CN108460189A - A kind of curtain wall mounting design method based on BIM technology - Google Patents

A kind of curtain wall mounting design method based on BIM technology Download PDF

Info

Publication number
CN108460189A
CN108460189A CN201810115323.3A CN201810115323A CN108460189A CN 108460189 A CN108460189 A CN 108460189A CN 201810115323 A CN201810115323 A CN 201810115323A CN 108460189 A CN108460189 A CN 108460189A
Authority
CN
China
Prior art keywords
curtain wall
wall unit
unit component
installation
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810115323.3A
Other languages
Chinese (zh)
Inventor
赵山
薛洪春
周永祥
樊军
梁娜
韩爱红
司林军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Water Resources and Electric Power
Original Assignee
North China University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Water Resources and Electric Power filed Critical North China University of Water Resources and Electric Power
Priority to CN201810115323.3A priority Critical patent/CN108460189A/en
Publication of CN108460189A publication Critical patent/CN108460189A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Abstract

A kind of curtain wall mounting design method based on BIM technology comprising following steps:(1) the two-dimentional drawing of curtain wall is imported in BIM softwares Revit, the threedimensional model of curtain wall unit component to be installed is established according to modeling specification;(2) threedimensional model of above-mentioned curtain wall unit component is exported into detail drawing, factory is processed production according to the detail drawing of curtain wall unit component;(3) three-dimensional point cloud model of curtain wall unit component is established using fixed point cloud information;(4) information of curtain wall unit component is adjusted with process equipment;(5) three-dimensional point cloud model of the curtain wall unit component to meeting code requirement simulates curtain wall in Revit and carries out whole pre-installation, and entity component installation is carried out according to the process of pre-installation.The curtain wall mounting design method based on BIM technology of the present invention solves the problems, such as that curtain wall in-site installation difficulty is big, installation effectiveness is low low with precision.

Description

A kind of curtain wall mounting design method based on BIM technology
Technical field
The present invention relates to the Curtain Wall Design technical fields of building structure, and in particular, to a kind of based on BIM technology Curtain wall mounting design method.
Background technology
In recent years, with the fast development of Chinese society economy, the urbanization degree in city greatly improves.It is panoramic Building becomes a urban and indicates.Curtain wall as melt Building technology, building function, the art of architecture in one building external Watch box system deservedly becomes the main advanced external decoration of current building.
Curtain wall construction is still a difficult point in construction so far, and two-dimensional design drawing is difficult to show curtain wall effect after molding Fruit, unit in charge of construction rule of thumb check in drawing whether there is lacuna early period, with building plan size be inferred to plane figure, The position of built-in fitting, due to receiving two-dimensional limitation, it is difficult to the reasonability of consideration drawing that can be comprehensive.In work progress The position deviation for embedded part occur is big, need to rearrange postposition component, causes largely to do over again and that post-install is brought is serious Security risk, it is unreasonable due to layout, it causes the use of material a large amount of waste occur, tells somebody what one's real intentions are not in place, after these are all given Phase use brings influence, and traditional curtain wall construction quality needs the experience of the quality and curtain wall construction unit by drawing substantially, The case where in the presence of doing over again, can increase Master Cost and influence construction efficiency.
BIM (Building Information Modeling), also known as Building Information Model, are a kind of novel works The Computer Applied Technology of journey construction industry, every relevant information data by designing, using construction-engineering project is as mould The basis of type is shared in the lifecycle process in the stages such as the planning of construction project, design, construction, operation management And transmission, so that engineers and technicians is made correct understanding and efficiently reply to various architecture informations, is design team, unit in charge of construction And each side's construction bodies including building unit of operation provide the basis to cooperate, are improving production efficiency, are saving Cost plays a significant role with aspect is shortened the construction period.
For the above technical barrier, there is an urgent need for a kind of targetedly technical method or means, to assist engineering each side more effective Accurate Parametric designing, control, coordination and management are carried out to the curtain wall installation of large-scale, complicated construction project.
Invention content
To solve the above problems, the present invention provides a kind of curtain wall mounting design method based on BIM technology.The present invention's Curtain wall mounting design method based on BIM technology solves that curtain wall in-site installation difficulty is big, installation effectiveness is low low with precision asks Topic.
The present invention to solve above-mentioned technical problem used by technical solution be it is a kind of based on BIM technology curtain wall installation set Meter method comprising following steps:
(1) the two-dimentional drawing of curtain wall is imported in BIM softwares Revit, curtain wall unit to be installed is established according to modeling specification The threedimensional model of component fully considers space and utilizes the principle of material to greatest extent, utilizes BIM Structure Calculation functions when establishing Determine material, model, size, absolute altitude, angle, the node of the curtain wall unit component in the threedimensional model of installation curtain wall unit component Processing, pipeline headroom, thin portion structural information;
(2) threedimensional model of above-mentioned curtain wall unit component is imported in 3Dmax softwares, if curtain wall unit component is divided into Dry unit, renders facade effect after molding, exports the detail drawing of curtain wall unit component, and to the detail drawing of curtain wall unit component It is numbered, factory is processed production according to the detail drawing of curtain wall unit component;
(3) it uses three-dimensional laser scanner to carry out 3-D scanning to the curtain wall unit component of above-mentioned completion of processing, obtains The three-dimensional coordinate set of the numerous specified points of curtain wall unit component surface is taken, that is, pinpoints cloud information, is built using the fixed point cloud information The three-dimensional point cloud model of vertical curtain wall unit component;
(4) above-mentioned three-dimensional point cloud model is imported in Revit, with the curtain wall unit component that is had built up in step (1) Threedimensional model is compared, and obtains the deviation of curtain wall unit component entity, if deviation has exceeded wanting for curtain wall installation specification It asks, then the information of curtain wall unit component is adjusted with process equipment, until meeting the requirement of curtain wall installation specification;
(5) it is whole to simulate curtain wall progress in Revit for the three-dimensional point cloud model of the curtain wall unit component to meeting code requirement Body pre-installs, and includes the first simulation animation of the installation process of the embedded part and keel of setting curtain wall unit component, curtain wall list is arranged The second simulation animation that first component is combined with the embedded part;First simulation animation and second simulation animation are carried out Synthesis;And first simulation animation and second simulation animation after synthesis are demonstrated in output;During pre-installation The accumulated error for observing curtain wall unit component, if accumulated error can not be eliminated, with process equipment to there is the curtain wall list of error The information of first component is adjusted, until the curtain wall unit structure being had built up in the three-dimensional point cloud model of pre-installation and step (1) The threedimensional model of part exactly matches, and then curtain wall unit component manufacture is dispensed into construction site, is carried out according to the process of pre-installation Entity component is installed;
(6) it when entity component is installed, with BIM to the live unwrapping wire coordinate of three-dimensional modeling output of curtain wall unit component, puts Finally the installation of the frame of curtain wall unit component is positioned without the complementation of dead angle prism using continuous non-prism and 360 when sample.
Preferably, the detail drawing of curtain wall unit component includes size, angle, warp value, quantity and weight in the step (2) Information.
In any of the above-described scheme preferably, the threedimensional model of Revit softwares is led with dwf formats in step (2) Go out, opened with Navisworks, then import in 3Dmax softwares, then applies Navisworks software renders three-dimensional information models.
In any of the above-described scheme preferably, process equipment is adjusted curtain wall unit component in step (5), adjustment Data include the length of side, catercorner length, corner angle, apex angle coordinate data, arc length, sagitta, curtain wall unit component keel point Segment number, processing length, keel arc length and keel sagitta.
In any of the above-described scheme preferably, the method further includes the crashworthiness to curtain wall construction after step (6) Ability detecting step is hit, parametrization curtain wall BIM models are established specially in BIM softwares;To constituting each model in BIM models Unit carries out indoor impact resistant capability detection;Outdoor impact resistant capability detection is carried out to each model unit constituted in BIM models; Outdoor impact resistant capability detection exports crash data after meeting the requirements, and submits examining report.
In any of the above-described scheme preferably, the examining report includes form, position of collision and the collision of collision The coding of component.
The present invention be according to for many years practical application practice and experience obtained by, using best technological means and measure come into Row Combinatorial Optimization, obtains optimal technique effect, is not the simple superposition of technical characteristic and pieces together, therefore the present invention has Significant meaning.
Beneficial effects of the present invention:
1. the method for the present invention is by establishing the threedimensional model and three-dimensional point cloud model of curtain wall unit component, curtain wall unit structure The threedimensional model and three-dimensional point cloud model of part are compared, and are eliminated the deviation of curtain wall unit component entity, are improved in this way Installation accuracy and installation effectiveness, reduce installation difficulty.The error of curtain wall unit component is found by pre-installation and in time in work It is rectified and improved in factory, avoids construction site and do over again, ensured the duration, control construction cost.
2. the method for the present invention has given full play to the advantage of three-dimensional data, the utilization rate of material is improved, avoids wasting, Curtain wall use quality and safety are enhanced, threedimensional model also improves communication effectiveness, improves construction efficiency.
3. the method positioning of the present invention is convenient, accurately, it is greatly improved Curtain wall frame installation accuracy and welding quality, ensured Construction quality, and increase beauty, and construction safety;The present invention, which draws materials, to be facilitated, and easy to make, economical, societal benefits are notable, tool There is application value.
Specific implementation mode
Below in conjunction with specific embodiment, the invention will be further described, but claimed range is not limited thereto.
Embodiment 1
A kind of curtain wall mounting design method based on BIM technology comprising following steps:
(1) the two-dimentional drawing of curtain wall is imported in BIM softwares Revit, curtain wall unit to be installed is established according to modeling specification The threedimensional model of component fully considers space and utilizes the principle of material to greatest extent, utilizes BIM Structure Calculation functions when establishing Determine material, model, size, absolute altitude, angle, the node of the curtain wall unit component in the threedimensional model of installation curtain wall unit component Processing, pipeline headroom, thin portion structural information;
(2) threedimensional model of above-mentioned curtain wall unit component is imported in 3Dmax softwares, if curtain wall unit component is divided into Dry unit, renders facade effect after molding, exports the detail drawing of curtain wall unit component, and to the detail drawing of curtain wall unit component It is numbered, factory is processed production according to the detail drawing of curtain wall unit component;
(3) it uses three-dimensional laser scanner to carry out 3-D scanning to the curtain wall unit component of above-mentioned completion of processing, obtains The three-dimensional coordinate set of the numerous specified points of curtain wall unit component surface is taken, that is, pinpoints cloud information, is built using the fixed point cloud information The three-dimensional point cloud model of vertical curtain wall unit component;
(4) above-mentioned three-dimensional point cloud model is imported in Revit, with the curtain wall unit component that is had built up in step (1) Threedimensional model is compared, and obtains the deviation of curtain wall unit component entity, if deviation has exceeded wanting for curtain wall installation specification It asks, then the information of curtain wall unit component is adjusted with process equipment, until meeting the requirement of curtain wall installation specification;
(5) it is whole to simulate curtain wall progress in Revit for the three-dimensional point cloud model of the curtain wall unit component to meeting code requirement Body pre-installs, and includes the first simulation animation of the installation process of the embedded part and keel of setting curtain wall unit component, curtain wall list is arranged The second simulation animation that first component is combined with the embedded part;First simulation animation and second simulation animation are carried out Synthesis;And first simulation animation and second simulation animation after synthesis are demonstrated in output;During pre-installation The accumulated error for observing curtain wall unit component, if accumulated error can not be eliminated, with process equipment to there is the curtain wall list of error The information of first component is adjusted, until the curtain wall unit structure being had built up in the three-dimensional point cloud model of pre-installation and step (1) The threedimensional model of part exactly matches, and then curtain wall unit component manufacture is dispensed into construction site, is carried out according to the process of pre-installation Entity component is installed;
(6) it when entity component is installed, with BIM to the live unwrapping wire coordinate of three-dimensional modeling output of curtain wall unit component, puts Finally the installation of the frame of curtain wall unit component is positioned without the complementation of dead angle prism using continuous non-prism and 360 when sample.
The detail drawing of curtain wall unit component includes size, angle, warp value, quantity and weight information in the step (2).
The threedimensional model of Revit softwares is exported with dwf formats in step (2), is opened with Navisworks, then import In 3Dmax softwares, Navisworks software renders three-dimensional information models are then applied.
Process equipment is adjusted curtain wall unit component in step (5), adjustment data include the length of side, catercorner length, Corner angle, apex angle coordinate data, arc length, sagitta, the keel number of fragments of curtain wall unit component, processing length, keel arc length And keel sagitta.
The method further includes the impact resistant capability detecting step to curtain wall construction after step (6), specially in BIM Parametrization curtain wall BIM models are established in software;Indoor impact resistant capability inspection is carried out to each model unit constituted in BIM models It surveys;Outdoor impact resistant capability detection is carried out to each model unit constituted in BIM models;Outdoor impact resistant capability detection conforms to Crash data is exported after asking, and submits examining report.
The examining report includes the form collided, the coding of position of collision and crash element.
Embodiment 2
A kind of curtain wall mounting design method based on BIM technology comprising following steps:
(1) the two-dimentional drawing of curtain wall is imported in BIM softwares Revit, curtain wall unit to be installed is established according to modeling specification The threedimensional model of component fully considers space and utilizes the principle of material to greatest extent, utilizes BIM Structure Calculation functions when establishing Determine material, model, size, absolute altitude, angle, the node of the curtain wall unit component in the threedimensional model of installation curtain wall unit component Processing, pipeline headroom, thin portion structural information;
(2) threedimensional model of above-mentioned curtain wall unit component is imported in 3Dmax softwares, if curtain wall unit component is divided into Dry unit, renders facade effect after molding, exports the detail drawing of curtain wall unit component, and to the detail drawing of curtain wall unit component It is numbered, factory is processed production according to the detail drawing of curtain wall unit component;
(3) it uses three-dimensional laser scanner to carry out 3-D scanning to the curtain wall unit component of above-mentioned completion of processing, obtains The three-dimensional coordinate set of the numerous specified points of curtain wall unit component surface is taken, that is, pinpoints cloud information, is built using the fixed point cloud information The three-dimensional point cloud model of vertical curtain wall unit component;
(4) above-mentioned three-dimensional point cloud model is imported in Revit, with the curtain wall unit component that is had built up in step (1) Threedimensional model is compared, and obtains the deviation of curtain wall unit component entity, if deviation has exceeded wanting for curtain wall installation specification It asks, then the information of curtain wall unit component is adjusted with process equipment, until meeting the requirement of curtain wall installation specification;
(5) it is whole to simulate curtain wall progress in Revit for the three-dimensional point cloud model of the curtain wall unit component to meeting code requirement Body pre-installs, and includes the first simulation animation of the installation process of the embedded part and keel of setting curtain wall unit component, curtain wall list is arranged The second simulation animation that first component is combined with the embedded part;First simulation animation and second simulation animation are carried out Synthesis;And first simulation animation and second simulation animation after synthesis are demonstrated in output;During pre-installation The accumulated error for observing curtain wall unit component, if accumulated error can not be eliminated, with process equipment to there is the curtain wall list of error The information of first component is adjusted, until the curtain wall unit structure being had built up in the three-dimensional point cloud model of pre-installation and step (1) The threedimensional model of part exactly matches, and then curtain wall unit component manufacture is dispensed into construction site, is carried out according to the process of pre-installation Entity component is installed;
(6) it when entity component is installed, with BIM to the live unwrapping wire coordinate of three-dimensional modeling output of curtain wall unit component, puts Finally the installation of the frame of curtain wall unit component is positioned without the complementation of dead angle prism using continuous non-prism and 360 when sample.Tool Body, whole process is accurately positioned using total powerstation, and the skeleton column of all curtain wall unit components is numbered, and setting is independent Coordinate to ensure by the control of Curtain wall frame column installation error within 1mm, while ensureing that Curtain wall frame is moulded and meeting curtain Wall design requirement.Surveying setting-out personnel by the embedded part position of curtain wall unit component with line of ink marker bullet in structure, and with cross hairs mark Remember that bolt-center point, construction personnel drill according to point, anchor bolt and embedded part are installed.It is in place that node component is installed, through total powerstation and After spirit level review position, absolute altitude are errorless, node component and the frame body of construction are connected and fixed temporarily using short steel pipes, fastener. After node component is in place, the keel of each curtain wall unit component in mounting framework cell cube, first spot welding successively is fixed, and review is errorless It is welded again afterwards.Position will be designed on prefabricated each curtain wall unit lifting component to building structure using tower crane and jack Set, in building structure embedded part and keel be connected and fixed.
The detail drawing of curtain wall unit component includes size, angle, warp value, quantity and weight information in the step (2).
The threedimensional model of Revit softwares is exported with dwf formats in step (2), is opened with Navisworks, then import In 3Dmax softwares, Navisworks software renders three-dimensional information models are then applied.
Process equipment is adjusted curtain wall unit component in step (5), adjustment data include the length of side, catercorner length, Corner angle, apex angle coordinate data, arc length, sagitta, the keel number of fragments of curtain wall unit component, processing length, keel arc length And keel sagitta.
The method further includes the impact resistant capability detecting step to curtain wall construction after step (6), specially in BIM Parametrization curtain wall BIM models are established in software;Indoor impact resistant capability inspection is carried out to each model unit constituted in BIM models It surveys;Outdoor impact resistant capability detection is carried out to each model unit constituted in BIM models;Outdoor impact resistant capability detection conforms to Crash data is exported after asking, and submits examining report.
The examining report includes the form collided, the coding of position of collision and crash element.
The method of the present invention is by establishing the threedimensional model and three-dimensional point cloud model of curtain wall unit component, curtain wall unit component Threedimensional model and three-dimensional point cloud model be compared, eliminate the deviation of curtain wall unit component entity, improve peace in this way Precision and installation effectiveness are filled, installation difficulty is reduced.The error of curtain wall unit component is found by pre-installation and in time in factory In rectify and improve, avoid construction site and do over again, ensured the duration, control construction cost.
In addition, the method for the present invention has given full play to the advantage of three-dimensional data, the utilization rate of material is improved, wave is avoided Take, also enhance curtain wall use quality and safety, threedimensional model also improves communication effectiveness, improves construction efficiency.
Finally, method of the invention positioning is convenient, accurately, is greatly improved Curtain wall frame installation accuracy and welding quality, It ensure that construction quality, and increase beauty, and construction safety;The present invention, which draws materials, to be facilitated, and easy to make, economical, societal benefits are aobvious It writes, there is application value.
The above described is only a preferred embodiment of the present invention, being not that the invention has other forms of limitations, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. Imitate embodiment.But it is every without departing from technical solution of the present invention content, according to the technical essence of the invention to above example institute Any simple modification, equivalent variations and the remodeling made, still fall within the protection domain of technical solution of the present invention.

Claims (6)

1. a kind of curtain wall mounting design method based on BIM technology, which is characterized in that include the following steps:
(1) the two-dimentional drawing of curtain wall is imported in BIM softwares Revit, curtain wall unit component to be installed is established according to modeling specification Threedimensional model, fully considered when establishing space and to greatest extent utilize material principle, utilize BIM Structure Calculation functions determine Install the material of curtain wall unit component in the threedimensional model of curtain wall unit component, model, size, absolute altitude, angle, at node Reason, pipeline headroom, thin portion structural information;
(2) threedimensional model of above-mentioned curtain wall unit component is imported in 3Dmax softwares, curtain wall unit component is divided into several Unit renders facade effect after molding, exports the detail drawing of curtain wall unit component, and carry out to the detail drawing of curtain wall unit component Number, factory are processed production according to the detail drawing of curtain wall unit component;
(3) it uses three-dimensional laser scanner to carry out 3-D scanning to the curtain wall unit component of above-mentioned completion of processing, obtains curtain The three-dimensional coordinate set of the numerous specified points in wall unit member surface pinpoints cloud information, curtain is established using the fixed point cloud information The three-dimensional point cloud model of wall unit member;
(4) above-mentioned three-dimensional point cloud model is imported in Revit, the three-dimensional with the curtain wall unit component being had built up in step (1) Model is compared, and obtains the deviation of curtain wall unit component entity, if deviation has exceeded the requirement of curtain wall installation specification, The information of curtain wall unit component is adjusted with process equipment, until meeting the requirement of curtain wall installation specification;
(5) it is whole pre- to simulate curtain wall progress in Revit for the three-dimensional point cloud model of the curtain wall unit component to meeting code requirement Installation includes the first simulation animation of the installation process of the embedded part and keel of setting curtain wall unit component, curtain wall unit structure is arranged The second simulation animation that part is combined with the embedded part;First simulation animation and second simulation animation are closed At;And first simulation animation and second simulation animation after synthesis are demonstrated in output;It is seen during pre-installation The accumulated error of curtain wall unit component is examined, if accumulated error can not be eliminated, with process equipment to there is the curtain wall unit of error The information of component is adjusted, until the curtain wall unit component being had built up in the three-dimensional point cloud model of pre-installation and step (1) Threedimensional model exactly match, then curtain wall unit component manufacture is dispensed into construction site, is carried out according to the process of pre-installation real Body component is installed;
(6) when entity component is installed, with BIM to the live unwrapping wire coordinate of the three-dimensional modeling of curtain wall unit component output, when setting-out Using continuous non-prism and 360 without the complementation of dead angle prism, finally the installation of the frame of curtain wall unit component is positioned.
2. the curtain wall mounting design method according to claim 1 based on BIM technology, which is characterized in that the step (2) The detail drawing of middle curtain wall unit component includes size, angle, warp value, quantity and weight information.
3. the curtain wall mounting design method according to claim 2 based on BIM technology, which is characterized in that in step (2) The threedimensional model of Revit softwares is exported with dwf formats, is opened with Navisworks, then import in 3Dmax softwares, is then answered With Navisworks software renders three-dimensional information models.
4. the curtain wall mounting design method according to claim 3 based on BIM technology, which is characterized in that add in step (5) Construction equipment is adjusted curtain wall unit component, and adjustment data include the length of side, catercorner length, corner angle, apex angle number of coordinates According to, the keel number of fragments of arc length, sagitta, curtain wall unit component, processing length, keel arc length and keel sagitta.
5. the curtain wall mounting design method according to claim 4 based on BIM technology, which is characterized in that the method exists Further include the impact resistant capability detecting step to curtain wall construction after step (6), parametrization curtain is established specially in BIM softwares Wall BIM models;Indoor impact resistant capability detection is carried out to each model unit constituted in BIM models;To constituting in BIM models Each model unit carries out outdoor impact resistant capability detection;Outdoor impact resistant capability detection exports crash data after meeting the requirements, and carries Hand over examining report.
6. the curtain wall mounting design method according to claim 5 based on BIM technology, which is characterized in that the detection report Announcement includes the form collided, the coding of position of collision and crash element.
CN201810115323.3A 2018-02-06 2018-02-06 A kind of curtain wall mounting design method based on BIM technology Pending CN108460189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810115323.3A CN108460189A (en) 2018-02-06 2018-02-06 A kind of curtain wall mounting design method based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810115323.3A CN108460189A (en) 2018-02-06 2018-02-06 A kind of curtain wall mounting design method based on BIM technology

Publications (1)

Publication Number Publication Date
CN108460189A true CN108460189A (en) 2018-08-28

Family

ID=63239421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810115323.3A Pending CN108460189A (en) 2018-02-06 2018-02-06 A kind of curtain wall mounting design method based on BIM technology

Country Status (1)

Country Link
CN (1) CN108460189A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109299546A (en) * 2018-09-28 2019-02-01 浙江大境筑科技发展有限公司 Curtain wall engineering amount statistical method based on BIM
CN109440987A (en) * 2018-09-29 2019-03-08 中铁二局集团有限公司 A kind of construction method of the element type curtain wall of super high-rise building
CN109583033A (en) * 2018-11-02 2019-04-05 广东省水利水电第三工程局有限公司 Application method and system of the BIM adaptive model in special-shaped curtain wall construction
CN109740219A (en) * 2018-12-25 2019-05-10 三箭建设工程集团有限公司 A kind of double curved glass curtain wall preassembling system based on BIM
CN110056106A (en) * 2019-04-17 2019-07-26 中建八局第二建设有限公司 A kind of frame curtain wall quick assembling construction method and system based on BIM
CN110306809A (en) * 2019-07-23 2019-10-08 中国铁建大桥工程局集团有限公司 Steel construction curtain wall location and installation method for correcting error based on BIM 3 D laser scanning
CN110414181A (en) * 2019-08-08 2019-11-05 苏州宜特加建筑工程有限公司 A kind of design method of the heat insulating decorative board exterior wall based on BIM
CN110530344A (en) * 2019-09-18 2019-12-03 中国人民解放军63926部队 Utilize the method for the keel installation that total station and three-dimensional laser scanner assist
CN110569621A (en) * 2019-09-18 2019-12-13 中国十七冶集团有限公司 BIM technology-based multi-dimensional curved surface glass curtain wall design processing and installation method
CN110670772A (en) * 2019-09-30 2020-01-10 深圳龙源精造建设集团有限公司 Curtain wall installation method and system based on BIM technology
CN110864625A (en) * 2019-11-18 2020-03-06 上海建工四建集团有限公司 Method and system for installing, positioning and detecting construction site equipment
CN111005483A (en) * 2019-06-20 2020-04-14 方传斌 Curtain wall production and processing method based on BIM technology
CN111877616A (en) * 2020-05-26 2020-11-03 中建八局天津建设工程有限公司 Curtain wall installation method based on three-dimensional laser scanning
CN111931267A (en) * 2020-06-28 2020-11-13 上海市建筑装饰工程集团有限公司 Method for extracting processing data of special-shaped curtain wall keel
CN112177210A (en) * 2020-09-28 2021-01-05 苏州市华丽美登装饰装璜有限公司 Irrational multidirectional curved surface double-layer curtain wall construction structure and method based on BIM platform
CN112431420A (en) * 2020-07-30 2021-03-02 中建八局第二建设有限公司 Construction method of large-span double-sided arc aluminum plate curtain wall
CN112883997A (en) * 2021-01-11 2021-06-01 武汉坤能轨道系统技术有限公司 Rail transit fastener detection system and detection method
CN113177240A (en) * 2021-04-08 2021-07-27 中铁建工集团有限公司 Curtain wall construction method based on BIM and point cloud technology
CN113626915A (en) * 2021-08-06 2021-11-09 中国电建集团华东勘测设计研究院有限公司 Special-shaped curtain wall construction deviation rectifying method and device, storage medium and system
CN114577187A (en) * 2020-11-30 2022-06-03 中国核工业二三建设有限公司 Large-scale structure combined with laser scanning technology and equipment installation method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104123412A (en) * 2014-07-17 2014-10-29 金刚幕墙集团有限公司 Method for detecting collision of curtain wall through BIM technology
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN106968370A (en) * 2017-02-21 2017-07-21 中建七局建筑装饰工程有限公司 A kind of high speed payout, positioning and the baiting method of ball curtain wall
CN107165317A (en) * 2017-06-14 2017-09-15 中国建筑第六工程局有限公司 It is a kind of to be used for the steel disc shape node component and application process of special-shaped Curtain wall frame
WO2017181205A2 (en) * 2016-04-16 2017-10-19 Martinez Lazaro A Block interlocking module based (bim based) system to build architectural structures
CN107368618A (en) * 2017-06-01 2017-11-21 中国建筑第八工程局有限公司 A kind of hyperbolic curtain wall construction method based on BIM technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104123412A (en) * 2014-07-17 2014-10-29 金刚幕墙集团有限公司 Method for detecting collision of curtain wall through BIM technology
WO2017181205A2 (en) * 2016-04-16 2017-10-19 Martinez Lazaro A Block interlocking module based (bim based) system to build architectural structures
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN106968370A (en) * 2017-02-21 2017-07-21 中建七局建筑装饰工程有限公司 A kind of high speed payout, positioning and the baiting method of ball curtain wall
CN107368618A (en) * 2017-06-01 2017-11-21 中国建筑第八工程局有限公司 A kind of hyperbolic curtain wall construction method based on BIM technology
CN107165317A (en) * 2017-06-14 2017-09-15 中国建筑第六工程局有限公司 It is a kind of to be used for the steel disc shape node component and application process of special-shaped Curtain wall frame

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109299546A (en) * 2018-09-28 2019-02-01 浙江大境筑科技发展有限公司 Curtain wall engineering amount statistical method based on BIM
CN109440987A (en) * 2018-09-29 2019-03-08 中铁二局集团有限公司 A kind of construction method of the element type curtain wall of super high-rise building
CN109583033A (en) * 2018-11-02 2019-04-05 广东省水利水电第三工程局有限公司 Application method and system of the BIM adaptive model in special-shaped curtain wall construction
CN109583033B (en) * 2018-11-02 2020-09-15 广东省水利水电第三工程局有限公司 Application method and system of BIM self-adaptive model in construction of special-shaped curtain wall
CN109740219A (en) * 2018-12-25 2019-05-10 三箭建设工程集团有限公司 A kind of double curved glass curtain wall preassembling system based on BIM
CN109740219B (en) * 2018-12-25 2023-06-20 三箭建设工程集团有限公司 Hyperboloid glass curtain wall pre-assembling system based on BIM
CN110056106A (en) * 2019-04-17 2019-07-26 中建八局第二建设有限公司 A kind of frame curtain wall quick assembling construction method and system based on BIM
CN111005483A (en) * 2019-06-20 2020-04-14 方传斌 Curtain wall production and processing method based on BIM technology
CN110306809A (en) * 2019-07-23 2019-10-08 中国铁建大桥工程局集团有限公司 Steel construction curtain wall location and installation method for correcting error based on BIM 3 D laser scanning
CN110414181A (en) * 2019-08-08 2019-11-05 苏州宜特加建筑工程有限公司 A kind of design method of the heat insulating decorative board exterior wall based on BIM
CN110569621A (en) * 2019-09-18 2019-12-13 中国十七冶集团有限公司 BIM technology-based multi-dimensional curved surface glass curtain wall design processing and installation method
CN110530344A (en) * 2019-09-18 2019-12-03 中国人民解放军63926部队 Utilize the method for the keel installation that total station and three-dimensional laser scanner assist
CN110569621B (en) * 2019-09-18 2022-09-13 中国十七冶集团有限公司 BIM technology-based multi-dimensional curved surface glass curtain wall design processing and installation method
CN110670772B (en) * 2019-09-30 2021-05-28 深圳龙源精造建设集团有限公司 Curtain wall installation method and system based on BIM technology
CN110670772A (en) * 2019-09-30 2020-01-10 深圳龙源精造建设集团有限公司 Curtain wall installation method and system based on BIM technology
CN110864625A (en) * 2019-11-18 2020-03-06 上海建工四建集团有限公司 Method and system for installing, positioning and detecting construction site equipment
CN111877616A (en) * 2020-05-26 2020-11-03 中建八局天津建设工程有限公司 Curtain wall installation method based on three-dimensional laser scanning
CN111931267A (en) * 2020-06-28 2020-11-13 上海市建筑装饰工程集团有限公司 Method for extracting processing data of special-shaped curtain wall keel
CN112431420A (en) * 2020-07-30 2021-03-02 中建八局第二建设有限公司 Construction method of large-span double-sided arc aluminum plate curtain wall
CN112177210A (en) * 2020-09-28 2021-01-05 苏州市华丽美登装饰装璜有限公司 Irrational multidirectional curved surface double-layer curtain wall construction structure and method based on BIM platform
CN114577187A (en) * 2020-11-30 2022-06-03 中国核工业二三建设有限公司 Large-scale structure combined with laser scanning technology and equipment installation method
CN112883997A (en) * 2021-01-11 2021-06-01 武汉坤能轨道系统技术有限公司 Rail transit fastener detection system and detection method
CN113177240A (en) * 2021-04-08 2021-07-27 中铁建工集团有限公司 Curtain wall construction method based on BIM and point cloud technology
CN113177240B (en) * 2021-04-08 2023-08-08 中铁建工集团有限公司 Curtain wall construction method based on BIM and point cloud technology
CN113626915A (en) * 2021-08-06 2021-11-09 中国电建集团华东勘测设计研究院有限公司 Special-shaped curtain wall construction deviation rectifying method and device, storage medium and system
CN113626915B (en) * 2021-08-06 2023-11-28 中国电建集团华东勘测设计研究院有限公司 Abnormal curtain wall construction deviation rectifying method, device, storage medium and system

Similar Documents

Publication Publication Date Title
CN108460189A (en) A kind of curtain wall mounting design method based on BIM technology
CN106988221B (en) Unit construction bridge beam construction method based on BIM
CN106968370B (en) A kind of high speed payout, positioning and the baiting method of ball curtain wall
WO2021128675A1 (en) Bim technology-based method for constructing underground continuous wall
CN104123412B (en) A kind of curtain wall collision checking method by BIM technology
CN106326536A (en) Standardized construction method for hydraulic prefabricated member based on BIM (Building Information Modeling)
CN107885918A (en) A kind of Architectural Structure Design method and apparatus based on BIM technology
CN108228967A (en) A kind of production of assembled pipeline based on BIM and mounting process
CN108280281A (en) A kind of construction cost control method and system based on BIM technology
CN108427782A (en) A kind of three-dimensional building model treatment method and device based on BIM
CN105468796A (en) Method for establishing temporary support moulding bed system for steel structure assembly
CN108416162A (en) A kind of construction method of the spiral formula reinforced concrete structure based on BIM
Huang et al. A framework for integrating embodied carbon assessment and construction feasibility in prefabricated stations
CN109558629B (en) Method and device for generating reinforcement arrangement scheme
Samarasinghe et al. Innovative digital technologies
CN113392463A (en) Modular building design method based on BIM technology
CN104594508A (en) Multidimensional space steel structure installation joint positioning construction method
Annenkov Monitoring the deformation process of engineering structures using bim technologies
CN108427831A (en) A method of optimizing dell building structure using outdoor scene modeling and BIM technology
Hongyan et al. Comparative analysis of civil engineering quantity calculation based on glodon gtj and revit
CN110634186A (en) Arch cover method underground excavation construction method based on BIM
CN115408756A (en) Railway continuous beam construction method based on BIM
CN109711060A (en) Window frame connector automatic generation method, device and equipment based on assembled architecture
Li et al. Application of point cloud data in the construction and management of interior design
Wang et al. Research on 4D simulation technology of reconstruction engineering construction organization based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180828

RJ01 Rejection of invention patent application after publication