CN108331584A - Earthwork digging method under a kind of pipe curtain - Google Patents

Earthwork digging method under a kind of pipe curtain Download PDF

Info

Publication number
CN108331584A
CN108331584A CN201711481446.0A CN201711481446A CN108331584A CN 108331584 A CN108331584 A CN 108331584A CN 201711481446 A CN201711481446 A CN 201711481446A CN 108331584 A CN108331584 A CN 108331584A
Authority
CN
China
Prior art keywords
support
area
described piece
soil body
frost wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711481446.0A
Other languages
Chinese (zh)
Other versions
CN108331584B (en
Inventor
张阿晋
王新新
陈峰军
孙廉威
程子聪
周泉吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN201711481446.0A priority Critical patent/CN108331584B/en
Publication of CN108331584A publication Critical patent/CN108331584A/en
Application granted granted Critical
Publication of CN108331584B publication Critical patent/CN108331584B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Abstract

Earthwork digging method under a kind of pipe curtain of the present invention, is related to underground engineering construction technical field.For there are problems that complicated construction technique, security risk are more in existing soft clay area pipe-roof method work progress, be affected to top soil disturbance.Steps are as follows:Grating type frozen construction is implemented to the soil body below pipe curtain, excavates the soil body in block area one and block area two successively to jump storehouse digging mode, supporting apparatus is installed between the top and bottom frost wall in block area;Excavate the soil body among the frost wall of top and support one is installed;Excavate the top frost wall both sides residue soil body, is supporting both sides installation support two respectively, making to offset with support two at the top of supporting apparatus;Excavate the side frost wall between block area one and block area two, and the installation support three between two neighboring support two, integral horizontally-supported of support one, support two and three connection of support;Gradually implement earth excavation and Construction of Supporting along the length direction of pipe curtain repeatedly.

Description

Earthwork digging method under a kind of pipe curtain
Technical field
The present invention relates to underground engineering construction technical field, more particularly to a kind of pipe considering soil body composite support effect The lower earthwork digging method of curtain.
Background technology
Pipe-roof method is a kind of novel shallow mining method technology, its Construction Principle is the profit between starting well and received well With pipe jacking equipment by the steel pipe jacking soil body, connect to forming pipe row by fore shaft between each steel pipe, and water-stop is injected in fore shaft gap To reach sealing requirement, then, underground structure is applied under the protection of pipe curtain.
In the pipe-roof method work progress of soft clay area, pipe-roof method is mostly combined with box culvert jacking construction technique, in box culvert knot Structure successively jacking while, by the supporting role of box culvert structure, gradually dig out the soil body in box culvert structure, be finally completed pushing tow Construction of replacing;Either by the supporting role of arch tube curtain, interim branch is combined in the way of the earthwork partial excavation such as benching tunnelling method Support system completes earth excavation operation under pipe curtain.The working procedure that pipe-roof method is combined with box culvert jacking construction technique is more numerous Trivial, incremental launching construction complex process, security risk is more;The earth excavation technique of arch tube curtain combination temporary support system, for soft Native regional adaptability is poor, moreover, arch tube curtain wastes construction space, it is larger to the disturbing influence of necromancer body thereon.
Invention content
For in existing soft clay area pipe-roof method work progress there are complicated construction technique, security risk it is more, to upper necromancer The larger problem of body disturbing influence.The object of the present invention is to provide earthwork digging methods under a kind of pipe curtain, to being waited out below pipe curtain Excavator body takes grating type frozen construction, and combines and jump storehouse method and implement earth excavation construction successively, is utilized and existing freezes the soil body Supporting role, reduce disturbing influence caused by adjacent soil excavation, and avoid dangerous caused by the unordered excavation of the soil body Hidden danger.
The technical solution adopted by the present invention to solve the technical problems is:Earthwork digging method under a kind of pipe curtain, step is such as Under:
S1:Grating type frozen construction is implemented to the soil body below pipe curtain, the soil body below the pipe curtain is divided into grid-like Several block areas, are spaced piece of area one and block area two, and described piece of one soil body of area is not freeze the soil body, described piece of area two The soil body is to freeze the soil body, and frost wall is formed behind described piece of area one and described piece of two surrounding freezing soil of area, calculates analysis and determines institute The size of the excavation size and described piece of area one and described piece of two surrounding frost wall of area in the areas Shu Kuai one and described piece of area two;
S2:Excavated in described piece of area one with to jump storehouse digging mode and does not freeze the soil body, the top frost wall in described piece of area one Supporting apparatus is installed between the frost wall of bottom, then, then excavates the soil for being restored to non-frozen state in described piece of area two Body installs supporting apparatus between the top frost wall and bottom frost wall in described piece of area two;
S3:Excavate the position soil body among described piece of area one and described piece of two top frost wall of area and installs horizontally disposed Support one, one bottom of the support is by perpendicular affixed interim strut support in bottom frost wall;
S4:The remaining soil body for excavating two top frost wall both sides of described piece of area one and described piece of area, respectively in the support The horizontally disposed support two of one both sides installation, and the support one and the support two are affixed, make the supporting apparatus Top offsets with the support two, removes the interim strut;
S5:Excavate the side frost wall between described piece of area one and described piece of area two, and in the two neighboring support two Between installation support three, and the support one, support two and support three are connected into the horizontally-supported of entirety;
S6:Step S2 to S5 is repeated, the length direction along the pipe curtain gradually implements earth excavation and Construction of Supporting.
Preferably, in the step S2, the supporting apparatus includes by least four montants and being connected to adjacent two The chassis body that diagonal brace between montant described in root is constituted, described piece of area one or institute are installed on along the length direction of the pipe curtain A pair of of sliding rail on two bottom frost wall of the areas Shu Kuai, and at least four sliding supports of the montant bottom are connected to, The groove of the sliding support matches with the sliding rail.
Preferably, in the step S2, first freeze in described piece of area one, the top frost wall in described piece of area two and bottom At least four montants are installed between wall, after the step S4 all excavates the top frost wall and installs the support two, Diagonal brace is assembled between adjacent two montants to constitute chassis body, and the montant top is made to offset with the support two.
Preferably, in the step S6, along the pipe curtain length direction setting two neighboring described piece of area sliding rail it Between be threadedly coupled.
Preferably, it in the step S4, is respectively mounted at the top of every montant of the supporting apparatus there are one vertical position Compensation device is moved, the vertical displacement compensation device includes hydraulic cylinder, support base, mandril, at least two supporting racks, at least two A latch segment, at least two self-locking oil cylinders and PLC control unit, the piston rod of one end of the mandril and the hydraulic cylinder It is bolted, the other end of the mandril and the bottom of the support two offset, and the support base is sheathed on the outside of the mandril And be bolted with the hydraulic cylinder, at least two support frames as described above are distributed in the support base outer wall and affixed, each described A self-locking oil cylinder is respectively mounted on supporting rack, one end of the self-locking oil cylinder and the end plate of support frame as described above are hinged, the self-locking The other end of oil cylinder and semicircular latch segment pin connection, two latch segments are oppositely arranged and are sheathed on outside the mandril Side, the guide groove of the latch segment inner wall and the card tooth of the mandril outer wall are intermeshed, and displacement sensing is equipped in the hydraulic cylinder Device, and institute's displacement sensors are connect with the PLC control unit signal;When the vertical displacement compensation device and the branch When the gap of support two is excessive, signal is fed back to the P LC control units, the PLC control unit hair by institute's displacement sensors Going out instruction makes the piston rod of the hydraulic cylinder stretch out so that self-locking after the mandril is moved up and offseted with the support two; When the vertical displacement compensation device and the too small gap of the support two, the PLC control unit send out instruction make it is described The piston rod of hydraulic cylinder is shunk so that self-locking after the mandril is moved down and offseted with the support two.
Effect of the invention is that:Earthwork digging method under the pipe curtain of the present invention considers soil body composite support effect It answers, grating type frozen construction is taken to the soil body to be excavated below pipe curtain, and jump storehouse method is combined to implement earth excavation construction successively, The existing supporting role for freezing the soil body is maximally utilised, the stress of supporting apparatus can be reduced, has reduced it and support structure The area of section of part so that Construction of Supporting is physically easier to perform;Storehouse method is jumped while realizing continuous productive process, reduces adjacent soil Disturbing influence caused by body excavates ensure that the stability that earth excavation is constructed in small space under the pipe curtain of soft clay area, avoid Hidden danger caused by the soil body unordered excavation.
Description of the drawings
Fig. 1 to Fig. 6 be one embodiment of the invention pipe curtain under each construction procedure of earthwork digging method schematic diagram;
Fig. 7 is the structural schematic diagram of the vertical displacement compensation device of one embodiment of the invention.
Figure label is as follows:
Block area 1;Block area 22;Pipe curtain 10;Underground exterior-protected structure 11;Sliding rail 21;Sliding support 22;Montant 23;It is horizontal Support 24;Support a 24a;Support two 24b;Support three 24c;Interim strut 25;Diagonal brace 26;Top frost wall 32;Freeze bottom Wall 31;Side frost wall 33;
Vertical displacement compensation device 27;Hydraulic cylinder 271;Support base 272;Mandril 273;Supporting rack 274;End plate 275;From Lock oil cylinder 276;Latch segment 277.
Specific implementation mode
Earthwork digging method under a kind of pipe curtain proposed by the present invention is made below in conjunction with the drawings and specific embodiments further It is described in detail.According to following explanation and claims, advantages and features of the invention will become apparent from.It should be noted that attached Figure is all made of very simplified form and uses non-accurate ratio, only to convenient, lucidly the aid illustration present invention is real Apply the purpose of example.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this cannot As the limitation of technical solution of the present invention.
The present embodiment combination freezing process and jump storehouse method are constructed, and freezing process is will underground space surrounding soil be excavated In water freeze as ice and freeze the soil body with what the soil body was glued together into design profile, to resist soil pressure and every Exhausted underground water freezes the soil body and creates good carrying and sealing performance, and for the underground space service for constructing new, construction is completed Afterwards, freezing pipe is pulled out as needed, and non-frozen state will be gradually restored to by freezing the soil body.Jump storehouse method is will underground sky be excavated Between be divided into several block areas, and in such a way that interval is constructed, while realizing continuous productive process reducing the adjacent soil body opens Disturbing influence caused by digging.
Illustrate earthwork digging method under a kind of pipe curtain of the present invention with reference to Fig. 1 to Fig. 6, is as follows:
S1:Excavate the active well of pipe curtain to be onstructed region both sides, i.e. starting well and received well (not shown), construction The underground exterior-protected structure 11 in pipe curtain to be onstructed region applies pipe curtain 10 again;Implement grating type to the 10 lower section soil body of pipe curtain to freeze to apply The 10 lower section soil body of pipe curtain is divided into several grid-like block areas by work, i.e. spaced piece of one 1 He of area as shown in Fig. 1 Block area 22, one 1 soil body of block area are not freeze the soil body, and 22 soil body of block area is to freeze the soil body, block area 1 and 22 surrounding of block area soil Body forms frost wall after freezing, calculate and analyze the excavation size for determining block area 1 and block area 22 and block area 1 and block area The size of 22 surrounding frost walls;
S2:As shown in Fig. 2, using storehouse excavation construction process is jumped, do not freeze the soil body in first exploded slice area 1, in block area one Supporting apparatus is installed between 1 top frost wall 32 and bottom frost wall 31, then, as shown in figure 3, pulling out block area 22 Freezing pipe, then the soil body that non-frozen state is restored in block area 22 is excavated, in the top frost wall 32 in block area 22 and bottom Supporting apparatus is installed between frost wall 31;
S3:As shown in figure 4, under the supporting role of supporting apparatus, excavates block area 1 and 22 top of block area is freezed The 32 intermediate position soil body of wall simultaneously installs one 24a of horizontally disposed support, and one bottoms 24a of support are faced by perpendicular affixed When strut 25 be supported in bottom frost wall 31;
S4:As shown in figure 5, excavating the remaining soil body of 32 both sides of block area 1 and 22 top frost wall of block area, propping up respectively The both sides 24a installation two 24b of horizontally disposed support are supportted, and support a 24a and two 24b of support affixed, make supporting apparatus Top with support two 24b offset, remove interim strut 25;
S5:As shown in fig. 6, excavate the side frost wall 33 between block area 1 and block area 22, and in two neighboring support Three 24c of installation support between two 24b so that one 24a of support, two 24b and three 24c of support is supported to connect into the water of an entirety Flat support 24, horizontally-supported 24 is made of shaped steel or armored concrete;
S6:Step S2 to S5 is repeated, the length direction along pipe curtain 10 gradually implements earth excavation and Construction of Supporting, in soil After side is excavated, next step working procedure, such as underground structure are carried out along work or the construction of lower section soil excavation.
Earthwork digging method under the pipe curtain of the present invention, considers soil body composite support effect, waits out 10 lower section of pipe curtain Excavator body takes grating type frozen construction, and jump storehouse method is combined to implement earth excavation construction successively, has maximally utilised There is the supporting role for freezing the soil body, the stress of supporting apparatus can be reduced, reduces the area of section of its supporting member so that Construction of Supporting is physically easier to perform;Storehouse method is jumped while realizing continuous productive process, shadow is disturbed caused by reducing adjacent soil excavation It rings, ensure that the stability that earth excavation is constructed in the 10 times small spaces of pipe curtain of soft clay area, avoid the unordered excavation of the soil body and lead The hidden danger of cause.
In above-mentioned steps S2, supporting apparatus includes by least four montants 23 and being connected to adjacent two montants 23 Between diagonal brace 26 constitute chassis body, be installed on block area 1 or 22 bottom of block area along the length direction of pipe curtain 10 and freeze A pair of of sliding rail 21 on wall 31, and at least four sliding supports 22 of 23 bottom of montant are connected to, sliding support 22 Groove matches with sliding rail 21 so that chassis body can need to move along sliding rail 21 according to construction, preferably, the present embodiment Crossing brace is installed between adjacent two montants 23 and forms chassis body, structure is more reliable and more stable.
Supporting apparatus can be installed on after overall package in block area, certainly, in order to be more convenient for transport and construct, Can by each component of supporting apparatus in block area on-site consolidation, specifically, in step s 2, the areas Xian Kuai 1, block At least four montants 23 are installed between the top frost wall 32 and bottom frost wall 31 in area 22 and play temporary support, wait for step After S4 all excavates top frost wall 32 and installs two 24b of support, diagonal brace 26 is assembled between adjacent two montants 23 to constitute The more stable chassis body of structure makes 23 top of montant offset with two 24b of support.
In above-mentioned steps S6, it is threadedly coupled between the sliding rail 21 in two neighboring piece of area of 10 length direction of pipe curtain setting, Sliding rail 21 can need Fast Installation and dismounting according to construction, to realize the recycling of sliding rail 21, the sliding rail of the present embodiment 21 are made of shaped steel.
As shown in fig. 7, in above-mentioned steps S4, the top of every montant of supporting apparatus 23 is respectively mounted that there are one vertical Displacement compensation device 27, vertical displacement compensation device 27 include hydraulic cylinder 271, support base 272, mandril 273, at least two Support 274, at least two latch segments 277, at least two self-locking oil cylinders 276 and PLC control unit (not shown), top One end of bar 273 and the piston rod of hydraulic cylinder 271 are bolted, and the bottom of the other end and two 24b of support of mandril 273 offsets, Support base 272 is sheathed on 27 3 outside of mandril and is bolted with hydraulic cylinder 271, and at least two supporting racks 274 are distributed in support 272 outer walls of seat are simultaneously affixed, and a self-locking oil cylinder 276, one end of self-locking oil cylinder 276 and support are respectively mounted on each supporting rack 274 The end plate 275 of frame 274 is hinged, the other end of self-locking oil cylinder 276 and 277 pin connection of semicircular latch segment, two latch segments 277 are oppositely arranged and are sheathed on 273 outside of mandril, and the card tooth of the guide groove and 273 outer wall of mandril of 277 inner wall of latch segment is mutually nibbled It closes, displacement sensor is equipped in hydraulic cylinder 271, and displacement sensor is connect with P LC control unit signals.
When the gap between two 24b of vertical displacement compensation device 27 and support is excessive, displacement sensor feeds back signal To PLC control unit, PLC control unit, which is sent out, opens mechanical self-latching instruction, and the piston rod retraction of self-locking oil cylinder 276 drives two A latch segment 277 moves round about, and then, PLC control unit, which sends out instruction, makes the piston rod of hydraulic cylinder 271 stretch out, and makes It obtains mandril 273 to move up and two 24b is supported to offset, PLC control units send out self-locking instruction, make the piston of self-locking oil cylinder 276 It stretches out, two pieces of latch segments 277 is driven to move towards 273 position of locking mandril;On the contrary, working as vertical displacement compensation device 27 and water When the gap of flat support 24 is too small, PLC control unit, which sends out instruction, makes the piston rod of hydraulic cylinder 271 shrink so that mandril 273 Self-locking after moving down and offseting with two 24b of support.As it can be seen that high-precision displacement sensor can to supporting apparatus with Spacing between horizontally-supported 24 carries out real-time data acquisition and analysis, and controls mandril 273 by PLC control unit and stretch Realize the intelligent compensation of supporting apparatus vertical displacement, it is easy to operate, and also degree of regulation is high.The present embodiment it is vertical The structure of displacement compensation device 27 is only an example, it is not limited to this.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to right.

Claims (5)

1. earthwork digging method under a kind of pipe curtain, which is characterized in that steps are as follows:
S1:Grating type frozen construction is implemented to the soil body below pipe curtain, the soil body below the pipe curtain is divided into grid-like several The areas Ge Kuai are spaced piece of area one and block area two, and described piece of one soil body of area is not freeze the soil body, and described piece of two soil body of area is Freeze the soil body, form frost wall behind described piece of area one and described piece of two surrounding freezing soil of area, calculates analysis and determine described piece of area One and the excavation size in described piece of area two and the size in described piece of area one and described piece of two surrounding frost wall of area;
S2:Excavated in described piece of area one with to jump storehouse digging mode and does not freeze the soil body, the top frost wall in described piece of area one and bottom Supporting apparatus is installed between portion's frost wall, then, then excavates the soil body for being restored to non-frozen state in described piece of area two, Supporting apparatus is installed between the top frost wall and bottom frost wall in described piece of area two;
S3:Excavate the position soil body among described piece of area one and described piece of two top frost wall of area and horizontally disposed support is installed One, one bottom of the support is by perpendicular affixed interim strut support in bottom frost wall;
S4:The remaining soil body of two top frost wall both sides of described piece of area one and described piece of area is excavated, respectively in the support one or two The horizontally disposed support two of side installation, and the support one and the support two are affixed, make the top of the supporting apparatus It offsets with the support two, removes the interim strut;
S5:Excavate the side frost wall between described piece of area one and described piece of area two, and between the two neighboring support two Installation support three, and the support one, support two and support three are connected into the horizontally-supported of entirety;
S6:Step S2 to S5 is repeated, the length direction along the pipe curtain gradually implements earth excavation and Construction of Supporting.
2. earthwork digging method under pipe curtain according to claim 1, it is characterised in that:It is described interim in the step S2 Support device includes the chassis body being made of at least four montants and the diagonal brace being connected between adjacent two montants, edge The length direction of the pipe curtain is installed on a pair of of sliding rail on described piece of area one or described piece of two bottom frost wall of area, and respectively At least four sliding supports of the montant bottom are connected to, the groove of the sliding support matches with the sliding rail.
3. earthwork digging method under pipe curtain according to claim 2, it is characterised in that:In the step S2, first described Block area one, described piece of area two top frost wall and bottom frost wall between at least four montants are installed, wait for that the step S4 is complete After portion excavates the top frost wall and installs the support two, diagonal brace is assembled between adjacent two montants to constitute frame Frame body makes the montant top offset with the support two.
4. earthwork digging method under pipe curtain according to claim 1, it is characterised in that:In the step S6, along the pipe It is threadedly coupled between the sliding rail in the two neighboring described piece of area of curtain length direction setting.
5. earthwork digging method under pipe curtain according to any one of claims 1 to 4, it is characterised in that:In the step S4, It is respectively mounted at the top of every montant of the supporting apparatus there are one vertical displacement compensation device, the vertical displacement compensation fills It sets including hydraulic cylinder, support base, mandril, at least two supporting racks, at least two latch segments, at least two self-locking oil cylinders, and PLC control unit, one end of the mandril and the piston rod of the hydraulic cylinder are bolted, the other end of the mandril with it is described The bottom of support two offsets, and the support base is sheathed on the outside of the mandril and is bolted with the hydraulic cylinder, at least two Support frame as described above is distributed in the support base outer wall and affixed, and a self-locking oil cylinder is respectively mounted on each support frame as described above, described One end of self-locking oil cylinder and the end plate of support frame as described above are hinged, and the other end of the self-locking oil cylinder connects with semicircular latch segment pin It connects, two latch segments are oppositely arranged and are sheathed on the outside of the mandril, guide groove and the mandril of the latch segment inner wall The card tooth of outer wall is intermeshed, and displacement sensor is equipped in the hydraulic cylinder, and institute's displacement sensors and PLC controls are single First signal connection;When the vertical displacement compensation device and the excessive gap of the support two, institute's displacement sensors will be believed The PLC control unit number is fed back to, the PLC control unit, which sends out instruction, makes the piston rod of the hydraulic cylinder stretch out so that Self-locking after the mandril is moved up and offseted with the support two;When the vertical displacement compensation device and the support two When gap is too small, the PLC control unit, which sends out instruction, makes the piston rod of the hydraulic cylinder shrink so that the mandril is to moving down Self-locking after moving and offseting with the support two.
CN201711481446.0A 2017-12-29 2017-12-29 Earthwork digging method under a kind of pipe curtain Active CN108331584B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711481446.0A CN108331584B (en) 2017-12-29 2017-12-29 Earthwork digging method under a kind of pipe curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711481446.0A CN108331584B (en) 2017-12-29 2017-12-29 Earthwork digging method under a kind of pipe curtain

Publications (2)

Publication Number Publication Date
CN108331584A true CN108331584A (en) 2018-07-27
CN108331584B CN108331584B (en) 2019-11-15

Family

ID=62924641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711481446.0A Active CN108331584B (en) 2017-12-29 2017-12-29 Earthwork digging method under a kind of pipe curtain

Country Status (1)

Country Link
CN (1) CN108331584B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962613A (en) * 2021-02-19 2021-06-15 济南轨道交通集团有限公司 Sedimentation automatic compensation type foundation pit-crossing underground pipeline protection construction method and system
CN115492161A (en) * 2022-07-01 2022-12-20 上海建工一建集团有限公司 Construction method for storey-adding three-side enclosing pipe curtain of existing building basement

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4107455A1 (en) * 1991-03-08 1992-09-10 Messer Griesheim Gmbh METHOD FOR THE ACCELERATED FREEZING OF EARTH
JP2000230389A (en) * 1999-02-12 2000-08-22 Kumagai Gumi Co Ltd Construction of tunnel
CN104675403A (en) * 2014-12-18 2015-06-03 上海建工集团股份有限公司 Underground space construction method and supporting structure
CN105464134A (en) * 2015-12-31 2016-04-06 上海建工集团股份有限公司 Top-down and bottom-up combined construction method and supporting structure of multi-layer underground space below existing facility
CN105464686A (en) * 2015-12-31 2016-04-06 上海建工集团股份有限公司 Multistory underground space screen frame type tunneling construction method under existing facilities and support structure
CN205225281U (en) * 2015-12-14 2016-05-11 中建六局土木工程有限公司 For a short time, it secretly digs section support construction structures than super shallow rectangle that buries to cover to stride

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4107455A1 (en) * 1991-03-08 1992-09-10 Messer Griesheim Gmbh METHOD FOR THE ACCELERATED FREEZING OF EARTH
JP2000230389A (en) * 1999-02-12 2000-08-22 Kumagai Gumi Co Ltd Construction of tunnel
CN104675403A (en) * 2014-12-18 2015-06-03 上海建工集团股份有限公司 Underground space construction method and supporting structure
CN205225281U (en) * 2015-12-14 2016-05-11 中建六局土木工程有限公司 For a short time, it secretly digs section support construction structures than super shallow rectangle that buries to cover to stride
CN105464134A (en) * 2015-12-31 2016-04-06 上海建工集团股份有限公司 Top-down and bottom-up combined construction method and supporting structure of multi-layer underground space below existing facility
CN105464686A (en) * 2015-12-31 2016-04-06 上海建工集团股份有限公司 Multistory underground space screen frame type tunneling construction method under existing facilities and support structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴小建等: "大断面多层地下空间的管幕暗挖结构顺作施工工艺", 《建筑施工》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962613A (en) * 2021-02-19 2021-06-15 济南轨道交通集团有限公司 Sedimentation automatic compensation type foundation pit-crossing underground pipeline protection construction method and system
CN115492161A (en) * 2022-07-01 2022-12-20 上海建工一建集团有限公司 Construction method for storey-adding three-side enclosing pipe curtain of existing building basement
CN115492161B (en) * 2022-07-01 2023-11-14 上海建工一建集团有限公司 Construction method for building basement storey-adding three-side surrounding pipe curtain of existing building

Also Published As

Publication number Publication date
CN108331584B (en) 2019-11-15

Similar Documents

Publication Publication Date Title
CN108194102B (en) The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation
CN104074525B (en) Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
CN108915720B (en) A kind of large cross-section tunnel passes through fault belt construction method
CN105971648A (en) End support and equipment system of roadway-free and coal-pillar-free self-retained roadway mining method
CN104533428B (en) A kind of steep cliffs tunnel outlet engineering method
CN106049532A (en) Supporting and retaining device for open excavation construction of comprehensive pipe gallery and construction method thereof
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN108331584B (en) Earthwork digging method under a kind of pipe curtain
CN106968691A (en) Improve CD method construction methods in a kind of extremely frigid zones silty clay tunnel
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
Shang et al. A case history of Tunnel Boring Machine jamming in an inter-layer shear zone at the Yellow River Diversion Project in China
CN108239994A (en) A kind of temporary support system and its application method
CN105156123B (en) A kind of open type shield excavation machine and its application method
CN105201518A (en) Method for receiving and disassembly of large-diameter slurry balance shield in hole
CN110195598A (en) A kind of highway tunnel construction integrated control method
CN106437782A (en) Support and protection structure for large-section railroad tunnel in V class surrounding rock and construction method of structure
CN112160759A (en) Method for starting and trial tunneling of tunnel shield crossing river
CN106050277A (en) Strengthening process for soft-plastic collapsing body karst tunnel
CN108130910A (en) A kind of support system and its design method of the displacement of active control foundation pit
CN110566238A (en) Mud rock roof small coal pillar gob-side roadway supporting structure and method thereof
CN103541739A (en) Shallow-buried long-span small-clear-distance loess tunnel supporting system
CN108590671A (en) A kind of five steps, 14 excavation methods under advanced strong supporting system
CN208105276U (en) A kind of support system of active control foundation pit displacement
CN109594994A (en) Tunneling method under existing building
CN203257446U (en) Coal harbor arched supporting shield structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant