CN108343251A - A kind of continuance lifting method without bearing large space Steel Truss Beam - Google Patents

A kind of continuance lifting method without bearing large space Steel Truss Beam Download PDF

Info

Publication number
CN108343251A
CN108343251A CN201810433073.8A CN201810433073A CN108343251A CN 108343251 A CN108343251 A CN 108343251A CN 201810433073 A CN201810433073 A CN 201810433073A CN 108343251 A CN108343251 A CN 108343251A
Authority
CN
China
Prior art keywords
steel
truss beam
steel truss
cross bar
hoisting frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810433073.8A
Other languages
Chinese (zh)
Inventor
宋林
徐国友
孙刚
张望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201810433073.8A priority Critical patent/CN108343251A/en
Publication of CN108343251A publication Critical patent/CN108343251A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for

Abstract

The invention discloses a kind of continuance lifting methods without bearing large space Steel Truss Beam, include the following steps:1)Design hoisting frame structure and intensity;2)Make hoisting frame;3)Pre-plugged pre-embedded steel slab and connection bolt, are arranged bearing on pre-embedded steel slab;4)Two hoisting frames are installed respectively on pre-embedded steel slab;5)One centre-hole jack is installed in hoisting frame;6)The steel strand in centre-hole jack;7)Master station and pumping plant is respectively set on the top of two towers or column;8)The lower end of steel strand wires is fixedly connected with Steel Truss Beam;9)The both ends of Steel Truss Beam are connected by connecting plate with bearing respectively;10)It repeats the above steps, is completed until all Steel Truss Beams lift.The present invention can carry out the fast hoisting construction of Steel Truss Beam in narrow space and large span large space, easy for construction, and safety and reliability higher, economy are more preferable.

Description

A kind of continuance lifting method without bearing large space Steel Truss Beam
Technical field
The present invention relates to technical field of building construction more particularly to a kind of continuously carrying without bearing large space Steel Truss Beam Lifting method.
Background technology
With the quick steady-state growth of national economic development, infrastructure construction is greatly developed, in recent years long-span bridge Beam is built quantity and is continuously increased, and the asd number of large span venue is also continuously increased, and H is designed as certain Cable stayed Bridge Main Towers Type, king-post bottom end rail are generally prestressed concrete box beams, and upper beam is typically designed as large space Steel Truss Beam, and upper cross Beam is in construction, it is difficult to provide enough construction sites, lower part is without bearing, and lifting condition is poor, it is difficult to using conventional lifting side Method;Meanwhile for the narrow large span venue in certain construction sites or with basement, grandstand, periphery soil body backfill amount is big, Large-scale crane can not march into the arena, and the lifting construction difficulty for also resulting in Steel Truss Beam is very big.
Invention content
It is difficult it is an object of the invention to solve the lifting of large space Steel Truss Beam for deficiencies of the prior art Degree is big, construction trouble, and safety and reliability is low, less economical problem, provides a kind of without bearing large space steel truss The continuance lifting method set a roof beam in place, the fast hoisting that Steel Truss Beam can be carried out in narrow space and large span large space are applied Work, it is easy for construction, and safety and reliability higher, economy are more preferable.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is such:It is a kind of without bearing large space The continuance lifting method of Steel Truss Beam, it is characterised in that:Include the following steps:
1)The force analysis of hoisting frame in two lifting process of steel truss is carried out according to the structure of Steel Truss Beam, weight, then basis The force analysis result designs hoisting frame structure and intensity;
2)According to step 1)The hoisting frame of design makes hoisting frame, which has fixing end and overhanging end;
3)In the top pre-plugged pre-embedded steel slab and connection bolt of two towers or column that need to install Steel Truss Beam, on pre-embedded steel slab Bearing for being connected with Steel Truss Beam is set;
4)Two hoisting frames are installed respectively on pre-embedded steel slab, two hoisting frames and pass through support respectively close to the both sides of pre-embedded steel slab Truss is connected with pre-embedded steel slab;Wherein, hoisting frame overhangs end and is stretched out from the side of tower or column, and the hoisting frame on two towers or column Overhanging end is located at two towers or the adjacent side of column;
5)One centre-hole jack is installed respectively at the overhanging end of each hoisting frame, limit is set between jack and hoisting frame Moveable anchor is arranged in device, the upper end;
6)Several steel strand wires are worn in each centre-hole jack, wherein the upper end of steel strand wires sequentially passes through limit from bottom to up Position device, centre-hole jack and moveable anchor, lower end extend downward into the lower end of tower or column;
7)Master station and pumping plant is respectively set on the top of two towers or column, coordinates pumping plant to same tower or top end by master station 2 centre-hole jacks controlled;Then, to 4 centre-hole jack zero load joint-trials, make 4 centre-hole jacks Promote speed sync;
8)The lower end of steel strand wires in a wherein tower or the centre-hole jack of column upper end and one end of Steel Truss Beam are fixed and connected It connects, the lower end of the steel strand wires in the centre-hole jack of another tower or column upper end is fixedly connected with the other end of Steel Truss Beam, so Pumping plant is coordinated to carry out the promotion operation of Steel Truss Beam by master station afterwards, in lifting process, it is ensured that the both ends of Steel Truss Beam synchronize Rise, until Steel Truss Beam is promoted to the top of tower or column;
9)The both ends of Steel Truss Beam are connected by connecting plate with bearing respectively, and are fixedly connected by way of bolt weldering;
10)It repeats the above steps, is completed until all Steel Truss Beams lift.
Further, in step 2, the hoisting frame includes horizontally disposed H profile steel cross bar, one end of the H profile steel cross bar For fixing end, the other end is overhanging end;It is equipped with a compression montant, the lower end of the compression montant and H-type vertically on H profile steel cross bar Steel cross bar is fixedly connected, and the distance between the lower end of compression montant and the fixing end of H profile steel cross bar are more than itself and H profile steel cross bar The distance between overhanging end;It is respectively equipped with fixing end tension diagonal and overhanging end tension diagonal in the both sides of compression montant;Its In, the upper end of fixing end tension diagonal is fixedly connected with the upper end of compression montant, and lower end is inclined to the fixation extreme direction of H profile steel cross bar Tiltedly, and with H profile steel cross bar it is fixedly connected;The upper end of overhanging end tension diagonal is fixedly connected with the upper end of compression montant, and lower end is to H The overhanging extreme direction of shaped steel cross bar tilts, and is fixedly connected with H profile steel cross bar;It is fixed in the upside at the overhanging end of H profile steel cross bar There is jack chassis;The centre-hole jack is installed on the jack chassis
Further, between H profile steel cross bar and fixing end tension diagonal and between H profile steel cross bar and overhanging end tension diagonal It is distributed with reinforced pull rod that is vertical and being obliquely installed.
Further, safe anchor slab is additionally provided on hoisting frame;Steel Truss Beam is promoted to after the top of tower or column, steel strand wires It is fixedly connected with the safe anchor slab.
Further, a hinged seat is additionally provided on pre-embedded steel slab;The hinged seat include plate supported on both sides and be located at two Articulated slab between fagging, the articulated slab are rotatablely connected by bearing and two support plates;The both ends of the Steel Truss Beam are Inclined-plane after Steel Truss Beam is connected with bearing, then articulated slab and Steel Truss Beam is welded together.
Compared with prior art, the invention has the advantages that:
1, hoisting frame is simple in structure, mainly by the enough H profile steels of stress intensity(I-steel)Welding is formed, to make processing side Just, stability is good, and reliability is high, and of low cost;Large-scale crane is substituted using the hoisting frame to lift by crane, good economy performance.
2, by the way that the promotion that hoisting frame carries out Steel Truss Beam is arranged in tower or capital, the scope of application is wider, can be easily It is big that big large span venue roofing, large span are measured suitable for city narrow space, basement, grandstand or periphery soil body backfill The promotion of type Steel Space Truss beam;It solves certain Cable stayed Bridge Main Towers and is designed as H-type, in upper beam construction, it is difficult to which foot is provided Enough construction sites, lower part promote problem in place without bearing, the upper beam of lifting condition difference.
3, easy to operate, only need in advance in tower(Column)Upper end pre-plugged pre-embedded steel slab, then set on pre-embedded steel slab Hoisting frame is set, and hoisting frame is connected by logical sub-truss with the pre-embedded steel slab;In this way, passing through two towers(Column)The hoisting frame of upper end and Centre-hole jack on hoisting frame, then coordinate and draw anchor device and control system etc., it will be able to realization directly carries Steel Truss Beam It rises, efficiently solves certain Cable stayed Bridge Main Towers and be designed as H-type, in upper beam construction, it is difficult to enough construction sites are provided, under Portion promotes problem in place without bearing, the upper beam of lifting condition difference, and construction efficiency is high.
4, more convenient to use, reuse easy to remove can take hoisting frame after the completion of a steel truss two promotion Under, it is moved to the promotion for repeating Steel Truss Beam elsewhere.
Description of the drawings
Fig. 1 is the attachment structure schematic diagram of hoisting frame and sub-truss and pre-embedded steel slab.
Fig. 2 is the schematic diagram promoted using this hoisting frame.
Fig. 3 is a wherein tower or the vertical view of top end in Fig. 2.
In figure:1-H profile steel cross bar, 2-compression montants, 3-fixing end tension diagonals, 4-overhanging end tension diagonals, 5- Jack chassis, 6-centre-hole jacks, 7-reinforced pull rods, 8-sub-trusses, 9-pre-embedded steel slabs, 10-bearings, 11- Tower or column, 12-steel strand wires, 13-Steel Truss Beams, 14-connecting rods.
Specific implementation mode
Present invention will be further explained below with reference to the attached drawings and examples.
Embodiment:Referring to Fig. 1, Fig. 2 and Fig. 3, a kind of continuance lifting method without bearing large space Steel Truss Beam, packet Include following steps:
1)The force analysis of hoisting frame in two lifting process of steel truss is carried out according to the structure of Steel Truss Beam 13, weight, then root Hoisting frame structure and intensity are designed according to the force analysis result.
2)According to step 1)The hoisting frame of design makes hoisting frame, which has fixing end and overhanging end.Wherein, institute It includes horizontally disposed H profile steel cross bar 1 to state hoisting frame, and one end of the H profile steel cross bar 1 is fixing end, and the other end is overhanging end. A compression montant 2 is equipped on H profile steel cross bar 1 vertically, the lower end of the compression montant 2 is fixedly connected with H profile steel cross bar 1, and is pressurized The distance between the lower end of montant 2 and the fixing end of H profile steel cross bar 1 be more than between its overhanging end H profile steel cross bar 1 away from From.It is respectively equipped with fixing end tension diagonal 3 and overhanging end tension diagonal 4 in the both sides of compression montant 2;In H profile steel cross bar 1 and admittedly It is distributed with vertically and is obliquely installed between fixed end tension diagonal 3 and between H profile steel cross bar 1 and overhanging end tension diagonal 4 Reinforced pull rod 7.Wherein, the upper end of fixing end tension diagonal 3 is fixedly connected with the upper end of compression montant 2, and lower end is to H profile steel cross bar 1 fixation extreme direction tilts, and is fixedly connected with H profile steel cross bar 1;The upper end of overhanging end tension diagonal 4 is upper with compression montant 2 End is fixedly connected, and lower end is tilted to the overhanging extreme direction of H profile steel cross bar 1, and is fixedly connected with H profile steel cross bar 1.In H profile steel cross It is fixed with jack chassis 5 on the upside of the overhanging end of bar 1;The centre-hole jack 6 is installed on the jack chassis 5
3)In the top pre-plugged pre-embedded steel slab 9 and connection bolt of two towers or column 11 that need to install Steel Truss Beam 13, pre-buried Bearing 10 for being connected with Steel Truss Beam 13 is set on steel plate 9.
4)Two hoisting frames are installed respectively on pre-embedded steel slab 9, two hoisting frames and lead to respectively close to the both sides of pre-embedded steel slab 9 Sub-truss 8 is crossed with pre-embedded steel slab 9 to be connected;Wherein, hoisting frame overhangs end and is stretched out from the side of tower or column 11, and two towers or column 11 On the overhanging end of hoisting frame be located at two towers or the adjacent side of column 11.When practice of construction, two hoisting frames are passed through into connecting rod 14 are connected, to improve the intensity and connective stability of two hoisting frames.
5)One centre-hole jack 6 is installed respectively at the overhanging end of each hoisting frame, is arranged between jack and hoisting frame Moveable anchor is arranged in limiter, the upper end.
6)Several steel strand wires 12 are worn in each centre-hole jack 6, wherein the upper end of steel strand wires 12 from bottom to up according to Secondary to pass through limiter, centre-hole jack 6 and moveable anchor, lower end extends downward into the lower end of tower or column 11.
7)Master station and pumping plant is respectively set on the top of two towers or column 11, coordinate pumping plant to same tower by master station or 2 centre-hole jacks 6 on 11 top of column are controlled;Then, to the unloaded joint-trial of 4 centre-hole jacks 6, make 4 punchings The promotion speed sync of formula jack 6.
8)By the lower end of the steel strand wires 12 in the centre-hole jack 6 of 11 upper end of a wherein tower or column and Steel Truss Beam 13 One end is fixedly connected, lower end and the Steel Truss Beam 13 of the steel strand wires 12 in the centre-hole jack 6 of 11 upper end of another tower or column The other end is fixedly connected;Then pumping plant is coordinated to carry out the promotion operation of Steel Truss Beam 13 by master station, in lifting process, it is ensured that The both ends of Steel Truss Beam 13, which synchronize, to be risen;Until Steel Truss Beam 13 promotes the top to tower or column 11, the i.e. upside of steel truss two Face reaches the position that can be connected with bearing 10.When practice of construction, safe anchor slab is additionally provided on hoisting frame;Steel Truss Beam 13 carries After being raised to the top of tower or column 11, steel strand wires 12 are fixedly connected with the safe anchor slab.
9)The both ends of Steel Truss Beam 13 pass through respectively(At least one)Connecting plate is connected with bearing 10, also, Steel Truss Beam 13 It is fixedly connected with the connecting plate by way of bolt weldering with bearing 10;
During practice of construction, a hinged seat is additionally provided on pre-embedded steel slab 9;The hinged seat include plate supported on both sides and be located at two Articulated slab between support plate, the articulated slab pass through bearing(And the cooperation of shaft)It is rotatablely connected with two support plates.The steel The both ends of girder truss 13 are inclined-plane, after Steel Truss Beam 13 is connected with bearing 10, then articulated slab and Steel Truss Beam 13 are welded on Together.Wherein, in 13 lifting process of Steel Truss Beam, articulated slab is turned to away from the side of Steel Truss Beam 13, waits for steel truss After two are connected with bearing 10, it is rotated further by articulated slab, articulated slab is made to be bonded with Steel Truss Beam 13, and by articulated slab and Steel Truss Beam 13 Weld together, to further being supported to Steel Truss Beam 13, effectively promotes the stability and reliably of Steel Truss Beam 13 Property.
10)It repeats the above steps, is completed until all Steel Truss Beams 13 lift.
Finally, it should be noted that technical side the above examples are only used to illustrate the technical scheme of the present invention and are not limiting Case, it will be understood by those of ordinary skill in the art that, those are modified or replaced equivalently technical scheme of the present invention, and The objective and range for not departing from the technical program, are intended to be within the scope of the claims of the invention.

Claims (5)

1. a kind of continuance lifting method without bearing large space Steel Truss Beam, it is characterised in that:Include the following steps:
1)The force analysis of hoisting frame in two lifting process of steel truss is carried out according to the structure of Steel Truss Beam, weight, then basis The force analysis result designs hoisting frame structure and intensity;
2)According to step 1)The hoisting frame of design makes hoisting frame, which has fixing end and overhanging end;
3)In the top pre-plugged pre-embedded steel slab and connection bolt of two towers or column that need to install Steel Truss Beam, on pre-embedded steel slab Bearing for being connected with Steel Truss Beam is set;
4)Two hoisting frames are installed respectively on pre-embedded steel slab, two hoisting frames and pass through support respectively close to the both sides of pre-embedded steel slab Truss is connected with pre-embedded steel slab;Wherein, hoisting frame overhangs end and is stretched out from the side of tower or column, and the hoisting frame on two towers or column Overhanging end is located at two towers or the adjacent side of column;
5)One centre-hole jack is installed respectively at the overhanging end of each hoisting frame, limit is set between jack and hoisting frame Moveable anchor is arranged in device, the upper end;
6)Several steel strand wires are worn in each centre-hole jack, wherein the upper end of steel strand wires sequentially passes through limit from bottom to up Position device, centre-hole jack and moveable anchor, lower end extend downward into the lower end of tower or column;
7)Master station and pumping plant is respectively set on the top of two towers or column, coordinates pumping plant to same tower or top end by master station 2 centre-hole jacks controlled;Then, to 4 centre-hole jack zero load joint-trials, make 4 centre-hole jacks Promote speed sync;
8)The lower end of steel strand wires in a wherein tower or the centre-hole jack of column upper end and one end of Steel Truss Beam are fixed and connected It connects, the lower end of the steel strand wires in the centre-hole jack of another tower or column upper end is fixedly connected with the other end of Steel Truss Beam, so Pumping plant is coordinated to carry out the promotion operation of Steel Truss Beam by master station afterwards, in lifting process, it is ensured that the both ends of Steel Truss Beam synchronize Rise, until Steel Truss Beam is promoted to the top of tower or column;
9)The both ends of Steel Truss Beam are connected by connecting plate with bearing respectively, and are fixedly connected by way of bolt weldering;
10)It repeats the above steps, is completed until all Steel Truss Beams lift.
2. a kind of continuance lifting method without bearing large space Steel Truss Beam according to claim 1, it is characterised in that: In step 2, the hoisting frame includes horizontally disposed H profile steel cross bar, and one end of the H profile steel cross bar is fixing end, and the other end is Overhang end;It is equipped with a compression montant vertically on H profile steel cross bar, the lower end of the compression montant is fixedly connected with H profile steel cross bar, and The distance between the lower end of compression montant and the fixing end of H profile steel cross bar be more than between its overhanging end H profile steel cross bar away from From;It is respectively equipped with fixing end tension diagonal and overhanging end tension diagonal in the both sides of compression montant;Wherein, fixing end tension diagonal Upper end be fixedly connected with the upper end of compression montant, lower end to the fixation extreme direction of H profile steel cross bar tilt, and with H profile steel cross bar It is fixedly connected;The upper end of overhanging end tension diagonal is fixedly connected with the upper end of compression montant, and lower end is to the overhanging end of H profile steel cross bar Direction tilts, and is fixedly connected with H profile steel cross bar;It is fixed with jack chassis on the upside of the overhanging end of H profile steel cross bar;It is described Centre-hole jack is installed on the jack chassis.
3. a kind of continuance lifting method without bearing large space Steel Truss Beam according to claim 2, it is characterised in that: It is vertical to be distributed between H profile steel cross bar and fixing end tension diagonal and between H profile steel cross bar and overhanging end tension diagonal With the reinforced pull rod being obliquely installed.
4. a kind of continuance lifting method without bearing large space Steel Truss Beam according to claim 2, it is characterised in that: Safe anchor slab is additionally provided on hoisting frame;Steel Truss Beam is promoted to after the top of tower or column, and steel strand wires are fixed with the safe anchor slab Connection.
5. a kind of continuance lifting method without bearing large space Steel Truss Beam according to claim 1, it is characterised in that: A hinged seat is additionally provided on pre-embedded steel slab;The hinged seat includes plate supported on both sides and the articulated slab between two support plates, The articulated slab is rotatablely connected by bearing and two support plates;The both ends of the Steel Truss Beam are inclined-plane, Steel Truss Beam and branch After seat is connected, then articulated slab and Steel Truss Beam welded together.
CN201810433073.8A 2018-05-08 2018-05-08 A kind of continuance lifting method without bearing large space Steel Truss Beam Pending CN108343251A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810433073.8A CN108343251A (en) 2018-05-08 2018-05-08 A kind of continuance lifting method without bearing large space Steel Truss Beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810433073.8A CN108343251A (en) 2018-05-08 2018-05-08 A kind of continuance lifting method without bearing large space Steel Truss Beam

Publications (1)

Publication Number Publication Date
CN108343251A true CN108343251A (en) 2018-07-31

Family

ID=62955490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810433073.8A Pending CN108343251A (en) 2018-05-08 2018-05-08 A kind of continuance lifting method without bearing large space Steel Truss Beam

Country Status (1)

Country Link
CN (1) CN108343251A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439249A (en) * 2022-04-07 2022-05-06 中铁建工集团有限公司 Construction method for lifting large-span triangular truss through air swivel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094389A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Separable large-section truss girder hydraulic lifting device
CN203462764U (en) * 2013-08-20 2014-03-05 浙江精工钢结构集团有限公司 Large cantilever promotion counter-force frame
CN205012666U (en) * 2015-09-17 2016-02-03 浙江中成建工集团有限公司 High altitude steel construction vestibule integrally lift up support structure
CN205637619U (en) * 2016-04-07 2016-10-12 中建六局第三建筑工程有限公司 No post steel construction pipe truss hanging device of underground big space of large -span superelevation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094389A (en) * 2009-12-14 2011-06-15 上海市基础工程有限公司 Separable large-section truss girder hydraulic lifting device
CN203462764U (en) * 2013-08-20 2014-03-05 浙江精工钢结构集团有限公司 Large cantilever promotion counter-force frame
CN205012666U (en) * 2015-09-17 2016-02-03 浙江中成建工集团有限公司 High altitude steel construction vestibule integrally lift up support structure
CN205637619U (en) * 2016-04-07 2016-10-12 中建六局第三建筑工程有限公司 No post steel construction pipe truss hanging device of underground big space of large -span superelevation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439249A (en) * 2022-04-07 2022-05-06 中铁建工集团有限公司 Construction method for lifting large-span triangular truss through air swivel

Similar Documents

Publication Publication Date Title
CN106948268B (en) Variable-section steel box girder pushing combined device and using method thereof
CN103669224A (en) Method and steel pipe support for construction of arch tower of inclined arch tower double-cable-plane prestressed concrete cable-stayed bridge
CN209114332U (en) A kind of long big section bent cap bracket system of overhanging
CN113585075A (en) Cast-in-place bridge deck formwork for steel-concrete composite beam
CN203613467U (en) Steel pipe bracket for construction of arch tower in oblique arch tower double-cable plane pre-stressed concrete cable-stayed bridge
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN102659027A (en) Variable-span transit method for girder-erecting gantry crane
CN108343251A (en) A kind of continuance lifting method without bearing large space Steel Truss Beam
CN219175013U (en) Whole support that moves down of double-deck overhead bridge
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
CN208502273U (en) It is a kind of for without bearing large space Steel Truss Beam hoisting frame
CN207987749U (en) Ride cable-styled erection crane
CN115341701A (en) High-altitude overhanging steel bar truss floor support plate hanging formwork construction method
CN214117597U (en) Connecting joint of existing concrete column and heightened steel column
CN213233106U (en) Arch ring support
CN206319622U (en) A kind of roof system steel truss sliding rail
CN220431975U (en) Super-high adhesion structure of construction elevator
CN206844680U (en) Steel vestibule installation on ground load transfer device
CN211547346U (en) Formwork system for construction of inclined cable tower
CN206655139U (en) Wavelike steel webplate SCC engineering methods hang movable hanging basket with car convolution
CN216193962U (en) Track foundation reinforcing structure of water gantry crane
CN218406383U (en) Super high-rise truss type cantilever formwork support device
CN216275238U (en) Anti-overturning stable high pier column beam-lifting machine
CN219490682U (en) Basket hanging device for prestress construction of light T-pier cantilever cap beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180731

RJ01 Rejection of invention patent application after publication