosing is perpendicular to the fixed border, and the height 3-5cm of the enclosing, and thickness and institute It is identical to state fixed border.
Preferably, first molgogger is uniformly distributed along first guide lip, and first orienting roll The axis of column vertically with the padded plate of the fixation.
Preferably, the locking member is mating screw bolt and nut.
Preferably, the padded plate of activity is identical with the height of the padded plate of the fixation.
Preferably, the second molgogger is uniformly distributed along second guide lip, and second molgogger Axis vertically with the padded plate of activity.
Advantageous effect is:1, the present invention can be by the fixed border and the connecting plate to the laying height of mortar It is limited, to ensure the flatness of spreading bricks;
2, the laying width of mortar is limited using the padded plate of the fixation and the activity padded plate, to prevent When hammer presses brick body, mortar is fallen outward, ensures the aesthetics and flatness of built a wall body.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Obtain other attached drawings according to these attached drawings.
Fig. 1 is the space diagram of the present invention;
Fig. 2 is the longitudinal sectional drawing of the present invention;
Fig. 3 is the fixation mould bases structure chart of the present invention;
Fig. 4 is the mobile lateral plate structure figure of the present invention.
The reference numerals are as follows:
1, fixed mould bases;101, handle;102, enclosing;103, fixed border;104, fixed padded plate;105, it first is oriented to Roller;106, waist-shaped hole;107, the first guide lip;2, mobile side plate;201, connecting plate;202, stretch frame;203, it slides Baffle;204, locking hole;205, the padded plate of activity;206, the second guide lip;207, the second molgogger;3, locking member.
Specific implementation mode
To make the object, technical solutions and advantages of the present invention clearer, technical scheme of the present invention will be carried out below Detailed description.Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Base Embodiment in the present invention, those of ordinary skill in the art are obtained all without making creative work Other embodiment belongs to the range that the present invention is protected.
Shown in Fig. 1-Fig. 4, the present invention provides one kind to build a wall with quickly plastering mould bases, including fixed mould bases 1 and shifting Dynamic side plate 2, mobile side plate 2 is slidably mounted on 1 side of fixed mould bases, and mobile side plate 2 and fixed mould bases 1 are solid by locking member 3 Lock is tight;
Fixed mould bases 1 includes horizontally disposed fixed border 103, and fixed border 103 is U-shaped, the outside of fixed border 103 Edge is provided with enclosing 102, and waist-shaped hole 106 is provided on the two sides of enclosing 102, and the bottom of fixed border 103 is provided with transverse direction The first guide lip 107, and the first guide lip 107 vertically with fixed border 103, the inside of the first guide lip 107 with it is solid The angle of deckle frame 103 is provided with fixed padded plate 104, and 104 lower section of fixed padded plate is provided with the first molgogger 105, Handle 101 is provided with above the side of first guide lip 107, and handle 101 is fixedly mounted on 102 outside of enclosing;
Mobile side plate 2 includes the flexible frame 202 and sliding baffle 203 of both sides, and connection is provided among flexible frame 202 Plate 201, and connecting plate 201 is horizontally disposed, the setting of sliding baffle 203 is in 202 inside of flexible frame, and two slide baffles 203 Between interior spacing and the outline border size of enclosing 102 match, two sliding baffles 203 between olos and fixed border 103 U-shaped opening size matches, and flexible frame 202 is provided with locking hole 204, and locking member 3 can be made to be stretched through locking hole 204 Enter in waist-shaped hole 106, mobile side plate 2 and fixed mould bases 1 is linked together, 201 bottom of connecting plate is provided with straight down The angle of second guide lip 206,206 inside of the second guide lip and connecting plate 201 is provided with the padded plate 205 of activity, living It moves 205 lower section of padded plate and is provided with the second molgogger 207.
Preferably, the width of fixed border 103 is 1-2cm, thickness 0.5cm, so set, convenient for being fixed for guarantee The intensity of frame 103.
Enclosing 102 is perpendicular to fixed border 103, and the height 3-5cm of enclosing 102, and thickness and 103 phase of fixed border Together, so set, convenient for being blocked to mortar by enclosing 102, to prevent mortar when being laid with from 103 side of fixed border Edge is fallen.
First molgogger 105 is uniformly distributed along the first guide lip 107, and the axis of the first molgogger 105 is vertical , by the rotation of the first molgogger 105, make solid so set, convenient for fixing mould bases 1 when moving with the padded plate 104 of fixation Cover half frame 1 easily moves forward.
Locking member 3 is mating screw bolt and nut, so set, facilitating the locking of locking member 3 and loosening.
The padded plate 205 of activity is identical with the height of fixed padded plate 104, so set, convenient for making the mortar on brick body surface Height is laid with to be consistent.
Second molgogger 207 is uniformly distributed along the second guide lip 206, and the axis of the second molgogger 207 is vertical , by the rotation of the second molgogger 207, make shifting so set, side plate easy to remove 2 is when moving with the padded plate 205 of activity Dynamic side plate 2 easily moves forward.
Using the above structure, according to the width of institute's brick masonary, the first guide lip 107 and the second guide lip 206 are adjusted Between spacing, so that the first molgogger 105 and the second molgogger 207 is freely slid along the interior outside of wall respectively, adjust When section, connecting plate 201 only need to be pulled, so that flexible frame 202 is slid along enclosing 102, you can to realize the tune to mould bases inboard width Section, after the completion of adjusting, locking member 3 is locked, to make mobile side plate 2 be fixed together with fixed mould bases 1, in use, making solid Fixed padded plate 104 and movable padded plate 205 are tightly attached to the surface of lower layer's wall, make the first molgogger 105 and the second orienting roll Column 207 is fitted in the surfaces externally and internally of lower layer's wall, and mortar is then poured into the rectangle that fixed border 103 and connecting plate 201 surround In frame, then mortar shakeout, keeps the height of mortar concordant with 103 height of fixed border, can so accurately control mortar Laying depth after laying, then drags fixed mould bases 1 by handle 101 and is moved forward along wall, continues to spread mortar If since the padded plate 104 of fixation and movable padded plate 205 block the edge inside and outside brick body, to make the mortar of laying A distance is still remained with apart from wall edge, to make brick body when hammering pressure into shape, certain extension space is reserved for mortar, prevents Mortar is fallen, while also be can avoid mortar and being protruded wall.
It is advanced optimized for above-described embodiment, although using fixed padded plate 104 and living in the above-described embodiments Move padded plate and 205 block the edge inside and outside brick body so that the mortar of laying apart from wall edge still remain with one section away from From, to make brick body when hammering pressure into shape, certain extension space is reserved for mortar, prevents mortar from falling, but in mould bases use Early period in the process there is still a need for mortar is poured into mold using cleaver is rough, is then spread out mortar using cleaver It is flat, it is less efficient, therefore be further improved to realize quickly shakeouing for mud using the blade structure that can be pushed and pulled, it is specific to improve Structure is:Being adjacent on the medial surface of brick for two longer parallel edges of the fixed border 103 is provided with fluted body slideway, Scraper plate is installed, scraper plate is slided by sliding block in slideway, and middle scraper is articulated and connected with sliding block in slideway;Setting at the top of scraper plate There are drawing handle, the similar length of scraper plate bottom width and two shorter parallel edges of fixed border 103, the vertical height of scraper plate It is identical as the height of fixed border 103.
The articulated connection of scraper plate and sliding block in the improved structure allows scraper plate to adjust its angle of inclination and makes, at it Angle of inclination can be adjusted on trip path so that shakeouing action is smoothed out.
The improved structure can also solve another defect:Although mould bases be by can mutual dislocation sliding fixation mould bases It is formed with mobile side plate two parts, but dislocation sliding only can adapt to the width of brick, not adapt to the length of brick, Therefore the vertical height of scraper plate Curve guide impeller identical as the height of fixed border 103 is coordinated to the articulated connection of scraper plate and sliding block, It can make the length according to brick that scraper plate is stuck in any place in slideway, due to the vertical height and fixed border of scraper plate 103 height is identical, and the effect of scraper plate at this time is similar to gate of cutting off the water supply, and can completely limit the mortar in fixed border 103 For target brick block length, and stop that mud flows out.
Additionally due to padded harden structure designs so that mortar flows just shakeouts brick adjacent edges, in technique of building a wall It also needs to carry out the mortar between brick before knocking off and smoothes out beautification process, the dull face of cleaver is utilized in traditional handicraft or with one The tablet for determining thickness carries out mortar floating in brickwork joint, in the present invention by the structural integrity to 105 He of the first molgogger In second molgogger 207:The cylinder of first molgogger 105 and the second molgogger 207 is cylinder, the circumference of the cylinder There are two annular protrusion, two annular protrusions are separately positioned on the both ends of cylinder for setting on face, realize and play mould in guiding ball Frame sliding is while be clamped in newest one layer of brick both sides, additionally it is possible to by the mortar in the brickwork joint among neighbouring relatively low two layers into Row smoothes out neat.
The height of cylinder is suitable with the double thickness of brick, the annular protrusion there are two settings on the periphery of the cylinder, Two annular protrusions are separately positioned on the both ends of cylinder, and two raised to can be designed so that as the height built a wall increases, often Mortar between two layers of brick can be smoothed out twice, and operating efficiency is smoothed out to increase to smooth out aesthetic effect and promoted.
In addition mould bases is being pulled using handle 101, mould bases is smooth under the rolling support of molgogger, in order to prevent handle It is firmly uneven that one side molgogger is caused to be adjacent to brick, and another side molgogger is adjacent to brick far from brick, to cause Mould bases bit freezing can not smooth out sliding, therefore cylinder is disposed as elastomeric material, and the spontaneous retractility of the elastic material can To make up the above-mentioned bit freezing phenomenon that firmly inhomogeneities is brought to a certain extent, because the cylinder of elastic material can ensure position The molgogger moment in brick both sides can be kept in contact with brick, to ensure normal sliding.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (8)

1. one kind is built a wall with quickly plastering mould bases, it is characterised in that:Including fixed mould bases (1) and mobile side plate (2), the movement Side plate (2) is slidably mounted on fixed mould bases (1) side, and the mobile side plate (2) passes through lock with the fixed mould bases (1) The tight fixed locking of part (3);
The fixed mould bases (1) includes horizontally disposed fixed border (103), the fixed border (103) be it is U-shaped, it is described solid The outer edge of deckle frame (103) is provided with enclosing (102), and waist-shaped hole (106) is provided on the two sides of the enclosing (102), The bottom of the fixed border (103) is provided with lateral the first guide lip (107), and first guide lip (107) Vertically with the fixed border (103), the angle on the inside of first guide lip (107) with the fixed border (103) It is provided with fixed padded plate (104), is provided with the first molgogger (105) below the padded plate of fixation (104), described first It is provided with handle (101) above the side of guide lip (107), and the handle (101) is fixedly mounted on the enclosing (102) outside Side;
The mobile side plate (2) includes the flexible frame (202) and sliding baffle (203) of both sides, in the flexible frame (202) Between be provided with connecting plate (201), and the connecting plate (201) is horizontally disposed, and sliding baffle (203) setting is stretched described On the inside of frame (202), and the outline border size phase of the interior spacing and the enclosing (102) between two sliding baffles (203) Matching, two olos slid between baffles (203) and the U-shaped opening size of the fixed border (103) match, The flexible frame (202) is provided with locking hole (204), and the locking member (3) can be made to stretch into institute through the locking hole (204) It states in waist-shaped hole (106), the mobile side plate (2) and the fixed mould bases (1) is linked together, the connecting plate (201) Bottom is provided with the second guide lip (206) straight down, the second guide lip (206) inside and the connecting plate (201) angle is provided with the padded plate (205) of activity, and the second molgogger is provided with below the padded plate of activity (205) (207)。
2. one kind is built a wall with quickly plastering mould bases according to claim 1, it is characterised in that:
Being adjacent on the medial surface of brick for two longer parallel edges of the fixed border (103) is provided with fluted body slideway, Scraper plate is installed, scraper plate is slided by sliding block in slideway, and middle scraper is articulated and connected with sliding block in slideway;Setting at the top of scraper plate There are drawing handle, the similar length of scraper plate bottom width and two shorter parallel edges of fixed border (103), the vertical height of scraper plate Degree is identical as the height of fixed border 103, and the cylinder of the first molgogger (105) and the second molgogger (207) is cylinder, There are two annular protrusions, two annular protrusions to be separately positioned on the both ends of cylinder, the height of cylinder for setting on the periphery of the cylinder Degree is close with the double thickness of brick, and cylinder is elastomeric material.
3. being built a wall with quickly plastering mould bases according to the described one kind of any one of claim 1-2, it is characterised in that:The fixed border (103) width is 1-2cm, thickness 0.5cm.
4. being built a wall with quickly plastering mould bases according to the described one kind of any one of claim 1-2, it is characterised in that:The enclosing (102) perpendicular to the fixed border (103), and the height 3-5cm of the enclosing (102), and thickness and the fixed border (103) identical;
5. wanting the described one kind of any one of 1-3 to build a wall with quickly plastering mould bases according to right, it is characterised in that:First orienting roll Column (105) is uniformly distributed along first guide lip (107), and the axis of first molgogger (105) is perpendicular to institute State fixed padded plate (104).
6. being built a wall with quickly plastering mould bases according to the described one kind of any one of claim 1-4, it is characterised in that:The locking member (3) it is mating screw bolt and nut.
7. being built a wall with quickly plastering mould bases according to the described one kind of any one of claim 1-2, it is characterised in that:The activity is padded Plate (205) is identical with the height of the padded plate of the fixation (104).
8. being built a wall with quickly plastering mould bases according to the described one kind in any one of claim 1-2,5, it is characterised in that:Second orienting roll Column (207) is uniformly distributed along second guide lip (206), and the axis of second molgogger (207) is perpendicular to institute State the padded plate (205) of activity.
CN201810197430.5A 2018-03-11 2018-03-11 Quick plastering formwork for wall building Active CN108487651B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810197430.5A CN108487651B (en) 2018-03-11 2018-03-11 Quick plastering formwork for wall building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810197430.5A CN108487651B (en) 2018-03-11 2018-03-11 Quick plastering formwork for wall building

Publications (2)

Publication Number Publication Date
CN108487651A true CN108487651A (en) 2018-09-04
CN108487651B CN108487651B (en) 2020-07-17

Family

ID=63338221

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810197430.5A Active CN108487651B (en) 2018-03-11 2018-03-11 Quick plastering formwork for wall building

Country Status (1)

Country Link
CN (1) CN108487651B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908753A (en) * 2022-05-23 2022-08-16 中国建筑土木建设有限公司 Thickness control device of pipeline cushion layer and using method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201106288Y (en) * 2007-10-17 2008-08-27 中天建设集团有限公司 Masonry pointing joint stick
CN204152221U (en) * 2014-10-24 2015-02-11 中建海峡建设发展有限公司 Jointing instrument
CN204663014U (en) * 2015-05-12 2015-09-23 中国十七冶集团有限公司 A kind of mortar mortar joint precise control device
CN106894640A (en) * 2017-03-21 2017-06-27 中建三局第建设工程有限责任公司 One kind builds device and its application method by laying bricks or stones
CN206928667U (en) * 2017-06-05 2018-01-26 上海市浦东新区建设(集团)有限公司 A kind of Simple adjustable mortar masonry quality control device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201106288Y (en) * 2007-10-17 2008-08-27 中天建设集团有限公司 Masonry pointing joint stick
CN204152221U (en) * 2014-10-24 2015-02-11 中建海峡建设发展有限公司 Jointing instrument
CN204663014U (en) * 2015-05-12 2015-09-23 中国十七冶集团有限公司 A kind of mortar mortar joint precise control device
CN106894640A (en) * 2017-03-21 2017-06-27 中建三局第建设工程有限责任公司 One kind builds device and its application method by laying bricks or stones
CN206928667U (en) * 2017-06-05 2018-01-26 上海市浦东新区建设(集团)有限公司 A kind of Simple adjustable mortar masonry quality control device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908753A (en) * 2022-05-23 2022-08-16 中国建筑土木建设有限公司 Thickness control device of pipeline cushion layer and using method thereof

Also Published As

Publication number Publication date
CN108487651B (en) 2020-07-17

Similar Documents

Publication Publication Date Title
CA2566706C (en) Concrete sideform system
CN203361206U (en) Basement advanced water-stop post-cast strip construction structure
CN106894640A (en) One kind builds device and its application method by laying bricks or stones
CN110644723A (en) Construction method for laying floor tiles for building decoration
CN206205466U (en) A kind of masonry mortar lying device
CN108487651A (en) One kind is built a wall with quickly plastering mould bases
CN212389031U (en) Mortar spreader for mortar joints of masonry
CN204825542U (en) Multifunctional road square brick
CN216339345U (en) Adjustable groove template convenient to assemble
CN111550017B (en) Multifunctional mortar trowelling device
CN212201376U (en) Mortar spreading mold for building brick wall
CN209976052U (en) Masonry mortar paving equipment
CN108193889A (en) A kind of masonry wall quickly spread slurry, jointing device
CN207892258U (en) A kind of masonry wall quickly spread slurry, jointing device
CN111677302A (en) Wall building auxiliary tool
CN207727934U (en) Wall construction robot device of plastering a wall
CN214786156U (en) Masonry engineering plastering unit of adjustable width
CN215107032U (en) Mortar strickle-off ruler for paving bricks
CN210316413U (en) Adjustable concrete automatic allocation device for tile construction
CN215055537U (en) Mortar smearing device for wall building
CN207988452U (en) A kind of equipment for controlling walltile edge patch and filleting precision
CN205907886U (en) Building energy conservation and structure integration composite self -insulation building block
CN218715301U (en) Pointing device of adjustable infilled wall mortar joint
CN110984598A (en) Ash paving device for different masonry structures
CN211775931U (en) Mortar joint plastering device for brick masonry

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant