CN108458334A - A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke - Google Patents

A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke Download PDF

Info

Publication number
CN108458334A
CN108458334A CN201810173882.XA CN201810173882A CN108458334A CN 108458334 A CN108458334 A CN 108458334A CN 201810173882 A CN201810173882 A CN 201810173882A CN 108458334 A CN108458334 A CN 108458334A
Authority
CN
China
Prior art keywords
heat
medium water
heat medium
heat exchanger
white smoke
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810173882.XA
Other languages
Chinese (zh)
Inventor
张锡乾
吴冲
耿宣
卢虎
杨彭飞
石旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huadian Engineering Group Co Ltd
Huadian Environmental Protection Engineering and Technology Co Ltd
Original Assignee
China Huadian Engineering Group Co Ltd
Huadian Environmental Protection Engineering and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huadian Engineering Group Co Ltd, Huadian Environmental Protection Engineering and Technology Co Ltd filed Critical China Huadian Engineering Group Co Ltd
Priority to CN201810173882.XA priority Critical patent/CN108458334A/en
Publication of CN108458334A publication Critical patent/CN108458334A/en
Pending legal-status Critical Current

Links

Classifications

    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22—STEAM GENERATION
    • F22D—PREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
    • F22D1/00—Feed-water heaters, i.e. economisers or like preheaters
    • F22D1/003—Feed-water heater systems
    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23J—REMOVAL OR TREATMENT OF COMBUSTION PRODUCTS OR COMBUSTION RESIDUES; FLUES 
    • F23J15/00—Arrangements of devices for treating smoke or fumes
    • F23J15/06—Arrangements of devices for treating smoke or fumes of coolers
    • F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23L—SUPPLYING AIR OR NON-COMBUSTIBLE LIQUIDS OR GASES TO COMBUSTION APPARATUS IN GENERAL ; VALVES OR DAMPERS SPECIALLY ADAPTED FOR CONTROLLING AIR SUPPLY OR DRAUGHT IN COMBUSTION APPARATUS; INDUCING DRAUGHT IN COMBUSTION APPARATUS; TOPS FOR CHIMNEYS OR VENTILATING SHAFTS; TERMINALS FOR FLUES
    • F23L15/00—Heating of air supplied for combustion
    • F23L15/04—Arrangements of recuperators
    • F23L15/045—Arrangements of recuperators using intermediate heat-transfer fluids
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00—Combustion technologies with mitigation potential
    • Y02E20/34—Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chimneys And Flues (AREA)

Abstract

The invention discloses a kind of novel thermal power plant's low temperature heat and the device and method of eliminating white smoke, belong to the industrial flue gas cleanings such as coal-fired power station boiler, Industrial Boiler, eliminating white smoke and waste heat recovery field.It is sequentially connected with through pipeline cycle between condensing heat exchanger, warm wind device assembly, heating agent water-circulating pump in the present apparatus, pipeline between condensing heat exchanger and warm wind device assembly is heating agent waterpipe, it is additionally provided with bypass duct on heating agent waterpipe, the end of bypass duct is connected with mechanical-draft cooling tower, and mechanical-draft cooling tower is also connected with heating agent water-circulating pump through pipeline.Condensing heat exchanger is mounted in the flue between chimney and absorption tower, and condensing heat exchanger is connect through bottom discharge pipe with absorption tower.Present apparatus device integration is high, easy to operate, and the method for additionally providing thermal power plant's low temperature heat and eliminating white smoke makes the risk of low-temperature corrosion of air preheater substantially reduce, and convenient for the moisture in extraction saturation wet flue gas, and then plays the role of eliminating white cigarette.

Description

一种新型火电厂低温余热利用及消白烟的装置和方法A new device and method for utilization of low-temperature waste heat and elimination of white smoke in thermal power plants

技术领域technical field

本发明涉及一种新型火电厂低温余热利用及消白烟的装置和方法,属于燃煤电站锅炉、工业锅炉等工业烟气净化、消白烟及余热回收领域。The invention relates to a novel low-temperature waste heat utilization device and method for thermal power plant and white smoke elimination, and belongs to the field of industrial flue gas purification, white smoke elimination and waste heat recovery of coal-fired power plant boilers and industrial boilers.

背景技术Background technique

燃煤电厂锅炉在运行中排烟热损失所占比重较大,目前,火电厂的能量利用率比较低,全厂热效率在35%~45%之间,约60%的能量被排放到环境中,没有被利用;并且一些火力发电厂运行排烟温度常常高于设计值,能量散失较大。同时,我国北方绝大多数的电厂室外环境温度低于-15℃左右,一次风、二次风温度较低,如果不经暖风器的换热,直接进入到空气预热器后,容易造成空气预热器的低温腐蚀,严重影响锅炉机组的运行安全。目前,火电厂吸收塔出口排烟温度在50℃左右,吸收塔出口烟气是饱和湿烟气,携带大量水蒸气,这部分水蒸气含有大量汽化潜热;同时,由于脱硫出口烟气为饱和湿烟气,排出烟囱后与冷空气混合,导致烟气中的水汽骤然凝结形成白烟,尤其在冬天,容易造成视觉上的污染,影响环境美观。因此,降低电站锅炉的排烟温度对于节能减排,消除烟囱出口白色烟雾具有重要的实际意义。Coal-fired power plant boilers account for a large proportion of exhaust heat loss during operation. At present, the energy utilization rate of thermal power plants is relatively low. The thermal efficiency of the whole plant is between 35% and 45%, and about 60% of the energy is discharged into the environment. , has not been utilized; and the exhaust gas temperature of some thermal power plants is often higher than the design value, and the energy loss is relatively large. At the same time, the outdoor ambient temperature of most power plants in northern my country is lower than -15°C, and the temperature of the primary air and secondary air is relatively low. The low-temperature corrosion of the air preheater seriously affects the operation safety of the boiler unit. At present, the flue gas temperature at the outlet of the absorption tower in thermal power plants is around 50°C, and the flue gas at the outlet of the absorption tower is saturated wet flue gas, which carries a large amount of water vapor. This part of water vapor contains a large amount of latent heat of vaporization; The flue gas, after being discharged from the chimney, mixes with the cold air, causing the water vapor in the flue gas to condense suddenly to form white smoke, especially in winter, it is easy to cause visual pollution and affect the appearance of the environment. Therefore, reducing the exhaust gas temperature of power plant boilers has important practical significance for energy saving and emission reduction, and for eliminating white smoke at the chimney outlet.

针对上述问题,以往的做法主要是:对于处理烟囱出口白烟的问题,一般采用烟气再热的方法,早期电厂主要采用GGH的较多,即利用脱硫前高温烟气的热量来加热脱硫后烟气,加热后的烟气温度在75℃以上,该方案起到了消白烟的作用,并没有对能量充分利用,同时容易造成设备低于酸露点腐蚀以及设备堵塞泄漏的问题。近几年消白烟的方法有MGGH,MGGH是一种水媒是换热器,该方案一般是在电除尘器入口安装降温段换热器,在脱硫出口安装升温段换热器,利用电除尘器前烟气的热量后加热脱硫后的烟气,该方案起到了在一定程度上起到了消白烟作用,但是并没有对能量充分利用。In view of the above problems, the previous practice is mainly: to deal with the problem of white smoke at the chimney outlet, the method of flue gas reheating is generally used. Early power plants mainly use GGH, that is, use the heat of high-temperature flue gas before desulfurization to heat the desulfurization. Flue gas, the temperature of the heated flue gas is above 75°C. This solution has the effect of eliminating white smoke, but does not make full use of energy. At the same time, it is easy to cause corrosion of equipment below the acid dew point and leakage of equipment blockage. In recent years, MGGH has been used to eliminate white smoke. MGGH is a water medium heat exchanger. The solution is generally to install a heat exchanger in the cooling section at the inlet of the electrostatic precipitator, and a heat exchanger in the heating section at the desulfurization outlet. The heat of the flue gas in front of the dust collector heats the flue gas after desulfurization. This scheme has played a role in eliminating white smoke to a certain extent, but it has not fully utilized the energy.

发明内容Contents of the invention

本发明的目的在于,提供一种新型火电厂低温余热利用及消白烟的装置,解决了现有技术的不足,该装置设备集成度高、操作简单、运行可靠;同时本发明还提供了一种新型火电厂低温余热利用及消白烟的方法,使空气预热器低温腐蚀的风险大大降低,同时使得脱硫出口烟气温度下降1~5℃左右,便于提取饱和湿烟气中的水分,进而起到消除白烟作用。The purpose of the present invention is to provide a new type of low-temperature waste heat utilization and white smoke elimination device in thermal power plants, which solves the shortcomings of the prior art. The device has high integration, simple operation and reliable operation; at the same time, the present invention also provides a device A new method of low-temperature waste heat utilization and white smoke elimination in thermal power plants greatly reduces the risk of low-temperature corrosion of the air preheater, and at the same time reduces the temperature of the flue gas at the desulfurization outlet by about 1-5 °C, which facilitates the extraction of moisture in the saturated wet flue gas. And then play the role of eliminating white smoke.

为解决上述技术问题,本发明采用如下的技术方案:In order to solve the problems of the technologies described above, the present invention adopts the following technical solutions:

一种新型火电厂低温余热利用及消白烟的装置包括烟囱、冷凝换热器、热媒水循环泵、旁路管道、机械通风冷却塔、热媒水管道、吸收塔、底部排水管和暖风器组件,所述吸收塔的顶部经烟道连接有烟囱,所述冷凝换热器、暖风器组件、热媒水循环泵之间经管道循环顺次连接,即热媒水循环泵出口与冷凝换热器入口相连接。所述冷凝换热器与暖风器组件之间的管道为热媒水管道,所述热媒水管道上还设有旁路管道,所述旁路管道的端部连接有机械通风冷却塔,所述机械通风冷却塔也经管道连接有热媒水循环泵。其中冷凝换热器安装在烟囱与吸收塔之间的烟道内,所述冷凝换热器经底部排水管与吸收塔连接。A new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant includes a chimney, a condensing heat exchanger, a heat medium water circulation pump, a bypass pipe, a mechanical ventilation cooling tower, a heat medium water pipe, an absorption tower, a bottom drain pipe and a warm air The top of the absorption tower is connected to a chimney through a flue, and the condensation heat exchanger, the heater assembly, and the heat medium water circulation pump are connected in sequence through pipeline circulation, that is, the outlet of the heat medium water circulation pump is connected to the condensate exchanger. connected to the heater inlet. The pipeline between the condensing heat exchanger and the air heater assembly is a heat medium water pipeline, and a bypass pipeline is also provided on the heat medium water pipeline, and the end of the bypass pipeline is connected with a mechanical ventilation cooling tower, The mechanical ventilation cooling tower is also connected with a heat medium water circulation pump through pipelines. Wherein the condensing heat exchanger is installed in the flue between the chimney and the absorption tower, and the condensing heat exchanger is connected with the absorption tower through a bottom drain pipe.

前述的新型火电厂低温余热利用及消白烟的装置,所述暖风器组件包括一次风暖风器和二次风暖风器,所述一次风暖风器的出口经管道连接于热媒水循环泵的入口,所述二次风暖风器的出口也经管道连接于热媒水循环泵的入口。其中一次风暖风器设于一次风机出口与空气预热器入口之间的风道上,其中二次风暖风器设于二次风机出口与空气预热器入口之间的风道上。In the aforementioned device for utilization of low-temperature waste heat and elimination of white smoke in a thermal power plant, the heater assembly includes a primary air heater and a secondary air heater, and the outlet of the primary air heater is connected to the heat medium through a pipeline. The inlet of the water circulation pump and the outlet of the secondary air heater are also connected to the inlet of the heat medium water circulation pump through pipelines. The primary air heater is arranged on the air passage between the outlet of the primary fan and the inlet of the air preheater, and the secondary air heater is arranged on the air passage between the outlet of the secondary fan and the inlet of the air preheater.

前述的新型火电厂低温余热利用及消白烟的装置,所述一次风暖风器和二次风暖风器的材质为铝合金或者普通碳钢。In the aforementioned new thermal power plant low-temperature waste heat utilization and white smoke elimination device, the primary air heater and the secondary air heater are made of aluminum alloy or ordinary carbon steel.

前述的新型火电厂低温余热利用及消白烟的装置,所述冷凝换热器由若干个换热模块组成,所述换热模块中的换热管材质为氟塑料或者不锈钢。In the aforementioned new low-temperature waste heat utilization and white smoke elimination device for thermal power plants, the condensing heat exchanger is composed of several heat exchange modules, and the heat exchange tubes in the heat exchange modules are made of fluoroplastic or stainless steel.

前述的新型火电厂低温余热利用及消白烟的装置还包括暖风器进口总阀和机械通风冷却塔入口阀门,所述暖风器进口总阀安装于热媒水管道上靠近暖风器组件的一端,所述机械通风冷却塔入口阀门安装于旁路管道上远离机械通风冷却塔的一端。The aforementioned device for low-temperature waste heat utilization and white smoke elimination in thermal power plants also includes a heater inlet master valve and a mechanical ventilation cooling tower inlet valve. The heater inlet master valve is installed on the heat medium water pipeline close to the heater assembly. One end of the mechanical draft cooling tower inlet valve is installed on the bypass pipe away from the end of the mechanical draft cooling tower.

前述的新型火电厂低温余热利用及消白烟的装置还包括机械通风冷却塔出口阀门和暖风器出口总阀,所述机械通风冷却塔出口阀门安装于机械通风冷却塔与热媒水循环泵之间的连接管道上,且是靠近机械通风冷却塔的一端。所述暖风器出口总阀安装于暖风器组件与热媒水循环泵之间的连接管道上,且是靠近暖风器组件的一端。The aforesaid new thermal power plant low-temperature waste heat utilization and white smoke elimination device also includes the outlet valve of the mechanical ventilation cooling tower and the main outlet valve of the heater. The outlet valve of the mechanical ventilation cooling tower is installed between the mechanical ventilation cooling tower and the heat medium water circulation pump. On the connecting pipe between them, and it is near the end of the mechanical ventilation cooling tower. The outlet main valve of the air heater is installed on the connecting pipe between the air heater assembly and the heat medium water circulation pump, and is near the end of the air heater assembly.

一种新型火电厂低温余热利用及消白烟的方法,采用前述的新型火电厂低温余热利用及消白烟的装置,包括以下步骤:A method for utilizing low-temperature waste heat and eliminating white smoke in a new type of thermal power plant, using the aforementioned device for utilizing low-temperature waste heat in a thermal power plant and eliminating white smoke, comprising the following steps:

S1,热媒水进入到冷凝换热器,通过冷凝换热器换热后热媒水温度升高,热媒水温度升高的同时使得吸收塔出口的烟气温度降低,从而提取烟气中的水分,进而起到消除白烟的作用,同时回收了一定的气化潜热;S1, the heat medium water enters the condensing heat exchanger, and the temperature of the heat medium water rises after passing through the condensing heat exchanger. The temperature of the heat medium water increases while the temperature of the flue gas at the outlet of the absorption tower decreases, thereby extracting the flue gas moisture, and then play the role of eliminating white smoke, while recovering a certain amount of latent heat of vaporization;

S2,升温后的热媒水经热媒水管道进入暖风器组件换热,具体的,包括以下步骤:S2, the heated heat medium water enters the heater assembly through the heat medium water pipeline for heat exchange, specifically, the following steps are included:

S21,升温后的热媒水进入一次风暖风器中,通过一次风暖风器的换热作用,使一次风温度升高,热媒水温度降低,升温后的一次风进入空气预热器;S21, the heated heat medium water enters the primary air heater, through the heat exchange effect of the primary air heater, the temperature of the primary air rises, the temperature of the heat medium water decreases, and the heated primary air enters the air preheater ;

S22,升温后的热媒水进入二次风暖风器中,通过二次风暖风器的换热作用,使二次风温度升高,热媒水温度降低,升温后的二次风进入空气预热器;S22, the heated heat medium water enters the secondary air heater, through the heat exchange effect of the secondary air heater, the temperature of the secondary air increases, the temperature of the heat medium water decreases, and the heated secondary air enters Air preheater;

S3,降温后的热媒水在热媒水循环泵的作用下,再次进入冷凝换热器中循环换热。该种方法适宜于冬季工况,冬季时,中国北方绝大多数的电厂室外环境温度低于-15℃左右,一次风、二次风如果不经暖风器组件的换热,直接进入到空气预热器后,容易造成空气预热器的低温腐蚀,严重影响锅炉机组的运行安全。为防止空气预热器低温腐蚀,冬季时关闭热媒水管道的旁路管道阀门,即关闭机械通风冷却塔入口阀门,使热媒水不经过机械通风冷却塔而直接进入到一次风暖风器和二次风暖风器进行换热,使风温从-15℃升高到25℃,从而降低空气预热器的低温腐蚀情况;同时,热媒水温度从45℃减低到25℃,然后通过热媒水循环泵升压的作用,使热媒水重新进入冷凝换热器换热,从而降低吸收塔出口烟气温度,减少烟气中的水分,起到消白烟的作用。S3, the cooled heat medium water enters the condensing heat exchanger again to exchange heat under the action of the heat medium water circulation pump. This method is suitable for winter working conditions. In winter, the outdoor ambient temperature of most power plants in northern China is lower than -15°C. If the primary air and secondary air directly enter the air without the heat exchange of the heater components After the preheater, it is easy to cause low-temperature corrosion of the air preheater, which seriously affects the operation safety of the boiler unit. In order to prevent low-temperature corrosion of the air preheater, the bypass pipe valve of the heat medium water pipeline is closed in winter, that is, the inlet valve of the mechanical ventilation cooling tower is closed, so that the heat medium water directly enters the primary air heater without passing through the mechanical ventilation cooling tower Exchange heat with the secondary air heater to increase the air temperature from -15°C to 25°C, thereby reducing the low-temperature corrosion of the air preheater; at the same time, the temperature of the heat medium water is reduced from 45°C to 25°C, and then Through the boosting effect of the heat medium water circulation pump, the heat medium water re-enters the condensing heat exchanger for heat exchange, thereby reducing the temperature of the flue gas at the outlet of the absorption tower, reducing the moisture in the flue gas, and playing the role of eliminating white smoke.

一种新型火电厂低温余热利用及消白烟的方法,采用前述的新型火电厂低温余热利用及消白烟的装置,包括以下步骤:A method for utilizing low-temperature waste heat and eliminating white smoke in a new type of thermal power plant, using the aforementioned device for utilizing low-temperature waste heat in a thermal power plant and eliminating white smoke, comprising the following steps:

S1,热媒水进入到冷凝换热器,通过冷凝换热器换热后热媒水温度升高,热媒水温度升高的同时使得吸收塔出口的烟气温度降低;S1, the heat medium water enters the condensing heat exchanger, and the temperature of the heat medium water increases after passing through the condensing heat exchanger, and the temperature of the heat medium water increases while the temperature of the flue gas at the outlet of the absorption tower decreases;

S2,升温后的热媒水经热媒水管道、旁路管道进入机械通风冷却塔进行喷淋降温,其中热媒水经过其中的喷淋填料减温后落入低温冷却水池;S2, the heated heat medium water enters the mechanical ventilation cooling tower through the heat medium water pipe and the bypass pipe for spraying and cooling, wherein the heat medium water falls into the low-temperature cooling pool after passing through the spray filler to reduce the temperature;

S3,降温后的热媒水在热媒水循环泵的作用下,再次进入冷凝换热器中循环换热。该种方法适宜于夏季工况,夏季时,由于环境温度在25~30℃左右,使暖风器入口风温高于原设计暖风器出口热媒水温度值,使暖风器组件不能够起到良好的换热效果。因此,为减少热媒水循环管道的阻力,关闭热媒水管道上暖风器组件的进出口管道阀门,即关闭暖风器进口总阀和暖风器出口总阀,使热媒水不经过暖风器组件而直接进入到机械通风冷却塔进行换热,使热媒水温度从45℃降低到25℃,然后通过热媒水循环泵升压的作用,使热媒水重新进入冷凝换热器换热,从而降低吸收塔出口烟气温度,减少烟气中的水分,起到消白烟的作用。S3, the cooled heat medium water enters the condensing heat exchanger again to exchange heat under the action of the heat medium water circulation pump. This method is suitable for working conditions in summer. In summer, because the ambient temperature is around 25-30°C, the air temperature at the inlet of the heater is higher than the temperature of the heat medium water at the outlet of the heater originally designed, so that the heater components cannot Play a good heat exchange effect. Therefore, in order to reduce the resistance of the heat medium water circulation pipeline, close the inlet and outlet pipe valves of the heater assembly on the heat medium water pipeline, that is, close the main inlet valve of the heater and the main outlet valve of the heater, so that the heat medium water does not pass through the heater. The fan assembly directly enters the mechanical ventilation cooling tower for heat exchange, reducing the temperature of the heat medium water from 45°C to 25°C, and then through the boosting effect of the heat medium water circulation pump, the heat medium water re-enters the condensing heat exchanger for exchange Heat, thereby reducing the temperature of the flue gas at the outlet of the absorption tower, reducing the moisture in the flue gas, and playing the role of eliminating white smoke.

前述的新型火电厂低温余热利用及消白烟的方法,所述冷凝换热器、一次风暖风器、二次风暖风器与热媒水之间的换热方式均为逆流换热,相比于其他换热方式,逆流换热可以强化换热,提高换热效率。In the aforementioned method for utilization of low-temperature waste heat in thermal power plants and elimination of white smoke, the heat exchange methods between the condensing heat exchanger, the primary air heater, the secondary air heater and the heat medium water are countercurrent heat exchange, Compared with other heat transfer methods, countercurrent heat transfer can strengthen heat transfer and improve heat transfer efficiency.

与现有技术相比,本发明的有益之处在于:Compared with the prior art, the benefits of the present invention are:

1、通过采用本发明中的装置,热媒水通过冷凝换热器,使脱硫出口烟气温度下降1~5℃,降低脱硫出口的饱和湿烟气的含湿量,回收一定的热量,同时收集烟气中的水分约10~15t/h,进而起到消白烟的作用;1. By adopting the device in the present invention, the heat medium water passes through the condensing heat exchanger to reduce the temperature of the flue gas at the desulfurization outlet by 1-5°C, reduce the moisture content of the saturated wet flue gas at the desulfurization outlet, and recover a certain amount of heat. Collect the moisture in the flue gas about 10-15t/h, and then play the role of eliminating white smoke;

2、热媒水通过冷凝换热器后温度从25℃升高到45℃左右,然后再进入到一次风暖风器和二次风暖风器进行换热,对一次风和二次风进行加热,使低温余热得以充分利用;2. After the heat medium water passes through the condensing heat exchanger, the temperature rises from 25°C to about 45°C, and then enters the primary air heater and the secondary air heater for heat exchange, and the primary air and secondary air are Heating, so that the low temperature waste heat can be fully utilized;

3、由于热媒水温度较低,不存在热媒水在管道中汽化的现象,因此热媒水的压力接近常压,进一步提高了装置运行的稳定性;3. Due to the low temperature of the heat medium water, there is no phenomenon of vaporization of the heat medium water in the pipeline, so the pressure of the heat medium water is close to normal pressure, which further improves the stability of the device operation;

4、吸收塔出口烟气通过冷凝换热器后,烟气中的气态水凝结为液态水,烟气中的一部分粉尘、细颗粒物也会被收集下来,也能起到一定的除尘作用;4. After the flue gas at the outlet of the absorption tower passes through the condensing heat exchanger, the gaseous water in the flue gas condenses into liquid water, and part of the dust and fine particles in the flue gas will also be collected, which can also play a certain role in dust removal;

5、采用新型火电厂低温余热利用及消白烟的方法,提高了空气预热器入口风温,回收了烟气热量,消除了白烟,提高了锅炉效率,降低了吸收塔出口粉尘浓度,实现电厂超低排放,提高了锅炉运行的经济性,该低温余热利用和消白烟装置适用但不局限于燃煤电站锅炉、工业锅炉等领域。5. Adopting a new type of thermal power plant low-temperature waste heat utilization and white smoke elimination method, the air temperature at the inlet of the air preheater is increased, the heat of the flue gas is recovered, the white smoke is eliminated, the boiler efficiency is improved, and the dust concentration at the outlet of the absorption tower is reduced. Realize the ultra-low emission of the power plant and improve the economy of boiler operation. The low-temperature waste heat utilization and white smoke elimination device is suitable for but not limited to coal-fired power plant boilers, industrial boilers and other fields.

附图说明Description of drawings

图1是本发明的工作流程图;Fig. 1 is a work flow chart of the present invention;

图2是本发明中机械通风冷却塔的工作原理图;Fig. 2 is the working principle figure of mechanical ventilation cooling tower among the present invention;

图3是本发明的湿空气饱和曲线图。Figure 3 is a graph of the humid air saturation curve of the present invention.

附图标记的含义:1-烟囱,2-冷凝换热器,3-热媒水循环泵,4-旁路管道,5-机械通风冷却塔,6-机械通风冷却塔出口阀门,7-暖风器出口总阀,8-一次风暖风器,9-二次风暖风器,10-暖风器进口总阀,11-机械通风冷却塔入口阀门,12-热媒水管道,13-吸收塔,14-底部排水管,15-暖风器组件。Meanings of reference signs: 1-chimney, 2-condensing heat exchanger, 3-heat medium water circulation pump, 4-bypass pipe, 5-mechanical ventilation cooling tower, 6-exit valve of mechanical ventilation cooling tower, 7-warm air Main outlet valve of the device, 8-primary air heater, 9-secondary air heater, 10-heater inlet main valve, 11-mechanical ventilation cooling tower inlet valve, 12-heat medium water pipe, 13-absorption Tower, 14-bottom drain pipe, 15-air heater assembly.

下面结合附图和具体实施方式对本发明作进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

具体实施方式Detailed ways

本发明的实施例1:如图1所示,一种新型火电厂低温余热利用及消白烟的装置,冷凝换热器2布置在吸收塔13与烟囱1之间的烟道内,由若干个小的换热模块组成,换热模块中的换热管采用氟塑料管或不锈钢管。若是冷凝换热器2的换热管采用不锈钢材质,则布置方式为烟道烟气流动方向m个(其中m可以为1或2)、烟道高度方向n个(其中n可以为1,2,3,4或者5)在烟道中形成积木型布置。一次风暖风器8安装在一次风机出口和空气预热器入口之间的风道上,二次风暖风器9安装在二次风机出口和空气预热器入口之间的风道上。其中一次风暖风器8和二次风暖风器9采用铝合金或普通碳钢等材质。热媒水管道12为闭式循环系统,25℃的热媒水进入到冷凝换热器2,通过冷凝换热器2换热后热媒水温度从25℃左右升高到45℃左右,热媒水升温约20℃,同时使吸收塔13出口的烟气温度下降1~5℃左右,从而提取烟气中的水分,进而起到消除白烟作用,同时回收了一定的气化潜热。热媒水通过冷凝换热器2换热后,热媒水温度从25℃左右升高到45℃左右,然后进入到一次风暖暖风器8和二次风暖风器9进行换热,通过暖风器组件15的换热作用,使一次风和二次风的风温从-15℃左右升高到25℃左右,使热媒水从冷凝换热器2回收的热量加热一次风和二次风,实现能量的回收;然后热媒水温度从45℃左右降低到25℃左右,换热后的热媒水经热媒水循环泵3再次进入到冷凝换热器2进行循环换热。Embodiment 1 of the present invention: as shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant, the condensation heat exchanger 2 is arranged in the flue between the absorption tower 13 and the chimney 1, and consists of several It is composed of small heat exchange modules, and the heat exchange tubes in the heat exchange modules are made of fluorine plastic tubes or stainless steel tubes. If the heat exchange tubes of the condensing heat exchanger 2 are made of stainless steel, the arrangement is m in the flue gas flow direction (where m can be 1 or 2), and n in the flue height direction (where n can be 1, 2 , 3, 4 or 5) form a building block arrangement in the flue. The primary air heater 8 is installed on the air duct between the outlet of the primary fan and the inlet of the air preheater, and the secondary air heater 9 is installed on the air duct between the outlet of the secondary fan and the inlet of the air preheater. Wherein the primary air heater 8 and the secondary air heater 9 are made of materials such as aluminum alloy or common carbon steel. The heat medium water pipeline 12 is a closed circulation system. The heat medium water at 25°C enters the condensation heat exchanger 2, and after heat exchange through the condensation heat exchanger 2, the temperature of the heat medium water rises from about 25°C to about 45°C. The temperature of the medium water is raised by about 20°C, and at the same time, the temperature of the flue gas at the outlet of the absorption tower 13 is lowered by about 1-5°C, thereby extracting the moisture in the flue gas, thereby eliminating the white smoke, and recovering a certain amount of latent heat of vaporization. After the heat medium water exchanges heat through the condensing heat exchanger 2, the temperature of the heat medium water rises from about 25°C to about 45°C, and then enters the primary air heater 8 and the secondary air heater 9 for heat exchange. Through the heat exchange function of the air heater assembly 15, the air temperature of the primary air and the secondary air is raised from about -15°C to about 25°C, and the heat recovered by the heat medium water from the condensing heat exchanger 2 is heated to the primary air and the secondary air. The secondary air realizes energy recovery; then the temperature of the heat medium water is reduced from about 45°C to about 25°C, and the heat medium water after heat exchange enters the condensing heat exchanger 2 again through the heat medium water circulation pump 3 for heat exchange.

实施例2:如图1所示,一种新型火电厂低温余热利用及消白烟的装置,冷凝换热器2布置在吸收塔13与烟囱1之间的烟道,由若干个小的换热模块组成,换热模块中的换热管采用氟塑料材质或不锈钢材质。冷凝换热器2的换热管若采用不锈钢材质,则布置方式为烟道烟气流动方向m个(m一般为不大于2的正整数)、烟道高度方向n个(n一般为不大于5的正整数)在烟道中成积木型布置。通过冷凝换热器2换热后热媒水温度从25℃左右升高到45℃左右,热媒水升温约20℃,同时使吸收塔13出口的烟气温度下降1~5℃左右,从而提取烟气中的水分,进而起到消除白烟作用,同时回收了一定的气化潜热。夏季环境温度较高时,由于环境温度在25~30℃左右,使暖风器入口风温高于原设计暖风器出口热媒水温度值,使暖风器组件15不能够起到良好的换热效果;因此为减少热媒水循环管道的阻力,关闭热媒水管道12的一次风、二次风暖风器的进口管道阀门即暖风器进口总阀10和出口管道阀门即暖风器出口总阀7,开启机械通风冷却塔入口阀门11和机械通风冷却塔出口阀门6,使热媒水不经过暖风器组件15直接通过机械通风冷却塔5进行减温后再次循环换热,机械通风冷却塔5安装在热媒水循环泵3入口的旁路管道4上,45℃的热媒水经由机械通风冷却塔5热水入口进入到机械通风冷却塔5进行喷淋降温,并经喷淋填料减温至约25℃后落入机械通风冷却塔5的低温冷却水池,最后通过热媒水循环泵3的作用返回冷凝换热器2再次进行循环换热,从而降低吸收塔13出口烟气温度,减少烟气中的水分,起到消白烟的作用。Embodiment 2: As shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant, the condensation heat exchanger 2 is arranged in the flue between the absorption tower 13 and the chimney 1, and consists of several small heat exchangers Composed of heat modules, the heat exchange tubes in the heat exchange module are made of fluoroplastic or stainless steel. If the heat exchange tubes of the condensing heat exchanger 2 are made of stainless steel, the arrangement will be m in the flue gas flow direction (m is generally a positive integer not greater than 2), and n in the flue height direction (n is generally not greater than A positive integer of 5) is arranged in the form of building blocks in the flue. After heat exchange through the condensing heat exchanger 2, the temperature of the heat medium water rises from about 25°C to about 45°C, and the temperature of the heat medium water rises by about 20°C, and at the same time, the temperature of the flue gas at the outlet of the absorption tower 13 drops by about 1 to 5°C, thereby The water in the flue gas is extracted to eliminate the white smoke, and at the same time recover a certain amount of latent heat of gasification. When the ambient temperature is high in summer, because the ambient temperature is around 25-30°C, the air temperature at the inlet of the air heater is higher than the temperature of the heat medium water at the outlet of the air heater originally designed, so that the air heater assembly 15 cannot play a good role. Heat exchange effect; therefore, in order to reduce the resistance of the heat medium water circulation pipeline, close the primary air of the heat medium water pipeline 12, the inlet pipeline valve of the secondary air heater, that is, the main inlet valve 10 of the heater, and the outlet pipeline valve, that is, the heater The main outlet valve 7 opens the inlet valve 11 of the mechanical ventilation cooling tower and the outlet valve 6 of the mechanical ventilation cooling tower, so that the heat medium water does not pass through the heater assembly 15 and directly passes through the mechanical ventilation cooling tower 5 to reduce the temperature and then circulate heat again. The ventilation cooling tower 5 is installed on the bypass pipe 4 at the inlet of the heat medium water circulation pump 3, and the heat medium water at 45°C enters the mechanical ventilation cooling tower 5 through the hot water inlet of the mechanical ventilation cooling tower 5 for spray cooling, and after spraying After the filler is cooled to about 25°C, it falls into the low-temperature cooling pool of the mechanical ventilation cooling tower 5, and finally returns to the condensing heat exchanger 2 through the action of the heat medium water circulation pump 3 to perform circulation heat exchange again, thereby reducing the flue gas temperature at the outlet of the absorption tower 13 , reduce the moisture in the flue gas, and play the role of eliminating white smoke.

实施例3:如图1所示,一种新型火电厂低温余热利用及消白烟的装置包括烟囱1、冷凝换热器2、热媒水循环泵3、旁路管道4、机械通风冷却塔5、热媒水管道12、吸收塔13、底部排水管14和暖风器组件15,所述吸收塔13的顶部经烟道连接有烟囱1,所述冷凝换热器2、暖风器组件15、热媒水循环泵3之间经管道循环顺次连接,即热媒水循环泵3出口与冷凝换热器2入口相连接。所述冷凝换热器2与暖风器组件15之间的管道为热媒水管道12,所述热媒水管道12上还设有旁路管道4,所述旁路管道4的端部连接有机械通风冷却塔5,所述机械通风冷却塔5也经管道连接有热媒水循环泵3。其中冷凝换热器2安装在烟囱1与吸收塔13之间的烟道内,所述冷凝换热器2经底部排水管14与吸收塔13连接。所述暖风器组件15包括一次风暖风器8和二次风暖风器9,所述一次风暖风器8的出口经管道连接于热媒水循环泵3的入口,所述二次风暖风器9的出口也经管道连接于热媒水循环泵3的入口。其中一次风暖风器8设于一次风机出口与空气预热器入口之间的风道上,其中二次风暖风器9设于二次风机出口与空气预热器入口之间的风道上。所述一次风暖风器8和二次风暖风器9的材质为铝合金或者普通碳钢。Embodiment 3: As shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant includes a chimney 1, a condensation heat exchanger 2, a heat medium water circulation pump 3, a bypass pipe 4, and a mechanical ventilation cooling tower 5 , heat medium water pipeline 12, absorption tower 13, bottom drain pipe 14 and air heater assembly 15, the top of said absorption tower 13 is connected with chimney 1 through flue, described condensing heat exchanger 2, air heater assembly 15 1. The heat medium water circulation pumps 3 are connected in sequence through pipeline circulation, that is, the outlet of the heat medium water circulation pump 3 is connected with the inlet of the condensing heat exchanger 2 . The pipeline between the condensing heat exchanger 2 and the heater assembly 15 is a heat medium water pipeline 12, and a bypass pipeline 4 is also provided on the heat medium water pipeline 12, and the end of the bypass pipeline 4 is connected to There is a mechanical ventilation cooling tower 5, and the mechanical ventilation cooling tower 5 is also connected with a heat medium water circulation pump 3 through pipelines. Wherein the condensing heat exchanger 2 is installed in the flue between the chimney 1 and the absorption tower 13 , and the condensing heat exchanger 2 is connected to the absorption tower 13 through the bottom drain pipe 14 . The heater assembly 15 includes a primary air heater 8 and a secondary air heater 9, the outlet of the primary air heater 8 is connected to the inlet of the heat medium water circulation pump 3 through a pipeline, and the secondary air The outlet of air heater 9 is also connected to the inlet of heating medium water circulation pump 3 through pipeline. Wherein the primary air heater 8 is arranged on the air duct between the outlet of the primary fan and the inlet of the air preheater, and wherein the secondary air heater 9 is arranged on the air duct between the outlet of the secondary fan and the inlet of the air preheater. The primary air heater 8 and the secondary air heater 9 are made of aluminum alloy or common carbon steel.

实施例4:如图1所示,一种新型火电厂低温余热利用及消白烟的装置包括烟囱1、冷凝换热器2、热媒水循环泵3、旁路管道4、机械通风冷却塔5、热媒水管道12、吸收塔13、底部排水管14和暖风器组件15,所述吸收塔13的顶部经烟道连接有烟囱1,所述冷凝换热器2、暖风器组件15、热媒水循环泵3之间经管道循环顺次连接,即热媒水循环泵3出口与冷凝换热器2入口相连接。所述冷凝换热器2与暖风器组件15之间的管道为热媒水管道12,所述热媒水管道12上还设有旁路管道4,所述旁路管道4的端部连接有机械通风冷却塔5,所述机械通风冷却塔5也经管道连接有热媒水循环泵3。其中冷凝换热器2安装在烟囱1与吸收塔13之间的烟道内,所述冷凝换热器2经底部排水管14与吸收塔13连接。所述冷凝换热器2由若干个换热模块组成,所述换热模块中的换热管材质为氟塑料或者不锈钢。所述换热模块中的换热管材质为不锈钢,所述换热管的布置方式为烟道烟气流动方向m个(m一般为不大于2的正整数)、烟道高度方向n个(n一般为不大于5的正整数),在烟道内成积木型布置。Embodiment 4: As shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant includes a chimney 1, a condensation heat exchanger 2, a heat medium water circulation pump 3, a bypass pipe 4, and a mechanical ventilation cooling tower 5 , heat medium water pipeline 12, absorption tower 13, bottom drain pipe 14 and air heater assembly 15, the top of said absorption tower 13 is connected with chimney 1 through flue, described condensing heat exchanger 2, air heater assembly 15 1. The heat medium water circulation pumps 3 are connected in sequence through pipeline circulation, that is, the outlet of the heat medium water circulation pump 3 is connected with the inlet of the condensing heat exchanger 2 . The pipeline between the condensing heat exchanger 2 and the heater assembly 15 is a heat medium water pipeline 12, and a bypass pipeline 4 is also provided on the heat medium water pipeline 12, and the end of the bypass pipeline 4 is connected to There is a mechanical ventilation cooling tower 5, and the mechanical ventilation cooling tower 5 is also connected with a heat medium water circulation pump 3 through pipelines. Wherein the condensing heat exchanger 2 is installed in the flue between the chimney 1 and the absorption tower 13 , and the condensing heat exchanger 2 is connected to the absorption tower 13 through the bottom drain pipe 14 . The condensing heat exchanger 2 is composed of several heat exchange modules, and the heat exchange tubes in the heat exchange modules are made of fluoroplastic or stainless steel. The heat exchange tubes in the heat exchange module are made of stainless steel, and the arrangement of the heat exchange tubes is m in the flow direction of the flue gas (m is generally a positive integer not greater than 2), n in the height direction of the flue ( n is generally a positive integer not greater than 5), and they are arranged in the form of building blocks in the flue.

实施例5:如图1所示,一种新型火电厂低温余热利用及消白烟的装置包括烟囱1、冷凝换热器2、热媒水循环泵3、旁路管道4、机械通风冷却塔5、热媒水管道12、吸收塔13、底部排水管14和暖风器组件15,所述吸收塔13的顶部经烟道连接有烟囱1,所述冷凝换热器2、暖风器组件15、热媒水循环泵3之间经管道循环顺次连接,即热媒水循环泵3出口与冷凝换热器2入口相连接。所述冷凝换热器2与暖风器组件15之间的管道为热媒水管道12,所述热媒水管道12上还设有旁路管道4,所述旁路管道4的端部连接有机械通风冷却塔5,所述机械通风冷却塔5也经管道连接有热媒水循环泵3。其中冷凝换热器2安装在烟囱1与吸收塔13之间的烟道内,所述冷凝换热器2经底部排水管14与吸收塔13连接。火电厂低温余热利用及消白烟的装置还包括暖风器进口总阀10和机械通风冷却塔入口阀门11,所述暖风器进口总阀10安装于热媒水管道12上靠近暖风器组件15的一端,所述机械通风冷却塔入口阀门11安装于旁路管道4上远离机械通风冷却塔5的一端。Embodiment 5: As shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant includes a chimney 1, a condensation heat exchanger 2, a heat medium water circulation pump 3, a bypass pipe 4, and a mechanical ventilation cooling tower 5 , heat medium water pipeline 12, absorption tower 13, bottom drain pipe 14 and air heater assembly 15, the top of said absorption tower 13 is connected with chimney 1 through flue, described condensing heat exchanger 2, air heater assembly 15 1. The heat medium water circulation pumps 3 are connected in sequence through pipeline circulation, that is, the outlet of the heat medium water circulation pump 3 is connected with the inlet of the condensing heat exchanger 2 . The pipeline between the condensing heat exchanger 2 and the heater assembly 15 is a heat medium water pipeline 12, and a bypass pipeline 4 is also provided on the heat medium water pipeline 12, and the end of the bypass pipeline 4 is connected to There is a mechanical ventilation cooling tower 5, and the mechanical ventilation cooling tower 5 is also connected with a heat medium water circulation pump 3 through pipelines. Wherein the condensing heat exchanger 2 is installed in the flue between the chimney 1 and the absorption tower 13 , and the condensing heat exchanger 2 is connected to the absorption tower 13 through the bottom drain pipe 14 . The device for utilizing low-temperature waste heat and eliminating white smoke in a thermal power plant also includes a heater inlet valve 10 and a mechanical ventilation cooling tower inlet valve 11. The heater inlet valve 10 is installed on a heat medium water pipeline 12 close to the heater. One end of the component 15 , the inlet valve 11 of the mechanical draft cooling tower is installed on the end of the bypass pipe 4 away from the mechanical draft cooling tower 5 .

实施例6:如图1所示,一种新型火电厂低温余热利用及消白烟的装置包括烟囱1、冷凝换热器2、热媒水循环泵3、旁路管道4、机械通风冷却塔5、热媒水管道12、吸收塔13、底部排水管14和暖风器组件15,所述吸收塔13的顶部经烟道连接有烟囱1,所述冷凝换热器2、暖风器组件15、热媒水循环泵3之间经管道循环顺次连接,即热媒水循环泵3出口与冷凝换热器2入口相连接。所述冷凝换热器2与暖风器组件15之间的管道为热媒水管道12,所述热媒水管道12上还设有旁路管道4,所述旁路管道4的端部连接有机械通风冷却塔5,所述机械通风冷却塔5也经管道连接有热媒水循环泵3。其中冷凝换热器2安装在烟囱1与吸收塔13之间的烟道内,所述冷凝换热器2经底部排水管14与吸收塔13连接。新型火电厂低温余热利用及消白烟的装置还包括机械通风冷却塔出口阀门6和暖风器出口总阀7,所述机械通风冷却塔出口阀门6安装于机械通风冷却塔5与热媒水循环泵3之间的连接管道上,且是靠近机械通风冷却塔5的一端。所述暖风器出口总阀7安装于暖风器组件15与热媒水循环泵3之间的连接管道上,且是靠近暖风器组件15的一端。Embodiment 6: As shown in Figure 1, a new type of low-temperature waste heat utilization and white smoke elimination device in a thermal power plant includes a chimney 1, a condensation heat exchanger 2, a heat medium water circulation pump 3, a bypass pipe 4, and a mechanical ventilation cooling tower 5 , heat medium water pipeline 12, absorption tower 13, bottom drain pipe 14 and air heater assembly 15, the top of said absorption tower 13 is connected with chimney 1 through flue, described condensing heat exchanger 2, air heater assembly 15 1. The heat medium water circulation pumps 3 are connected in sequence through pipeline circulation, that is, the outlet of the heat medium water circulation pump 3 is connected with the inlet of the condensing heat exchanger 2 . The pipeline between the condensing heat exchanger 2 and the heater assembly 15 is a heat medium water pipeline 12, and a bypass pipeline 4 is also provided on the heat medium water pipeline 12, and the end of the bypass pipeline 4 is connected to There is a mechanical ventilation cooling tower 5, and the mechanical ventilation cooling tower 5 is also connected with a heat medium water circulation pump 3 through pipelines. Wherein the condensing heat exchanger 2 is installed in the flue between the chimney 1 and the absorption tower 13 , and the condensing heat exchanger 2 is connected to the absorption tower 13 through the bottom drain pipe 14 . The device for utilizing low-temperature waste heat and eliminating white smoke in a new thermal power plant also includes a mechanical ventilation cooling tower outlet valve 6 and a heater outlet master valve 7. The mechanical ventilation cooling tower outlet valve 6 is installed on the mechanical ventilation cooling tower 5 and the heat medium water circulation On the connecting pipe between the pumps 3, and near the end of the mechanical ventilation cooling tower 5. The heater outlet main valve 7 is installed on the connecting pipe between the heater assembly 15 and the heat medium water circulation pump 3 , and is near the end of the heater assembly 15 .

实施例7:如图1~图3所示,一种新型火电厂低温余热利用及消白烟的方法,采用前述的新型火电厂低温余热利用及消白烟的装置,包括以下步骤:Embodiment 7: As shown in Figures 1 to 3, a method for utilization of low-temperature waste heat and elimination of white smoke in a new type of thermal power plant adopts the aforementioned device for utilization of low-temperature waste heat of a thermal power plant and elimination of white smoke, including the following steps:

S1,热媒水进入到冷凝换热器2,通过冷凝换热器2换热后热媒水温度升高,热媒水温度升高的同时使得吸收塔13出口的烟气温度降低,从而提取烟气中的水分,进而起到消除白烟的作用,同时回收了一定的气化潜热;S1, the heat medium water enters the condensing heat exchanger 2, and the temperature of the heat medium water increases after passing through the condensing heat exchanger 2. The temperature of the heat medium water increases while the temperature of the flue gas at the outlet of the absorption tower 13 decreases, thereby extracting Moisture in the flue gas, and then play a role in eliminating white smoke, while recovering a certain amount of latent heat of gasification;

S2,升温后的热媒水经热媒水管道12进入暖风器组件15换热,具体的,包括以下步骤:S2, the heated heat medium water enters the heater assembly 15 through the heat medium water pipeline 12 for heat exchange, specifically, the following steps are included:

S21,升温后的热媒水进入一次风暖风器8中,通过一次风暖风器8的换热作用,使一次风温度升高,热媒水温度降低,升温后的一次风进入空气预热器;S21, the heated heat medium water enters the primary air heater 8, through the heat exchange effect of the primary air heater 8, the temperature of the primary air rises, the temperature of the heat medium water decreases, and the heated primary air enters the air preheater Heater;

S22,升温后的热媒水进入二次风暖风器9中,通过二次风暖风器9的换热作用,使二次风温度升高,热媒水温度降低,升温后的二次风进入空气预热器;S22, the heated heat medium water enters the secondary air heater 9, through the heat exchange effect of the secondary air heater 9, the temperature of the secondary air rises, the temperature of the heat medium water decreases, and the heated secondary air Air enters the air preheater;

S3,降温后的热媒水在热媒水循环泵3的作用下,再次进入冷凝换热器2中循环换热。该种方法适宜于冬季工况,冬季时,中国北方绝大多数的电厂室外环境温度低于-15℃左右,一次风、二次风如果不经暖风器组件15的换热,直接进入到空气预热器后,容易造成空气预热器的低温腐蚀,严重影响锅炉机组的运行安全。为防止空气预热器低温腐蚀,冬季时关闭热媒水管道12的旁路管道4阀门,即关闭机械通风冷却塔入口阀门11,使热媒水不经过机械通风冷却塔5而直接进入到一次风暖风器8和二次风暖风器9进行换热,使风温从-15℃升高到25℃,从而降低空气预热器的低温腐蚀情况;同时,热媒水温度从45℃减低到25℃,然后通过热媒水循环泵3升压的作用,使热媒水重新进入冷凝换热器2换热,从而降低吸收塔13出口烟气温度,减少烟气中的水分,起到消白烟的作用。进一步的,其中所述冷凝换热器2、一次风暖风器8、二次风暖风器9与热媒水之间的换热方式均为逆流换热,相比于其他换热方式,逆流换热可以强化换热、提高换热效率。S3, the cooled heat medium water enters the condensing heat exchanger 2 again for heat exchange under the action of the heat medium water circulation pump 3 . This method is suitable for working conditions in winter. In winter, the outdoor ambient temperature of most of the power plants in northern China is lower than -15°C. After the air preheater, it is easy to cause low-temperature corrosion of the air preheater, which seriously affects the operation safety of the boiler unit. In order to prevent the low-temperature corrosion of the air preheater, the bypass pipe 4 valve of the heat medium water pipeline 12 is closed in winter, that is, the inlet valve 11 of the mechanical ventilation cooling tower is closed, so that the heat medium water directly enters the primary water without passing through the mechanical ventilation cooling tower 5. The air heater 8 and the secondary air heater 9 exchange heat to increase the air temperature from -15°C to 25°C, thereby reducing the low-temperature corrosion of the air preheater; at the same time, the temperature of the heat medium water increases from 45°C reduce to 25°C, and then increase the pressure of the heat medium water circulation pump 3, so that the heat medium water re-enters the condensing heat exchanger 2 for heat exchange, thereby reducing the temperature of the flue gas at the outlet of the absorption tower 13, reducing the moisture in the flue gas, and The effect of eliminating white smoke. Further, the heat exchange methods between the condensing heat exchanger 2, the primary air heater 8, the secondary air heater 9 and the heat medium water are all countercurrent heat exchange, compared with other heat exchange methods, Countercurrent heat exchange can strengthen heat exchange and improve heat exchange efficiency.

实施例8:如图1~图3所示,一种新型火电厂低温余热利用及消白烟的方法,采用前述的新型火电厂低温余热利用及消白烟的装置,包括以下步骤:Embodiment 8: As shown in Figures 1 to 3, a method for utilization of low-temperature waste heat and elimination of white smoke in a new type of thermal power plant uses the aforementioned device for utilization of low-temperature waste heat of a thermal power plant and elimination of white smoke, including the following steps:

S1,热媒水进入到冷凝换热器2,通过冷凝换热器2换热后热媒水温度升高,热媒水温度升高的同时使得吸收塔13出口的烟气温度降低;S1, the heat medium water enters the condensing heat exchanger 2, and the temperature of the heat medium water increases after passing through the condensing heat exchanger 2, and the temperature of the heat medium water increases while the temperature of the flue gas at the outlet of the absorption tower 13 decreases;

S2,升温后的热媒水经热媒水管道12、旁路管道4进入机械通风冷却塔5进行喷淋降温,其中热媒水经过其中的喷淋填料减温后落入低温冷却水池;S2, the heated heat medium water enters the mechanical ventilation cooling tower 5 through the heat medium water pipeline 12 and the bypass pipeline 4 to spray and cool down, wherein the heat medium water falls into the low-temperature cooling pool after passing through the spray filler therein for cooling;

S3,降温后的热媒水在热媒水循环泵3的作用下,再次进入冷凝换热器2中循环换热。该种方法适宜于夏季工况,夏季时,由于环境温度在25~30℃左右,使暖风器入口风温高于原设计暖风器出口热媒水温度值,使暖风器组件15不能够起到良好的换热效果。因此,为减少热媒水循环管道的阻力,关闭热媒水管道12上暖风器组件15的进出口管道阀门,即关闭暖风器进口总阀10和暖风器出口总阀7,使热媒水不经过暖风器组件15而直接进入到机械通风冷却塔5进行换热,使热媒水温度从45℃降低到25℃,然后通过热媒水循环泵3升压的作用,使热媒水重新进入冷凝换热器2换热,从而降低吸收塔13出口烟气温度,减少烟气中的水分,起到消白烟的作用。S3, the cooled heat medium water enters the condensing heat exchanger 2 again for heat exchange under the action of the heat medium water circulation pump 3 . This method is suitable for working conditions in summer. In summer, since the ambient temperature is around 25-30°C, the air temperature at the inlet of the heater is higher than the temperature of the heat medium water at the outlet of the heater in the original design, so that the heater assembly 15 does not Can play a good heat exchange effect. Therefore, in order to reduce the resistance of the heat medium water circulation pipeline, close the inlet and outlet pipe valves of the heater assembly 15 on the heat medium water pipeline 12, that is, close the heater inlet main valve 10 and the heater outlet main valve 7, so that the heat medium The water directly enters the mechanical ventilation cooling tower 5 without going through the heater assembly 15 for heat exchange, reducing the temperature of the heat medium water from 45°C to 25°C, and then boosting the pressure of the heat medium water circulation pump 3 to make the heat medium water Re-enter the condensing heat exchanger 2 for heat exchange, thereby reducing the temperature of the flue gas at the outlet of the absorption tower 13, reducing the moisture in the flue gas, and playing the role of eliminating white smoke.

本发明的一种实施例的工作原理:如图1所示,高温烟气离开吸收塔13后,经烟道进入到冷凝换热器2,通过冷凝换热器2的换热作用,热媒水后温度从25℃左右升高到45℃左右,热媒水升温约20℃,同时使吸收塔13出口的烟气温度下降1~5℃左右,从而提取烟气中的水分,使烟气的含湿量大大的降低,进而起到消除白烟作用,并回收了一定的气化潜热。冬季时,升温后的热媒水不经过机械通风冷却塔5而直接进入到一次风暖风器8和二次风暖风器9进行换热,通过暖风器组件15的换热作用,使一次风和二次风的风温从-15℃左右升高到25℃左右,使热媒水从冷凝换热器2回收的热量加热一次风和二次风,实现能量的回收;然后热媒水温度从45℃左右降低到25℃左右,换热后的热媒水经热媒水循环泵3升压的作用,再次进入到冷凝换热器2进行循环换热。The working principle of an embodiment of the present invention: as shown in Figure 1, after the high-temperature flue gas leaves the absorption tower 13, it enters the condensation heat exchanger 2 through the flue, and through the heat exchange effect of the condensation heat exchanger 2, the heat medium After the water temperature rises from about 25°C to about 45°C, the temperature of the heat medium water rises by about 20°C, and at the same time reduces the temperature of the flue gas at the outlet of the absorption tower 13 by about 1-5°C, thereby extracting the moisture in the flue gas and making the flue gas The moisture content is greatly reduced, thereby eliminating white smoke and recovering a certain amount of latent heat of vaporization. In winter, the heated heat medium water directly enters the primary air heater 8 and the secondary air heater 9 for heat exchange without passing through the mechanical ventilation cooling tower 5, and through the heat exchange effect of the heater assembly 15, the The air temperature of the primary air and the secondary air rises from about -15°C to about 25°C, so that the heat recovered by the heat medium water from the condensation heat exchanger 2 heats the primary air and the secondary air to realize energy recovery; then the heat medium The water temperature drops from about 45°C to about 25°C, and the heat medium water after heat exchange is boosted by the heat medium water circulation pump 3, and then enters the condensing heat exchanger 2 again for heat exchange.

如图2所示,由于夏季环境温度较高,使暖风器入口风温高于原设计暖风器出口热媒水温度值,暖风器组件15不能够起到良好的换热效果,因此为减少热媒水循环管道的阻力,关闭热媒水管道12的一次风、二次风暖风器的进出口管道阀门,热媒水直接通过机械通风冷却塔5进行减温后再次循环换热,机械通风冷却塔5安装在热媒水循环泵3入口的旁路管道4上,45℃的热媒水经由机械通风冷却塔5热水入口进入到机械通风冷却塔5进行喷淋降温,并经喷淋填料减温至约25℃后落入机械通风冷却塔5的低温冷却水池,通过机械通风冷却塔5冷水出口排出,最后通过热媒水循环泵3的作用返回冷凝换热器2再次进行循环换热,从而降低脱硫出口烟气温度,减少烟气中的水分,起到消白烟的作用。As shown in Figure 2, due to the high ambient temperature in summer, the air temperature at the inlet of the air heater is higher than the temperature of the heat medium water at the outlet of the air heater originally designed, and the air heater assembly 15 cannot achieve a good heat exchange effect, so In order to reduce the resistance of the heat medium water circulation pipeline, the inlet and outlet pipeline valves of the primary air and secondary air heaters of the heat medium water pipeline 12 are closed, and the heat medium water directly passes through the mechanical ventilation cooling tower 5 for temperature reduction and then circulates heat again. The mechanical ventilation cooling tower 5 is installed on the bypass pipe 4 at the inlet of the heat medium water circulation pump 3, and the heat medium water at 45°C enters the mechanical ventilation cooling tower 5 through the hot water inlet of the mechanical ventilation cooling tower 5 for spraying and cooling. After the temperature of the drenching filler is reduced to about 25°C, it falls into the low-temperature cooling water pool of the mechanical ventilation cooling tower 5, and is discharged through the outlet of the mechanical ventilation cooling tower 5 cold water, and finally returns to the condensation heat exchanger 2 through the action of the heat medium water circulation pump 3 for circulation again. Heat, thereby reducing the flue gas temperature at the desulfurization outlet, reducing the moisture in the flue gas, and playing the role of eliminating white smoke.

从图3中可以看到,未安装冷凝换热器2时,烟气的含湿量在A点位置,通过降温后烟气温度到达B点,烟气从B点排出烟囱1进入大气后到达C点,从图3中可以看出,当烟气从A到C时与湿饱和蒸汽线相交,如果相交,说明产生白烟,当烟气从B到C时没有与湿饱和蒸汽线相交,说明不产生白烟,因此通过本装置可以起到消除白烟的效果。It can be seen from Figure 3 that when the condensing heat exchanger 2 is not installed, the moisture content of the flue gas is at point A, and the temperature of the flue gas reaches point B after cooling, and the flue gas is discharged from point B through the chimney 1 and enters the atmosphere. At point C, it can be seen from Figure 3 that when the flue gas crosses the wet saturated steam line from A to C, if it intersects, it means that white smoke is produced, and when the flue gas goes from B to C, it does not cross the wet saturated steam line It shows that no white smoke is produced, so the device can eliminate white smoke.

同时,本发明还可以起到低温余热利用的作用。热媒水经冷凝换热器2后温度从25℃左右升高到45℃左右,收集烟气中的水分约8~12t/h,从而起到消白烟的效果,然后进入暖风器组件15,热媒水温度从45℃左右降低到25℃左右,将冷凝回收的热量用于加热暖风器组件15,实现热量的回收。At the same time, the invention can also play the role of low-temperature waste heat utilization. After the heat medium water passes through the condensing heat exchanger 2, the temperature rises from about 25°C to about 45°C, and the moisture in the flue gas is collected for about 8-12t/h, thereby achieving the effect of eliminating white smoke, and then enters the heater assembly 15. The temperature of the heat medium water is reduced from about 45°C to about 25°C, and the heat recovered by condensation is used to heat the air heater assembly 15 to realize heat recovery.

根据季节不同,分为冬季和夏季工况。冬季时,中国北方绝大多数的电厂室外环境温度低于-15℃左右,一次风、二次风如果不经暖风器的换热,直接进入到空气预热器后,容易造成空气预热器的低温腐蚀,严重影响锅炉机组的运行安全。为防止空气预热器低温腐蚀,因此冬季时关闭热媒水管道12上旁路管道4机械通风冷却塔5的进出口阀门,使热媒水不经过机械通风冷却塔5,而直接进入到一次风暖风器8和二次风暖风器9进行换热,使风温从-15℃升高到25℃,从而降低空气预热器的低温腐蚀情况。同时,热媒水温度从45℃减低到25℃,然后通过热媒水循环泵3升压的作用,使热媒水重新进入冷凝换热器2换热,从而降低脱硫出口烟气温度,减少烟气中的水分,起到消白烟的作用。According to different seasons, it is divided into winter and summer working conditions. In winter, the outdoor ambient temperature of most power plants in northern China is lower than -15°C. If the primary air and secondary air directly enter the air preheater without the heat exchange of the heater, it is easy to cause air preheating. The low-temperature corrosion of the device seriously affects the operation safety of the boiler unit. In order to prevent low-temperature corrosion of the air preheater, the inlet and outlet valves of the bypass pipe 4 on the heat medium water pipeline 12 and the mechanical ventilation cooling tower 5 are closed in winter so that the heat medium water does not pass through the mechanical ventilation cooling tower 5 and directly enters the primary The air heater 8 and the secondary air heater 9 exchange heat to increase the air temperature from -15°C to 25°C, thereby reducing the low-temperature corrosion of the air preheater. At the same time, the temperature of the heat medium water is reduced from 45°C to 25°C, and then the heat medium water re-enters the condensing heat exchanger 2 for heat exchange through the pressure boost of the heat medium water circulation pump 3, thereby reducing the temperature of the flue gas at the desulfurization outlet and reducing the smoke. The moisture in the air plays the role of eliminating white smoke.

夏季时,由于环境温度在25~30℃左右,使暖风器入口风温高于原设计暖风器出口热媒水温度值,使暖风器组件15不能够起到良好的换热效果,因此为减少热媒水循环管道的阻力,关闭热媒水管道12的一次风、二次风暖风器的进出口管道阀门,使热媒水不经过暖风器组件15,而直接进入到机械通风冷却塔5进行换热,使热媒水温度从45℃降低到25℃,然后通过热媒水循环泵3升压的作用,使热媒水重新进入冷凝换热器2换热,从而降低脱硫出口烟气温度,减少烟气中的水分,起到消白烟的作用。In summer, since the ambient temperature is around 25-30°C, the air temperature at the inlet of the air heater is higher than the temperature of the heat medium water at the outlet of the air heater originally designed, so that the air heater assembly 15 cannot achieve a good heat exchange effect. Therefore, in order to reduce the resistance of the heat medium water circulation pipeline, the inlet and outlet pipe valves of the primary air and secondary air heaters of the heat medium water pipeline 12 are closed, so that the heat medium water directly enters the mechanical ventilation without passing through the heater assembly 15 The cooling tower 5 conducts heat exchange to reduce the temperature of the heat medium water from 45°C to 25°C, and then the heat medium water re-enters the condensing heat exchanger 2 for heat exchange through the pressure boost of the heat medium water circulation pump 3, thereby reducing the desulfurization outlet Increase the flue gas temperature, reduce the moisture in the flue gas, and play the role of eliminating white smoke.

Claims (9)

1. the device of a kind of novel thermal power plant's low temperature heat and eliminating white smoke, which is characterized in that changed including chimney (1), condensation Hot device (2), heating agent water-circulating pump (3), bypass duct (4), mechanical-draft cooling tower (5), heating agent waterpipe (12), absorption tower (13), the top of bottom discharge pipe (14) and warm wind device assembly (15), the absorption tower (13) is connected with chimney (1) through flue, It is sequentially connected with through pipeline cycle between the condensing heat exchanger (2), warm wind device assembly (15), heating agent water-circulating pump (3), it is described cold Solidifying pipeline between heat exchanger (2) and warm wind device assembly (15) is heating agent waterpipe (12), is gone back on the heating agent waterpipe (12) Equipped with bypass duct (4), the end of the bypass duct (4) is connected with mechanical-draft cooling tower (5), the force ventilation cooling Tower (5) is also connected with heating agent water-circulating pump (3) through pipeline;Wherein condensing heat exchanger (2) is mounted on chimney (1) and absorption tower (13) Between flue in, the condensing heat exchanger (2) connect through bottom discharge pipe (14) with absorption tower (13).
2. the device of novel thermal power plant's low temperature heat according to claim 1 and eliminating white smoke, which is characterized in that described Warm wind device assembly (15) includes First air steam air heater (8) and Secondary Air steam air heater (9), the outlet of the First air steam air heater (8) The entrance of heating agent water-circulating pump (3) is connected to through pipeline, the outlet of the Secondary Air steam air heater (9) is also connected to heating agent through pipeline The entrance of water-circulating pump (3);Wherein First air steam air heater (8) is set to the wind between primary air fan outlet and air preheater entrance On road, wherein Secondary Air steam air heater (9) is set on the air duct that overfire air fan exports between air preheater entrance.
3. the device of novel thermal power plant's low temperature heat according to claim 2 and eliminating white smoke, which is characterized in that described The material of First air steam air heater (8) and Secondary Air steam air heater (9) is aluminium alloy or ordinary carbon steel.
4. the device of novel thermal power plant's low temperature heat according to claim 1 and eliminating white smoke, which is characterized in that described Condensing heat exchanger (2) is made of several heat exchange modules, and the heat exchanger tube material in the heat exchange module is fluoroplastics or stainless Steel.
5. the device of novel thermal power plant's low temperature heat according to claim 1 and eliminating white smoke, which is characterized in that also wrap Steam air heater import main valve (10) and mechanical-draft cooling tower inlet valve (11) are included, the steam air heater import main valve (10) is installed on It is installed on close to one end of warm wind device assembly (15), the mechanical-draft cooling tower inlet valve (11) on heating agent waterpipe (12) One end far from mechanical-draft cooling tower (5) on bypass duct (4).
6. the device of novel thermal power plant's low temperature heat according to claim 1 and eliminating white smoke, which is characterized in that also wrap Include mechanical-draft cooling tower outlet valve (6) and steam air heater outlet main valve (7), the mechanical-draft cooling tower outlet valve (6) It is installed in the connecting pipe between mechanical-draft cooling tower (5) and heating agent water-circulating pump (3), and is proximate to force ventilation cooling One end of tower (5);The steam air heater outlet main valve (7) is installed between warm wind device assembly (15) and heating agent water-circulating pump (3) In connecting pipe, and it is proximate to one end of warm wind device assembly (15).
It is any described novel using claim 1~6 7. a kind of method of novel thermal power plant's low temperature heat and eliminating white smoke The device of thermal power plant's low temperature heat and eliminating white smoke, which is characterized in that include the following steps:
S1, heat medium water enter condensing heat exchanger (2), and heating agent coolant-temperature gage increases after being exchanged heat by condensing heat exchanger (2), heat medium water Temperature makes the flue-gas temperature that absorption tower (13) exports reduce while raising;
S2, the heat medium water after heating exchange heat through heating agent waterpipe (12) into warm wind device assembly (15), specifically, including following step Suddenly:
S21, the heat medium water after heating enter in First air steam air heater (8), are acted on, are made by the heat exchange of First air steam air heater (8) One time air temperature increases, and heating agent coolant-temperature gage reduces, and the First air after heating enters air preheater;
S22, the heat medium water after heating enter in Secondary Air steam air heater (9), are acted on, are made by the heat exchange of Secondary Air steam air heater (9) Secondary Air temperature increases, and heating agent coolant-temperature gage reduces, and the Secondary Air after heating enters air preheater;
S3, the heat medium water after cooling are again introduced into circulating picture-changing in condensing heat exchanger (2) under the action of heating agent water-circulating pump (3) Heat.
It is any described novel using claim 1~6 8. a kind of method of novel thermal power plant's low temperature heat and eliminating white smoke The device of thermal power plant's low temperature heat and eliminating white smoke, which is characterized in that include the following steps:
S1, heat medium water enter condensing heat exchanger (2), and heating agent coolant-temperature gage increases after being exchanged heat by condensing heat exchanger (2), heat medium water Temperature makes the flue-gas temperature that absorption tower (13) exports reduce while raising;
S2, the heat medium water after heating are sprayed through heating agent waterpipe (12), bypass duct (4) into mechanical-draft cooling tower (5) Leaching cooling;
S3, the heat medium water after cooling are again introduced into circulating picture-changing in condensing heat exchanger (2) under the action of heating agent water-circulating pump (3) Heat.
9. the method for novel thermal power plant's low temperature heat according to claim 7 and eliminating white smoke, which is characterized in that described The heat exchange mode of condensing heat exchanger (2), First air steam air heater (8), Secondary Air steam air heater (9) between heat medium water is that adverse current is changed Heat.
CN201810173882.XA 2018-03-02 2018-03-02 A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke Pending CN108458334A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810173882.XA CN108458334A (en) 2018-03-02 2018-03-02 A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810173882.XA CN108458334A (en) 2018-03-02 2018-03-02 A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke

Publications (1)

Publication Number Publication Date
CN108458334A true CN108458334A (en) 2018-08-28

Family

ID=63219806

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810173882.XA Pending CN108458334A (en) 2018-03-02 2018-03-02 A kind of device and method of novel thermal power plant's low temperature heat and eliminating white smoke

Country Status (1)

Country Link
CN (1) CN108458334A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109701354A (en) * 2019-02-28 2019-05-03 中国电力工程顾问集团西北电力设计院有限公司 A compulsory white smoke elimination device
CN109737446A (en) * 2019-01-06 2019-05-10 大唐(北京)能源管理有限公司 A thermal power plant boiler exhaust waste heat recovery and flue gas whitening system
CN110081724A (en) * 2019-04-30 2019-08-02 浙江菲达环保科技股份有限公司 A kind of bituminous concrete rotary kiln flue gas condensing reheating disappears white system
CN110410811A (en) * 2019-07-19 2019-11-05 浙江菲达环保科技股份有限公司 A kind of recycling of wet desulfurization flue gas waste heat, disappear white system and method
CN112377369A (en) * 2020-11-24 2021-02-19 武瑞香 Wet cold thermal power generating unit and wind energy combined utilization power generation device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102305413A (en) * 2011-07-28 2012-01-04 中国电力工程顾问集团西南电力设计院 Exhaust gas waste heat recovery and emission reduction comprehensive application system for coal-fired boiler in thermal power plant
CN104832939A (en) * 2015-04-28 2015-08-12 杭州华电能源工程有限公司 System and method for recovering water of smoke based on fluorine plastic heat exchanger
CN205690425U (en) * 2016-08-16 2016-11-16 华电章丘发电有限公司 A kind of residual heat from boiler fume Multi-class propagation combines condensation water heating supply air system
CN106287771A (en) * 2016-09-14 2017-01-04 西安热工研究院有限公司 A kind of coal-fired power station boiler fume afterheat utilizes system with moisture combined recovery
CN106440465A (en) * 2016-08-31 2017-02-22 浙江浙能节能科技有限公司 Energy-saving type thermal power plant flue gas moisture recovering system
CN106678771A (en) * 2016-08-05 2017-05-17 杭州华电能源工程有限公司 Air heater and low-low temperature economizer coupled energy-saving and environmental-friendly integrated system and method based on fluoroplastic heat exchanger
CN206320726U (en) * 2016-12-16 2017-07-11 东方电气集团东方锅炉股份有限公司 A kind of thermal power plant's tail flue gas afterheat utilizing system coupled based on machine stove depth
CN107218592A (en) * 2017-06-10 2017-09-29 哈尔滨恒昇电站设备有限公司 A kind of fume afterheat complex control system and its application method
CN107676805A (en) * 2017-09-22 2018-02-09 华电电力科学研究院 A kind of efficiently water intaking eliminating white smoke cooperation-removal pollutant device and its method of work
CN207936045U (en) * 2018-03-02 2018-10-02 中国华电科工集团有限公司 A kind of device of novel thermal power plant's low temperature heat and eliminating white smoke

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102305413A (en) * 2011-07-28 2012-01-04 中国电力工程顾问集团西南电力设计院 Exhaust gas waste heat recovery and emission reduction comprehensive application system for coal-fired boiler in thermal power plant
CN104832939A (en) * 2015-04-28 2015-08-12 杭州华电能源工程有限公司 System and method for recovering water of smoke based on fluorine plastic heat exchanger
CN106678771A (en) * 2016-08-05 2017-05-17 杭州华电能源工程有限公司 Air heater and low-low temperature economizer coupled energy-saving and environmental-friendly integrated system and method based on fluoroplastic heat exchanger
CN205690425U (en) * 2016-08-16 2016-11-16 华电章丘发电有限公司 A kind of residual heat from boiler fume Multi-class propagation combines condensation water heating supply air system
CN106440465A (en) * 2016-08-31 2017-02-22 浙江浙能节能科技有限公司 Energy-saving type thermal power plant flue gas moisture recovering system
CN106287771A (en) * 2016-09-14 2017-01-04 西安热工研究院有限公司 A kind of coal-fired power station boiler fume afterheat utilizes system with moisture combined recovery
CN206320726U (en) * 2016-12-16 2017-07-11 东方电气集团东方锅炉股份有限公司 A kind of thermal power plant's tail flue gas afterheat utilizing system coupled based on machine stove depth
CN107218592A (en) * 2017-06-10 2017-09-29 哈尔滨恒昇电站设备有限公司 A kind of fume afterheat complex control system and its application method
CN107676805A (en) * 2017-09-22 2018-02-09 华电电力科学研究院 A kind of efficiently water intaking eliminating white smoke cooperation-removal pollutant device and its method of work
CN207936045U (en) * 2018-03-02 2018-10-02 中国华电科工集团有限公司 A kind of device of novel thermal power plant's low temperature heat and eliminating white smoke

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109737446A (en) * 2019-01-06 2019-05-10 大唐(北京)能源管理有限公司 A thermal power plant boiler exhaust waste heat recovery and flue gas whitening system
CN109701354A (en) * 2019-02-28 2019-05-03 中国电力工程顾问集团西北电力设计院有限公司 A compulsory white smoke elimination device
CN110081724A (en) * 2019-04-30 2019-08-02 浙江菲达环保科技股份有限公司 A kind of bituminous concrete rotary kiln flue gas condensing reheating disappears white system
CN110410811A (en) * 2019-07-19 2019-11-05 浙江菲达环保科技股份有限公司 A kind of recycling of wet desulfurization flue gas waste heat, disappear white system and method
CN112377369A (en) * 2020-11-24 2021-02-19 武瑞香 Wet cold thermal power generating unit and wind energy combined utilization power generation device

Similar Documents

Publication Publication Date Title
CN101709879B (en) System for deep cooling and waste heat recovery of smoke gas in boiler
CN107120714B (en) A year-round comprehensive utilization energy-saving system
CN104100994B (en) A kind of based on flue gas waste heat recovery and the boiler energy-saving emission-reduction system of thermal technology again
CN103968401B (en) Dedusting-desulfurization-UTILIZATION OF VESIDUAL HEAT IN integral system of low PM2.5 discharge
CN204923035U (en) Processing system is synthesized to coal fired boiler's flue gas
CN202092207U (en) Central heating system recovering waste heat of smoke through absorbing type heat pump
WO2018014768A1 (en) Residual heat reuse system for turbine-boiler integrated heat energy circulation
CN105937773A (en) Power station boiler condensing flue gas dehumidification and purification energy-saving system
CN104964265B (en) Horizontal type phase-change heat exchanger and the united energy-saving and emission-reduction system of prefix type hydrophily formula GGH and energy-saving and emission-reduction method
CN109945278A (en) An energy-saving system using absorption heat pump for deep recovery of flue gas waste heat for central heating
CN203518318U (en) Spray-type air source absorption heat pump
CN109668165B (en) Hot secondary air and flue gas waste heat utilization system and thermal power generation unit
CN109974062A (en) A deep recovery system of flue gas waste heat using absorption heat pump and two-stage heat exchanger
CN209034070U (en) A kind of cooling dehumidification by condensation decontamination reheating of flue gas disappears white system
CN204593428U (en) Boiler low-temperature fume waste-heat recovery device
CN108194939B (en) Device and method for waste heat cascade utilization and white smoke elimination of thermal power plant
CN109737446A (en) A thermal power plant boiler exhaust waste heat recovery and flue gas whitening system
CN102444901A (en) Coal power plant combined type heat pipe flue gas waste heat recovery system and method
CN106678771A (en) Air heater and low-low temperature economizer coupled energy-saving and environmental-friendly integrated system and method based on fluoroplastic heat exchanger
CN209371290U (en) A kind of flue gas deep treatment and waste-heat recovery device based on heat pipe heat exchanging technology
CN106247371B (en) A comprehensive utilization device for flue gas waste heat in a thermal power plant
CN109945277A (en) An energy-saving system using electric heat pump to deeply recover waste heat from flue gas of thermal power plant for central heating
CN201636884U (en) A boiler flue gas deep cooling waste heat recovery device
CN105674315A (en) Double-circuit and double-circulation heat exchanging system
CN111408240A (en) A device and method for deep condensation and latent heat recovery and whitening of wet desulfurization flue gas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180828