CN108411865A - A kind of construction method of water conservancy diversion discharge structure - Google Patents

A kind of construction method of water conservancy diversion discharge structure Download PDF

Info

Publication number
CN108411865A
CN108411865A CN201810281794.1A CN201810281794A CN108411865A CN 108411865 A CN108411865 A CN 108411865A CN 201810281794 A CN201810281794 A CN 201810281794A CN 108411865 A CN108411865 A CN 108411865A
Authority
CN
China
Prior art keywords
conservancy diversion
water conservancy
discharge structure
water
diversion discharge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810281794.1A
Other languages
Chinese (zh)
Inventor
杨虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201810281794.1A priority Critical patent/CN108411865A/en
Publication of CN108411865A publication Critical patent/CN108411865A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of construction methods of water conservancy diversion discharge structure comprising step:1), in the entrance of water conservancy diversion discharge structure and/or outlet port build Temporary Cofferdam, the water retaining structure which constructs as water conservancy diversion discharge structure;2), Temporary Cofferdam protection in riverbank construct to be formed water conservancy diversion discharge structure import open channel and/or outlet open channel;3), import open channel and/or outlet open channel in construction form rubber dam;4), remove Temporary Cofferdam so that using rubber dam become water conservancy diversion discharge structure construction temporary water retaining cofferdam;5), wait for water conservancy diversion discharge structure all after the completion of construction, release the air or water in rubber dam.The Temporary Cofferdam that the present invention is effectively shortened water conservancy diversion discharge structure removes the time, the air or water in rubber dam can rapidly be released, so that river in water from water conservancy diversion discharge structure overcurrent, can be effectively increased river closure cofferdam dry season construction duration.

Description

A kind of construction method of water conservancy diversion discharge structure
Technical field
The present invention relates to hydraulic and hydroelectric engineering technical fields, and in particular to a kind of construction method of water conservancy diversion discharge structure.
Background technology
Shutting off for river usually requires first to build water conservancy diversion discharge structure, and water conservancy diversion discharge structure is one provisional or forever The engineering construction of long property, it is often very urgent that one of its feature, which is the duration, if cannot complete on schedule, be will result in entire Effective construction duration in the postponement shut off and the dry season for shortening cofferdam, water conservancy diversion discharge structure are by former streamflow from cofferdam Upstream is oriented to the flow-guiding channels such as diversion tunnel, the diversion canal in cofferdam downstream.
Under normal conditions, the import open channel of water conservancy diversion discharge structure and outlet open channel in generally require build Temporary Cofferdam work For the water retaining structure of water conservancy diversion discharge structure construction, wait for that water conservancy diversion discharge structure builds completion, dry season, interim riverbed was cut The Temporary Cofferdam is removed before stream, and the water in river is introduced into water conservancy diversion discharge structure to the changed course for realizing rivers current, in order to Carry out river shut off and coffering.However, the prior art, for the engineering in Large River, coffering is larger, Shut off and cofferdam needs to complete construction within a dry season, the construction period is nervous, and water conservancy diversion discharge structure imports and exports open channel Interior Temporary Cofferdam structural shape is generally concrete or rock structure type, and projects amount is big, long in time limit, directly affects river Road shuts off the time started, accounts for the pressure riverway cofferdam construction time in dry season.
Invention content
In order to solve water conservancy diversion discharge structure inlet and outlet open channel inner concrete or rock structure Temporary Cofferdam in the prior art Projects amount is big, long in time limit, accounts for the problem of pressing the river closure cofferdam construction time in dry season, the present invention provides a kind of water conservancy diversion The construction method of discharge structure.Specific technical solution and steps are as follows.
1), in the entrance of water conservancy diversion discharge structure and/or outlet port build Temporary Cofferdam, the Temporary Cofferdam is as water conservancy diversion The water retaining structure of discharge structure construction;
2), Temporary Cofferdam protection in riverbank construct to be formed water conservancy diversion discharge structure import open channel and/or outlet open channel;
3), the import open channel and/or outlet open channel in construction form rubber dam;
4), remove Temporary Cofferdam so that using rubber dam become water conservancy diversion discharge structure construction temporary water retaining cofferdam;
5), wait for water conservancy diversion discharge structure all after the completion of construction, release the air or water in rubber dam, and remove rubber dam Dam bag, water conservancy diversion discharge structure start overcurrent.
In the above-mentioned technical solutions, the height of the rubber dam according to the import of the diversion structure before river closure and/ Or the water blocking water level of outlet determines.
In the above-mentioned technical solutions, the water conservancy diversion discharge structure is diversion tunnel or diversion canal.
Construction method of the present invention relative to existing water conservancy diversion discharge structure, is effectively shortened water conservancy diversion discharge structure Temporary Cofferdam remove the time, can dry season arrive after, rapidly release rubber dam in air or water so that in river Water from water conservancy diversion discharge structure overcurrent, can be effectively increased river closure cofferdam dry season construction duration.
Description of the drawings
Fig. 1 is the floor map of the present invention;
Fig. 2 is the sectional view along water conservancy diversion discharge structure axis in Fig. 1.
In figure:The rivers 1-, the riverbanks 2-, 3- water conservancy diversion discharge structure, 4- imports open channel, 5- rubber dams, 6- Temporary Cofferdams.
Specific implementation mode
Present invention is further described in detail below in conjunction with the accompanying drawings.
Referring to Fig. 1-2, the construction method of water conservancy diversion discharge structure mainly includes the following steps that:
1), water conservancy diversion discharge structure 3 entry position build Temporary Cofferdam 6, the Temporary Cofferdam 6 be used as water conservancy diversion discharge structure The water retaining structure of construction;
2), the riverbank 2 in the protection of Temporary Cofferdam 6, which is constructed, forms the import open channel 4 of water conservancy diversion discharge structure 3;
3), in the import open channel 4 construction form rubber dam 5, the height of rubber dam 5 is built according to the water conservancy diversion before river closure The water blocking water level of import and/or the outlet of object determines;
4), flood end, remove Temporary Cofferdam 6 so that using rubber dam 5 become water conservancy diversion discharge structure 3 import open channel 4 it is interim The remainder of water-retaining cofferdam, water conservancy diversion discharge structure 3 is mainly that import open channel and the part exported between open channel continue to construct;
5), dry season arrive after, water conservancy diversion discharge structure 3 all construction complete, release rubber dam 5 in air or water, and The dam bag of rubber dam 5 is removed, water conservancy diversion discharge structure 3 starts overcurrent, and river 1 has river closure construction condition and starts to shut off.
Wherein, it is consistent with import to export arrangement and method for construction for water conservancy diversion discharge structure 3;Water conservancy diversion discharge structure 3 can be water conservancy diversion The flow-guiding channels such as hole or diversion canal.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, it will be understood by those of ordinary skill in the art that:It still may be used With technical scheme described in the above embodiments is modified or equivalent replacement of some of the technical features; And these modifications or replacements, various embodiments of the present invention technical solution that it does not separate the essence of the corresponding technical solution spirit and Range.

Claims (3)

1. a kind of construction method of water conservancy diversion discharge structure, which is characterized in that include the following steps:
1), in water conservancy diversion discharge structure(3)Entrance and/or outlet port build Temporary Cofferdam(6), the Temporary Cofferdam(6)Make For the water retaining structure of water conservancy diversion discharge structure construction;
2), in Temporary Cofferdam(6)Riverbank in protection(2)Construction forms the import open channel of water conservancy diversion discharge structure(4)And/or go out Mouth open channel;
3), in the import open channel(4)And/or construction forms rubber dam in outlet open channel(5);
4), remove Temporary Cofferdam(6)So that utilize rubber dam(5)As the temporary water retaining cofferdam of water conservancy diversion discharge structure construction;
5), wait for water conservancy diversion discharge structure(3)All after the completion of construction, rubber dam is released(5)Interior air or water, and remove rubber Jiao Ba(5)Dam bag, water conservancy diversion discharge structure(3)Start overcurrent.
2. a kind of construction method of water conservancy diversion discharge structure according to claim 1, which is characterized in that the rubber dam (5)Height determined according to the water blocking water level of import and/or the outlet of the diversion structure before river closure.
3. a kind of construction method of water conservancy diversion discharge structure according to claim 1, which is characterized in that the water conservancy diversion is let out Water buildings(3)For diversion tunnel or diversion canal.
CN201810281794.1A 2018-04-02 2018-04-02 A kind of construction method of water conservancy diversion discharge structure Pending CN108411865A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810281794.1A CN108411865A (en) 2018-04-02 2018-04-02 A kind of construction method of water conservancy diversion discharge structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810281794.1A CN108411865A (en) 2018-04-02 2018-04-02 A kind of construction method of water conservancy diversion discharge structure

Publications (1)

Publication Number Publication Date
CN108411865A true CN108411865A (en) 2018-08-17

Family

ID=63133999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810281794.1A Pending CN108411865A (en) 2018-04-02 2018-04-02 A kind of construction method of water conservancy diversion discharge structure

Country Status (1)

Country Link
CN (1) CN108411865A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356124A (en) * 2018-11-21 2019-02-19 中国电建集团成都勘测设计研究院有限公司 Cavern usual friendship fork structure
CN109371914A (en) * 2018-12-25 2019-02-22 中国电建集团成都勘测设计研究院有限公司 A kind of discharge channel structure convenient for later period reconstruction
CN111305141A (en) * 2019-11-29 2020-06-19 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN117328410A (en) * 2023-09-07 2024-01-02 北京城建道桥建设集团有限公司 Dam blocking construction method with low excavation quantity and rapid construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010101149A (en) * 2008-10-22 2010-05-06 Korea Electric Power Corp Bubble preventing water channel structure for water discharge passage in power station
CN102900058A (en) * 2012-11-12 2013-01-30 中国水电顾问集团华东勘测设计研究院 Diversion construction method of wide-riverbed dam type hydropower station
CN204080733U (en) * 2014-09-03 2015-01-07 朱贺 Combination moving type rubber dam
CN204282296U (en) * 2014-10-30 2015-04-22 上海市堤防(泵闸)设施管理处 The interim flood control dike of a kind of assembling rubber dam
CN106930236A (en) * 2017-04-18 2017-07-07 黄醒明 A kind of dykes and dams folding method and the closure pipe closed up for dykes and dams
CN107816050A (en) * 2017-12-07 2018-03-20 中铁二十局集团第六工程有限公司 A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010101149A (en) * 2008-10-22 2010-05-06 Korea Electric Power Corp Bubble preventing water channel structure for water discharge passage in power station
CN102900058A (en) * 2012-11-12 2013-01-30 中国水电顾问集团华东勘测设计研究院 Diversion construction method of wide-riverbed dam type hydropower station
CN204080733U (en) * 2014-09-03 2015-01-07 朱贺 Combination moving type rubber dam
CN204282296U (en) * 2014-10-30 2015-04-22 上海市堤防(泵闸)设施管理处 The interim flood control dike of a kind of assembling rubber dam
CN106930236A (en) * 2017-04-18 2017-07-07 黄醒明 A kind of dykes and dams folding method and the closure pipe closed up for dykes and dams
CN107816050A (en) * 2017-12-07 2018-03-20 中铁二十局集团第六工程有限公司 A kind of concrete cofferdam and earth rock cofferdam combined cofferdam and its construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
但汉仁等: "《橡胶坝在桥巩水电站施工导流中的应用》", 《红河水》 *
夏仲平: "《水利水电工程导截流技术》", 《水利水电施工》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356124A (en) * 2018-11-21 2019-02-19 中国电建集团成都勘测设计研究院有限公司 Cavern usual friendship fork structure
CN109356124B (en) * 2018-11-21 2023-11-21 中国电建集团成都勘测设计研究院有限公司 Chamber level crossing fork structure
CN109371914A (en) * 2018-12-25 2019-02-22 中国电建集团成都勘测设计研究院有限公司 A kind of discharge channel structure convenient for later period reconstruction
CN109371914B (en) * 2018-12-25 2023-09-26 中国电建集团成都勘测设计研究院有限公司 Drain channel structure convenient to later stage rebuild
CN111305141A (en) * 2019-11-29 2020-06-19 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN111305141B (en) * 2019-11-29 2021-11-26 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN117328410A (en) * 2023-09-07 2024-01-02 北京城建道桥建设集团有限公司 Dam blocking construction method with low excavation quantity and rapid construction
CN117328410B (en) * 2023-09-07 2024-04-23 北京城建道桥建设集团有限公司 Dam blocking construction method with low excavation quantity and rapid construction

Similar Documents

Publication Publication Date Title
CN108411865A (en) A kind of construction method of water conservancy diversion discharge structure
CN104963322A (en) Hydraulic junction facility
CN105386426B (en) The ecological drainage tunnel and method that diversion tunnel reconstruction controls for gates of segmental shape
CN104060619A (en) Construction method and structure of hydraulic core-wall rockfill dam without cofferdams
CN107858990A (en) The arrangement of Canyon Area high dam ditch engineering of water treatment
CN106930230A (en) The governing system and method for a kind of tidal black-odor riverway of single-pass
CN108316259A (en) Diversion tunnel sets up lock under interim plug joint gate and blocks arrangement and method
CN204825802U (en) Compound line type overflow weir
CN202440787U (en) Riverway diversion device
CN108677892A (en) Diversion tunnel working tunnel is used as reconstruction structure of the ecology for water hole
CN106400751A (en) Sand blocking ridge structure and construction process thereof
CN107893406B (en) Diversion tunnel group lower brake plugging program
CN116575412A (en) Composite plugging device and construction method
CN105421310A (en) Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock
CN204715310U (en) A kind of reservoir desilting system
CN206173879U (en) Gravity dam construction diversion structure
CN207597336U (en) The arrangement of Canyon Area high dam ditch engineering of water treatment
CN205999865U (en) A kind of sediment trapping bank structure
CN2434338Y (en) Dam bag
CN206529746U (en) A kind of Concrete Dam Construction arrangement of excessively stream arch dam free removal
CN205530166U (en) Full pipeline diversion power generation facility
CN109371914B (en) Drain channel structure convenient to later stage rebuild
CN210216332U (en) Retaining dam structure for overhauling whole tunnel section of hydroelectric engineering diversion tunnel in canyon region
CN210562058U (en) Ecological diversion tunnel structure capable of being used for flood season of main flood of ultra-high rock-fill dam
CN212714848U (en) Initial diversion tunnel plugging gate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817

RJ01 Rejection of invention patent application after publication