CN108360328B - Construction method for compacting periphery of asphalt pavement inspection well and transition well cover - Google Patents

Construction method for compacting periphery of asphalt pavement inspection well and transition well cover Download PDF

Info

Publication number
CN108360328B
CN108360328B CN201810164453.6A CN201810164453A CN108360328B CN 108360328 B CN108360328 B CN 108360328B CN 201810164453 A CN201810164453 A CN 201810164453A CN 108360328 B CN108360328 B CN 108360328B
Authority
CN
China
Prior art keywords
well
asphalt
periphery
cover
seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810164453.6A
Other languages
Chinese (zh)
Other versions
CN108360328A (en
Inventor
粟思橙
曹小康
杨荣强
蔡向昇
邝雁军
韦道孟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCFEB Civil Engineering Co Ltd
Original Assignee
CCFEB Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCFEB Civil Engineering Co Ltd filed Critical CCFEB Civil Engineering Co Ltd
Priority to CN201810164453.6A priority Critical patent/CN108360328B/en
Publication of CN108360328A publication Critical patent/CN108360328A/en
Application granted granted Critical
Publication of CN108360328B publication Critical patent/CN108360328B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Road Repair (AREA)

Abstract

The invention provides a construction method for compacting the periphery of an asphalt pavement inspection well, which comprises the following steps: the transition well cover covers the inspection shaft; paving and rolling the lower asphalt surface layer; taking out the transitional well cover; reinforcing the periphery of the well seat and the well cover; installing a well seat and a well cover; paving an asphalt upper surface layer; and (6) integral rolling. Through transition well lid cover inspection pit shaft, well seat well lid periphery pour fine aggregate concrete reinforcement and well seat well lid with the mortar bed course pad up realize wholly rolling, improved the degree of compaction of pitch surface course around the inspection shaft, solved the two kinds of roughness problems of pitch surface course around the inspection shaft. The transitional well cover provided by the invention has the advantages of simple structure, light weight and capability of being used repeatedly.

Description

Construction method for compacting periphery of asphalt pavement inspection well and transition well cover
Technical Field
The invention relates to the technical field of inspection well construction, in particular to a construction method for compacting the periphery of an asphalt pavement inspection well and a transition well cover.
Background
The compaction thickness of the asphalt surface layer refers to the actual thickness of the asphalt surface layer after rolling according to a construction scheme, the loose paving thickness is determined through a test section, and the paving thickness of the asphalt mixture can reach the designed thickness after compaction under the given construction conditions of the asphalt mixture, a rolling machine, a rolling method and the like. The loose paving thickness and the compaction thickness do not have an accurate and strict functional relationship, but are influenced by many factors such as the characteristics of the asphalt mixture, the construction temperature, the combination of compaction tools and machines, the compaction method, the compaction pass and the like, and a mathematical relationship is presented by a statistical rule. Therefore, only rough control of the compacted thickness is possible during the construction of the asphalt surface course, and it is difficult to strictly control the compacted thickness within a precise range.
The road roller has the following pushing effect: in the process of advancing or retreating the road roller, as the surface of the rolling wheel and the asphalt mixture have larger horizontal friction force, the asphalt mixture can be pushed to move in a wave shape along the running direction of the road roller, and the temporary well cover or the permanent well seat can be displaced or deformed by the horizontal load conducted by the asphalt mixture under the condition of not being fixed firmly. The effect is not controlled to be in place, and the problem of poor flatness around the inspection well is easily caused.
The problems of local protrusion, pits and the like of the asphalt surface layer around the inspection well are caused by the fixation of the height of the well cover in the rolling process and the dynamic and uncertain change of the thickness of the asphalt mixture. The problem is the flatness which is directly caused by the dynamic response among the road roller, the asphalt mixture and the well seat in the construction process and is directly displayed after the construction is finished, and the problem is called as the initial flatness problem.
In the operation process, the asphalt surface layer around the well is loosened, cracked and settled, so that the flatness of the asphalt surface layer around the well is reduced, the passing quality of vehicles is influenced, and the vehicles jump when passing. The problems are uneven settlement caused by insufficient compaction of asphalt surface layers around wells or insufficient compaction of base layers and subgrades in the range around wells, and are gradually developed in the operation period to cause unevenness and vehicle jumping around wells, so the problems are called as 'later-stage flatness problems'.
At present, the construction around the asphalt surface layer of the inspection well usually adopts a method of shielding the inspection well mouth by a transition cover plate, then paving the asphalt surface layer by layer, cutting off asphalt near the inspection well mouth, installing an inspection well seat and a well cover by taking the elevation of the asphalt surface layer as a basis, and finally paving an asphalt mixture manually to fill up the vacancy around the well seat.
The existing method has the following defects:
1. and the asphalt surface layer around the inspection well is cut off together after the two surface layers are paved. After the well base is installed, the surrounding gap is repaired and rolled layer by layer in an artificial material distribution mode. Because the elevation of the inspection well base is higher than that of the asphalt lower surface layer, a road roller at the axillary angle part around the well base cannot roll in place during the construction of the asphalt lower surface layer, so that the compactness of the asphalt lower surface layer at the position is insufficient, and the later-stage flatness problem is generated.
2. Because the range of the cut-off part is small, only a small-sized roller can be used for rolling. The tonnage of the rolling machine is light, the rolling wheel is partially rolled on the upper surface layer of the formed asphalt in a cross-joint manner, the rolling effective load is further reduced, the lack of compactness is easily caused, and the later-stage flatness problem is generated.
3. Similarly, because the range of the cut-off part is small, one part of the rolling wheel presses on the rigid formed asphalt upper surface layer and the other part presses on the flexible hot-mixed asphalt mixture during cross-seam rolling in the rolling process, and the rolling wheel can incline towards the flexible asphalt mixture under the action of gravity to form a local pit, so that the problem of initial flatness is generated.
4. The total amount, the uniformity and the paving flatness of the asphalt mixture are difficult to control by manual distribution, the flatness of an asphalt surface layer around a well seat is easily influenced, and the problem of initial flatness is generated.
5. The formed asphalt surface layer needs to be removed by milling by a milling machine, and the cost of a mechanical machine is high.
6. When the well seat is not firmly fixed, the transition phenomenon of the asphalt mixture around the well in the rolling process of the road roller interacts with the well seat, so that the asphalt mixture is easily accumulated locally, and a bulge or a pit is generated.
Disclosure of Invention
The invention provides a construction method for compacting the periphery of an asphalt pavement inspection well and a transitional well cover, which are used for solving the two flatness problems of an asphalt surface layer around the inspection well.
The technical scheme adopted by the invention is as follows:
according to one aspect of the invention, a construction method for compacting the periphery of an asphalt pavement inspection well is provided, which comprises the following steps:
the transition well cover covers the inspection shaft;
paving and rolling the lower asphalt surface layer;
taking out the transitional well cover: after the rolling of the lower layer of the asphalt is finished, excavating asphalt mixture on the surface of the transition well cover and in the peripheral range, and taking out the transition well cover;
and (3) reinforcing the periphery of the well seat and the well cover: pouring fine stone concrete at the periphery of a preset installation position of a well seat and a well cover;
installing a well seat and a well cover: installing a well seat and a well cover, and padding the lower part of the well seat and the well cover with a mortar cushion layer;
paving an asphalt upper surface layer: paving an asphalt upper surface layer before the mortar cushion layer is initially set;
and (3) integral rolling: and integrally rolling the well seat, the well cover and the asphalt upper surface layer.
Further, before the step of rolling the lower layer of the asphalt, the method also comprises the step of inserting the steel bar heads into the asphalt mixture to find the position of the transition well cover and marking the transition well cover.
Further, the step of reinforcing the periphery of the well seat and the well lid comprises the following steps: temporarily placing the well seat and the well lid at a preset installation position, sleeving the inner mold steel ring on the periphery of the well seat and the well lid to pour fine aggregate concrete, and taking out the well seat and the inner mold steel ring after the fine aggregate concrete is initially set.
Further, the step of installing the well seat and the well lid comprises the following steps: and drawing a cross line with the elevation of the flat stone to loft to a preset installation position of the well base and the well lid, and upwards lifting 3-5 mm to control the installation elevation of the well base and the well lid.
Further, before the step of paving the asphalt upper layer, the method also comprises the steps of covering fiber paper on the surface of the well seat and the well cover and brushing asphalt separant on the surface of the fiber paper.
Further, the integral rolling step comprises: when two steel wheel road rollers and rubber tyer road roller rolled near well seat well lid to rolling well seat well lid to just rolling well seat well lid to the route of well seat well lid, well seat well lid position is avoided to adjacent wheel trace, and the non-overlapping portion of wheel trace is rolled along the supplementary of well seat well lid edge repeatedly by small-size steel wheel road roller around the well seat well lid, rolls the in-process and clears up the bituminous mixture who is passed to well seat well lid surface repeatedly.
According to another aspect of the invention, a transition manhole cover applied to the construction method for compacting the periphery of the asphalt pavement manhole is provided, and is used for covering the manhole shaft, wherein the transition manhole cover comprises a circular cover plate and a plurality of blocking legs which are uniformly arranged along the circumferential direction of the cover plate and are positioned below the cover plate, and the blocking legs are provided with arc-shaped outer surfaces used for contacting with the manhole shaft to limit the horizontal movement of the transition manhole cover.
Further, a plurality of reinforcing ribs connected to the blocking legs to support the blocking legs intersect at the center of the cover plate.
Further, the cover plate is provided with a plurality of handles convenient for moving the transitional well cover above.
Furthermore, two ends of the handle are respectively sleeved with a nut, and the nuts are welded on the cover plate.
The invention has the following beneficial effects:
the invention provides a construction method for compacting the periphery of an asphalt pavement inspection well, which comprises the following steps: the transition well cover covers the inspection shaft; paving and rolling the lower asphalt surface layer; taking out the transitional well cover; reinforcing the periphery of the well seat and the well cover; installing a well seat and a well cover; paving an asphalt upper surface layer; and (6) integral rolling. Through transition well lid cover inspection pit shaft, well seat well lid periphery pour fine aggregate concrete reinforcement and well seat well lid with the mortar bed course pad up realize wholly rolling, improved the degree of compaction of pitch surface course around the inspection shaft, solved the two kinds of roughness problems of pitch surface course around the inspection shaft. The transitional well cover provided by the invention has the advantages of simple structure, light weight and capability of being used repeatedly.
In addition to the objects, features and advantages described above, other objects, features and advantages of the present invention are also provided. The present invention will be described in further detail below with reference to the accompanying drawings.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, illustrate embodiments of the invention and, together with the description, serve to explain the invention and not to limit the invention. In the drawings:
FIG. 1 is a schematic flow chart of a construction method for compacting the periphery of an asphalt pavement inspection well according to a preferred embodiment of the invention;
FIG. 2 is a schematic illustration of the rolling of an asphalt sub-layer in accordance with a preferred embodiment of the present invention;
FIG. 3 is a schematic view of the reinforcement of the periphery of the well base and the well lid according to the preferred embodiment of the present invention;
FIG. 4 is a schematic view of the integral rolling of the well base cover and the asphalt top layer of the preferred embodiment of the present invention;
FIG. 5 is a schematic view of the bottom of the transitional well lid of the preferred embodiment of the present invention;
FIG. 6 is a schematic view of a transitional well cover top of a preferred embodiment of the present invention;
fig. 7 is a schematic view of the inner mold steel ring of the preferred embodiment of the present invention.
Description of reference numerals:
100. a transitional well cover; 110. a cover plate; 120. blocking legs; 121. reinforcing ribs; 130. a handle; 131. a nut; 200. inspecting the shaft; 300. a base layer; 400. a lower asphalt layer; 500. fine stone concrete; 600. an inner mold steel ring; 700. a well base and a well cover; 800. and (4) an asphalt upper surface layer.
Detailed Description
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1 to 4, according to an aspect of the present invention, there is provided a construction method for compacting the periphery of an asphalt pavement inspection well, including the steps of:
in step S1, the transition manhole cover 100 covers the inspection shaft 200.
Maintenance of the road base 300 is completed and cleaned, and after the kerbstone is built, the inspection shaft 200 is covered by the transition well cover 100 before the construction of the asphalt lower surface layer 400.
And step S2, paving and rolling the asphalt lower surface layer 400.
Step S3, taking out the transition manhole cover 100: and after the rolling of the asphalt lower surface layer 400 is finished, excavating asphalt mixture on the surface of the transition well lid 100 and in the peripheral range, and taking out the transition well lid 100.
The asphalt mixture above the transition well lid 100 and around needs to be removed after the asphalt lower surface layer 400 is rolled, local unevenness of the well mouth can be eliminated by the removing process in the construction process, and the flatness after forming is not affected. And after the asphalt lower surface layer 400 is rolled, the transition well lid 100 can dig out asphalt covering the transition well lid 100 and the periphery while the asphalt is hot, and the transition well lid 100 is turned to the front for continuous use. The transition well lid 100 has small usage amount once, can be recycled for a plurality of times in single construction, and has low material cost. Because the transition well cover 100 is dug out before the asphalt lower surface layer 400 is cooled, the asphalt mixture is small in digging difficulty, simple and convenient to construct and convenient to popularize.
Step S4, reinforcing the periphery of the well seat and the well cover 700: and pouring fine stone concrete 500 at the periphery of the preset installation position of the well seat and the well cover 700.
After the fine aggregate concrete 500 backfilled between the well base well cover 700 and the asphalt lower surface layer 400 is finally set, lateral restraint is formed on the well base well cover 700, the well base well cover 700 is prevented from moving laterally under the pushing effect of a road roller, the well base well cover 700 is only allowed to sink vertically, and local protrusions or pits generated by pushing of asphalt mixtures are reduced. The fine aggregate concrete 500 belongs to a temporary structure required in the process of the technical scheme, and does not play a role in using an asphalt surface layer and an inspection well after construction.
Step S5, installing the well base and the well lid 700: and (3) installing the well base and the well cover 700, and padding the well base and the well cover 700 with a mortar cushion layer.
Step S6, paving an asphalt upper surface layer 800: the asphalt top layer 800 begins to be laid before the mortar mat sets initially.
Before the mortar cushion layer at the bottom of the well seat well lid 700 is initially set, for example, within 1 hour after the mortar cushion layer is filled, paving of the asphalt upper layer 800 is started, and by utilizing the limited degree of plasticity of the mortar in the state close to the initial setting state, the well seat well lid 700 can be settled together with the asphalt upper layer 800 within a certain range, so that conditions are provided for integral rolling of the well seat well lid 700 and the asphalt upper layer 800.
After the paving of the asphalt upper surface layer 800 is completed, the asphalt mixture scattered on the surface of the well base and well cover 700 is manually swept, so that the well base and well cover 700 and the asphalt upper surface layer 800 can be integrally settled and integrally rolled and molded in the construction process.
Step S7, integral rolling: the well base and cover 700 and the asphalt upper layer 800 are rolled integrally.
The asphalt upper layer 800 is integrally rolled and formed without taking out the well seat and the well cover 700 or removing the asphalt mixture around the well, so that the technical processing requirement of well backfill is avoided.
And opening the traffic after the asphalt upper surface layer 800 is naturally cooled to below 50 ℃.
The main function of the transition well lid 100 is to prevent the asphalt mixture from falling into the inspection shaft 200, so that the asphalt lower surface layer 400 is paved and rolled by a machine, and is formed in one step without affecting the well flatness of the asphalt lower surface layer 400. Therefore, the requirement of the transitional well lid 100 on rigidity and geometric shape is not high, and the transitional well lid can be roughly adjusted to be approximately flat after deformation, so that the use requirement can be met.
The transition well cover 100 covers the inspection shaft 200, fine stone concrete 500 is poured on the periphery of the well seat and well cover 700 for reinforcement, and the well seat and well cover 700 is padded up by a mortar cushion layer to realize integral rolling, so that the compactness of the asphalt surface layer around the inspection shaft is improved, and the two flatness problems of the asphalt surface layer around the inspection shaft are solved. The transition well lid 100 provided by the invention has the advantages of simple structure, light weight and capability of being used repeatedly.
Preferably, referring to fig. 2, before the step of rolling the asphalt lower layer 400, a step of inserting a steel bar head into the asphalt mixture to locate and mark the transition manhole cover 100 is further included. The steel bar heads have larger touch feeling and make sound when impacting the transition well lid 100, so that the position of the transition well lid 100 can be conveniently found out. The markings are made to facilitate later retrieval and removal of the transition well lid 100.
Preferably, referring to fig. 3 and 7, the step of reinforcing the periphery of the well seat and the well lid 700 comprises: temporarily placing the well seat and the well cover 700 at a preset installation position, sleeving the inner mold steel ring 600 on the periphery of the well seat and the well cover 700, pouring the fine aggregate concrete 500, and taking out the well seat and the well cover 700 and the inner mold steel ring 600 after the fine aggregate concrete 500 is initially set. The inner mold steel ring 600 is used as an inner mold for pouring the fine stone concrete 500, and the well seat well cover 700 is positioned and supports the inner mold steel ring 600. The fine stone concrete 500 is tightly attached to the well seat and the well cover 700, and particularly, the pressure is not great at the axillary corner, so that the weak link of uneven settlement is not formed.
The thickness of the fine aggregate concrete 500 backfilled around the well seat and the well cover 700 can be controlled by self, and the fine aggregate concrete does not need to be leveled with the elevation of the asphalt lower surface layer 400, so that when the asphalt upper surface layer 800 is paved, the space around the well is abundant, a long, narrow and deep well back part does not exist, the asphalt mixture backfilling and integral rolling forming of the asphalt upper surface layer 800 are facilitated, and the well back part is not easy to become a defective part.
Preferably, referring to fig. 4, the step of installing the well lid 700 comprises: and drawing a cross line with the elevation of the flat stone to loft to a preset installation position of the well base and the well lid 700, and lifting upwards by 3-5 mm to control the installation elevation of the well base and the well lid 700. Flush according to design flat kerbstone elevation and pitch upper surface 800 design elevation, control well seat well lid 700's elevation according to the principle that exceeds pitch upper surface 800 design elevation 3 ~ 5 mm. The well base and the well lid 700 are settled due to the plasticity of the mortar cushion layer in the integral rolling process, and finally settled to the designed elevation of the asphalt upper layer 800 and flush with the asphalt upper layer 800.
Preferably, referring to fig. 4, before the step of spreading the asphalt upper layer 800, the method further comprises the step of covering the surface of the well base and well cover 700 with fiber paper, and brushing the surface of the fiber paper with an asphalt release agent. The fiber paper covers the surface of the well base and the well cover 700 to prevent the asphalt mixture from polluting the surface of the well base and the well cover 700. The asphalt separant is vegetable oil which is commonly used in asphalt construction and used for preventing asphalt mixture from adhering to a rubber wheel of a road roller, and has the main effects that the scattered asphalt mixture which is scattered on the surface of the well base and well cover 700 is prevented from adhering to the well base and well cover 700 and is difficult to remove, and the well base and well cover 700 sinks excessively under the action of the scattered asphalt mixture when the whole rolling is caused and is lower than the designed elevation.
Preferably, with reference to fig. 4, the integral rolling step comprises: when the double-steel-wheel road roller and the rubber-wheel road roller are rolled to the position near the well seat and well cover 700, the double-steel-wheel road roller and the rubber-wheel road roller roll the well seat and well cover 700 along the route opposite to the well seat and well cover 700, the adjacent wheel tracks avoid the position of the well seat and well cover 700, the wheel tracks of the periphery of the well seat and well cover 700 are repeatedly supplemented and rolled along the edge of the well seat and well cover 700 by the small-sized steel-wheel road roller, and the asphalt mixture pushed to the surface of the well seat and well cover 700.
The well base, the well cover 700 and the surrounding asphalt mixture are integrally rolled and formed by a double-steel-wheel road roller and a rubber-wheel road roller, and the compactness is guaranteed. In the rolling process, the asphalt mixture near the periphery of the well is compacted mainly by a small steel wheel road roller, and the running route of the road roller is reasonably organized, so that the rolling wheel inclination phenomenon and the formation of local pits caused by the rigidity difference between the well base and the well cover 700 and the asphalt mixture and the self weight of the road roller can be avoided.
The height of the well seat and well cover 700 can be always kept consistent with the height of the asphalt upper layer 800 by arranging a specially-assigned person to timely shovel off the asphalt mixture on the well seat and well cover 700 by using a shovel, so that the problems of insufficient compactness and poor well periphery flatness are avoided. The operation is simple, no additional auxiliary tool is required to be installed or arranged, and the cost is low.
Referring to fig. 5 and 6, according to another aspect of the present invention, there is provided a transition manhole cover 100 applied to the construction method for compacting the periphery of the asphalt pavement manhole, for covering a manhole shaft 200, wherein the transition manhole cover 100 includes a circular cover plate 110 and a plurality of blocking legs 120 located below the cover plate 110 and uniformly spaced along the circumferential direction of the cover plate 110, and the blocking legs 120 have an arc-shaped outer surface for contacting the manhole shaft 200 to limit horizontal movement of the transition manhole cover 100.
The transition well lid 100 is directly placed on the inspection shaft 200, the cover plate 110 is in surface contact with the inspection shaft 200, the horizontal displacement of the transition well lid 100 is limited by the blocking legs 120, the blocking legs 120 are also in surface contact with the inspection shaft 200 due to the arc-shaped outer surfaces, most of the vertical load of the rolling wheels is directly transmitted to the inspection shaft 200, the horizontal load is transmitted to the inspection shaft 200 by the blocking legs 120 below the cover plate 110, the transition well lid 100 is good in stress, low in deformation probability, high in production efficiency and low in cost, the requirement on the rigidity of the transition well lid 100 is low, and the contradiction between the rigidity and the production efficiency and the production cost can be coordinated.
Preferably, referring to fig. 5, a plurality of reinforcing ribs 121 connected to the leg shield 120 to support the leg shield 120 intersect at the center of the cover plate 110. The reinforcing ribs 121 can reinforce the structural strength of the transition well lid 100, so that the cover plate 110 is not easy to deform, and the blocking legs 120 are not easy to damage.
Preferably, referring to fig. 6, a plurality of handles 130 are provided above the cover plate 110 to facilitate movement of the transit manhole cover 100. Handle 130 may facilitate the covering of transition well lid 100 onto manhole 200 and the removal of transition well lid 100.
Preferably, referring to fig. 6, a nut 131 is sleeved on each end of the handle 130, and the nut 131 is welded to the cover plate 110. The handle 130 can rotate in the hole of the nut 131, so that the handle is convenient to hold by hands, and when the asphalt pavement paving machine is not used, the handle 130 can be tightly attached to the cover plate 110, so that the paving and rolling of the asphalt lower surface layer 400 cannot be influenced.
The construction method for compacting the periphery of the asphalt pavement inspection well and the transitional well cover provided by the invention also have the following advantages:
(1) the paving of the asphalt mixture is completely controlled by the paver, manual material distribution is not needed in the whole process, the total using amount of the asphalt mixture, the paving thickness, the paving uniformity and the paving flatness are easy to control, and the flatness problem caused by the accumulation of local asphalt mixture can be avoided.
(2) The construction method does not need to chiseling or cold milling the formed asphalt surface layer, has simple construction and low machine shift cost.
(3) The construction method has the advantages that the conventional design content is eliminated, a permanent device does not need to be additionally arranged, and the construction cost is low. Meanwhile, each technical measure is simple and convenient to operate, low in cost and free of remarkable influence on construction cost.
The construction method for compacting the periphery of the asphalt pavement inspection well and the construction practice of the transition well cover of the 370 inspection wells of the municipal road engineering of 5.8 kilometers are implemented, and the construction parameters are adjusted and continuously improved by continuously trying and optimizing technical measures, so that the invention is formed. Practical application verifies that the method has good effects on the aspects of engineering cost, cost control of manual machinery, construction period guarantee and the like while improving the flatness of the asphalt surface layer around the inspection well.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (9)

1. A construction method for compacting the periphery of an asphalt pavement inspection well is characterized by comprising the following steps:
the transition well cover covers the inspection shaft;
paving and rolling the lower asphalt surface layer;
taking out the transitional well cover: after the rolling of the lower layer of the asphalt is finished, excavating asphalt mixture on the surface of the transition well cover and in the peripheral range, and taking out the transition well cover;
and (3) reinforcing the periphery of the well seat and the well cover: pouring fine stone concrete at the periphery of a preset installation position of a well seat and a well cover;
installing a well seat and a well cover: installing a well seat and a well lid, and padding the lower part of the well seat and the well lid by using a mortar cushion layer to ensure that the installation elevation of the well seat and the well lid is 3-5 mm higher than the design elevation of the upper asphalt layer;
paving an asphalt upper surface layer: paving an asphalt upper surface layer before the mortar cushion layer is initially set;
and (3) integral rolling: carry out whole to well seat well lid and pitch upper strata and roll, the plasticity of the finite degree when utilizing the near initial set state of mortar, well seat well lid subsides with pitch upper strata together, well seat well lid finally subsides to the design elevation on pitch upper strata and flushes with pitch upper strata, when two steel wheel road rollers roll near well seat well lid with the rubber tyer road roller, roll well seat well lid with just rolling the route to well seat well lid, well seat well lid position is kept away from to adjacent wheel trace, the non-overlapping portion of wheel trace is rolled along well seat well lid edge by small-size steel wheel road roller repeatedly, roll the in-process and clear up the bituminous mixture who is pushed well seat well lid surface repeatedly.
2. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 1,
before the step of rolling the lower layer of the asphalt, the method also comprises the step of inserting a steel bar head into the asphalt mixture to find the position of the transition well cover and marking the position.
3. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 1,
the step of reinforcing the periphery of the well seat and the well lid comprises the following steps: temporarily placing the well seat and the well lid at a preset installation position, sleeving the inner mold steel ring on the periphery of the well seat and the well lid to pour fine aggregate concrete, and taking out the well seat and the inner mold steel ring after the fine aggregate concrete is initially set.
4. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 1,
the step of installing the well seat and the well lid comprises the following steps: and drawing a cross line with the elevation of the flat stone to loft to a preset installation position of the well base and the well lid, and upwards lifting 3-5 mm to control the installation elevation of the well base and the well lid.
5. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 1,
before the step of paving the asphalt upper layer, the method also comprises the steps of covering fiber paper on the surface of the well seat and the well cover and brushing an asphalt separant on the surface of the fiber paper.
6. The construction method for compacting the periphery of the asphalt pavement inspection well according to any one of claims 1 to 5,
the transition well lid (100) includes circular apron (110) and is located apron (110) below is followed a plurality of fender legs (120) that the even interval of circumference of apron (110) set up, keep off leg (120) have be used for contacting with inspection shaft (200) in order to restrict transition well lid (100) horizontal migration's arc surface.
7. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 6,
a plurality of reinforcing ribs (121) connected with the blocking legs (120) to support the blocking legs (120) intersect at the center of the cover plate (110).
8. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 6,
a plurality of handles (130) convenient to move are arranged above the cover plate (110) and are used for the transition well lid (100).
9. The construction method for compacting the periphery of the asphalt pavement inspection well according to claim 8,
two ends of the handle (130) are respectively sleeved with a nut (131), and the nuts (131) are welded on the cover plate (110).
CN201810164453.6A 2018-02-27 2018-02-27 Construction method for compacting periphery of asphalt pavement inspection well and transition well cover Active CN108360328B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810164453.6A CN108360328B (en) 2018-02-27 2018-02-27 Construction method for compacting periphery of asphalt pavement inspection well and transition well cover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810164453.6A CN108360328B (en) 2018-02-27 2018-02-27 Construction method for compacting periphery of asphalt pavement inspection well and transition well cover

Publications (2)

Publication Number Publication Date
CN108360328A CN108360328A (en) 2018-08-03
CN108360328B true CN108360328B (en) 2021-05-07

Family

ID=63003062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810164453.6A Active CN108360328B (en) 2018-02-27 2018-02-27 Construction method for compacting periphery of asphalt pavement inspection well and transition well cover

Country Status (1)

Country Link
CN (1) CN108360328B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685203B (en) * 2019-09-19 2021-04-20 杭州南岳建设工程有限公司 Method for ensuring compactness of periphery of gully of inspection well
CN112647543B (en) * 2021-01-12 2022-04-12 湖北路远建设集团有限公司 Rigid mounting construction method for manhole cover
CN114658039A (en) * 2022-04-18 2022-06-24 日照市政工程有限公司 Inspection well protective cover plate and pavement asphalt laying construction method applying same

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04131407A (en) * 1990-09-22 1992-05-06 Nichireki Chem Ind Co Ltd Method for repairing area around manhole or the like area
JP2007016510A (en) * 2005-07-08 2007-01-25 Hanex Road:Kk Temporary cover for manhole
CN203475479U (en) * 2013-09-18 2014-03-12 南安市方圆水泥制品有限公司 Double-layer dropping and moving prevention well lid
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
CN205369314U (en) * 2016-01-21 2016-07-06 山东泰山抽水蓄能电站有限责任公司 Water level peephole handhole door of conveniently opening and close
CN206408650U (en) * 2016-12-07 2017-08-15 东南(福建)汽车工业有限公司 A kind of cover plate of handle automatic hidden

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04131407A (en) * 1990-09-22 1992-05-06 Nichireki Chem Ind Co Ltd Method for repairing area around manhole or the like area
JP2007016510A (en) * 2005-07-08 2007-01-25 Hanex Road:Kk Temporary cover for manhole
CN203475479U (en) * 2013-09-18 2014-03-12 南安市方圆水泥制品有限公司 Double-layer dropping and moving prevention well lid
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
CN205369314U (en) * 2016-01-21 2016-07-06 山东泰山抽水蓄能电站有限责任公司 Water level peephole handhole door of conveniently opening and close
CN206408650U (en) * 2016-12-07 2017-08-15 东南(福建)汽车工业有限公司 A kind of cover plate of handle automatic hidden

Also Published As

Publication number Publication date
CN108360328A (en) 2018-08-03

Similar Documents

Publication Publication Date Title
CN108360328B (en) Construction method for compacting periphery of asphalt pavement inspection well and transition well cover
CN109972659B (en) Novel municipal inspection well structure and construction method
CN104695300B (en) The technique of a kind of bituminous paving inspection shaft lifting and lift structure thereof
CN107761501A (en) A kind of road construction method
CN110295628A (en) A kind of pavement construction method with inspection shaft
CN105421571A (en) Sewer well and rainwater well construction process
CN112796346A (en) Anti-settling well lid construction method
CN116815733A (en) Construction process for quality control of high-fill roadbed in collapsible loess area
TWI691632B (en) Longitudinal trench forming equipment for paving, paving construction method and construction evaluation method of asphalt paving
CN112647543B (en) Rigid mounting construction method for manhole cover
CN204435151U (en) A kind of flexible pavement manhole lift structure
CN110804939A (en) Reinforced structure of abutment jump car
RU2256747C2 (en) Method for forming interface between bridge roadway and embankment
CN115030224A (en) Municipal road inspection well and construction method thereof
CN210013101U (en) Highway basic level step type fluting restoration structure
CN111926649A (en) Reinforced integrally-built crossing plate for railway special line and line rail fixing device
CN204676387U (en) A kind of cement concrete pavement becomes base layer structure
CN220079604U (en) Roadbed edge protection mechanism
CN116084541A (en) Rain grate, and mounting structure and method for same
CN212505689U (en) Reinforced integrally-built crossing plate for railway special line and line rail fixing device
CN219327111U (en) Anti-sedimentation manhole cover installation matching device
CN113882204B (en) High-fill embankment filling construction process
CN113463691A (en) Method for installing anti-settling well cover of newly-built road
JP4954934B2 (en) Gutter block
CN215759173U (en) UHPC reinforced structure is sewed up to road well lid limit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant