CN108388980A - A kind of project cost data management system - Google Patents

A kind of project cost data management system Download PDF

Info

Publication number
CN108388980A
CN108388980A CN201810120869.8A CN201810120869A CN108388980A CN 108388980 A CN108388980 A CN 108388980A CN 201810120869 A CN201810120869 A CN 201810120869A CN 108388980 A CN108388980 A CN 108388980A
Authority
CN
China
Prior art keywords
project
module
information
implementation
achievement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810120869.8A
Other languages
Chinese (zh)
Inventor
谭文华
郭诚茹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Qun Lun Project Management Co Ltd
Original Assignee
Shenzhen Qun Lun Project Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Qun Lun Project Management Co Ltd filed Critical Shenzhen Qun Lun Project Management Co Ltd
Priority to CN201810120869.8A priority Critical patent/CN108388980A/en
Publication of CN108388980A publication Critical patent/CN108388980A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses project cost data management systems, including:Project screening module, Project contract module, project Registration Module, project implementation module, project profiling module, project database, project process display module and the monthly audit achievement gathering module of project.Beneficial effects of the present invention:Pass through a series of flows such as project collection, contract management, project registration, the project implementation and Data storage, realize with no paper network office and rationally balanced task scheduling, relatively reasonable performance allocation result, specification flow, resource-sharing in realization company, inter-sectional collaboration efficiency is improved, human resources are saved.

Description

A kind of project cost data management system
Technical field
The present invention relates to Cost Management fields, in particular to a kind of project cost data management system.
Background technology
The working environment of Internet era has huge difference with traditional office environment, as long as there is Network Office System, only It wants that network can be accessed, so that it may which, to realize information sharing, still, for project cost management aspect, many enterprises still make It works by hand, operation flow and management process redundancy are complicated, not only time-consuming and laborious, but also Expenses Cost.
Invention content
The purpose of the present invention is to provide a kind of project cost data management systems, to solve existing progress work by hand Low, the of high cost problem of journey Project Cost way to manage efficiency.
To achieve the above object, the project cost data management system designed by the present invention includes:Project screening mould Block, Project contract module, project Registration Module, project implementation module, project profiling module, project database, project process are aobvious Show module and the monthly audit achievement gathering module of project;
The project screening module is used to receive all items information of the terminal input of project manager, from all items The project information is sent to the project Registration Module, to institute by the project information that the project of having been turned on is filtered out in mesh information It states the project of having been turned on to be worked out, obtains described having been turned on the establishment information of project and being sent to the Project contract module and institute State project implementation module;
The Project contract module is used to have been turned on the establishment information of project according to, and to establish registration of contracts information concurrent It send to the project implementation module, the registration of contracts information includes contract pay imformation and Office Of Contract Settlements information;
The project Registration Module receives times of the terminal input of the project manager for receiving the project information Business distribution information generates task distribution list according to the project information and the task allocation information and is sent to the project reality Apply module, single implementation personal information, auditor's information and the working hour information for including each task of task distribution;
The project implementation module is used to receive each cost for itself task of the terminal input of the implementation personnel The establishment information in stage has been turned on project to improve the establishment information for having been turned on project according to described in after improving Establishment information, the registration of contracts information and the single generation project Outcome Document of task distribution are simultaneously sent to the project filing Module;Each cost stage includes estimating stage, budgetary estimate stage, budget stage, base number of a tender stage and accounts settling phase;
The project profiling module receives the terminal input of the auditor for receiving the project achievement file The msu message for the project achievement file, judge whether the project achievement file closes according to the msu message Lattice in this way then file the project achievement file, and the project achievement file is otherwise retracted into the project implementation Module;
The project database is used to store the msu message that the project profiling module receives;
The project process display module is used to show that the project achievement file that the project profiling module judges to be No qualification;
The information that the monthly audit achievement gathering module of project is used to receive the project database generates monthly situation Summary sheet exports self-defined report, configuration management and improves Cost Index source.
Further, further include 3-D effect generation module, for receiving the monthly audit achievement gathering module of the project Monthly situation summary sheet, by high performance graphics cluster server after received monthly situation summary sheet is handled Cover various building models, and portray in detail towards six Channel Synchronous parallel image operations with six groups of 3D projecting apparatus.
Preferably, the monthly audit achievement gathering module of the project includes self-defined report output module, can be according to sieve The engineering key message of row allows user to need the information exported according to the self-defined selection of oneself demand, forms self-defined report, and Corresponding engineering can be exported according to screening conditions.
Beneficial effects of the present invention:Pass through project collection, contract management, project registration, the project implementation and Data storage Etc. a series of flows, with no paper network office and rationally balanced task scheduling are realized, relatively reasonable performance allocation result, Specification flow, resource-sharing in realization company, improves inter-sectional collaboration efficiency, saves human resources.
Description of the drawings
Fig. 1 is the structural schematic diagram of the project cost data management system of the present invention.
Specific implementation mode
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
Project cost data management system as shown in Figure 1 includes:Project screening module, Project contract module, item Mesh Registration Module, project implementation module, project profiling module, project database, project process display module and project are monthly careful Core achievement gathering module;
Project screening module is used to receive all items information of the terminal input of project manager, from all items information Project information is sent to project Registration Module, worked out having been turned on project by the project information for filtering out the project of having been turned on, It obtains having been turned on the establishment information of project and is sent to Project contract module and project implementation module;
Project contract module is used to establish registration of contracts information according to the establishment information for the project that has been turned on and be sent to project Implement module, registration of contracts information includes contract pay imformation and Office Of Contract Settlements information;
Project Registration Module receives the task allocation information of the terminal input of project manager for receiving project information, Task distribution list is generated according to project information and task allocation information and is sent to project implementation module, and single task distribution includes each Implementation personal information, auditor's information and the working hour information of task;
Project implementation module is used to receive the volume in each cost stage for itself task of the terminal input of implementation personnel Information processed, to improve the establishment information for the project that has been turned on, according to the establishment information for having been turned on project after improving, registration of contracts Information and the single generation project Outcome Document of task distribution are simultaneously sent to project profiling module;Each cost stage include estimating stage, Budgetary estimate stage, budget stage, base number of a tender stage and accounts settling phase;
Project profiling module for receiving project Outcome Document, and receive auditor terminal input for project at The msu message of fruit file judges whether project achievement file qualified according to msu message, in this way then to project achievement file into Row filing, is otherwise retracted into project implementation module by project achievement file;
Project database is used for the msu message that stored items profiling module receives;
Project process display module is used to show whether the project achievement file that project profiling module judges to be qualified;
The information that the monthly audit achievement gathering module of project is used to receive project database generates monthly situation summary sheet, defeated Go out self-defined report, configuration management and improves Cost Index source.
Further include 3-D effect generation module, the monthly situation for receiving the monthly audit achievement gathering module of project summarizes Table passes through high performance graphics cluster server and six groups of 3D projections after being handled received monthly situation summary sheet Instrument covers various building models, and portray in detail towards six Channel Synchronous parallel image operations.
The monthly audit achievement gathering module of project includes self-defined report output module, can be crucial according to the engineering enumerated Information allows user to need the information exported according to the self-defined selection of oneself demand, forms self-defined report, and can be according to screening item Part exports corresponding engineering.
System is the Services Oriented Achitecture based on Java EE platforms;Interface specification is Web Service interfaces rule Model.
It is preferential using being developed based on J2EE frameworks when selecting technologies in order to meet application requirement, at the same require be System is also developed using the Java technology of identical SDK versions, ensures the consistency of application program and better compatibility.Simultaneously High-performance Web website is set up, efficiency of research and development is improved, ensures software quality, it is flat through appraisal of helping after investment projects of capital assets Platform is quasi- to be researched and developed using Java EE platforms, and is introduced Tomcat servers and disposed.Simultaneously Java EE platforms and Tomcat servers can easily be switched under Linux, Unix system and run, and be well suited for the realization of SOA framework and various SOA The erection of infrastructure service.
Services Oriented Achitecture (service-orientedarchitecture, SOA) is a component model, it The different function of application program is divided into service, good interface is defined between being serviced by these and contract connects. Interface is defined by the way of neutral, and this feature that there is neutral interface to define is known as the loose coupling between servicing It closes, independently of hardware platform, operating system and the programming language for realizing service, this to build various services in systems for it Can by a kind of unification and it is general in a manner of interact.
The SOA design philosophys of system application are mainly reflected in service-oriented Service Component design process.System uses Web Service interface specification can directly be transmitted by interface and exchange data or carry out data exchange using XML.On the one hand can disappear Except coupled relation complicated between each operation system, on the other hand can ensure that opposite independence between other operation systems, Integrality and safety are the data exchange modes used between new application system.For intensive using the finance of component model Change service application technical system, all service applications for externally providing interface access can be sealed in the way of service Dress, while in order to ensure that various business services object can flexibly be called by other service objects, the service publication of component should adopt With the similar deployment calculated and the bus mode of hardware systems is serviced.
This system is a complicated enterprise-level application, has very high want to the reliability, availability, performance of system It asks.Distributed and multi tier architecture has better upgradability and flexibility than traditional client/server configuration.Client End uses Web modes, the function of system is accessed by browser, client zero installation, is convenient for easy to use, beautiful interface System upgrade is safeguarded.And ensures the consistency of platform and agreement, and use B/S frameworks, can more facilitate the group of realization system Partization designs.
System operation establishes project information, registry by project manager (responsible person) or authorized person, with contract information To originate, associated client contract information, selection Category of consulting (establishment, audit, management), selects in consulting entry item information Hold (Category of consulting is establishment, and reference content is investment estimate establishment, estimation per design establishment, Engineering Settlement establishment etc.), fill in and appoint It is engaged in distributing list (specified authorized personnel, it is possible to specify to oneself, one or more implementation people can be assigned to), the step for selecting school to examine Personnel's (level-one audit, two level audit, three-level audit) that are rapid and specifying each step audit, progress the pre- of working hour are appraised and decided and pre-allocate (being associated in the working hour performance of database module).Project registration is completed to be committed in next step.
Authorized personnel distributes content according to job order and starts authorized strength work.Mainly by estimation, budgetary estimate, budget, the base number of a tender, clearing Stage is managed.In each cost stage, authorized personnel establishes project file by way of creating or importing and carries out work The establishment of journey cost uploads to higher level's audit after working out.
First trial and review are carried out to Outcome Document.First trial:First trial personnel carry out first trial to Outcome Document, mainly to each The form problem of file is audited.Review:Technology confirmation is carried out to Outcome Document, index, material price etc., mainly to each The technological rationality of a file content is audited;Working hour is appraised and decided and is distributed;Filing is submitted if there is no problem.Here appraise and decide Working hour auto-associating be saved in the working hour performance in database module, index and material price are then automatically saved to data In index storehouse and price library in library module, facilitate inquiry.

Claims (3)

1. a kind of project cost data management system, which is characterized in that
Including:Project screening module, Project contract module, project Registration Module, project implementation module, project profiling module, item Mesh database, project process display module and the monthly audit achievement gathering module of project;
The project screening module is used to receive all items information of the terminal input of project manager, believes from all items The project information is sent to the project Registration Module by the project information that the project of having been turned on is filtered out in breath, to it is described Startup project is worked out, and obtains described having been turned on the establishment information of project and being sent to the Project contract module and the item Mesh implements module;
The establishment information that the Project contract module is used to have been turned on project according to is established registration of contracts information and is sent to The project implementation module, the registration of contracts information include contract pay imformation and Office Of Contract Settlements information;
The project Registration Module receives the task point of the terminal input of the project manager for receiving the project information With information, task distribution list is generated according to the project information and the task allocation information and is sent to the project implementation mould Block, single implementation personal information, auditor's information and the working hour information for including each task of task distribution;
The project implementation module is used to receive each cost stage for itself task of the terminal input of the implementation personnel Establishment information, to improve the establishment information for having been turned on project, according to the establishment for having been turned on project described in after improving Information, the registration of contracts information and the single generation project Outcome Document of task distribution are simultaneously sent to the project filing mould Block;Each cost stage includes estimating stage, budgetary estimate stage, budget stage, base number of a tender stage and accounts settling phase;
The project profiling module receives the needle of the terminal input of the auditor for receiving the project achievement file To the msu message of the project achievement file, judge whether the project achievement file is qualified according to the msu message, such as It is to file to the project achievement file, the project achievement file is otherwise retracted into the project implementation module;
The project database is used to store the msu message that the project profiling module receives;
The project process display module is used to show whether the project achievement file that the project profiling module judges closes Lattice;
The information that the monthly audit achievement gathering module of project is used to receive the project database generates monthly situation and summarizes Table exports self-defined report, configuration management and improves Cost Index source.
2. project cost data management system according to claim 1, which is characterized in that further include 3-D effect life At module, the monthly situation summary sheet for receiving the monthly audit achievement gathering module of the project will be received monthly Situation summary sheet handled after by high performance graphics cluster server and six groups of 3D projecting apparatus, it is parallel towards six Channel Synchronous Image operation is covered various building models, and is portrayed in detail.
3. project cost data management system according to claim 1, which is characterized in that the monthly audit of project Achievement gathering module includes self-defined report output module, user can be allowed according to oneself according to the engineering key message enumerated The self-defined selection of demand needs the information exported, forms self-defined report, and can export corresponding engineering according to screening conditions.
CN201810120869.8A 2018-02-07 2018-02-07 A kind of project cost data management system Pending CN108388980A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810120869.8A CN108388980A (en) 2018-02-07 2018-02-07 A kind of project cost data management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810120869.8A CN108388980A (en) 2018-02-07 2018-02-07 A kind of project cost data management system

Publications (1)

Publication Number Publication Date
CN108388980A true CN108388980A (en) 2018-08-10

Family

ID=63075394

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810120869.8A Pending CN108388980A (en) 2018-02-07 2018-02-07 A kind of project cost data management system

Country Status (1)

Country Link
CN (1) CN108388980A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109284919A (en) * 2018-09-13 2019-01-29 深圳市栋森工程项目管理有限公司 A kind of project cost project management system
CN109377156A (en) * 2018-09-13 2019-02-22 深圳市栋森工程项目管理有限公司 A kind of project cost project checking method
CN109711692A (en) * 2018-12-17 2019-05-03 深圳壹账通智能科技有限公司 KPI INDEX MANAGEMENT method, apparatus, computer equipment and storage medium
CN109993323A (en) * 2019-03-21 2019-07-09 广州翔实工程咨询有限公司 A kind of maintenance engineering automatic settlement method, system and storage medium
CN110610305A (en) * 2019-08-29 2019-12-24 广州华源创兴计算机服务有限公司 Data center full life cycle integrated service dispatching master control system
CN111429100A (en) * 2020-03-25 2020-07-17 陕西合友网络科技有限公司 Construction project cost system and cost method
CN111950986A (en) * 2020-08-18 2020-11-17 山东泰和建设管理有限公司 Cost consultation business process management method and system
CN113743893A (en) * 2021-08-27 2021-12-03 国核电力规划设计研究院有限公司 Intelligent cooperative processing system and method for engineering project life cycle

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243485A (en) * 2015-09-23 2016-01-13 河北科技师范学院 BIM network technology based architecture engineering management system platform
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN106447197A (en) * 2016-09-28 2017-02-22 国网山东省电力公司经济技术研究院 Construction cost data management system
CN107392568A (en) * 2017-07-04 2017-11-24 成都正信石油天然气工程造价咨询有限公司 A kind of project cost management system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243485A (en) * 2015-09-23 2016-01-13 河北科技师范学院 BIM network technology based architecture engineering management system platform
CN105373885A (en) * 2015-11-10 2016-03-02 国网福建省电力有限公司 Electric power engineering design review and technical economic evaluation information system
CN106447197A (en) * 2016-09-28 2017-02-22 国网山东省电力公司经济技术研究院 Construction cost data management system
CN107392568A (en) * 2017-07-04 2017-11-24 成都正信石油天然气工程造价咨询有限公司 A kind of project cost management system

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109284919A (en) * 2018-09-13 2019-01-29 深圳市栋森工程项目管理有限公司 A kind of project cost project management system
CN109377156A (en) * 2018-09-13 2019-02-22 深圳市栋森工程项目管理有限公司 A kind of project cost project checking method
CN109711692A (en) * 2018-12-17 2019-05-03 深圳壹账通智能科技有限公司 KPI INDEX MANAGEMENT method, apparatus, computer equipment and storage medium
CN109993323A (en) * 2019-03-21 2019-07-09 广州翔实工程咨询有限公司 A kind of maintenance engineering automatic settlement method, system and storage medium
CN110610305A (en) * 2019-08-29 2019-12-24 广州华源创兴计算机服务有限公司 Data center full life cycle integrated service dispatching master control system
CN111429100A (en) * 2020-03-25 2020-07-17 陕西合友网络科技有限公司 Construction project cost system and cost method
CN111950986A (en) * 2020-08-18 2020-11-17 山东泰和建设管理有限公司 Cost consultation business process management method and system
CN113743893A (en) * 2021-08-27 2021-12-03 国核电力规划设计研究院有限公司 Intelligent cooperative processing system and method for engineering project life cycle
CN113743893B (en) * 2021-08-27 2023-11-17 国核电力规划设计研究院有限公司 Intelligent cooperative processing system and method for whole life cycle of engineering project

Similar Documents

Publication Publication Date Title
CN108388980A (en) A kind of project cost data management system
US11489926B2 (en) Automated platform provisioning system
CN101388904B (en) GIS service aggregating method, device and system
US8965801B2 (en) Provision of support services as a service
CN111552471A (en) Task arrangement method and system under hybrid cloud environment
CN102542367B (en) Cloud computing network workflow processing method, device and system based on domain model
US20110153684A1 (en) Systems and methods for automatic provisioning of a user designed virtual private data center in a multi-tenant system
US20120110566A1 (en) Apparatus and method for setting up multi-tenant saas applications
CN107836007A (en) It was found that and issue API information
Froehlich et al. Application framework issues when evolving business applications for electronic commerce
US20210103862A1 (en) Methods and apparatus for exposing workflow process definitions as business objects
CN107392568A (en) A kind of project cost management system
CN109462508A (en) Node deployment method, device and storage medium
Shan et al. Solution architecture for n-tier applications
CN101751255B (en) Method and device for realizing service organization by workflow middleware conforming to XPDL specification
US8875137B2 (en) Configurable mass data portioning for parallel processing
MX2013005359A (en) System and method for consolidating account data.
Dimitrakos Common capabilities for service oriented infrastructures and platforms: An overview
CN110490554A (en) Workflow management method, device, computer equipment and storage medium
CN115600969A (en) Service processing method and device, electronic equipment and computer readable medium
CN107944743A (en) The operation and maintenance method, apparatus and system of a kind of large computer system
Unnamalai et al. Service-oriented architecture for cloud computing
CN107505852A (en) A kind of cloud manufacturing service comprising artificial intelligence describes the construction method of file
Matejaš et al. Building a BPM application in an SOA-based legacy environment
JP2021125264A (en) Information processing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180810