CN108590671A - A kind of five steps, 14 excavation methods under advanced strong supporting system - Google Patents

A kind of five steps, 14 excavation methods under advanced strong supporting system Download PDF

Info

Publication number
CN108590671A
CN108590671A CN201810456915.1A CN201810456915A CN108590671A CN 108590671 A CN108590671 A CN 108590671A CN 201810456915 A CN201810456915 A CN 201810456915A CN 108590671 A CN108590671 A CN 108590671A
Authority
CN
China
Prior art keywords
tunnel
base tunnel
excavated
steps
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810456915.1A
Other languages
Chinese (zh)
Inventor
潘建立
张斌梁
刘应亮
马胜利
李刚
汪国贤
穆军明
蒋峰峰
郝风光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810456915.1A priority Critical patent/CN108590671A/en
Publication of CN108590671A publication Critical patent/CN108590671A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Five steps, 14 excavation methods that the invention discloses a kind of under advanced strong supporting system, i.e. in tunnel, big cross section is divided into 14, five step and is excavated, 22b I-steel can be used in preliminary bracing, spacing 30cm, C25 gunite concretes 30cm is thick, and temporary support is using the shaped steel of HW400 × 400 × 13, spacing 1.2m, first of stull, all perpendicular support Two bors d's oeuveres, the second~tetra- stull are single.Advantageous effect of the present invention is:First floor pilot drive section is larger, is conducive to mechanization excavation construction;Excavation sequence is reasonable, and frozen soil strength is big, and stability is good, ensures that face is stable and structure stress is safe;Middle drift is leading, weakens both sides pilot tunnel frozen soil, reduces Mechanical Excavation of Frozen Soil difficulty, improves construction efficiency;Middle base tunnel only has temporary support process, and speed of application is fast;Monitoring measurement connection and reasonable arrangement can effectively monitor excavation risk, and excavating sequences can effectively be instructed to implement Dynamic Construction;This method is safe and reliable, can effectively reduce face unstability, cave in, the excessive equivalent risk of support system deformation.

Description

A kind of five steps, 14 excavation methods under advanced strong supporting system
Technical field
The present invention relates to the technical fields of tunnelling, and in particular to one kind adds for steel pipe curtain freezes advance support form Under big cross section five steps, 14 excavation methods.
Background technology
Port Zhuhai and Macao bridge Zhuhai connecting line is the important component of port Zhuhai and Macao bridge, and Gong Bei tunnel is port Zhuhai and Macao bridge pearl The main projects of extra large connecting line, port Zhuhai and Macao bridge Zhuhai connecting line Gong Bei tunnel port tunneling segment length 255m, under wear Gong Beikou Strip between bank and Macao barrier gate port, distance of the curtain engineering away from structure pile foundation only have 0.46m, are covered at the top of pipe curtain recently Soil thickness about 4~5m.The daily incoming and outgoing vehicles in port are 7000 average, and about 230,000 person-times of the stream of people's total amount entered and left the border daily is wanted Ask construction that cannot generate any influence to port customs clearance.Tunnel mainly passes through geological conditions, from top to bottom for:Miscellaneous fill, mud, Very soft sill clay, silt clay, accidental powder, fine sand layer;Underground water 3m or so, is connected with seawater, belongs to weak soil rich water Geology.Tunnel excavation section is 336.8m2, is combined using pipe curtain advance support+horizontal frozen sealing, and big cross section divides pilot tunnel It excavates.Pipe curtain is made of 36 φ 1620mm push pipes, 35.5~35.8mm of tube spacing.Pipe curtain is freezing pipe, is formed and is frozen after cooling The frost wall for tying wall 2~2.6m thickness, to form " pipe curtain advance support+horizontal frozen sealing " strong advanced levels support system. Large cross section excavation easily occurs that earth's surface local collapse, ground settlement are excessive, face unstability, cave in, prop under environment above System deforms prominent mud, water burst equivalent risk between excessive, pipe, and five steps, 14 excavation methods are proposed in order to reduce risk.
Invention content
In view of it is encountered in actual excavation the technical issues of, the purpose of the present invention be that effectively reduce large cross section excavation When easily occur earth's surface local collapse, ground settlement is excessive, face unstability, cave in, support system deformation is excessive, mud of dashing forward between pipe, Water burst equivalent risk, it is proposed that safe and reliable, practical five steps, 14 excavation methods.
To achieve the goals above, the technical solution adopted by the present invention is as follows:
A kind of five steps, 14 excavation methods under advanced strong supporting system the described method comprises the following steps:
S1 first steps first excavate " 1 " base tunnel, rear to excavate " 2 " base tunnel, and " 2 " base tunnel lags behind " 1 " base tunnel about 5m;
S2 second steps are excavated with the longitudinally spaced 15m of first step, and base tunnel " 3 " in first excavating installs temporary support in time, Then it excavates and claims left and right two side base tunnels " 4 ", " 5 ", between the middle base tunnel " 3 " and the arranged on left and right sides base tunnel " 4 ", " 5 " Spacing about 5m, dislocation is kept to be excavated;
The longitudinally spaced 15m of S3 thirds step and second step is excavated, base tunnel in first excavating " 6, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 7 ", " 8 ", between the middle base tunnel " 6 " and the arranged on left and right sides base tunnel " 7 ", " 8 " Spacing about 5m, dislocation is kept to be excavated;
The longitudinally spaced 15m of the 4th steps of S4 and third step is excavated, base tunnel in first excavating " 9, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 10 ", " 11 ", the middle base tunnel " 9 " and the arranged on left and right sides base tunnel " 10 ", " 11 " Between keep spacing about 5m, dislocation excavated;
The 5th steps of S5 and the longitudinally spaced 15m of the 4th step are excavated, base tunnel in first excavating " 12, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 13 ", " 14 ", the middle base tunnel " 12 " and the arranged on left and right sides base tunnel " 13 ", " 14 " Between keep spacing about 5m, dislocation excavated.
It should be noted that each step height about 3.8~5.0m.
It should be noted that when each base tunnel often excavates 1~2 I-steel spacing, should closely follow apply preliminary bracing with it is interim Supporting construction.
It should be further noted that in the technical solution of aforementioned present invention, 1,2, the numbers such as 3....14 be not pair The limitation of the present invention, is only for as differentiation.
Based on above-mentioned, the present invention also provides a kind of five steps, 14 excavation methods under advanced strong supporting system Monitoring arrangement, monitoring arrangement includes at least Vault settlement, tunnel inner periphery displacement, bracing members Internal Force Monitoring, initial stage branch Internal stress is protected, wherein
The Vault settlement:It is arranged in tunnel top, a section arranges 3, mono- measuring frequency section of every 5~10m;
The tunnel inner periphery displacement:Per section 16 measuring points of temporary cloth, mono- measuring frequency section of every 5~10m;
The bracing members internal stress:Each section 22 measuring points of temporary cloth, mono- measuring frequency section of every 20~30m;
The preliminary bracing internal stress:15 measuring points, mono- measuring frequency section of every 20~30m is arranged in each section.
Advantageous effect of the present invention is:
(1) first floor pilot drive section is larger, is conducive to mechanization excavation construction;
(2) excavation sequence is reasonable, and frozen soil strength is big, and stability is good, ensures that face is stable and structure stress is safe;
(3) middle drift is leading, weakens both sides pilot tunnel frozen soil, reduces Mechanical Excavation of Frozen Soil difficulty, improves construction efficiency;
(4) base tunnel only has temporary support process in, and speed of application is fast;
(5) monitoring measurement connection and reasonable arrangement can effectively monitor excavation risk, can effectively instruct excavating sequences to implement dynamic and apply Work;
(6) this method is safe and reliable, can effectively reduce face unstability, cave in, the support system deformation wind such as excessive Danger.
Description of the drawings
Fig. 1 is the transverse cross-sectional profile schematic diagram of the present invention;
Fig. 2 is 14 position views in Fig. 1;
Fig. 3 is the flow diagram of the excavation method of the present invention;
Fig. 4 is Vault settlement of the present invention, tunnel inner periphery displacement monitoring layout drawing;
Fig. 5 is that preliminary bracing of the present invention and gib internal stress monitor layout drawing.
Specific implementation mode
The invention will be further described below, it should be noted that the present embodiment premised on the technical program, Detailed embodiment and specific operating process are given, but protection scope of the present invention is not limited to present embodiment.
As shown in FIG. 1 to 3, the present invention is a kind of five steps, 14 excavation methods under advanced strong supporting system, It the described method comprises the following steps:
S1 first steps first excavate " 1 " base tunnel, rear to excavate " 2 " base tunnel, and " 2 " base tunnel lags behind " 1 " base tunnel about 5m;
S2 second steps are excavated with the longitudinally spaced 15m of first step, and base tunnel " 3 " in first excavating installs temporary support in time, Then it excavates and claims left and right two side base tunnels " 4 ", " 5 ", between the middle base tunnel " 3 " and the arranged on left and right sides base tunnel " 4 ", " 5 " Spacing about 5m, dislocation is kept to be excavated;
The longitudinally spaced 15m of S3 thirds step and second step is excavated, base tunnel in first excavating " 6, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 7 ", " 8 ", between the middle base tunnel " 6 " and the arranged on left and right sides base tunnel " 7 ", " 8 " Spacing about 5m, dislocation is kept to be excavated;
The longitudinally spaced 15m of the 4th steps of S4 and third step is excavated, base tunnel in first excavating " 9, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 10 ", " 11 ", the middle base tunnel " 9 " and the arranged on left and right sides base tunnel " 10 ", " 11 " Between keep spacing about 5m, dislocation excavated;
The 5th steps of S5 and the longitudinally spaced 15m of the 4th step are excavated, base tunnel in first excavating " 12, temporary support is installed in time, Then it excavates and claims left and right two side base tunnels " 13 ", " 14 ", the middle base tunnel " 12 " and the arranged on left and right sides base tunnel " 13 ", " 14 " Between keep spacing about 5m, dislocation excavated.
It should be noted that each step height about 3.8~5.0m.
It should be noted that when each base tunnel often excavates 1~2 I-steel spacing, should closely follow apply preliminary bracing with it is interim Supporting construction.
It should be further noted that in the technical solution of aforementioned present invention, 1,2, the numbers such as 3....14 be not pair The limitation of the present invention, is only for as differentiation.
Based on above-mentioned, as shown in Figure 4, Figure 5, the present invention also provides a kind of five steps under advanced strong supporting system The monitoring arrangement of 14 excavation methods, the monitoring arrangement is including at least in Vault settlement, tunnel inner periphery displacement, bracing members Power monitoring, preliminary bracing internal stress, wherein:
The Vault settlement:It is arranged in tunnel top, a section arranges 3, mono- measuring frequency section of every 5~10m;
The tunnel inner periphery displacement:Per section 16 measuring points of temporary cloth, mono- measuring frequency section of every 5~10m;
The bracing members internal stress:Each section 22 measuring points of temporary cloth, mono- measuring frequency section of every 20~30m;
The preliminary bracing internal stress:15 measuring points, mono- measuring frequency section of every 20~30m is arranged in each section.
Further, in Fig. 4, triangle represents settlement observation point, dot represents convergence monitoring point for displacement;It is rectangular in Fig. 5 Shape represents preliminary bracing and gib internal stress monitoring point.
Further, can be found out by Tables 1 and 2, by using construction method of the present invention, construction personnel is first First can dynamic realtime, control work progress, guiding construction comprehensively;Secondly obtained data precision is high, accurately, in time may be used It leans on;Again, it can be directed to monitoring and controlling early warning value, convenient for making emergency disposal measure to accident.
The construction monitoring frequency meter of 1 excavating load of the present invention of table
Serial number Monitoring project Monitoring accuracy Early warning value
1 Vault settlement 0.5mm Aggregate-value:30mm, rate of displacement:2mm/d
2 Periphery displacement 0.5mm Relative displacement aggregate-value:0.30%
3 Bracing members internal force 0.5% (F.S) 70% design controlling value
4 Support lining internal force 0.5% (F.S) 70% design controlling value
The pointing precision and early warning controlling value of 2 excavating load of the present invention of table
For those skilled in the art, technical solution that can be as described above and design are made other each Kind is corresponding to be changed and deforms, and all these change and deform the protection model that should all belong to the claims in the present invention Within enclosing.

Claims (4)

1. a kind of five steps, 14 excavation methods under advanced strong supporting system, which is characterized in that the method includes with Lower step:
S1 first steps first excavate " 1 " base tunnel, rear to excavate " 2 " base tunnel, and " 2 " base tunnel lags behind " 1 " base tunnel about 5m;
S2 second steps are excavated with the longitudinally spaced 15m of first step, and base tunnel " 3 " in first excavating installs temporary support, then in time It excavates and claims left and right two side base tunnels " 4 ", " 5 ", kept between the middle base tunnel " 3 " and the arranged on left and right sides base tunnel " 4 ", " 5 " Spacing about 5m, dislocation are excavated;
The longitudinally spaced 15m of S3 thirds step and second step is excavated, and base tunnel in first excavating " 6, temporary support is installed in time, then It excavates and claims left and right two side base tunnels " 7 ", " 8 ", kept between the middle base tunnel " 6 " and the arranged on left and right sides base tunnel " 7 ", " 8 " Spacing about 5m, dislocation are excavated;
The longitudinally spaced 15m of the 4th steps of S4 and third step is excavated, and base tunnel in first excavating " 9, temporary support is installed in time, then It excavates and claims left and right two side base tunnels " 10 ", " 11 ", between the middle base tunnel " 9 " and the arranged on left and right sides base tunnel " 10 ", " 11 " Spacing about 5m, dislocation is kept to be excavated;
The 5th steps of S5 and the longitudinally spaced 15m of the 4th step are excavated, and base tunnel in first excavating " 12, temporary support is installed in time, then It excavates and claims left and right two side base tunnels " 13 ", " 14 ", between the middle base tunnel " 12 " and the arranged on left and right sides base tunnel " 13 ", " 14 " Spacing about 5m, dislocation is kept to be excavated.
2. five steps, 14 excavation methods according to claim 1 under advanced strong supporting system, which is characterized in that When each base tunnel often excavates 1~2 I-steel spacing, it should closely follow and apply preliminary bracing and temporary support structures.
3. five steps, 14 excavation methods according to claim 1 under advanced strong supporting system, which is characterized in that Each step height about 3.8~5.0m.
4. a kind of monitoring for five 14 excavation methods of step under advanced strong supporting system as described in claim 1 Arrangement, which is characterized in that monitoring arrangement is including at least Vault settlement, tunnel inner periphery displacement, bracing members Internal Force Monitoring, first Phase supporting internal stress, wherein
The Vault settlement:It is arranged in tunnel top, a section arranges 3, mono- measuring frequency section of every 5~10m;
The tunnel inner periphery displacement:Per section 16 measuring points of temporary cloth, mono- measuring frequency section of every 5~10m;
The bracing members internal stress:Each section 22 measuring points of temporary cloth, mono- measuring frequency section of every 20~30m;
The preliminary bracing internal stress:15 measuring points, mono- measuring frequency section of every 20~30m is arranged in each section.
CN201810456915.1A 2018-05-14 2018-05-14 A kind of five steps, 14 excavation methods under advanced strong supporting system Pending CN108590671A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810456915.1A CN108590671A (en) 2018-05-14 2018-05-14 A kind of five steps, 14 excavation methods under advanced strong supporting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810456915.1A CN108590671A (en) 2018-05-14 2018-05-14 A kind of five steps, 14 excavation methods under advanced strong supporting system

Publications (1)

Publication Number Publication Date
CN108590671A true CN108590671A (en) 2018-09-28

Family

ID=63637416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810456915.1A Pending CN108590671A (en) 2018-05-14 2018-05-14 A kind of five steps, 14 excavation methods under advanced strong supporting system

Country Status (1)

Country Link
CN (1) CN108590671A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109139021A (en) * 2018-11-01 2019-01-04 中铁十八局集团有限公司 A kind of more pilot tunnel Construction Organization Methods of multi-step
CN109184802A (en) * 2018-11-01 2019-01-11 中铁十八局集团有限公司 A kind of more pilot tunnel tunnel informations monitoring construction methods of big cross section
CN109630162A (en) * 2018-12-24 2019-04-16 中铁十八局集团有限公司 A method of it is quickly connect based on the heavy-duty steel of advance support with pipe curtain

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113391A (en) * 1997-06-27 1999-01-19 Taisei Corp Tail seal device and tail seal brush for shield excavating machine
CN101182772A (en) * 2007-11-20 2008-05-21 中铁二局股份有限公司 Two lines intersection small radius, shallow earth covering and large longitudinal slope complicated linetype shield construction method
CN101761346A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Method for constructing metamorphic rock confined water tunnel
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102636153A (en) * 2012-04-25 2012-08-15 中国十七冶集团有限公司 Observation method of crown settlement and periphery convergence of tunnel
CN103527209A (en) * 2013-10-22 2014-01-22 北京交通大学 Micro disturbance tunneling method used for shield machine to tunnel under building on rich water weak formation
CN104564128A (en) * 2014-12-10 2015-04-29 中铁二十局集团有限公司 Deformation monitoring method for shallow-buried excavation tunnel construction
CN105134258A (en) * 2015-08-14 2015-12-09 中国建筑土木建设有限公司 Construction method by utilizing multiple steps and leg-locking of pipe shed for completely-weathered VI-grade surrounding rock of tunnel
CN106677795A (en) * 2017-01-11 2017-05-17 广东工业大学 Structure and installation process of single deck steel concrete composite lining for high water pressure tunnels in coastal area
CN106761773A (en) * 2016-12-12 2017-05-31 四川福庆隧道机械设备有限公司 A kind of method for tunnel construction

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1113391A (en) * 1997-06-27 1999-01-19 Taisei Corp Tail seal device and tail seal brush for shield excavating machine
CN101182772A (en) * 2007-11-20 2008-05-21 中铁二局股份有限公司 Two lines intersection small radius, shallow earth covering and large longitudinal slope complicated linetype shield construction method
CN101761346A (en) * 2009-12-30 2010-06-30 中铁十二局集团第二工程有限公司 Method for constructing metamorphic rock confined water tunnel
CN102182466A (en) * 2011-04-08 2011-09-14 中铁上海设计院集团有限公司 Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel
CN102636153A (en) * 2012-04-25 2012-08-15 中国十七冶集团有限公司 Observation method of crown settlement and periphery convergence of tunnel
CN103527209A (en) * 2013-10-22 2014-01-22 北京交通大学 Micro disturbance tunneling method used for shield machine to tunnel under building on rich water weak formation
CN104564128A (en) * 2014-12-10 2015-04-29 中铁二十局集团有限公司 Deformation monitoring method for shallow-buried excavation tunnel construction
CN105134258A (en) * 2015-08-14 2015-12-09 中国建筑土木建设有限公司 Construction method by utilizing multiple steps and leg-locking of pipe shed for completely-weathered VI-grade surrounding rock of tunnel
CN106761773A (en) * 2016-12-12 2017-05-31 四川福庆隧道机械设备有限公司 A kind of method for tunnel construction
CN106677795A (en) * 2017-01-11 2017-05-17 广东工业大学 Structure and installation process of single deck steel concrete composite lining for high water pressure tunnels in coastal area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘继国等: "港珠澳大桥拱北隧道超大断面浅埋暗挖工法", 《水下隧道建设与管理技术论文集》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109139021A (en) * 2018-11-01 2019-01-04 中铁十八局集团有限公司 A kind of more pilot tunnel Construction Organization Methods of multi-step
CN109184802A (en) * 2018-11-01 2019-01-11 中铁十八局集团有限公司 A kind of more pilot tunnel tunnel informations monitoring construction methods of big cross section
CN109630162A (en) * 2018-12-24 2019-04-16 中铁十八局集团有限公司 A method of it is quickly connect based on the heavy-duty steel of advance support with pipe curtain
CN109630162B (en) * 2018-12-24 2020-02-14 中铁十八局集团有限公司 Method for quickly connecting heavy steel and pipe curtain based on advanced support

Similar Documents

Publication Publication Date Title
CN104074525B (en) Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
Hu et al. Artificial ground freezing in tunnelling through aquifer soil layers: A case study in Nanjing Metro Line 2
CN101387202B (en) Method for enlarging and digging tunnel portal at weak surrounding rock section in tunnel
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
Chen et al. Recent advances in high slope reinforcement in China: Case studies
CN105804758A (en) Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel
CN104912562A (en) Construction method for deformation control over existing operation tunnel crossing under shield
CN105257301A (en) Method for reinforcing collapse of weak surrounding rock of shallow embedded and mining tunnel
CN103775092A (en) Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN204941545U (en) Station boring construction system
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN108590671A (en) A kind of five steps, 14 excavation methods under advanced strong supporting system
CN109611103B (en) Method for reinforcing shield section suspended boulder group
CN108457658A (en) A kind of texture stratum tunnel list hole bidirectional construction crosses section constructing method
CN105909263A (en) Eolian sand stratum highway tunnel structure and construction method thereof
CN103046523A (en) Method for monitoring horizontal deformation of foundation pit and slope support
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN109268028A (en) A kind of large-span underground chamber half range mistake is away from excavation supporting method
CN205895242U (en) Low -angle crossing tunnel structure
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN104141500A (en) Hardened sand gravel stratum cavern construction method
CN111156005A (en) Construction method for tunnel to pass through subway station at close distance
CN107191206A (en) A kind of step construction method of Shallow-buried Large-span Tunnel Unit two six
CN112145227B (en) Facility for preventing water inrush and mud gushing of tunnel and construction method
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190508

Address after: 072750 Hebei Baoding Zhuozhou Guanyun Road China Railway 18 Bureau Group First Engineering Co., Ltd.

Applicant after: THE 1ST ENGINEERING CO., LTD. OF CHINA RAILWAY 18TH BUREAU GROUP CO., LTD.

Address before: 072750 Hebei Baoding Zhuozhou Guanyun Road China Railway 18 Bureau Group First Engineering Co., Ltd.

Applicant before: Yao Xiaoning

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928