CN105421310A - Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock - Google Patents
Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock Download PDFInfo
- Publication number
- CN105421310A CN105421310A CN201510997207.5A CN201510997207A CN105421310A CN 105421310 A CN105421310 A CN 105421310A CN 201510997207 A CN201510997207 A CN 201510997207A CN 105421310 A CN105421310 A CN 105421310A
- Authority
- CN
- China
- Prior art keywords
- lock
- diversion tunnel
- lock chamber
- steel sheet
- gate
- Prior art date
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 32
- 239000010959 steel Substances 0.000 claims abstract description 32
- 238000010276 construction Methods 0.000 claims abstract description 24
- 239000011901 water Substances 0.000 claims abstract description 14
- 239000000463 materials Substances 0.000 claims abstract description 7
- 239000000203 mixtures Substances 0.000 claims abstract description 4
- 239000000945 fillers Substances 0.000 claims description 27
- 238000003672 processing method Methods 0.000 claims description 11
- 229920000742 Cotton Polymers 0.000 claims description 8
- 239000004927 clay Substances 0.000 claims description 8
- 229910052570 clay Inorganic materials 0.000 claims description 8
- 230000000694 effects Effects 0.000 claims description 8
- 239000010410 layers Substances 0.000 claims description 8
- 210000000481 Breast Anatomy 0.000 claims description 6
- 239000011435 rock Substances 0.000 claims description 6
- 239000004575 stone Substances 0.000 claims description 3
- 238000004080 punching Methods 0.000 claims description 2
- 230000000903 blocking Effects 0.000 abstract description 2
- 238000009991 scouring Methods 0.000 abstract 1
- 238000000034 methods Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000005755 formation reactions Methods 0.000 description 2
- 241000209202 Bromus secalinus Species 0.000 description 1
- 241000731961 Juncaceae Species 0.000 description 1
- 238000000280 densification Methods 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 230000002349 favourable Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
- E02B9/02—Water-ways
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/16—Sealings or joints
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
Description
Technical field
the present invention relates to processing method and the structure of seepage after lock under a kind of Diversion Tunnel lock chamber, belong to water conservancy and hydropower training works technical field.
Background technology
diversion Tunnel is when the construction of hydropower stations phase, prearranged a kind of construction diversion mode.Diversion Tunnel is generally temporary building, is damming constantly, allows river by Diversion Tunnel from the upstream flow of dam to downstream.After dam engineering is completed, river just can from the dam current by pass overcurrent completed, and namely the mission of Diversion Tunnel terminates, and needs Diversion Tunnel shutoff or separately uses it for anything else.
usually constructed import lock chamber in the import of Diversion Tunnel, in Construction for Hydroelectric Project water conservancy diversion process, the working life of inlet of diversion tunnel lock chamber often runs through the whole construction diversion period, and comparatively large-engineering often reaches the several years.Because in lock chamber, Di Kan position is subject to current scour for a long time, if exist, river bed load is more, lock chamber input elevation is lower, the factor such as longer, Diversion Tunnel extended active duty of free pressure flow alternating periods in lock chamber, the destruction that then in lock chamber, Di Kan position is subject to is more serious, is sometimes reached several meters by the hole degree of depth that water is gone out.Cause under Diversion Tunnel shutoff that lock late gate and end bank can not be completely closed, there is infiltration in various degree in hole, affect the construction of Diversion tunnel plug, and then impact generates electricity the duration.
for the situation that lock late gate under above-mentioned Diversion Tunnel shutoff and end bank can not close completely, at present conventional processing method adopts again to descend lock, repairs lock chamber bank position of going to the bottom.Although current processing method can meet the needs of engineering, the duration is longer, can incur loss through delay the generating duration, particularly greatly influenced for larger power station economic benefit.
Summary of the invention
the object of the invention is to, there is provided that a kind of structure is simple, processing method that construction is easy to seepage after lock under Diversion Tunnel lock chamber and structure, to take processing scheme timely both can meet requirement of engineering, generating construction period can be met again, thus overcome the deficiencies in the prior art.
technical scheme of the present invention is achieved in that
under a kind of Diversion Tunnel lock chamber of the present invention, after lock, the processing method of seepage is that the method is under inlet of diversion tunnel lock chamber after lock, and before lock chamber, open channel section topples over native stone formation cofferdam, makes most of rivers current let out from permanent building or let out under other passages; To cheating the current infiltrated from gate lower bottom Kan Chong, take the three kinds of different materials combination leak stopping of Larsen steel sheet pile, filler and underwater concrete; And then carry out Diversion Tunnel plugging construction.
in preceding method, described Larsen steel sheet pile gos deep into below bosom, gate undershoot hole more than 0.5m, and is close to gate and arranges and guarantee that steel sheet pile is stable vertically.
in preceding method, described filler comprises galvanized wire gabion, clay, loess and cotton-wool, and filler is pressed into by hydraulic pressure effect in the Larsen steel sheet pile gap leaked, and guarantees that it is filled and closely knitly reaches stagnant water effect.
in preceding method, described underwater concrete is the layer of concrete of building covering on filler.
according to the anti-leakage structure after lock under of the present invention a kind of Diversion Tunnel lock chamber that said method is constructed, comprise the lock chamber being located at inlet of diversion tunnel place, the gate in lock chamber is in closed condition; Be provided with earth rock cofferdam before gate, have bottom gate gone out by water rush hole, be provided with one group of Larsen steel sheet pile at the upstream face of gate, be provided with filler bottom Larsen steel sheet pile upstream face, above filler, be provided with layer of concrete.
in aforementioned structure, described one group of Larsen steel sheet pile is close to gate upstream face, and Larsen steel sheet pile bottom extends below bosom, punching hole more than 0.5m.
in aforementioned structure, described filler is the mixed fillers be made up of galvanized wire gabion, clay, loess and cotton-wool.
owing to have employed technique scheme, compared with prior art, the present invention by laying loss circulation material before gate, guarantees plug construction safety in Diversion Tunnel hole in the present invention, to solve under Diversion Tunnel lock chamber after lock, cannot carry out the situation of plug construction fast.The present invention not only has that structure is simple, construction is easy to advantage, and while solving end bank leakage problems in time, effectively reduces construction costs.The present invention is particularly useful for the situation that big-and-middle-sized engineering Diversion Tunnel section larger running time is longer, the plug construction period is tighter.
Accompanying drawing explanation
fig. 1 is structural representation of the present invention.
being labeled as in figure: 1-Diversion Tunnel, 2-lock chamber, 3-gate, 4-earth rock cofferdam, 5-rushes hole, 6-Larsen steel sheet pile, 7-filler, 8-layer of concrete.
Detailed description of the invention
below in conjunction with drawings and Examples, the present invention is described in further detail, but not as any limitation of the invention.
the processing method of seepage after lock under a kind of Diversion Tunnel lock chamber of the present invention, as shown in Figure 1: the method is under inlet of diversion tunnel lock chamber after lock, before lock chamber, open channel section topples over native stone formation cofferdam, makes most of rivers current let out from permanent building or let out under other passages; To cheating the current infiltrated from gate lower bottom Kan Chong, take the three kinds of different materials combination leak stopping of Larsen steel sheet pile, filler and underwater concrete; And then carry out Diversion Tunnel plugging construction.Larsen steel sheet pile gos deep into below bosom, gate undershoot hole more than 0.5m, and is close to gate and arranges and guarantee that steel sheet pile is stable vertically.Filler comprises galvanized wire gabion, clay, loess and cotton-wool, and filler is pressed into by hydraulic pressure effect in the Larsen steel sheet pile gap leaked, and guarantees that it is filled and closely knitly reaches stagnant water effect.Underwater concrete is the layer of concrete of building covering on filler.
according to the anti-leakage structure after lock under of the present invention a kind of Diversion Tunnel lock chamber that said method is constructed, as shown in Figure 1, this structure comprises the lock chamber 2 being located at Diversion Tunnel 1 import department, and the gate 3 in lock chamber 2 is in closed condition; It is characterized in that: before gate 3, be provided with earth rock cofferdam 4, have bottom gate 3 gone out by water rush hole 5, be provided with one group of Larsen steel sheet pile 6 at the upstream face of gate 3, be provided with filler 7 bottom Larsen steel sheet pile 6 upstream face, above filler 7, be provided with layer of concrete 8.One group of Larsen steel sheet pile 6 is close to gate 3 upstream face, and Larsen steel sheet pile 6 bottom extends and rushes below bosom, hole 5 more than 0.5m.Filler 7 is the mixed fillers be made up of galvanized wire gabion, clay, loess and cotton-wool.
Embodiment
this is such as shown in Fig. 1, and in Fig. 1, arrow represents water (flow) direction.This example is main to be implemented in accordance with the following steps:
the first step, in conjunction with river diversion scheme during construction, permanent building is complete build after, to Diversion Tunnel 1 import lock chamber 2 times locks, now find gate leak for 3 times seriously, reason is that end bank washes away for many years, formed comparatively favourable opposition cheat 5, cause carrying out Diversion tunnel plug dry work.
second step, constructs in time in order to ensure Diversion tunnel plug, does not affect power station reservoir impoundment power generation, needs to take engineering measure to gate 3 lower leak stopping, does not affect plug construction.First, suitably pile in lock chamber 2 import open channel section and build earth rock cofferdam 4, for the engineering time is won in gate 3 lower leak stopping, if river discharge is larger need open permanent building earial drainage, guarantee blocking construction safety under gate.
3rd step, after lock chamber import earth rock cofferdam heap has been built, carry out Larsen steel sheet pile 6 and construct, Larsen steel sheet pile 6 has been close to gate 3, guarantees vertically stable.The heap in cofferdam builds height, should be able to guarantee that Larsen steel sheet pile 6 has been constructed, and opens permanent building earial drainage if desired.
4th step, after Larsen steel sheet pile 6 has been constructed, the filler 7 be made up of galvanized wire gabion, clay, loess, cotton-wool etc. of jettisoninging in Larsen steel sheet pile 6 upstream face bottom.Now retaining can be continued, by hydraulic pressure effect, the fillers 7 such as galvanized wire gabion, clay, loess, cotton-wool are pushed in Larsen steel sheet pile 6 gap leaked, guarantee that it is filled and closely knitly reach stagnant water effect, then build underwater concrete and form layer of concrete, densification is carried out to plugging material, prevents from, in retaining process, leaking, now water leakage of gate situation reduces greatly, can carry out plug construction.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510997207.5A CN105421310A (en) | 2015-12-28 | 2015-12-28 | Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510997207.5A CN105421310A (en) | 2015-12-28 | 2015-12-28 | Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105421310A true CN105421310A (en) | 2016-03-23 |
Family
ID=55499822
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510997207.5A CN105421310A (en) | 2015-12-28 | 2015-12-28 | Treatment method and structure for leakage of diversion tunnel lock chamber after lowering down lock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105421310A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109137850A (en) * | 2018-08-17 | 2019-01-04 | 中水电第十工程局(郑州)有限公司 | A kind of extremely frigid zones winter diversion tunnel construction method that mostly dike shuts off in an opposite direction |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008007787A1 (en) * | 2008-02-06 | 2009-08-20 | Rösch, Günther, Dipl.-Ing. (FH) | Water intake for stream water removal from running waters for smaller discharge hydropower plants in the medium and high pressure ranges |
CN102011596A (en) * | 2010-11-29 | 2011-04-13 | 中铁三局集团有限公司 | Shield originating or receiving end tunnel portal maintenance process |
CN204591292U (en) * | 2015-04-27 | 2015-08-26 | 浙江大学城市学院 | A kind of Novel shield reinforcing structure |
-
2015
- 2015-12-28 CN CN201510997207.5A patent/CN105421310A/en not_active Application Discontinuation
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102008007787A1 (en) * | 2008-02-06 | 2009-08-20 | Rösch, Günther, Dipl.-Ing. (FH) | Water intake for stream water removal from running waters for smaller discharge hydropower plants in the medium and high pressure ranges |
CN102011596A (en) * | 2010-11-29 | 2011-04-13 | 中铁三局集团有限公司 | Shield originating or receiving end tunnel portal maintenance process |
CN204591292U (en) * | 2015-04-27 | 2015-08-26 | 浙江大学城市学院 | A kind of Novel shield reinforcing structure |
Non-Patent Citations (1)
Title |
---|
郭金婷等: ""大岗山水电站导流隧洞下闸后渗漏处理"", 《水力发电》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109137850A (en) * | 2018-08-17 | 2019-01-04 | 中水电第十工程局(郑州)有限公司 | A kind of extremely frigid zones winter diversion tunnel construction method that mostly dike shuts off in an opposite direction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103343543B (en) | Foundation pit dewatering well pressure-reduction-type plugging method | |
CN104131575B (en) | A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation | |
CN204238170U (en) | A kind of open channel scouring on bedrock model test apparatus | |
CN104499510B (en) | A kind of antiseep composite barrier | |
CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
CN103277120A (en) | Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft | |
CN108086296B (en) | Dynamic and static combined grouting foundation reinforcing construction method | |
CN106015737B (en) | The construction method of cross a river immersed tube integral installation | |
CN203174616U (en) | Clay foundation rain falling and water saving system | |
CN102061706B (en) | Assembly steel box cofferdam and construction method thereof | |
Ni et al. | Characterising the failure pattern of a station box of Taipei Rapid Transit System (TRTS) and its rehabilitation | |
CN103526721B (en) | A kind of permeable pile foundation groynes | |
CN102605750B (en) | Grouting reinforcement and earthquake resisting method for earth and rockfill dam | |
CN104631475A (en) | Safe and fast construction method of down-traversing river shallow depth bored tunnel | |
CN205077453U (en) | Dam structure that panel rock -fill dam and upstream cofferdam combine | |
CN108193606B (en) | A kind of means of defence of local scour near pier | |
CN109098687A (en) | Single stop grouting plug retrusive sublevel grouting device and method suitable for crack rock | |
CN104878739A (en) | Drainage material assembly capable of being transversely connected with plastic drainage boards and method for constructing drainage material assembly | |
CN105201448A (en) | Method for water-stopping grouting plugging in high-pressure high-flow water gush channel | |
CN102619227A (en) | Grouting device, assembly and grouting method for single pipe pile foundation of offshore wind turbine generating set | |
CN105781575A (en) | Water-rich stratum pipe piece combination structure and construction method thereof | |
CN101713197A (en) | Method for sealing foundation pit pressure reduction well | |
CN104264698A (en) | Construction method of clay core earth rock cofferdam | |
CN108952776A (en) | A kind of method of the equidistant horizontal orientation concordant bored grouting transformation dual limestone of roof and floor | |
CN103510493B (en) | Low overflow dam cave depot type hydropower station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160323 |