CN108364112A - Task-decomposing system and computer readable storage medium - Google Patents

Task-decomposing system and computer readable storage medium Download PDF

Info

Publication number
CN108364112A
CN108364112A CN201711431195.5A CN201711431195A CN108364112A CN 108364112 A CN108364112 A CN 108364112A CN 201711431195 A CN201711431195 A CN 201711431195A CN 108364112 A CN108364112 A CN 108364112A
Authority
CN
China
Prior art keywords
task
construction
work order
subtask
construction personnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711431195.5A
Other languages
Chinese (zh)
Inventor
张斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mobile Group Guangdong Co Ltd
Original Assignee
China Mobile Group Guangdong Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mobile Group Guangdong Co Ltd filed Critical China Mobile Group Guangdong Co Ltd
Priority to CN201711431195.5A priority Critical patent/CN108364112A/en
Publication of CN108364112A publication Critical patent/CN108364112A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to computer application fields, more particularly to a kind of Task-decomposing system, there is computer readable storage medium in the system, computer program is stored in the medium, the program can be executed by processor, the present invention passes through Task-decomposing using Software for Design after acquisition task at Project Manager, multiple subtasks that task is split out, it recycles the mode distributed on line that subtask is directly assigned to construction personnel, ensures that task is assigned with being in time, task assignment situation, which can be recalled, traces;Work order is pushed by software, work order lists action, to guide and construction personnel is reminded to make according to either simplex, prevents the phenomenon that task is omitted, construction personnel does over again in vain and inefficiency.

Description

Task-decomposing system and computer readable storage medium
Technical field
The present invention relates to computer application field more particularly to a kind of Task-decomposing system, there is computer can in the system Storage medium is read, is stored with computer program in the medium, which can be executed by processor.
Background technology
In the project of communication engineering, since there are quantities huge, complex procedures, each profession (including wireless, transmission, Core, data etc.) factors such as interdepend, it is very big to build difficulty, it is necessary to dependent on accurately design scheme, design drawing And fine construction plan ensures engineering construction.However due in work progress destabilizing factor it is more, design scheme, design Drawing may change, and construction plan also can make tune according to actual conditions (such as atrocious weather, owner's fitness is low) It is whole.
But current unit in charge of construction is in finished item construction task, is decomposited and respectively applies according to the plan of administrator's discharge Crew and its subordinate construction personnel need completing for task daily, and strict implement task is realized.Wherein spread superintendent and Construction personnel is recorded by paper records, mobile phone or by approach such as memory, experiences, completes the work on the same day item by item.But it is this There are many problems, such as notice of task largely to rely on manually for mode, it is difficult to the assignment case of logger task;For another example construct The approach that team leader and construction personnel receive task more disperses, and easy tos produce the risk of omission task.
Invention content
The purpose of the present invention is in project construction, making the appointment of task be in time, the clear action of construction personnel.
For this purpose, providing a kind of computer readable storage medium, it is stored with computer program, which is used for unit in charge of construction The communication equipment of administrator, the program realize following steps when being executed by processor:
Task acquisition module:The acquisition task from Project Manager;
Task assignment step:The multiple subtasks split out by the task are obtained, constructor is assigned for each subtask Member;
Work order pushes step:To each subtask, the work order corresponding to the subtask is pushed to corresponding construction personnel Communication equipment on.
Further, in task assigning step, each subtask belonged in a construction area is assigned to jointly The same construction team ensures that a construction area matches the principle of a construction team, construction team is made efficiently and easily to construct, reduces The communication cost that different construction team's cooperations generate.
Further, in task assigning step, the excellent basic subtask for assigning foundation construction structure, rear assign needs to rely on The basis subtask is come the attached subtask implemented.
Further, in task assigning step, the window selected for unit in charge of construction administrator is provided, for unit in charge of construction Administrator implements the fractionation.
Further, in work order pushes step, the work order is all pushed daily, all construction personnel is guided daily And remind, make its clear daily task of construction personnel, task is avoided to omit phenomenon, the operation of significant increase site operation personnel Accuracy and order.
Further, further include scheduling steps:If receiving the work order that construction personnel retracts, which is pushed temporarily Onto the communication equipment of other construction personnel.When receiving the work order that construction personnel retracts, unit in charge of construction administrator assigns temporarily, real Existing flexible dispatching, ensures project operation.
Task-decomposing system is also provided, the communication equipment of the communication equipment of unit in charge of construction administrator and construction personnel is included,
The communication equipment of unit in charge of construction administrator includes first processor and above-mentioned computer readable storage medium, the meter Computer program on calculation machine readable storage medium storing program for executing can be executed by first processor;
The communication equipment of construction personnel includes second processor and another computer readable storage medium, the media storage There is computer program, it is characterised in that work order obtaining step is realized when the program is executed by second processor:If if according to construction The input of personnel receives the subtask of unit in charge of construction administrator appointment, then obtains the work order corresponding to the subtask, will be in work order Action be shown to construction personnel, to guide construction personnel to work according to work order.
Further, when the computer program in the communication equipment of construction personnel is executed by second processor, note is also realized Record step:It records a video to the workload task amount completed, the image recorded is documented in work order corresponding position, and by work order It is back at unit in charge of construction administrator and/or Project Manager, so can intuitively feed back the live performance of construction personnel, Practical foundation is provided for remote scheduling decision, construction site is closely continuously got up with remote scheduling decision, forms mutually branch The relationship of support.
Further, the image to record adds watermark information automatically, to enable a person to differentiate the true and false of video recording, avoids making Disadvantage behavior generates, and Data Preparation is carried out for following project auditing.
Further, which includes video time, to avoid examination phenomenon is delayed, ensures the duration on time according to plan It completes, watermark information further includes video recording place, is carried out an acceptance inspection using other construction grounds to avoid construction team, prevents to practise fraud.
Further, in work order retracts step, it also will pulled back from reason and be sent to unit in charge of construction administrator, be unit in charge of construction The choice of administrator provides basis for estimation.
Further, when the computer program in the communication equipment of construction personnel is executed by second processor, work is also realized Singly retract step:If if according to the input of construction personnel, the subtask of unit in charge of construction administrator appointment is not received, by the work order It returns on the communication equipment of unit in charge of construction administrator.In the case where construction personnel is difficult to construct, construction personnel can be by soft The work order that part is retracted, to notify unit in charge of construction that administrator is scheduled, advice method is flexibly and fast.
Similarly, in work order obtaining step, the work order is all obtained daily.
Advantageous effect:
The present invention, by Task-decomposing, task is split out using Software for Design after acquisition task at Project Manager Multiple subtasks recycle the mode distributed on line that subtask is directly assigned to construction personnel, ensure that task is in time ground It assigns, task assignment situation, which can be recalled, traces;Work order is pushed by software, work order lists action, to guide and remind Construction personnel makees according to either simplex, prevents the phenomenon that task is omitted, construction personnel does over again in vain and inefficiency.
Specific implementation mode
The invention is further described with the following Examples.
Task-decomposing software is installed in respectively on the mobile phone of Project Manager, unit in charge of construction administrator and construction personnel, and three The permission of person is had nothing in common with each other.
Total manager of the Project Manager as project, task is published to by project construction task or urgent temporary duty It decomposes on software.After unit in charge of construction administrator knows the task that total manager is sent out by the Task-decomposing software on its mobile phone, Task is split into multiple subtasks on the Task-decomposing software, and is configured for each subtask by the case where according to construction team Process and construction area.After the completion of configuration, the Task-decomposing software on unit in charge of construction's pipeline person's mobile phone is according to each subtask institute Each subtask is automatically classified in the region of construction;Further according to the dependence between each subtask, automatically to each Subtask in class is ranked up, and wherein before the subtask row of foundation construction structure, the son that need to rely on other processes to implement is appointed After business is arranged successively by degree of dependence.Then, Task-decomposing software refers to each subtask belonged in a construction area jointly The same construction team is tasked, and each subtask that the construction team is responsible for is individually assigned to each construction in the construction team Personnel preferentially assign forward subtask of sorting when appointment.
Construction personnel determines and receives the subtask being assigned by the Task-decomposing software on its mobile phone.If constructor Member receives to assign subtask, then the attaching relation of the subtask determines at once, and hereafter unit in charge of construction administrator utilizes its mobile phone, Preset task pushes the time in Task-decomposing software, should implement on the day of so that Task-decomposing software is pushed it daily for construction personnel Work order.Wherein, the change conditions for the subtask that the content of work order is assigned according to the construction personnel and change.
If construction personnel's same day can be connect with normal construction, construction personnel by the Task-decomposing software on mobile phone Single, the action in work order is shown to construction personnel by Task-decomposing software at this time, to guide its work.After work, Construction personnel is recorded a video by the action that Task-decomposing software completes this day, and is said to not completing task amount Bright registration.Video recording and situation explanation are uploaded to unit in charge of construction administrator by Task-decomposing software automatically after the completion of registration, make construction Unit management person can clear accurately control project process.During video recording, Task-decomposing software is by accessing mobile phone In clock know the time occurred of recording a video, obtain position occurred of recording a video by accessing in mobile phone GPS functions, so Afterwards automatically in video recording time occurred, position and inner label watermark to the image recorded.
If construction personnel's same day fortuitous event can not occur after normal construction or order, construction personnel opens on mobile phone Task-decomposing software carries out corresponding subtask to turn single and illustration, and Task-decomposing software is automatically by the construction personnel at this time The same day work order and the reason being responsible for are returned to unit in charge of construction administrator, are assigned temporarily by unit in charge of construction administrator.
In entire project construction process, Task-decomposing software monitor in real time each construction team task performance and scene it is different Reason condition, and situation is shown to unit in charge of construction administrator, to facilitate unit in charge of construction administrator to check scheduling, ensure project fortune Row.When Project Manager issues urgent temporary duty, Task-decomposing software plays frame with logical on the mobile phone of unit in charge of construction administrator Know that unit in charge of construction administrator, unit in charge of construction administrator assign urgent temporary duty by Task-decomposing software, coordinates The operation of each construction team.During project construction, Task-decomposing software also records each construction team in real time and construction personnel completes The timeliness and quantity of task, for statistical analysis according to this and follow-up examination.
It should be noted that Task-decomposing software is not necessarily mounted on mobile phone, tablet, self-made Instrument etc. can also be mounted in On other hand-held terminal devices with the same function, it can also be installed on computer.The mode taken pictures may be used instead of upper The video recording mode stated.
Finally it should be noted that above example is only to illustrate the technical solution of the invention, rather than to this hair It is bright create protection domain limitation, although being explained in detail to the invention with reference to preferred embodiment, this field it is general Lead to it will be appreciated by the skilled person that can be modified or replaced equivalently to the technical solution of the invention, without departing from this The spirit and scope of innovation and creation technical solution.

Claims (10)

1. a kind of computer readable storage medium, is stored with computer program, the program is for the logical of unit in charge of construction administrator Believe equipment, it is characterised in that the program realizes following steps when being executed by processor:
Task acquisition module:The acquisition task from Project Manager;
Task assignment step:The task is split into multiple subtasks, construction personnel is assigned for each subtask;
Work order pushes step:To each subtask, the work order corresponding to the subtask is pushed to the logical of corresponding construction personnel Believe in equipment.
2. a kind of computer readable storage medium according to claim 1, it is characterised in that:In task assigning step, Each subtask in a construction area will be belonged to, is individually assigned to belong to each construction personnel of a construction team.
3. a kind of computer readable storage medium according to claim 1 or 2, it is characterised in that:In task assigning step In, the excellent basic subtask for assigning foundation construction structure is rear that the attached son that need to rely on the basic subtask to implement is assigned to appoint Business.
4. a kind of computer readable storage medium according to claim 1, it is characterised in that:In task assigning step, It is split with specific reference to the input of unit in charge of construction administrator.
5. a kind of computer readable storage medium according to claim 1,2 or 4, it is characterised in that further include scheduling step Suddenly:If receiving the work order that construction personnel retracts, which is pushed on the communication equipment of other construction personnel temporarily.
6. Task-decomposing system includes the communication equipment of the communication equipment of unit in charge of construction administrator and construction personnel,
The communication equipment of unit in charge of construction administrator includes first processor and such as power computer-readable storage of 1-5 any one of them Medium, the computer program on the computer readable storage medium can be executed by first processor;
The communication equipment of construction personnel includes second processor and another computer readable storage medium, which has meter Calculation machine program, it is characterised in that work order obtaining step is realized when the program is executed by second processor:If according to construction personnel's Input receives the subtask of unit in charge of construction administrator appointment, then the work order corresponding to the subtask is obtained, by the work in work order Content is shown to construction personnel, to guide construction personnel to work according to work order.
7. Task-decomposing system according to claim 6, it is characterised in that the computer in the communication equipment of construction personnel When program is executed by second processor, recording step is also realized:It records a video, will record to the workload task amount completed Image be documented in work order corresponding position, and work order is back on the communication equipment of unit in charge of construction administrator.
8. Task-decomposing system according to claim 7, it is characterised in that:Image to record adds watermark letter automatically The upload is just carried out after breath.
9. Task-decomposing system according to claim 8, it is characterised in that:The watermark information includes that video recording is occurred Time and/or position.
10. according to claim 6-9 any one of them Task-decomposing systems, it is characterised in that in the communication equipment of construction personnel Computer program when being executed by second processor, also realize that work order retracts step:If according to the input of construction personnel, do not receive The subtask that unit in charge of construction administrator assigns, then return to the work order on the communication equipment of unit in charge of construction administrator.
CN201711431195.5A 2017-12-26 2017-12-26 Task-decomposing system and computer readable storage medium Pending CN108364112A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711431195.5A CN108364112A (en) 2017-12-26 2017-12-26 Task-decomposing system and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711431195.5A CN108364112A (en) 2017-12-26 2017-12-26 Task-decomposing system and computer readable storage medium

Publications (1)

Publication Number Publication Date
CN108364112A true CN108364112A (en) 2018-08-03

Family

ID=63010133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711431195.5A Pending CN108364112A (en) 2017-12-26 2017-12-26 Task-decomposing system and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN108364112A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109388971A (en) * 2018-10-26 2019-02-26 杭州虹晟信息科技有限公司 Big data platform mobile office system based on cloud
CN109615317A (en) * 2018-11-20 2019-04-12 泰康保险集团股份有限公司 The generation method and device of work plan
CN111429104A (en) * 2020-04-03 2020-07-17 青岛大学 Crowdsourcing item execution device, method, equipment and readable storage medium
CN111429088A (en) * 2020-03-10 2020-07-17 岭东核电有限公司 Process test result sending method and device, computer equipment and storage medium
CN111798106A (en) * 2020-06-18 2020-10-20 北京亿宇嘉隆科技有限公司 Project management method and system
CN112286177A (en) * 2019-07-10 2021-01-29 丰田自动车株式会社 Remote driving request processing device
CN112561403A (en) * 2021-01-18 2021-03-26 杭银消费金融股份有限公司 Business work order processing method and system
CN112990702A (en) * 2021-03-12 2021-06-18 深圳工盟科技有限公司 Construction team matching method, device and equipment based on construction task and storage medium

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101645148A (en) * 2009-06-19 2010-02-10 中国科学院声学研究所 Construction order management method applied to operation support system and management system thereof
CN101866457A (en) * 2010-06-23 2010-10-20 用友软件股份有限公司 Method and system for making project plan
CN104850954A (en) * 2015-05-25 2015-08-19 苏州金螳螂建筑装饰股份有限公司 System and method for processing construction information of architectural decoration project
CN105184438A (en) * 2015-07-16 2015-12-23 陈飞 System for managing human resources based on capacities and method of system
CN105373901A (en) * 2015-12-15 2016-03-02 国网北京市电力公司 Grid fault worksheet handling method, apparatus, and system
CN106096905A (en) * 2016-05-31 2016-11-09 北京诚公通信工程监理股份有限公司 A kind of project management method and system
CN106127367A (en) * 2016-06-15 2016-11-16 中邮建技术有限公司 A kind of scene anti-cheating inspection method single with random group based on mobile terminal
CN106203893A (en) * 2016-09-09 2016-12-07 扬州大学 A kind of method for allocating tasks of based on genetic algorithm under mass-rent environment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101645148A (en) * 2009-06-19 2010-02-10 中国科学院声学研究所 Construction order management method applied to operation support system and management system thereof
CN101866457A (en) * 2010-06-23 2010-10-20 用友软件股份有限公司 Method and system for making project plan
CN104850954A (en) * 2015-05-25 2015-08-19 苏州金螳螂建筑装饰股份有限公司 System and method for processing construction information of architectural decoration project
CN105184438A (en) * 2015-07-16 2015-12-23 陈飞 System for managing human resources based on capacities and method of system
CN105373901A (en) * 2015-12-15 2016-03-02 国网北京市电力公司 Grid fault worksheet handling method, apparatus, and system
CN106096905A (en) * 2016-05-31 2016-11-09 北京诚公通信工程监理股份有限公司 A kind of project management method and system
CN106127367A (en) * 2016-06-15 2016-11-16 中邮建技术有限公司 A kind of scene anti-cheating inspection method single with random group based on mobile terminal
CN106203893A (en) * 2016-09-09 2016-12-07 扬州大学 A kind of method for allocating tasks of based on genetic algorithm under mass-rent environment

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109388971A (en) * 2018-10-26 2019-02-26 杭州虹晟信息科技有限公司 Big data platform mobile office system based on cloud
CN109388971B (en) * 2018-10-26 2021-10-15 广西电网有限责任公司 Cloud-based big data platform mobile office system
CN109615317A (en) * 2018-11-20 2019-04-12 泰康保险集团股份有限公司 The generation method and device of work plan
CN112286177A (en) * 2019-07-10 2021-01-29 丰田自动车株式会社 Remote driving request processing device
CN111429088A (en) * 2020-03-10 2020-07-17 岭东核电有限公司 Process test result sending method and device, computer equipment and storage medium
CN111429088B (en) * 2020-03-10 2023-09-19 岭东核电有限公司 Method, device, computer equipment and storage medium for transmitting process test results
CN111429104A (en) * 2020-04-03 2020-07-17 青岛大学 Crowdsourcing item execution device, method, equipment and readable storage medium
CN111798106A (en) * 2020-06-18 2020-10-20 北京亿宇嘉隆科技有限公司 Project management method and system
CN112561403A (en) * 2021-01-18 2021-03-26 杭银消费金融股份有限公司 Business work order processing method and system
CN112561403B (en) * 2021-01-18 2024-03-19 杭银消费金融股份有限公司 Business work order processing method and system
CN112990702A (en) * 2021-03-12 2021-06-18 深圳工盟科技有限公司 Construction team matching method, device and equipment based on construction task and storage medium

Similar Documents

Publication Publication Date Title
CN108364112A (en) Task-decomposing system and computer readable storage medium
US20190087787A1 (en) Visualization and analysis of scheduling data
US10042981B2 (en) Method and apparatus for supporting task scheduling in a radiation therapy workflow via prediction of critical workload
US10402769B2 (en) Employee preference identification in a wellness management system
CN107680240B (en) Intelligent number-booking method for image examination of hospital patients
DE202015009252U1 (en) Diagnose and optimize cloud sharing pipelines
CN102254357A (en) Attendance system and attendance method
CN108874919A (en) Planned land use automatic inspection method, electronic equipment, storage medium and system
KR101934338B1 (en) Business Management System, Method And Recording Medium
DE102012103634A1 (en) Schedule events for several invitees
CN109325024A (en) Label display method, apparatus, terminal device and the storage medium of project
CN111160779A (en) Priority-based scheduling and attendance management method, system and equipment
DE102013206354A1 (en) Adaptive assessment of object relevance based on dynamic user properties
CN110413527A (en) Test macro, test method, electronic equipment and computer readable storage medium
KR101959791B1 (en) Business Management System, Method And Recording Medium
US20150032506A1 (en) Demand forecast segmentation apparatus and method, apparatus and method for adjusting demand forecast and recording medium recording program thereof
CN109416788A (en) The management method and equipment of plant protection task
CN111079400A (en) Task scheduling informatization management system, method and storage medium
KR101677580B1 (en) Method and system for providing sport service using platform
CN111291982A (en) Rental work order recommendation sequence evaluation method, system, electronic equipment and storage medium
US20200355323A1 (en) Interchangeable control module for fixed and portable lubricant dispensing devices
CN114092061A (en) Visual project progress management system and method
US20120079397A1 (en) Scheduling system
CN105608108A (en) Universal GIS data collaborative collection method and apparatus as well as server
CN105956766B (en) Method and device for hardware planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803