CN108429109A - A kind of mud stone class geology Grounding Measure of GSM - Google Patents

A kind of mud stone class geology Grounding Measure of GSM Download PDF

Info

Publication number
CN108429109A
CN108429109A CN201810298467.7A CN201810298467A CN108429109A CN 108429109 A CN108429109 A CN 108429109A CN 201810298467 A CN201810298467 A CN 201810298467A CN 108429109 A CN108429109 A CN 108429109A
Authority
CN
China
Prior art keywords
grounding
steel
welding
ground
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810298467.7A
Other languages
Chinese (zh)
Inventor
续亮亮
刘强强
石志强
郝典贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Industrial Equipment Installation Group Co Ltd
Original Assignee
Shanxi Industrial Equipment Installation Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Industrial Equipment Installation Group Co Ltd filed Critical Shanxi Industrial Equipment Installation Group Co Ltd
Priority to CN201810298467.7A priority Critical patent/CN108429109A/en
Publication of CN108429109A publication Critical patent/CN108429109A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • H01R43/20Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors for assembling or disassembling contact members with insulating base, case or sleeve

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Manufacturing Of Electrical Connectors (AREA)

Abstract

The invention discloses a kind of mud stone class geology Grounding Measure of GSM, include the following steps:Step 1, standby material and scene prepare;Step 2, measurement and positioning and grooving;Step 3, Grounding Grids laying;Step 4, horizontal grounding objects laying;Step 5, earthed system welding;Step 6, trench backfill;Step 7, ground outlet;Step 8, ground outlet are connect with ground connection busbar;Step 9, ground resistance measure;By following 50*6 zinc-coated flat steel sheets horizontal grounding objects, and single length >=6m;The Grounding Grids of 50*50*5,2500mm;The Q235 galvanized steel plain sheets of 100mm*100mm*10mm;The ground outlet of 50mm*5mm, T2 purple band steel is got all the ready, is checked and accepted by foundation pit bearing capacity, this method, be conducive to reduce resistance well, improve anti-corrosion capability, step voltage can be reduced, so that personnel safety factor is improved, while having good antiseepage outlet capacity, is conducive to antirust.

Description

A kind of mud stone class geology Grounding Measure of GSM
Technical field
The present invention relates to mud stone class geology grounded screen technical field of construction, specially a kind of mud stone class geology grounded screen construction Method.
Background technology
Lightening protection engineering is that difficulty of construction maximum is also a most important subitem in building, due to the different grounded screens of environment Design there is also larger difference, the earth work of system is mainly by grounding body, and connecting line forms ground networks, wherein influencing Earthing effect it is several because being known as soil resistivity, grounding body selects the anti-corrosion of earthing material and rational cloth to draw ground networks. Since grounded screen is easy to be ignored by people as concealed work, often only pays attention to the measurement result of last ground resistance, work as ground connection It is easy to cause and does over again when resistivity measurements are undesirable, increase construction cost.Therefore while focusing on construction results more Focus on work progress.But with the raising of voltage class of electric power system and the increase of capacity, accident caused by imperfect earth Expansion problem occurs repeatedly.
It is mostly rock for mountain area geology, soil resistivity is high, constructional difficulties, it is difficult to reach design grounded screen electric resistance and want It asks, works out the engineering method and carry out guiding construction, ensure that plant area's grounded screen meets design requirement, meet construction needs, transported for power plant Row provides safe and reliable service condition.
Existing plant area's grounding construction method, can not reduce resistance well, and anti-corrosion capability is relatively low, can not reduce Step voltage makes personal safety reduce, while without good antiseepage outlet capacity, being unfavorable for antirust, for this defect, so It is necessary that we, which design a kind of mud stone class geology Grounding Measure of GSM,.
Invention content
The purpose of the present invention is to provide a kind of mud stone class geology Grounding Measure of GSM, to solve in above-mentioned background technology The problem of proposition.
To achieve the above object, the present invention provides the following technical solutions:
A kind of mud stone class geology Grounding Measure of GSM, includes the following steps:Step 1, standby material and scene prepare;Step 2 is surveyed Amount positioning and grooving;Step 3, Grounding Grids laying;Step 4, horizontal grounding objects laying;Step 5, earthed system welding; Step 6, trench backfill;Step 7, ground outlet;Step 8, ground outlet are connect with ground connection busbar;Step 9, ground connection Resistance measurement;
Wherein in above-mentioned step one, by following 50*6 zinc-coated flat steel sheets horizontal grounding objects, and single length >=6m;50*50*5、 The Grounding Grids of 2500mm;The Q235 galvanized steel plain sheets of 100mm*100mm*10mm;The ground outlet of 50*6 zinc-coated flat steel sheets is standby Together, ensure have corresponding constructing operation face, substrate leveling is finished, checked and accepted by foundation pit bearing capacity, working face composite earthing network Surveying setting-out spreads lime and marks and checked and accepted by management after hours, and site operation electricity consumption power supply sockets in place;
Wherein in above-mentioned step two, unwrapping wire, agent structure earth excavation are measured according to earthing or grounding means floor plan And the smooth rear progress surveying setting-out of substrate, it is marked with lime, after composite earthing network measurement and positioning, is built by design requirement distance The rear excavation grooves of object 1m or so are built, excavation size is 800*800, and length is determined that channel away compares engineering drawing by design drawing Paper, the groove at bottom plate local subsidence also answer local subsidence, sink laying when do circular arc of the turning radius not less than 5m and handle;
Wherein in above-mentioned step three, hole is drilled out with drilling machine, drains hole internal water accumulation(Prevent pulp dilution)Afterwards, it is put into Grounding Grids are simultaneously welded with horizontal grounding objects, are finally pressed into slurry, until being full of entire friction reducer fill area, friction reducer is used Every meter of about 20Kg is measured, and ensures that Grounding Grids are located at friction reducer fill area centre;
Wherein in above-mentioned step four, ditch internal water accumulation is drained, lay horizontal grounding objects and is connect as required with adjacently body, Horizontal grounding objects are 50*6 zinc-coated flat steel sheets, stand up laying, horizontal grounding objects are under bed course at 825mm, and horizontal grounding objects are in bottom plate Local subsidence is also answered in laying at local subsidence, and circular arc of the turning radius not less than 5m should be done by sinking when laying is handled, and is being in the milk It is preceding that bottom support is carried out to horizontal grounding objects, facilitate drag reducing agent slurry to wrap up, ensures that horizontal grounding objects should be at friction reducer filling District center position, the size of friction reducer package level grounding body band steel are 150mm*100mm, every meter of friction reducer dosage about 20kg, After slurry tentatively solidification, element soil or clay are backfilled, and tamp;
Wherein in above-mentioned step five, grounding body welding uses exothermic weld, horizontal grounding objects welding form to be divided into word weldering It connects, T words weld, cross welding and the welding with Grounding Grids, firm welding, no rosin joint, desoldering, solder skip, grounding flat steel are vertical It is curved(Width direction is bent)Inside radius of the bend be more than 1.5 times of width, plane bending of flat steel(Thickness direction is bent)Inside radius of the bend More than 2 times thickness, the connection of vertical drawing line and horizontal grounding objects can be used and first twist and warp, then carry out overlap welding, twist and warp diameter It is reliable in order to connect when band steel is welded with Zinc-coated angle steel stick grounding body more than band steel width, except in the progress of its contact site both sides Welding is outer, and the arc clamp curved by band steel is also welded with Grounding Grids;
Wherein in above-mentioned step six, after the laying connection of integrated ground system segment, rammed using plain soil or clay backfilling Real, every layer of backfill thickness control is manually tamped in 250~300mm using the cooperation of small-sized ramming machine;
Wherein in above-mentioned step seven, non magnetic steel pipe is arranged when drawing in grounded screen(A100mm, wall thickness 4mm)Protective grounding is drawn Outlet, which is located under structure base slab lowest level structure reinforcing bars, on concrete cover, and ensures that ground connection is drawn Line is not contacted with structure reinforcing bars, if line position is at slope on grounding lead, suitably to adjust non-magnetic steel length of tube, it is ensured that be higher by Plate face 100mm, galvanized steel plain sheet seal ring(A292, thickness 10mm)Sealing welding is on outer wall of steel pipe, fixed block(10mm*20mm* 20mm galvanized steel plain sheets)It is welded on steel pipe inner wall, steel pipe surface applies antirust paint(Coal-tar epoxy thick-slurry type antirust paint), in steel pipe Silicon rubber filling is closely knit, and the 0.3MPa water pressure tests are impermeable, and it is 100mm that ground outlet, which reserves steel pipe opening length,;
Wherein in above-mentioned step eight, the grounded lead-out wire of grounded screen is drawn, and is reserved grounded screen and is connected with each other with structure reinforcing bars Condition(That is pre-embedded steel slab), pre-embedded steel slab passes through main reinforcement in A16 round steel and structural upright and welds, commissure full weld, after welding Preservative treatment is carried out to weld seam, pre-embedded steel slab outer surface exposes to structural column surface, and position is higher by structure base slab 500mm, and Apparent label is made on column where steel plate, ground outlet is attached by cable to each ground connection busbar, is connect to forceful electric power The cable connection of ground busbar is completed by electric substation's profession, and the cable connection to light current ground connection busbar is complete by station power and lighting profession At pre-embedded steel slab only makees reservation conditions with the cable connection of each ground connection busbar;
Wherein in above-mentioned step nine, whole process is in strict accordance with design drawing and GB50169-2006《Electric device is installed ENG land is constructed and acceptance specification》Construction, every section construction after be detected, measurement method according to《Earthing or grounding means power frequency Survey is led in the measurement of characterisitic parameter》(DL/T475-2006)It carries out, when such as finding that earth resistance is more than design requirement, need to take Remedial measure, tissue supervisor and construction unit carry out in-site measurement when measurement, determine that ground resistance meets the requirements.
According to above-mentioned technical proposal, the proportioning of friction reducer and water in the step 3 is friction reducer:Water=0.4 ~ 0.6: 1, Grounding Grids are Zinc-coated angle steel bar material.
According to above-mentioned technical proposal, backfill requirement in the step 4 with fine earth be not allow for brick, bulk stone, Mixed mud is built and rubbish.
According to above-mentioned technical proposal, welding in the step 5 drives away water it should be noted that the preceding dry heat tool die of welding Gas, using banister brush or other soft article cleaning molds, clamping mold and the adaptation for checking mould contact surface, mold folder is For open-close module, the tight ness rating of mold folder has an impact the effect of welding, conscientiously checks that mold presss from both sides before welding starts, And make the appropriate adjustments, the adaptation of the adaptation of mold folder and mold is adjusted optimally, is powered by installation and adjustment mold folder Carry out exothermic weld, timely cleaning mold after welding.
According to above-mentioned technical proposal, the aperture of hole is Ф 120-150mm in the step 3.
Compared with prior art, the beneficial effects of the invention are as follows:1. drilling out hole with drilling machine, hole internal water accumulation is drained (Prevent pulp dilution)Afterwards, Grounding Grids are put into and are welded with horizontal grounding objects, are finally pressed into slurry, until full of entire Friction reducer fill area, every meter of friction reducer dosage about 20Kg, and ensure that Grounding Grids are located at friction reducer fill area centre, it drops Resist and the proportioning of water are friction reducer:Water=0.4 ~ 0.6:1, be conducive to reduce resistance well, improve anti-corrosion capability, it can Step voltage is reduced, making the person, the safety is improved;
2. steel pipe surface applies antirust paint(Coal-tar epoxy thick-slurry type antirust paint), silicon rubber fills closely knit, 0.3MPa water in steel pipe Pressure experiment is impermeable, and it is 100mm that ground outlet, which reserves steel pipe opening length, is conducive to promote antiseepage outlet capacity, while advantageous In antirust.
Description of the drawings
Fig. 1 is the mud stone class geology Grounding Measure of GSM flow chart of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, a kind of mud stone class geology Grounding Measure of GSM includes the following steps:Step 1, standby material and scene are accurate It is standby;Step 2, measurement and positioning and grooving;Step 3, Grounding Grids laying;Step 4, horizontal grounding objects laying;Step 5, Earthed system is welded;Step 6, trench backfill;Step 7, ground outlet;Step 8, ground outlet connect with ground connection busbar It connects;Step 9, ground resistance measure;
Wherein in above-mentioned step one, by following 50*6 zinc-coated flat steel sheets horizontal grounding objects, and single length >=6m;50*50*5、 The Grounding Grids of 2500mm;The Q235 galvanized steel plain sheets of 100mm*100mm*10mm;The grounding lead of 50mm*5mm, T2 purple band steel Outlet is got all the ready, and guarantee has corresponding constructing operation face, and substrate leveling is finished, checked and accepted by foundation pit bearing capacity, working face synthesis Grounded screen surveying setting-out spreads lime and marks and checked and accepted by management after hours, and site operation electricity consumption power supply sockets in place;
Wherein in above-mentioned step two, unwrapping wire, agent structure earth excavation are measured according to earthing or grounding means floor plan And the smooth rear progress surveying setting-out of substrate, it is marked with lime, after composite earthing network measurement and positioning, is built by design requirement distance The rear excavation grooves of object 1m or so are built, excavation size is 800*800, and length is determined that channel away compares engineering drawing by design drawing Paper, the groove at bottom plate local subsidence also answer local subsidence, sink laying when do circular arc of the turning radius not less than 5m and handle;
Wherein in above-mentioned step three, hole is drilled out with drilling machine, drains hole internal water accumulation(Prevent pulp dilution)Afterwards, it is put into Grounding Grids are simultaneously welded with horizontal grounding objects, are finally pressed into slurry, until being full of entire friction reducer fill area, friction reducer is used Every meter of about 20Kg is measured, and ensures that Grounding Grids are located at friction reducer fill area centre;
Wherein in above-mentioned step four, ditch internal water accumulation is drained, lay horizontal grounding objects and is connect as required with adjacently body, Horizontal grounding objects are 50*6 zinc-coated flat steel sheets, stand up laying, horizontal grounding objects are under bed course at 825mm, and horizontal grounding objects are in bottom plate Local subsidence is also answered in laying at local subsidence, and circular arc of the turning radius not less than 5m should be done by sinking when laying is handled, and is being in the milk It is preceding that bottom support is carried out to horizontal grounding objects, facilitate drag reducing agent slurry to wrap up, ensures that horizontal grounding objects should be at friction reducer filling District center position, the size of friction reducer package level grounding body band steel are 150mm*100mm, every meter of friction reducer dosage about 20kg, After slurry tentatively solidification, element soil or clay are backfilled, and tamp;
Wherein in above-mentioned step five, grounding body welding uses exothermic weld, horizontal grounding objects welding form to be divided into word weldering It connects, T words weld, cross welding and the welding with Grounding Grids, firm welding, no rosin joint, desoldering, solder skip, grounding flat steel are vertical It is curved(Width direction is bent)Inside radius of the bend be more than 1.5 times of width, plane bending of flat steel(Thickness direction is bent)Inside radius of the bend More than 2 times thickness, the connection of vertical drawing line and horizontal grounding objects can be used and first twist and warp, then carry out overlap welding, twist and warp diameter It is reliable in order to connect when band steel is welded with Zinc-coated angle steel stick grounding body more than band steel width, except in the progress of its contact site both sides Welding is outer, and the arc clamp curved by band steel is also welded with Grounding Grids;
Wherein in above-mentioned step six, after the laying connection of integrated ground system segment, rammed using plain soil or clay backfilling Real, every layer of backfill thickness control is manually tamped in 250~300mm using the cooperation of small-sized ramming machine;
Wherein in above-mentioned step seven, non magnetic steel pipe is arranged when drawing in grounded screen(A100mm, wall thickness 4mm)Protective grounding is drawn Outlet, which is located under structure base slab lowest level structure reinforcing bars, on concrete cover, and ensures that ground connection is drawn Line is not contacted with structure reinforcing bars, if line position is at slope on grounding lead, suitably to adjust non-magnetic steel length of tube, it is ensured that be higher by Plate face 100mm, galvanized steel plain sheet seal ring(A292, thickness 10mm)Sealing welding is on outer wall of steel pipe, fixed block(10mm*20mm* 20mm galvanized steel plain sheets)It is welded on steel pipe inner wall, steel pipe surface applies antirust paint(Coal-tar epoxy thick-slurry type antirust paint), in steel pipe Silicon rubber filling is closely knit, and the 0.3MPa water pressure tests are impermeable, and it is 100mm that ground outlet, which reserves steel pipe opening length,;
Wherein in above-mentioned step eight, the grounded lead-out wire of grounded screen is drawn, and is reserved grounded screen and is connected with each other with structure reinforcing bars Condition(That is pre-embedded steel slab), pre-embedded steel slab passes through main reinforcement in A16 round steel and structural upright and welds, commissure full weld, after welding Preservative treatment is carried out to weld seam, pre-embedded steel slab outer surface exposes to structural column surface, and position is higher by structure base slab 500mm, and Apparent label is made on column where steel plate, ground outlet is attached by cable to each ground connection busbar, is connect to forceful electric power The cable connection of ground busbar is completed by electric substation's profession, and the cable connection to light current ground connection busbar is complete by station power and lighting profession At pre-embedded steel slab only makees reservation conditions with the cable connection of each ground connection busbar;
Wherein in above-mentioned step nine, whole process is in strict accordance with design drawing and GB50169-2006《Electric device is installed ENG land is constructed and acceptance specification》Construction, every section construction after be detected, measurement method according to《Earthing or grounding means power frequency Survey is led in the measurement of characterisitic parameter》(DL/T475-2006)It carries out, when such as finding that earth resistance is more than design requirement, need to take Remedial measure, tissue supervisor and construction unit carry out in-site measurement when measurement, determine that ground resistance meets the requirements.
According to above-mentioned technical proposal, the proportioning of friction reducer and water in step 3 is friction reducer:Water=0.4 ~ 0.6:1, it hangs down Directly body is Zinc-coated angle steel bar material, is conducive to the effect for promoting friction reducer.
According to above-mentioned technical proposal, the backfill requirement in step 4 is not allow for brick, bulk stone, mixed mud with fine earth Civil engineering is built and rubbish, is conducive to make to banket more to tamp, and prevents from influencing earthing effect.
According to above-mentioned technical proposal, welding in step 5 is driven away aqueous vapor, is made it should be noted that the preceding dry heat tool die of welding With banister brush or other soft article cleaning molds, clamping mold and the adaptation for checking mould contact surface, mold folder is to be used for Open-close module, the tight ness rating of mold folder has an impact the effect of welding, conscientiously checks that mold presss from both sides before welding starts, and do The adaptation of the adaptation of mold folder and mold is adjusted optimally, is powered and carries out by appropriate adjustment, installation and adjustment mold folder Exothermic weld, timely cleaning mold after welding are conducive to remove the oxide layer on band steel, also help copper when preventing operation Liquid leaks out from gap.
According to above-mentioned technical proposal, the aperture of hole is Ф 120-150mm in step 3, is conducive to place vertical ground connection Body.
Based on above-mentioned, it is an advantage of the current invention that the present invention drills out hole with drilling machine, hole internal water accumulation is drained(It prevents Pulp dilution)Afterwards, Grounding Grids are put into and are welded with horizontal grounding objects, are finally pressed into slurry, until being hindered full of entire drop Agent fill area, every meter of friction reducer dosage about 20Kg, and ensure that Grounding Grids are located at friction reducer fill area centre, friction reducer Proportioning with water is friction reducer:Water=0.4 ~ 0.6:1, be conducive to reduce resistance well, improve anti-corrosion capability, can reduce Step voltage, making the person, the safety is improved;Non magnetic steel pipe is arranged when drawing in grounded screen(A100mm, wall thickness 4mm)Protective grounding Lead-out wire, the steel pipe bottom are located under structure base slab lowest level structure reinforcing bars, on concrete cover, and ensure grounding lead Outlet is not contacted with structure reinforcing bars, if line position is at slope on grounding lead, suitably to adjust non-magnetic steel length of tube, it is ensured that high Go out plate face 100mm, galvanized steel plain sheet seal ring(A292, thickness 10mm)Sealing welding is on outer wall of steel pipe, fixed block(10mm*20mm* 20mm galvanized steel plain sheets)It is welded on steel pipe inner wall, steel pipe surface applies antirust paint(Coal-tar epoxy thick-slurry type antirust paint), in steel pipe Silicon rubber filling is closely knit, and the 0.3MPa water pressure tests are impermeable, and it is 100mm that ground outlet, which reserves steel pipe opening length, is conducive to Antiseepage outlet capacity is promoted, while being conducive to antirust.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of mud stone class geology Grounding Measure of GSM, includes the following steps:Step 1, standby material and scene prepare;Step 2, Measurement and positioning and grooving;Step 3, Grounding Grids laying;Step 4, horizontal grounding objects laying;Step 5, earthed system weldering It connects;Step 6, trench backfill;Step 7, ground outlet;Step 8, ground outlet are connect with ground connection busbar;Step 9, Ground resistance measures;It is characterized in that:
Wherein in above-mentioned step one, by following 50*6 zinc-coated flat steel sheets horizontal grounding objects, and single length >=6m;50*50*5、 The Grounding Grids of 2500mm;The Q235 galvanized steel plain sheets of 100mm*100mm*10mm;The ground outlet of 50*6 zinc-coated flat steel sheets is standby Together, constructing operation face, substrate leveling are finished, are checked and accepted by foundation pit bearing capacity, working face composite earthing network surveying setting-out has worked It spreads lime after finishing to mark and check and accept by management, site operation electricity consumption power supply sockets in place;
Wherein in above-mentioned step two, unwrapping wire, agent structure earth excavation are measured according to earthing or grounding means floor plan And the smooth rear progress surveying setting-out of substrate, it is marked with lime, after composite earthing network measurement and positioning, is built by design requirement distance The rear excavation grooves of object 1m or so are built, excavation size is 800*800, and length is determined that channel away compares engineering drawing by design drawing Paper, the groove at bottom plate local subsidence also answer local subsidence, sink laying when do circular arc of the turning radius not less than 5m and handle;
Wherein in above-mentioned step three, hole is drilled out with drilling machine, after draining hole internal water accumulation, be put into Grounding Grids and with Horizontal grounding objects weld, and are finally pressed into slurry, until being full of entire friction reducer fill area, every meter of friction reducer dosage about 20Kg;
Wherein in above-mentioned step four, ditch internal water accumulation is drained, lay horizontal grounding objects and is connect as required with adjacently body, Horizontal grounding objects are 50*6 zinc-coated flat steel sheets, stand up laying, horizontal grounding objects are under bed course at 825mm, and horizontal grounding objects are in bottom plate Local subsidence is also answered in laying at local subsidence, and circular arc of the turning radius not less than 5m should be done by sinking when laying is handled, and is being in the milk It is preceding that bottom support is carried out to horizontal grounding objects, facilitate drag reducing agent slurry to wrap up, the size of friction reducer package level grounding body band steel Element soil or clay are backfilled, and tamp after slurry tentatively solidification for 150mm*100mm, every meter of friction reducer dosage about 20kg;
Wherein in above-mentioned step five, grounding body welding uses exothermic weld, horizontal grounding objects welding form to be divided into word weldering It connects, T words weld, cross welding and the welding with Grounding Grids, firm welding, no rosin joint, desoldering, solder skip, grounding flat steel are vertical It is curved(Width direction is bent)Inside radius of the bend be more than 1.5 times of width, plane bending of flat steel(Thickness direction is bent)Inside radius of the bend More than 2 times thickness, the connection of vertical drawing line and horizontal grounding objects can be used and first twist and warp, then carry out overlap welding, twist and warp diameter It is reliable in order to connect when band steel is welded with Zinc-coated angle steel stick grounding body more than band steel width, except in the progress of its contact site both sides Welding is outer, and the arc clamp curved by band steel is also welded with Grounding Grids;
Wherein in above-mentioned step six, after the laying connection of integrated ground system segment, rammed using plain soil or clay backfilling Real, every layer of backfill thickness control is manually tamped in 250~300mm using the cooperation of small-sized ramming machine;
Wherein in above-mentioned step seven, non-magnetic steel protection of pipe ground outlet, the steel pipe bottom are set when grounded screen is drawn Under structure base slab lowest level structure reinforcing bars, on concrete cover, and ensure ground outlet not with structure reinforcing bars Contact, if line position is at slope on grounding lead, suitably adjust non-magnetic steel length of tube, it is ensured that it is higher by plate face 100mm, it is zinc-plated On outer wall of steel pipe, fixed block is welded on steel pipe inner wall steel plate water-stopping ring sealing welding, steel pipe surface painting antirust paint, in steel pipe Silicon rubber filling is closely knit, and the 0.3MPa water pressure tests are impermeable, and it is 100mm that ground outlet, which reserves steel pipe opening length,;
Wherein in above-mentioned step eight, the grounded lead-out wire of grounded screen is drawn, and is reserved grounded screen and is connected with each other with structure reinforcing bars Condition, pre-embedded steel slab welded by main reinforcement in A16 round steel and structural upright, and commissure full weld prevents weld seam after welding Corruption processing, pre-embedded steel slab outer surface expose to structural column surface, and position is higher by structure base slab 500mm, and the column where steel plate On make apparent label, ground outlet is attached to each ground connection busbar by cable, to forceful electric power ground connection busbar cable Connection is completed by electric substation's profession, and the cable connection to light current ground connection busbar is completed by station power and lighting profession, pre-embedded steel slab Cable connection with each ground connection busbar only makees reservation conditions;
Wherein in above-mentioned step nine, whole process is in strict accordance with design drawing and GB50169-2006《Electric device is installed ENG land is constructed and acceptance specification》Construction, every section construction after be detected, measurement method according to《Earthing or grounding means power frequency Survey is led in the measurement of characterisitic parameter》It carries out, when such as finding that earth resistance is more than design requirement, need to adopt remedial measures, measure When tissue supervisor and construction unit carry out in-site measurement, determine that ground resistance meets the requirements.
2. a kind of mud stone class geology Grounding Measure of GSM according to claim 1, it is characterised in that:Drop in the step 3 Resist and the proportioning of water are friction reducer:Water=0.4 ~ 0.6:1, Grounding Grids are Zinc-coated angle steel bar material.
3. a kind of mud stone class geology Grounding Measure of GSM according to claim 1, it is characterised in that:Returning in the step 4 Requirement of banketing is not allow for brick, bulk stone, mixed mud building and rubbish with fine earth.
4. a kind of mud stone class geology Grounding Measure of GSM according to claim 1, it is characterised in that:It is welded in the step 5 It should be noted that dry heat tool die before welding, drives away aqueous vapor, uses banister brush or other soft article cleaning molds, clamping die Have and check that the adaptation of mould contact surface, mold folder are effect of the tight ness rating that mold presss from both sides to welding for open-close module Have an impact, conscientiously checks that mold presss from both sides before welding starts, and make the appropriate adjustments, installation and adjustment mold folder, by the close of mold folder The right adaptation with mold is adjusted optimally, and is powered and is carried out exothermic weld, timely cleaning mold after welding.
5. a kind of mud stone class geology Grounding Measure of GSM according to claim 1, it is characterised in that:Hole in the step 3 Aperture be Ф 120-150mm.
CN201810298467.7A 2018-04-04 2018-04-04 A kind of mud stone class geology Grounding Measure of GSM Pending CN108429109A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810298467.7A CN108429109A (en) 2018-04-04 2018-04-04 A kind of mud stone class geology Grounding Measure of GSM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810298467.7A CN108429109A (en) 2018-04-04 2018-04-04 A kind of mud stone class geology Grounding Measure of GSM

Publications (1)

Publication Number Publication Date
CN108429109A true CN108429109A (en) 2018-08-21

Family

ID=63160533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810298467.7A Pending CN108429109A (en) 2018-04-04 2018-04-04 A kind of mud stone class geology Grounding Measure of GSM

Country Status (1)

Country Link
CN (1) CN108429109A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109921338A (en) * 2019-03-19 2019-06-21 成都建工工业设备安装有限公司 A kind of photo-voltaic power generation station grounded screen connection laying method
CN113394634A (en) * 2021-06-22 2021-09-14 中国电建集团河南工程有限公司 Construction method of three-dimensional compound grounding grid in desert soil

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101030458A (en) * 2006-12-06 2007-09-05 王跃山 Non-corrosive assembled grounding electrode and impedance-reducing material and its production
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN104820144A (en) * 2015-04-17 2015-08-05 国家电网公司 Resistance reduction analysis and measure system applied to transformer station lightning-proof grounding system
CN106877019A (en) * 2017-02-15 2017-06-20 中铁二十局集团电务电化工程有限公司 A kind of arid geology grounded screen and its construction and application method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101030458A (en) * 2006-12-06 2007-09-05 王跃山 Non-corrosive assembled grounding electrode and impedance-reducing material and its production
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN104820144A (en) * 2015-04-17 2015-08-05 国家电网公司 Resistance reduction analysis and measure system applied to transformer station lightning-proof grounding system
CN106877019A (en) * 2017-02-15 2017-06-20 中铁二十局集团电务电化工程有限公司 A kind of arid geology grounded screen and its construction and application method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
七秒记忆小七: "综合接地施工方案", 《百度文库 HTTPS://WENKU.BAIDU.COM/VIEW/DC33F039B80D6C85EC3A87C24028915F804D847A.HTML?FROM=SEARCH》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109921338A (en) * 2019-03-19 2019-06-21 成都建工工业设备安装有限公司 A kind of photo-voltaic power generation station grounded screen connection laying method
CN113394634A (en) * 2021-06-22 2021-09-14 中国电建集团河南工程有限公司 Construction method of three-dimensional compound grounding grid in desert soil

Similar Documents

Publication Publication Date Title
CN108511930A (en) A kind of mud stone class geology grounded screen construction technology
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN108166526A (en) Municipal integrated comprehensive lays the construction technology of pipeline
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN107059946A (en) A kind of basement drain plate and its construction
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
WO2016138776A1 (en) Lowly disposed line structure used in medium-low speed magnetic levitation traffic engineering fill section
CN101807785A (en) Prefabricated assembled cable trench and installation method thereof
CN111764428A (en) Trapezoidal socket structure of underground municipal comprehensive pipe gallery and construction method thereof
CN108429109A (en) A kind of mud stone class geology Grounding Measure of GSM
CN103603368A (en) Construction method for reverse construction of continuous wall encountering underground pipeline
CN113931665B (en) Loose soil layer tunnel waterproof construction method
CN108411933A (en) Soft soil foundation concrete reinforced pipe construction method and its foundation structure
CN209369832U (en) Steel pipe behind fill concrete structure in a kind of tunnel
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN112177022A (en) Construction method of prefabricated socket joint type interface pipeline
CN110685234B (en) Construction method of corrugated steel pipe culvert
CN109026022B (en) Reinforcing structure and reinforcing method for pebble-drift stratum shield river crossing
CN111254945A (en) Construction method of municipal comprehensive pipeline channel
CN107940102B (en) Underground raw water pipeline protection construction method
CN113775819B (en) Construction method for in-situ protection large-diameter oil and gas pipeline concrete structure
CN105926660A (en) Construction method of wind power low pile bearing platform foundation in intertidal zone
CN110056071A (en) A kind of municipal administration storm sewer assembling module and construction method
CN206110120U (en) A rectangle concrete pile for making up piping lane lateral wall
CN213982282U (en) Stray current eliminating system for gas pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180821

RJ01 Rejection of invention patent application after publication