CN108396653A - 一种钢结构桥梁施工方法 - Google Patents
一种钢结构桥梁施工方法 Download PDFInfo
- Publication number
- CN108396653A CN108396653A CN201810171368.2A CN201810171368A CN108396653A CN 108396653 A CN108396653 A CN 108396653A CN 201810171368 A CN201810171368 A CN 201810171368A CN 108396653 A CN108396653 A CN 108396653A
- Authority
- CN
- China
- Prior art keywords
- steel
- welding
- manufacture
- construction method
- bridge beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Abstract
本发明涉及桥梁施工技术领域,尤其是一种钢结构桥梁施工方法,包括以下步骤:S1、材料选择;S2、钢材预处理;S3、钢结构放样、下料、加工:S4、分段制造:A1、胎架制造;A2、钢桁架阶段制造;A3、阶段制造;A4、钢桁架阶段组装;S5、吊运;S6、现场拼装。本发明提供了一种钢结构桥梁的施工方法,能够快速、安全、有效地完成钢结构桥梁的整体架设施工,适用范围广。
Description
技术领域
本发明涉及桥梁施工技术领域,尤其涉及一种钢结构桥梁施工方法。
背景技术
桥梁,一般指架设在江河湖海上,使车辆行人等能顺利通行的构筑物。为适应现代高速发展的交通行业,桥梁亦引申为跨越山涧、不良地质或满足其他交通需要而架设的使通行更加便捷的建筑物。 桥梁一般由上部构造、下部结构、支座和附属构造物组成,上部结构又称桥跨结构,是跨越障碍的主要结构;下部结构包括桥台、桥墩和基础;支座为桥跨结构与桥墩或桥台的支承处所设置的传力装置;附属构造物则指桥头搭板、锥形护坡、护岸、导流工程等。如何快速、安全、 有效地完成钢结构桥梁的整体架设施工,是亟待解决的问题。
发明内容
本发明的目的是为了解决现有技术中存在的缺点,而提出的一种钢结构桥梁施工方法。
为了实现上述目的,本发明采用了如下技术方案:
设计一种钢结构桥梁施工方法,包括以下步骤:
S1、材料选择:钢结构主要采用Q345qC和Q345C钢材,焊焊接材料选用J507焊条,焊条直径为Φ3.2mm和Φ4mm;
S2、钢材预处理:钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm;
S3、钢结构放样、下料、加工:
S4、分段制造:
A1、胎架制造;
A2、钢桁架阶段制造:所有的钢桁架分段在水平胎架上侧装,再上总装胎架上合拢;
A3、阶段制造:按图纸开出节段的中心线和检验线并根据其划出各纵横构件安装线,纵向按每米加放1mm的焊接收缩余量;把上弦杆、下弦杆、腹杆、竖杆、横梁、装饰杆件及顶部上横撑等在平台上先拼装、焊接,焊后矫正变形;
钢板直接上胎架拼接,焊接使用埋弧自动焊,焊接前磨掉坡口及其周围30mm范围内的铁锈、油漆等;钢桁架分左右两个平面分段在水平胎架上制作;底部横梁片体在专用胎架上制作;
A4、钢桁架阶段组装:将左、右钢桁架小合拢件分别吊上底部平面分段,对齐分段对合线和装配线;调整、对齐分段对合线和中心线,调整左、右钢桁架的角度以及高度并做好加强;安装顶部横撑平面小分段,并做好加强;安装其余散装件,并检查组合的完整性和正确性;
S5、吊运;
S6、现场拼装:用同一台全站仪在现场放出钢箱梁的中心线和各轴线,作为分段吊装定位的参照基准,要确保每一轴线相对位置精确,而且划线位置必须牢固,保证各定位线在施工过程中不发生偏差;分段定位时要确保准线重合,然后与支墩架钢性固定,合拢口适当加排板加强,减少焊接的收缩变形。
优选的,钢材表面质量:钢材表面不应有影响使用的有害缺陷,主要受力构件,如顶板、底板、腹板和横梁等,钢板厚度不允许出现负公差。
优选的,钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm。
优选的,S3具体步骤如下:
B1、放样:根据设计图纸、节段划分和工艺要求,采用1:1电脑放样,主桥钢桁架的腹板与顶板、底板垂直,横向结构垂直顶、底板设置,桥墩位置的横向结构垂直于水平面;
B2、号料;
B3、零件分离加工:采用数控切割,零件分离后要对变形进行矫直、矫平,之后对坡口、边缘进行加工,以使其不影响焊接施工。
优选的,B3中主要受力零件冷弯曲加工时,环境温度不宜低于-5℃,内侧弯曲半径不得小于板厚的15倍,否则工厂将采用热煨,热煨温度控制在920-980℃之间;零、部件在制造、起吊、运输过程中,如产生变形,根据其结构形式,可采用机械矫正或火焰矫正;火焰矫正时,温度控制在650℃-750℃,矫正后零件随空气缓慢冷却,降至室温以前,不得锤击或用水急冷。
优选的,A4中焊缝要求如下:对接焊缝的余高为2-3mm,必要时用砂轮磨光机磨平;焊缝要求与母材表面光顺过渡,同一焊缝的焊脚高度要一致;焊缝表面不准电弧光伤、裂纹、气孔及凹坑;主要对接焊缝的咬边不允许超过0.5mm,次要受力焊缝的咬边不允许超过1mm;钢板的对接焊缝应与母材表面打磨齐平。
本发明提出的一种钢结构桥梁施工方法,有益效果在于:本发明提供了一种钢结构桥梁的施工方法,能够快速、安全、 有效地完成钢结构桥梁的整体架设施工,适用范围广。
具体实施方式
下面对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。
一种钢结构桥梁施工方法,包括以下步骤:
S1、材料选择:钢结构主要采用Q345qC和Q345C钢材,焊焊接材料选用J507焊条,焊条直径为Φ3.2mm和Φ4mm;
S2、钢材预处理:钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm;
S3、钢结构放样、下料、加工:
S4、分段制造:
A1、胎架制造;
A2、钢桁架阶段制造:所有的钢桁架分段在水平胎架上侧装,再上总装胎架上合拢;
A3、阶段制造:按图纸开出节段的中心线和检验线并根据其划出各纵横构件安装线,纵向按每米加放1mm的焊接收缩余量;把上弦杆、下弦杆、腹杆、竖杆、横梁、装饰杆件及顶部上横撑等在平台上先拼装、焊接,焊后矫正变形;
钢板直接上胎架拼接,焊接使用埋弧自动焊,焊接前磨掉坡口及其周围30mm范围内的铁锈、油漆等;钢桁架分左右两个平面分段在水平胎架上制作;底部横梁片体在专用胎架上制作;
A4、钢桁架阶段组装:将左、右钢桁架小合拢件分别吊上底部平面分段,对齐分段对合线和装配线;调整、对齐分段对合线和中心线,调整左、右钢桁架的角度以及高度并做好加强;安装顶部横撑平面小分段,并做好加强;安装其余散装件,并检查组合的完整性和正确性;
S5、吊运;
S6、现场拼装:用同一台全站仪在现场放出钢箱梁的中心线和各轴线,作为分段吊装定位的参照基准,要确保每一轴线相对位置精确,而且划线位置必须牢固,保证各定位线在施工过程中不发生偏差;分段定位时要确保准线重合,然后与支墩架钢性固定,合拢口适当加排板加强,减少焊接的收缩变形。
钢材表面质量:钢材表面不应有影响使用的有害缺陷,主要受力构件,如顶板、底板、腹板和横梁等,钢板厚度不允许出现负公差。
钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm。
S3具体步骤如下:
B1、放样:根据设计图纸、节段划分和工艺要求,采用1:1电脑放样,主桥钢桁架的腹板与顶板、底板垂直,横向结构垂直顶、底板设置,桥墩位置的横向结构垂直于水平面;
B2、号料;
B3、零件分离加工:采用数控切割,零件分离后要对变形进行矫直、矫平,之后对坡口、边缘进行加工,以使其不影响焊接施工。
B3中主要受力零件冷弯曲加工时,环境温度不宜低于-5℃,内侧弯曲半径不得小于板厚的15倍,否则工厂将采用热煨,热煨温度控制在920-980℃之间;零、部件在制造、起吊、运输过程中,如产生变形,根据其结构形式,可采用机械矫正或火焰矫正;火焰矫正时,温度控制在650℃-750℃,矫正后零件随空气缓慢冷却,降至室温以前,不得锤击或用水急冷。
A4中焊缝要求如下:对接焊缝的余高为2-3mm,必要时用砂轮磨光机磨平;焊缝要求与母材表面光顺过渡,同一焊缝的焊脚高度要一致;焊缝表面不准电弧光伤、裂纹、气孔及凹坑;主要对接焊缝的咬边不允许超过0.5mm,次要受力焊缝的咬边不允许超过1mm;钢板的对接焊缝应与母材表面打磨齐平。
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。
Claims (6)
1.一种钢结构桥梁施工方法,其特征在于,包括以下步骤:
S1、材料选择:钢结构主要采用Q345qC和Q345C钢材,焊焊接材料选用J507焊条,焊条直径为Φ3.2mm和Φ4mm;
S2、钢材预处理:钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm;
S3、钢结构放样、下料、加工:
S4、分段制造:
A1、胎架制造;
A2、钢桁架阶段制造:所有的钢桁架分段在水平胎架上侧装,再上总装胎架上合拢;
A3、阶段制造:按图纸开出节段的中心线和检验线并根据其划出各纵横构件安装线,纵向按每米加放1mm的焊接收缩余量;把上弦杆、下弦杆、腹杆、竖杆、横梁、装饰杆件及顶部上横撑等在平台上先拼装、焊接,焊后矫正变形;
钢板直接上胎架拼接,焊接使用埋弧自动焊,焊接前磨掉坡口及其周围30mm范围内的铁锈、油漆等;钢桁架分左右两个平面分段在水平胎架上制作;底部横梁片体在专用胎架上制作;
A4、钢桁架阶段组装:将左、右钢桁架小合拢件分别吊上底部平面分段,对齐分段对合线和装配线;调整、对齐分段对合线和中心线,调整左、右钢桁架的角度以及高度并做好加强;安装顶部横撑平面小分段,并做好加强;安装其余散装件,并检查组合的完整性和正确性;
S5、吊运;
S6、现场拼装:用同一台全站仪在现场放出钢箱梁的中心线和各轴线,作为分段吊装定位的参照基准,要确保每一轴线相对位置精确,而且划线位置必须牢固,保证各定位线在施工过程中不发生偏差;分段定位时要确保准线重合,然后与支墩架钢性固定,合拢口适当加排板加强,减少焊接的收缩变形。
2.根据权利要求1所述的一种钢结构桥梁施工方法,其特征在于,钢材表面质量:钢材表面不应有影响使用的有害缺陷,主要受力构件,如顶板、底板、腹板和横梁等,钢板厚度不允许出现负公差。
3.根据权利要求1所述的一种钢结构桥梁施工方法,其特征在于:钢材表面预处理抛丸除锈达Sa2.5级,清洁后喷涂底漆,涂层厚度为20μm。
4.根据权利要求1所述的一种钢结构桥梁施工方法,其特征在于,S3具体步骤如下:
B1、放样:根据设计图纸、节段划分和工艺要求,采用1:1电脑放样,主桥钢桁架的腹板与顶板、底板垂直,横向结构垂直顶、底板设置,桥墩位置的横向结构垂直于水平面;
B2、号料;
B3、零件分离加工:采用数控切割,零件分离后要对变形进行矫直、矫平,之后对坡口、边缘进行加工,以使其不影响焊接施工。
5.根据权利要求4所述的一种钢结构桥梁施工方法,其特征在于,B3中主要受力零件冷弯曲加工时,环境温度不宜低于-5℃,内侧弯曲半径不得小于板厚的15倍,否则工厂将采用热煨,热煨温度控制在920-980℃之间;零、部件在制造、起吊、运输过程中,如产生变形,根据其结构形式,可采用机械矫正或火焰矫正;火焰矫正时,温度控制在650℃-750℃,矫正后零件随空气缓慢冷却,降至室温以前,不得锤击或用水急冷。
6.根据权利要求1所述的一种钢结构桥梁施工方法,其特征在于,A4中焊缝要求如下:对接焊缝的余高为2-3mm,必要时用砂轮磨光机磨平;焊缝要求与母材表面光顺过渡,同一焊缝的焊脚高度要一致;焊缝表面不准电弧光伤、裂纹、气孔及凹坑;主要对接焊缝的咬边不允许超过0.5mm,次要受力焊缝的咬边不允许超过1mm;钢板的对接焊缝应与母材表面打磨齐平。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810171368.2A CN108396653A (zh) | 2018-03-01 | 2018-03-01 | 一种钢结构桥梁施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810171368.2A CN108396653A (zh) | 2018-03-01 | 2018-03-01 | 一种钢结构桥梁施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108396653A true CN108396653A (zh) | 2018-08-14 |
Family
ID=63091411
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810171368.2A Pending CN108396653A (zh) | 2018-03-01 | 2018-03-01 | 一种钢结构桥梁施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108396653A (zh) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109877540A (zh) * | 2019-03-15 | 2019-06-14 | 湖南林森建筑有限公司 | 一种高层钢结构工程的施工方法 |
CN110205947A (zh) * | 2019-07-06 | 2019-09-06 | 中铁二十五局集团第五工程有限公司 | 一种天桥钢箱梁施工方法 |
CN110307957A (zh) * | 2019-07-02 | 2019-10-08 | 中国建筑第八工程局有限公司 | 一种风洞洞体高精度无棱镜放样工艺 |
CN110369955A (zh) * | 2019-07-24 | 2019-10-25 | 重庆交通建设(集团)有限责任公司 | 钢结构箱梁优化制造工艺 |
CN112211103A (zh) * | 2020-10-10 | 2021-01-12 | 山西省工业设备安装集团有限公司 | 输煤栈桥钢桁架组合安装安全专项施工工艺 |
CN113500273A (zh) * | 2021-06-07 | 2021-10-15 | 中铁十八局集团隧道工程有限公司 | 一种钢箱梁施工焊接工艺 |
CN113634473A (zh) * | 2021-08-10 | 2021-11-12 | 山东望意阳海绵城市建设有限公司 | 一种钢结构桥面的施工工艺 |
CN115255823A (zh) * | 2022-07-27 | 2022-11-01 | 中铁二十五局集团第二工程有限公司 | 一种钢梁顶板单元制造工艺 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101389044B1 (ko) * | 2013-07-19 | 2014-04-23 | (주)나우기술 | 교량용 강재거더 및 그 제작 방법과, 강재거더를 교각에 강결 설치하는 시공방법 |
CN103911950A (zh) * | 2014-02-21 | 2014-07-09 | 中铁宝桥集团有限公司 | 一种大型组合梁钢主梁整孔及制作方法 |
CN104060523A (zh) * | 2014-05-23 | 2014-09-24 | 浙江东南网架股份有限公司 | 一种超大型桥箱梁构件、专用胎架及其组装方法 |
KR101703820B1 (ko) * | 2016-08-17 | 2017-02-08 | 이경표 | ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법 및 이에 의해 제작된 교량용 콘크리트 충진 박스거더 |
-
2018
- 2018-03-01 CN CN201810171368.2A patent/CN108396653A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101389044B1 (ko) * | 2013-07-19 | 2014-04-23 | (주)나우기술 | 교량용 강재거더 및 그 제작 방법과, 강재거더를 교각에 강결 설치하는 시공방법 |
CN103911950A (zh) * | 2014-02-21 | 2014-07-09 | 中铁宝桥集团有限公司 | 一种大型组合梁钢主梁整孔及制作方法 |
CN104060523A (zh) * | 2014-05-23 | 2014-09-24 | 浙江东南网架股份有限公司 | 一种超大型桥箱梁构件、专用胎架及其组装方法 |
KR101703820B1 (ko) * | 2016-08-17 | 2017-02-08 | 이경표 | ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법 및 이에 의해 제작된 교량용 콘크리트 충진 박스거더 |
Non-Patent Citations (3)
Title |
---|
百度文库: "焊接工艺方案", 《百度文库》 * |
百度文库: "钢结构施工组织设计方案", 《百度文库》 * |
谭金华等主编: "《桥梁钢结构》", 28 February 2013, 武汉理工大学出版社 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109877540A (zh) * | 2019-03-15 | 2019-06-14 | 湖南林森建筑有限公司 | 一种高层钢结构工程的施工方法 |
CN110307957A (zh) * | 2019-07-02 | 2019-10-08 | 中国建筑第八工程局有限公司 | 一种风洞洞体高精度无棱镜放样工艺 |
CN110307957B (zh) * | 2019-07-02 | 2021-07-13 | 中国建筑第八工程局有限公司 | 一种风洞洞体高精度无棱镜放样工艺 |
CN110205947A (zh) * | 2019-07-06 | 2019-09-06 | 中铁二十五局集团第五工程有限公司 | 一种天桥钢箱梁施工方法 |
CN110369955A (zh) * | 2019-07-24 | 2019-10-25 | 重庆交通建设(集团)有限责任公司 | 钢结构箱梁优化制造工艺 |
CN112211103A (zh) * | 2020-10-10 | 2021-01-12 | 山西省工业设备安装集团有限公司 | 输煤栈桥钢桁架组合安装安全专项施工工艺 |
CN113500273A (zh) * | 2021-06-07 | 2021-10-15 | 中铁十八局集团隧道工程有限公司 | 一种钢箱梁施工焊接工艺 |
CN113634473A (zh) * | 2021-08-10 | 2021-11-12 | 山东望意阳海绵城市建设有限公司 | 一种钢结构桥面的施工工艺 |
CN115255823A (zh) * | 2022-07-27 | 2022-11-01 | 中铁二十五局集团第二工程有限公司 | 一种钢梁顶板单元制造工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108396653A (zh) | 一种钢结构桥梁施工方法 | |
CN103806660B (zh) | 劲性混凝土结构梁-柱节点施工方法 | |
CN103410322B (zh) | 大跨度平行桁架钢连廊施工方法 | |
CN101691787B (zh) | 中高层钢结构建筑逆向施工工艺 | |
CN106703416B (zh) | 狭小空间中钢结构屋架拔杆吊装方法 | |
CN104389268B (zh) | 一种带有定位结构的钢塔柱及其吊装施工方法 | |
CN101440667A (zh) | 大跨度单层雨棚网壳结构安装方法 | |
CN107100309A (zh) | 一种用于整体吊装大型多棱角悬挑桁架的施工方法 | |
CN105888069A (zh) | 大跨度张弦梁安装方法 | |
CN110303265B (zh) | 一种低温储罐内罐顶板施工工艺及低温储罐施工工艺 | |
CN102102444A (zh) | 大型铸钢构件的拼装、定位施工方法 | |
CN115162182B (zh) | 一种悬臂式钢箱梁高精度缆索吊装施工方法 | |
CN101936009A (zh) | 深水单壁钢吊箱围堰及其施工方法 | |
CN106567548B (zh) | 方形原煤斗分段安装工法 | |
CN110725324A (zh) | 一种剪力墙高肢导墙转换支撑结构及其施工方法 | |
CN105317052A (zh) | 一种塔吊基础螺栓固定方法 | |
CN103495793A (zh) | 改进的大吨位铸钢构件复杂节点吊装焊接施工方法 | |
CN107419907B (zh) | 一种炼钢塔楼钢结构平台的交错安装焊接方法 | |
Hayward et al. | Steel detailers' manual | |
CN109252526A (zh) | 基于预应力鱼腹梁支撑技术的装配式支护结构施工工艺 | |
CN204298736U (zh) | 一种带有定位结构的钢塔柱 | |
CN101492966B (zh) | 特大钢结构悬臂的施工方法 | |
CN108381128B (zh) | 一种吊点穿出工形耐候钢边主梁制作方法 | |
CN102554559A (zh) | 一种船闸球节点弧形三角闸门制作方法 | |
CN111335268A (zh) | 一种大坝深孔工作弧门支铰大梁底部钢衬模板及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180814 |
|
WD01 | Invention patent application deemed withdrawn after publication |