CN108374526A - 大跨度屋面板的预制与吊装方法 - Google Patents
大跨度屋面板的预制与吊装方法 Download PDFInfo
- Publication number
- CN108374526A CN108374526A CN201810157744.2A CN201810157744A CN108374526A CN 108374526 A CN108374526 A CN 108374526A CN 201810157744 A CN201810157744 A CN 201810157744A CN 108374526 A CN108374526 A CN 108374526A
- Authority
- CN
- China
- Prior art keywords
- building
- roof boarding
- crane
- prefabricated
- long
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04D—ROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
- E04D15/00—Apparatus or tools for roof working
- E04D15/02—Apparatus or tools for roof working for roof coverings comprising tiles, shingles, or like roofing elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
大跨度屋面板的预制与吊装方法,在围护结构已经施工完成的建筑物中进行屋面板的浇筑,所述建筑物为长度大于宽度两倍以上的建筑物,所述建筑物的宽度为屋面板的跨度;屋面板在浇筑过程中沿着所述建筑物的长度方向伸展,并在宽度方向相互接近;吊装屋面板的吊车位于所述建筑物的外部,绕着所述建筑物逐个屋面板进行吊装;吊起顺序为先将靠近围护结构的屋面板吊起,并优先安装在外侧的围护结构上。本发明在已经完成围护结构的建筑内进行屋面板的预制,能够减少外部环境对屋面板制造质量的影响,而且在吊装过程中吊车在外而屋面板在建筑物的屋内,能够容易形成直接的视觉效果进行对齐,从而吊装精度和稳定性都大大提高。
Description
技术领域
本发明涉及建筑施工技术领域,尤其涉及大跨度屋面板的预制与吊装方法。
背景技术
大跨度的建筑在安装屋顶的时候,由于屋顶很重需要吊车安装,但吊装如此巨大和沉重的混凝土构件,不容易对准位置。而且,浇筑形成的屋面板也需要更高的质量,在工厂预制虽然条件好但运输要求较高,在现场预制则较难具有良好的预置条件。
发明内容
本发明的目的在于提出一种大跨度屋面板的预制与吊装方法,其能够最大程度上浇筑形成质量较好的屋面板,而且吊装过程更为准确可靠。
为达此目的,本发明采用以下技术方案:
大跨度屋面板的预制与吊装方法,步骤包括:
步骤一:
在围护结构已经施工完成的建筑物中进行屋面板的浇筑,所述建筑物为长度大于宽度两倍以上的建筑物,所述建筑物的宽度为屋面板的跨度;
屋面板在浇筑过程中沿着所述建筑物的长度方向伸展,并在宽度方向相互接近;
步骤二:
吊装屋面板的吊车位于所述建筑物的外部,绕着所述建筑物逐个屋面板进行吊装;吊起顺序为先将靠近围护结构的屋面板吊起,并优先安装在外侧的围护结构上。
所述屋面板在所述建筑物中按照两排的排列进行浇筑。
所述吊车沿着所述建筑物的外围以逆时针方向走动四个站位点,该四个站位点分别在所述建筑物的长边墙内各占两个。
所述吊车在吊车第一次站位点吊装起第一排的屋面板的一半,所述吊车在吊车第二次站位点吊装起第二排的屋面板的一半,所述吊车在第三次站位点吊装起第二排的屋面板的另一半,所述吊车在第四次站位点吊装起第一排的屋面板的另一半。
吊装完毕一批屋面板之后再进行下一批屋面板的预制和吊装,以此分批预制和吊装直至完成。
本发明在已经完成围护结构的建筑内进行屋面板的预制,能够减少外部环境对屋面板制造质量的影响,而且在吊装过程中吊车在外而屋面板在建筑物的屋内,能够容易形成直接的视觉效果进行对齐,从而吊装精度和稳定性都大大提高。
附图说明
图1是本发明的一个实施例的屋面板预制时的布置示意图。
图2是本发明的一个实施例的屋面板吊装时的布置示意图。
其中:
吊车第一次站位点A、吊车第二次站位点B、吊车第三次站位点C、吊车第四次站位点D、屋面板1、2、3、4、5、6、7、8、9、10、11、12、13、14、15、16。
具体实施方式
下面结合附图并通过具体实施方式来进一步说明本发明的技术方案。
大跨度屋面板的预制与吊装方法,步骤包括:
步骤一:
在围护结构已经施工完成的建筑物中进行屋面板的浇筑,所述建筑物为长度大于宽度两倍以上的建筑物,所述建筑物的宽度为屋面板的跨度;
屋面板在浇筑过程中沿着所述建筑物的长度方向伸展,并在宽度方向相互接近;
步骤二:
吊装屋面板的吊车位于所述建筑物的外部,绕着所述建筑物逐个屋面板进行吊装;吊起顺序为先将靠近围护结构的屋面板吊起,并优先安装在外侧的围护结构上。
本发明在已经完成围护结构的建筑内进行屋面板的预制,能够减少外部环境对屋面板制造质量的影响,而且在吊装过程中吊车在外而屋面板在建筑物的屋内,能够容易形成直接的视觉效果进行对齐,从而吊装精度和稳定性都大大提高。
所述屋面板在所述建筑物中按照两排的排列进行浇筑。
所述吊车沿着所述建筑物的外围以逆时针方向走动四个站位点,该四个站位点分别在所述建筑物的长边墙内各占两个。
所述吊车在吊车第一次站位点吊装起第一排的屋面板的一半,所述吊车在吊车第二次站位点吊装起第二排的屋面板的一半,所述吊车在第三次站位点吊装起第二排的屋面板的另一半,所述吊车在第四次站位点吊装起第一排的屋面板的另一半。
吊装完毕一批屋面板之后再进行下一批屋面板的预制和吊装,以此分批预制和吊装直至完成。
以上结合具体实施例描述了本发明的技术原理。这些描述只是为了解释本发明的原理,而不能以任何方式解释为对本发明保护范围的限制。基于此处的解释,本领域的技术人员不需要付出创造性的劳动即可联想到本发明的其它具体实施方式,这些方式都将落入本发明的保护范围之内。
Claims (5)
1.大跨度屋面板的预制与吊装方法,其特征在于:步骤包括:
步骤一:
在围护结构已经施工完成的建筑物中进行屋面板的浇筑,所述建筑物为长度大于宽度两倍以上的建筑物,所述建筑物的宽度为屋面板的跨度;
屋面板在浇筑过程中沿着所述建筑物的长度方向伸展,并在宽度方向相互接近;
步骤二:
吊装屋面板的吊车位于所述建筑物的外部,绕着所述建筑物逐个屋面板进行吊装;吊起顺序为先将靠近围护结构的屋面板吊起,并优先安装在外侧的围护结构上。
2.如权利要求1所述的大跨度屋面板的预制与吊装方法,其特征在于:所述屋面板在所述建筑物中按照两排的排列进行浇筑。
3.如权利要求2所述的大跨度屋面板的预制与吊装方法,其特征在于:所述吊车沿着所述建筑物的外围以逆时针方向走动四个站位点,该四个站位点分别在所述建筑物的长边墙内各占两个。
4.如权利要求3所述的大跨度屋面板的预制与吊装方法,其特征在于:
所述吊车在吊车第一次站位点吊装起第一排的屋面板的一半,所述吊车在吊车第二次站位点吊装起第二排的屋面板的一半,所述吊车在第三次站位点吊装起第二排的屋面板的另一半,所述吊车在第四次站位点吊装起第一排的屋面板的另一半。
5.如权利要求4所述的大跨度屋面板的预制与吊装方法,其特征在于:吊装完毕一批屋面板之后再进行下一批屋面板的预制和吊装,以此分批预制和吊装直至完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810157744.2A CN108374526A (zh) | 2018-02-24 | 2018-02-24 | 大跨度屋面板的预制与吊装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810157744.2A CN108374526A (zh) | 2018-02-24 | 2018-02-24 | 大跨度屋面板的预制与吊装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108374526A true CN108374526A (zh) | 2018-08-07 |
Family
ID=63017999
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810157744.2A Pending CN108374526A (zh) | 2018-02-24 | 2018-02-24 | 大跨度屋面板的预制与吊装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108374526A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101324146A (zh) * | 2008-08-11 | 2008-12-17 | 河北建工集团有限责任公司 | 大跨度弧形空腹梁吊装施工方法 |
CN101338603A (zh) * | 2008-08-08 | 2009-01-07 | 广州市建筑机械施工有限公司 | 拱形屋面板仓内预制施工工法 |
EP2610411A2 (en) * | 2010-08-25 | 2013-07-03 | Domingo Bengoa Saez De Cortazar | Semi-prefabricated building and associated construction method |
CN103395120A (zh) * | 2013-08-02 | 2013-11-20 | 叶长青 | 大跨度预制屋面板制作方法 |
-
2018
- 2018-02-24 CN CN201810157744.2A patent/CN108374526A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101338603A (zh) * | 2008-08-08 | 2009-01-07 | 广州市建筑机械施工有限公司 | 拱形屋面板仓内预制施工工法 |
CN101324146A (zh) * | 2008-08-11 | 2008-12-17 | 河北建工集团有限责任公司 | 大跨度弧形空腹梁吊装施工方法 |
EP2610411A2 (en) * | 2010-08-25 | 2013-07-03 | Domingo Bengoa Saez De Cortazar | Semi-prefabricated building and associated construction method |
CN103395120A (zh) * | 2013-08-02 | 2013-11-20 | 叶长青 | 大跨度预制屋面板制作方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103043526B (zh) | 地下连续墙超长钢筋笼整体吊装装置和方法 | |
CN205045698U (zh) | 一种钢筋笼吊装器具 | |
CN104032967B (zh) | 预制装配式框架结构构件吊装施工方法 | |
CN103711323A (zh) | 利用移动式管桁架平台安装屋面反吊顶板施工方法 | |
CN107190964A (zh) | 一种预制式电梯井操作平台的施工方法 | |
CN109095343A (zh) | 装配式吊架 | |
CN203173684U (zh) | 一种吊装钢筋笼的构件 | |
CN205637622U (zh) | 垂直单元式玻璃幕墙吊装系统 | |
CN207700708U (zh) | 一种单元式玻璃幕墙的三层环形吊装轨道 | |
CN204626998U (zh) | 一种附着升降脚手架用卸料台 | |
CN204057659U (zh) | 超大预制叠合面板起吊装置 | |
CN211470599U (zh) | 一种吊装辅助扁担梁 | |
CN108374526A (zh) | 大跨度屋面板的预制与吊装方法 | |
CN209353734U (zh) | 用于安装幕墙的双轨道装置 | |
CN207030735U (zh) | 预制阳台吊装辅助装置 | |
CN205170161U (zh) | 一种预制梁板钢筋骨架吊具 | |
CN205367457U (zh) | 一种预制混凝土构件安装特殊吊具 | |
CN108979152A (zh) | 用于大跨度钢桁架高空分段拼装的胎膜及其施工方法 | |
CN104355238A (zh) | 一种带有臂架结构的门式起重机 | |
CN205653104U (zh) | 一种单元板幕墙安装的活动吊车 | |
CN108529404A (zh) | 一种建筑使用升降机 | |
CN208948679U (zh) | 装配式吊架 | |
CN207792466U (zh) | 一种工具式吊笼 | |
CN107700854B (zh) | 一种超高层核心筒的钢板墙滑移安装装置和安装方法 | |
CN207001999U (zh) | 大型罐形设备吊装扁担梁 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180807 |
|
WD01 | Invention patent application deemed withdrawn after publication |