CN108360391A - A kind of concrete pier health preserving equipment - Google Patents

A kind of concrete pier health preserving equipment Download PDF

Info

Publication number
CN108360391A
CN108360391A CN201810433882.9A CN201810433882A CN108360391A CN 108360391 A CN108360391 A CN 108360391A CN 201810433882 A CN201810433882 A CN 201810433882A CN 108360391 A CN108360391 A CN 108360391A
Authority
CN
China
Prior art keywords
magnet
cloth
atomizer
cloth body
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810433882.9A
Other languages
Chinese (zh)
Other versions
CN108360391B (en
Inventor
任新根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Sonar Automation Technology Co.,Ltd.
Original Assignee
Huzhou Huake Construction Engineering Quality Inspection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huzhou Huake Construction Engineering Quality Inspection Co Ltd filed Critical Huzhou Huake Construction Engineering Quality Inspection Co Ltd
Priority to CN201810433882.9A priority Critical patent/CN108360391B/en
Publication of CN108360391A publication Critical patent/CN108360391A/en
Application granted granted Critical
Publication of CN108360391B publication Critical patent/CN108360391B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Abstract

The present invention relates to science of bridge building field more particularly to a kind of concrete pier health preserving equipments, including bridge pier, it is characterised in that further includes:Conserve cloth, control system, water tank, warm-air drier;Bridge pier ambient air humidity and temperature can be maintained automatically, ensure the maintenance quality of bridge pier.

Description

A kind of concrete pier health preserving equipment
Technical field:
The present invention relates to science of bridge building field more particularly to a kind of concrete pier health preserving equipments.
Background technology:
It is to improve concrete early stage and most it is well known that need implement to conserve meticulously to the concrete pier after just pouring Whole mechanical characteristic ensures the important means of the indexs such as concrete permeability resistance, durability.When conserving not in place, easily mix Solidifying soil Surface layer's concrete surface quality reduces, the main reason is that, when ambient humidity is less than inside concrete humidity, in concrete Portion, which leaves moisture evaporation channel and hole, causes surface layer loose;It is poor to conserve duration, concrete surface alternation of wetting and drying, in concrete When intensity is relatively low, is changed repeatedly by humiture, form surface drying shrinkage and thermal cracking;In gain in strength phase inner concrete table Layer is led to surface layer a certain range inner concrete intensity forever lost by ectocine maximum, however, widely used at present straight Watering maintenance process is connect, scaffold or Zigzag type ramp need to be retained for a long time, a large amount of construction equipment is occupied, leads to equipment turnover of constructing Utilization rate is relatively low;Maintenance personnel need to for several times climb to pier top daily, and watering maintenance, heavy workload are carried out to pier shaft and pier top;With Water directly sprays pier shaft and pier top pallet, and under the effect of sunlight, high temperature and wind, moisture evaporation is very fast, it is ensured that maintenance quality, often It must repeated multiple times watering maintenance;Low bridge pier is directly sprayed to bridge pier by the pressure on sprinkling truck implements maintenance, but sprays anti- Bullet rate is high;High pier is sent water to pier top with immersible pump, and when sprinkling is influenced by pier top pallet again, and water cannot all be sprayed onto pier shaft On, cause the waste of part energy consumption and water resource;Watering maintenance process.
Invention content:
The purpose of the present invention and provides a kind of concrete pier health preserving equipment aiming at the deficiency of the prior art, can be from It is dynamic to maintain bridge pier ambient air humidity and temperature, ensure the maintenance quality of bridge pier.
The technology solution of the present invention is as follows:
A kind of concrete pier health preserving equipment, including bridge pier, it is characterised in that further include:Conserve cloth, control system, water storage Case, warm-air drier;
The maintenance cloth includes cloth body, atomizing component, heating component, magnet assemblies, humidity detector, temperature detection dress It sets, component of restricting;
The cloth body has been sequentially distributed from inside to outside:First canvas layer, moisture barrier, thermal insulation layer, the second canvas layer;
The atomizing component includes water pipe, and distributive pipe, atomizer, the water pipe setting is in the thermal insulation layer, the water Pipe setting direction is consistent with cloth body direction;The atomizer is arranged in cloth body, and the atomizer connects water pipe by distributive pipe, The distributive pipe is equipped with water valve, and the atomizer is equipped with atomizer, and the atomizer stretches out outside the first canvas layer of cloth body; The water valve is electrically connected connected control system;The atomizer is electrically connected connected control system;The atomizer is multiple;Above and below any two The adjacent atomizer is apart from equal;The water pipe is made of hose material;
The bottom of storage tank is equipped with water pipe head, and the water pipe head is multiple, and the water pipe connects the water pipe and connects Head;The water tank is placed in top of bridge pier;
The heating component includes steam heating pipe, and the steam heating pipe is arranged in the thermal insulation layer, and the steam heating pipe is equipped with Heating is in charge of, and the heating is in charge of outside the first canvas layer for stretching out cloth body, and the heating, which is in charge of, is equipped with valve for heating installation valve, described warm Air valve is electrically connected connected control system;The heating, which is in charge of, to be distributed in for multiple and equidistant on the steam heating pipe;The steam heating pipe It is made of hose material;
The warm-air drier is equipped with multiple heating pipe joints;The steam heating pipe connects the heating pipe joint;
The rope component is arranged in cloth body left and right edges;
The magnet assemblies include the first magnet, the second magnet, and first magnet setting is on the cloth body left side, institute the Two magnet compare first magnet positions and are fixed on the right of the cloth body, first magnet and the second magnet poles direction phase Together;First magnet and the second magnet are multiple;
The cloth body inside middle portion is equipped with humidity control device, and the humidity control device is electrically connected the control system;
The cloth body inside middle portion is additionally provided with temperature-detecting device, and the temperature-detecting device is electrically connected the control system System;
The maintenance cloth is multiple, and the maintenance cloth vertically lays and is wrapped in the bridge pier surrounding.
Further, the cloth body upper and lower ends are equipped with a sling, and the sling is multiple, facilitates the fixation of maintenance cloth.
Further, the moisture barrier uses plastics film production;
Further, the thermal insulation layer is made of rock wool.
Further, first magnet and the second magnet using electromagnet structure and are electrically connected the control system.
Further, the pier coping portion is aerial is equipped with the maintenance cloth.
The beneficial effects of the present invention are:
1, bridge pier is wrapped in the inside by maintenance cloth, avoids sun solarization and wind;Magnet assemblies are arranged, and ensure that maintenance cloth is laid Gluing, sealing afterwards.
2, maintenance cloth is equipped with humidity detector, temperature-detecting device can realize the inspection for conserving humidity and temperature in cloth It surveys;It is additionally provided with atomizing component on maintenance cloth, heating component can realize the adjusting for conserving humidity and temperature in cloth;In conjunction with control system The automatic adjustment that can realize temperature and humidity;In addition, humidity detector, temperature-detecting device are conducive in maintenance processes Detection is conducive to bridge quality testing control.
3, cloth body is equipped with the intensity that canvas layer, moisture barrier, thermal insulation layer ensure that maintenance cloth, is conducive to conserve the humidity in cloth And the maintenance of temperature.
4, it is multiple that atomizer, heating, which are in charge of, and the convenient variation for different location is fine-tuned, and is not only contributed to The adjusting for further increasing maintenance quality, and being directed to is conducive to save the energy.
Description of the drawings:
The following drawings are only intended to schematically illustrate and explain the present invention, not delimit the scope of the invention.Wherein:
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is present invention maintenance cloth structure schematic diagram;
Fig. 3 is the section signal of present invention maintenance cloth;
Fig. 4 is enlarged drawing at the A of Fig. 2 of the present invention;
Fig. 5 is heating component installation structure schematic diagram of the present invention.
Specific implementation mode:
As shown in Fig. 1 to Fig. 5, a kind of concrete pier health preserving equipment, including bridge pier 1, it is characterised in that further include:Maintenance Cloth 2, control system 3, water tank 5, warm-air drier 4;
The maintenance cloth 2 includes cloth body 21, atomizing component 22, heating component 23, magnet assemblies 24, humidity detector 25, temperature-detecting device 26, rope component 27;
The cloth body 21 has been sequentially distributed from inside to outside:First canvas layer 211, moisture barrier 213, thermal insulation layer 212, the second sail Layer of cloth 214;
The atomizing component 22 include water pipe 221, distributive pipe 222, atomizer 223, the water pipe 221 setting it is described every In thermosphere 212,221 setting direction of the water pipe is consistent with 21 direction of cloth body;The atomizer 223 is arranged in cloth body, described Atomizer 223 connects water pipe 221 by distributive pipe 222, and the distributive pipe 222 is equipped with water valve 2221, and the atomizer 223 is equipped with Atomizer 2231, the atomizer 2231 stretch out outside the first canvas layer 211 of cloth body 21;The electrical connection control of the water valve 2221 System 3 processed;The atomizer 223 is electrically connected connected control system 3;The atomizer 223 is multiple;The neighbouring institute of any two Atomizer 223 is stated apart from equal;The water pipe 221 is made of hose material;
5 bottom of the water tank is equipped with water pipe head 51, and the water pipe head 51 is multiple, and the water pipe 221 connects institute State water pipe head 51;The water tank 5 is placed on the top of bridge pier 1;
The heating component 23 includes steam heating pipe 231, and the steam heating pipe 231 is arranged in the thermal insulation layer 212, described warm Tracheae 231 is in charge of 232 equipped with heating, and the heating is in charge of outside the first canvas layer 211 of 232 stretching cloth bodies 21, the heating It is in charge of 232 and is equipped with valve for heating installation valve 2321, the valve for heating installation valve 2321 is electrically connected connected control system 3;It is more that the heating, which is in charge of 232, A and equidistant is distributed on the steam heating pipe 231;The steam heating pipe 231 is made of hose material;
The warm-air drier 4 is equipped with multiple heating pipe joints 41;The steam heating pipe 231 connects the heating pipe joint 41;
The rope component 27 is arranged in 21 left and right edges of cloth body;
The magnet assemblies 24 include the first magnet 241, and the second magnet 242, the setting of the first magnet 241 is in the cloth 21 left side of body, the second magnet 242 compare first magnet positions and are fixed on 21 the right of the cloth body, first magnet 241 and 242 pole orientation of the second magnet it is identical;First magnet, 241 and second magnet 242 is multiple;
21 inside middle portion of cloth body is equipped with humidity control device 25, and the humidity control device is electrically connected the control system System 3;
21 inside middle portion of cloth body is additionally provided with temperature-detecting device 25, and the temperature-detecting device 25 is electrically connected the control System 3 processed;
The maintenance cloth 2 is multiple, and the maintenance cloth 2 vertically lays and is wrapped in 1 surrounding of the bridge pier.
Specifically, 21 upper and lower ends of cloth body are equipped with a sling 215, and the sling 215 is multiple.
Specifically, the moisture barrier 213 uses plastics film production;
Specifically, the thermal insulation layer 212 is made of rock wool.
Specifically, first magnet, 241 and second magnet 242 using electromagnet structure and is electrically connected the control system 3。
Specifically, 1 top of the bridge pier is aerial is equipped with the maintenance cloth 2.
The embodiment is to be illustrated the present invention, and is not intended to limit the present invention.Any those skilled in the art It can modify without violating the spirit and scope of the present invention to the embodiment, therefore the rights protection model of the present invention It encloses, it should be as listed by the claim of the present invention.

Claims (6)

1. a kind of concrete pier health preserving equipment, including bridge pier (1), it is characterised in that further include:Conserve cloth (2), control system (3), water tank (5), warm-air drier (4);
The maintenance cloth (2) includes cloth body (21), atomizing component (22), heating component (23), magnet assemblies (24), Humidity Detection Device (25), temperature-detecting device (26), rope component (27);
The cloth body (21) has been sequentially distributed from inside to outside:First canvas layer (211), moisture barrier (213), thermal insulation layer (212), Two canvas layers (214);
The atomizing component (22) includes water pipe (221), and distributive pipe (222), atomizer (223), the water pipe (221), which is arranged, to be existed In the thermal insulation layer (212), water pipe (221) setting direction is consistent with cloth body (21) direction;Atomizer (223) setting In cloth body, the atomizer (223) connects water pipe (221) by distributive pipe (222), and the distributive pipe (222) is equipped with water valve (2221), the atomizer (223) is equipped with atomizer (2231), and the atomizer (2231) stretches out the first of cloth body (21) Canvas layer (211) is outside;The water valve (2221) is electrically connected connected control system (3);The atomizer (223) is electrically connected connected control system (3);The atomizer (223) is multiple;The neighbouring atomizer (223) of any two is apart from equal;The water pipe (221) hose material is used to make;
Water tank (5) bottom is equipped with water pipe head (51), and the water pipe head (51) is multiple, and the water pipe (221) is even Connect the water pipe head (51);The water tank (5) is placed on bridge pier (1) top;
The heating component (23) includes steam heating pipe (231), and the steam heating pipe (231) is arranged in the thermal insulation layer (212), institute It states steam heating pipe (231) equipped with heating to be in charge of (232), the heating is in charge of the first canvas layer that (232) stretch out cloth body (21) (211) outside, the heating is in charge of (232) equipped with valve for heating installation valve (2321), valve for heating installation valve (2321) the electrical connection control system It unites (3);It is multiple and equidistant be distributed on the steam heating pipe (231) that the heating, which is in charge of (232),;The steam heating pipe (231) It is made of hose material;
The warm-air drier (4) is equipped with multiple heating pipe joints (41);The steam heating pipe (231) connects the heating pipe joint (41);
The rope component (27) is arranged in cloth body (21) left and right edges;
The magnet assemblies (24) include the first magnet (241), and the second magnet (242), the first magnet (241) setting is in institute Cloth body (21) left side is stated, the second magnet of institute (242) compares first magnet positions and is fixed on the right of the cloth body (21), described First magnet (241) and the second magnet (242) pole orientation are identical;First magnet (241) and the second magnet (242) are more It is a;
Cloth body (21) inside middle portion is equipped with humidity control device (25), and the humidity control device is electrically connected the control system It unites (3);
Cloth body (21) inside middle portion is additionally provided with temperature-detecting device (25), described in temperature-detecting device (25) electrical connection Control system (3);
The maintenance cloth (2) is multiple, and the maintenance cloth (2) vertically lays and be wrapped in the bridge pier (1) surrounding.
2. a kind of concrete pier health preserving equipment according to claim 1, it is characterised in that:Cloth body (21) upper and lower ends Equipped with a sling (215), the sling (215) is multiple.
3. a kind of concrete pier health preserving equipment according to claim 1, it is characterised in that:The moisture barrier (213) uses Plastics film production.
4. a kind of concrete pier health preserving equipment according to claim 1, it is characterised in that:The thermal insulation layer (212) uses Rock wool makes.
5. a kind of concrete pier health preserving equipment according to claim 1, it is characterised in that:
First magnet (241) and the second magnet (242) using electromagnet structure and are electrically connected the control system (3).
6. a kind of concrete pier health preserving equipment according to claim 1, it is characterised in that:
It is aerial at the top of the bridge pier (1) to be equipped with the maintenance cloth (2).
CN201810433882.9A 2018-05-08 2018-05-08 A kind of concrete pier health preserving equipment Active CN108360391B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810433882.9A CN108360391B (en) 2018-05-08 2018-05-08 A kind of concrete pier health preserving equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810433882.9A CN108360391B (en) 2018-05-08 2018-05-08 A kind of concrete pier health preserving equipment

Publications (2)

Publication Number Publication Date
CN108360391A true CN108360391A (en) 2018-08-03
CN108360391B CN108360391B (en) 2019-11-08

Family

ID=63011824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810433882.9A Active CN108360391B (en) 2018-05-08 2018-05-08 A kind of concrete pier health preserving equipment

Country Status (1)

Country Link
CN (1) CN108360391B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041994B (en) * 2019-12-24 2021-02-12 中交隧道工程局有限公司 Pier stud wraps up in mould device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103507150A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Energy-saving concrete curing device
CN205893924U (en) * 2016-07-27 2017-01-18 中铁十二局集团有限公司 Full automatic spray maintenance system of pier concrete
JP2017095920A (en) * 2015-11-20 2017-06-01 太平洋セメント株式会社 Tunnel segment and method for producing the same
CN206255994U (en) * 2016-12-05 2017-06-16 新疆北新路桥集团股份有限公司 A kind of winter care device of bridge concrete
CN106945158A (en) * 2017-03-09 2017-07-14 蒋春阳 A kind of concrete prefabricated element automatic maintenance device
CN207256505U (en) * 2017-09-28 2018-04-20 中冶建工集团有限公司 For conserving the curing means and curing system of cylindricality pile body

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103507150A (en) * 2012-06-19 2014-01-15 中铁十九局集团第一工程有限公司 Energy-saving concrete curing device
JP2017095920A (en) * 2015-11-20 2017-06-01 太平洋セメント株式会社 Tunnel segment and method for producing the same
CN205893924U (en) * 2016-07-27 2017-01-18 中铁十二局集团有限公司 Full automatic spray maintenance system of pier concrete
CN206255994U (en) * 2016-12-05 2017-06-16 新疆北新路桥集团股份有限公司 A kind of winter care device of bridge concrete
CN106945158A (en) * 2017-03-09 2017-07-14 蒋春阳 A kind of concrete prefabricated element automatic maintenance device
CN207256505U (en) * 2017-09-28 2018-04-20 中冶建工集团有限公司 For conserving the curing means and curing system of cylindricality pile body

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041994B (en) * 2019-12-24 2021-02-12 中交隧道工程局有限公司 Pier stud wraps up in mould device

Also Published As

Publication number Publication date
CN108360391B (en) 2019-11-08

Similar Documents

Publication Publication Date Title
CN204920254U (en) Maintenance of equipment of large tracts of land concrete regularization automatic spray
CN208362926U (en) A kind of multifunctional concrete bridge pier health cloth and laying apparatus
CN101091449A (en) Irrigation system
CN203563429U (en) Roof greening planting bed
CN204850504U (en) Concrete curing means
CN108252525A (en) A kind of concrete vertical structure intelligent spray curing system and method
CN104831873B (en) Combined intelligent rigid inverted roof with water storage and drainage functions
CN106747644A (en) A kind of concrete automatic maintenance device and automatic maintenance method
CN103696580A (en) Vertical thin-walled mass concrete spray maintenance device and method thereof
CN205232979U (en) Warmhouse booth without heating facility
CN108360391B (en) A kind of concrete pier health preserving equipment
CN205009378U (en) A intelligence sprays health preserving system for roof beam, board precasting yard
CN203595955U (en) System for automatically controlling ground temperature and ground humidity of greenhouse
CN108360390B (en) Multifunctional concrete pier health preserving cloth and laying device
CN208803375U (en) A kind of concrete pier health preserving equipment
CN207859123U (en) Curing kilns and prefabricated components curing system
CN207185405U (en) A kind of controllable photovoltaic agricultural greenhouse system of crop growth environment
CN208777172U (en) A kind of energy-saving concrete pier health preserving equipment
CN205491914U (en) Solar hot -air soil heating vegetable greenhouse
CN204482525U (en) A kind of double-layer inflatable booth with sun-shading frame
CN208597474U (en) A kind of photovoltaic infiltration irrigation system
CN215122902U (en) Wisdom garden soil humidity regulation and control subassembly
CN108385537B (en) A kind of energy-saving concrete pier health preserving equipment
CN105493955A (en) Greenhouse without need for heating facility
CN206521403U (en) A kind of concrete automatic maintenance device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190724

Address after: 313018 No.2 Business Building, Fukang Garden, Linghu Town, Nanxun District, Huzhou City, Zhejiang Province

Applicant after: Huzhou Zhen Shuo Automation Technology Co., Ltd.

Address before: 313009 Zhejiang city of Huzhou province Nanxun Economic Development Zone No. 1858 West Jiang Jiang Yang Cun centenarians

Applicant before: HUZHOU HUAKE CONSTRUCTION ENGINEERING QUALITY INSPECTION CO., LTD.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20191014

Address after: 317000 Shengli Village, Duqiao Town, Linhai City, Taizhou City, Zhejiang Province, No. 2-41

Applicant after: Ma Ling Ling

Address before: 313018 No.2 Business Building, Fukang Garden, Linghu Town, Nanxun District, Huzhou City, Zhejiang Province

Applicant before: Huzhou Zhen Shuo Automation Technology Co., Ltd.

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201126

Address after: Room 0102, 247 Renmin West Road, Chongchuan District, Nantong City, Jiangsu Province, 226000

Patentee after: Nantong Sonar Automation Technology Co.,Ltd.

Address before: 317000 Shengli Village, Duqiao Town, Linhai City, Taizhou City, Zhejiang Province, No. 2-41

Patentee before: Ma Lingling