JP2000230389A - Construction of tunnel - Google Patents
Construction of tunnelInfo
- Publication number
- JP2000230389A JP2000230389A JP11034014A JP3401499A JP2000230389A JP 2000230389 A JP2000230389 A JP 2000230389A JP 11034014 A JP11034014 A JP 11034014A JP 3401499 A JP3401499 A JP 3401499A JP 2000230389 A JP2000230389 A JP 2000230389A
- Authority
- JP
- Japan
- Prior art keywords
- ground
- tunnel
- shaft
- side walls
- refrigerant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、トンネルの構築方
法、特に自動車道路用トンネルのような大きい断面積を
有するトンネルの構築方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a tunnel, and more particularly to a method for constructing a tunnel having a large cross-sectional area, such as a motorway tunnel.
【0002】[0002]
【従来の技術】従来、大断面トンネルの構築のため、互
いに相対する一対の連続地中壁を築造してこれを土留壁
とした後、両土留壁間の地盤部分について開削すること
が行われている。2. Description of the Related Art Conventionally, in order to construct a large-section tunnel, a pair of continuous underground walls opposed to each other are constructed and used as earth retaining walls, and then a ground portion between the earth retaining walls is cut. ing.
【0003】これによれば、トンネル構築に伴う一般交
通の遮断をできる限り回避するため、開削中、開削空間
を覆工板で覆うことが行われている。According to this, in order to avoid as much as possible the interruption of general traffic associated with the construction of a tunnel, the digging space is covered with a lining plate during digging.
【0004】しかし、前記連続壁の築造には比較的長期
にわたる一般交通の遮断を必要とし、また、開削工事中
の騒音が前記覆工板を通して地上に漏れ、このために市
街地の環境悪化を招くという問題があった。[0004] However, the construction of the continuous wall requires a relatively long period of interruption of general traffic, and noise during the excavation work leaks to the ground through the lining plate, thereby deteriorating the environment in the city area. There was a problem.
【0005】[0005]
【発明が解決しようとする課題】本発明の目的は、一般
交通の遮断期間を短縮するトンネル構築方法を提供する
ことにある。また、本発明の他の目的は、トンネル掘削
時の騒音が地上に漏れにくいトンネル構築方法を提供す
ることにある。SUMMARY OF THE INVENTION It is an object of the present invention to provide a tunnel construction method for shortening a period of interruption of general traffic. Another object of the present invention is to provide a tunnel construction method in which noise during tunnel excavation hardly leaks to the ground.
【0006】[0006]
【課題を解決するための手段】本発明に係るトンネル構
築方法は、互いに平行な二条の立て坑を形成すること、
互いに交差する、各立て坑からその下方に伸びる複数の
冷媒循環用管および両立て坑の一方から水平に伸びる複
数の冷媒循環用管を地盤中に設置すること、前記管内に
冷媒を循環させ、これにより、凍土からなる互いに相対
する一対の側壁および両側壁に連なる頂壁を形成するこ
と、これらの壁に囲まれた地盤を掘削することを含む。
地盤掘削は、逆巻き工法を用いて行うことができる。According to the present invention, there is provided a tunnel construction method comprising: forming two parallel shafts;
Crossing each other, a plurality of refrigerant circulation tubes extending downward from each shaft and a plurality of refrigerant circulation tubes extending horizontally from one of the shafts are installed in the ground, and the refrigerant is circulated in the tubes, This includes forming a pair of opposing side walls and both side walls made of frozen soil and excavating the ground surrounded by these walls.
Ground excavation can be performed using a reverse winding method.
【0007】[0007]
【発明の作用および効果】本発明によれば、地盤中にそ
の一部を凍結して形成された一対の側壁および頂壁に囲
まれた地盤部分を掘削することから、掘削中の騒音が地
上に漏れにくい状態でのトンネルの構築が可能である。
また、前記側壁および頂壁を形成するために地盤中に設
置された冷媒循環用管への冷媒の供給は、これらの管を
地盤中に設置するために開削された二条の立て坑を覆工
板で覆う間に行うことができる。このため、前記立て坑
を開放状態にしておく期間、したがって一般交通の遮断
期間を短いものとすることができる。According to the present invention, a ground portion surrounded by a pair of side walls and a top wall formed by freezing a part of the ground in the ground is excavated. It is possible to construct a tunnel in a state where leakage is difficult.
Further, the supply of the refrigerant to the refrigerant circulation pipes installed in the ground to form the side walls and the top wall is performed by lining a double-pitted shaft that is cut and opened to install these pipes in the ground. This can be done while covering with a board. For this reason, it is possible to shorten the period in which the shaft is kept open, that is, the period in which general traffic is cut off.
【0008】[0008]
【発明の実施の形態】図1を参照すると、本発明に従っ
て構築された、矩形の横断面形状を有するトンネルが全
体に符号10で示されている。トンネル10は、例えば
高速道路を通すことができる程度の大きさの断面を有す
る。DETAILED DESCRIPTION OF THE INVENTION Referring to FIG. 1, a tunnel having a rectangular cross-sectional shape and constructed in accordance with the present invention is indicated generally by the numeral 10. The tunnel 10 has, for example, a cross section large enough to pass through a highway.
【0009】トンネル10の構築のため、まず、地盤1
1を開削して、互いに平行な二条の立て坑12,14を
形成する。To construct the tunnel 10, first, the ground 1
1 is cut to form two vertical shafts 12, 14 parallel to each other.
【0010】両立て坑12,14の長さは、トンネル1
0の構築予定長に等しい。[0010] The length of the double shafts 12, 14 is the length of the tunnel 1.
Equivalent to a planned construction length of 0.
【0011】両立て坑の内の一方の立て坑12は2つの
部分からなる。すなわち、深さの浅い立て坑部分16
と、該立て坑部分に連なる、より深さの深い立て坑部分
18とからなる。One of the two vertical shafts 12 has two parts. That is, the shaft portion 16 having a shallow depth
And a shaft section 18 having a greater depth connected to the shaft section.
【0012】これに対し、他方の立て坑14は、一方の
立て坑12における浅い立て坑部分16と同じ深さおよ
び幅寸法を有し、立て坑部分16と相対している。した
がって、深い立て坑部分18は、浅い立て坑部分16に
関し、立て坑14の側ではなく、立て坑14とは反対の
側に位置する。On the other hand, the other shaft 14 has the same depth and width as the shallow shaft portion 16 of one shaft 12, and is opposed to the shaft portion 16. Thus, the deep shaft portion 18 is located on the opposite side of the shaft 14 rather than the shaft 14 with respect to the shallow shaft portion 16.
【0013】両立て坑12,14の形成後、立て坑部分
16および立て坑14からこれらの下方へ鉛直に伸びる
複数の冷媒循環用管20,22と、立て坑部分18から
立て坑14の側へ水平に伸びる複数の冷媒循環用管24
を地盤11中に設置する。After the formation of the shafts 12, 14, a plurality of refrigerant circulation tubes 20, 22 extending vertically downward from the shaft shaft portion 16 and the shaft shaft 14, and from the shaft shaft portion 18 to the side of the shaft shaft 14. A plurality of refrigerant circulation tubes 24 extending horizontally
Is installed in the ground 11.
【0014】各管20,22,24は、例えば2つの開
口を有する二重管からなる。したがって、前記冷媒につ
いて、これを前記二重管の一の開口から供給し、他の開
口から回収することができ、この間に前記二重管内を循
環させることができる。前記冷媒の循環の間に前記二重
管の周囲の地中水を凍結させることができる。前記冷媒
として、例えば塩化カルシウムを用いることができる。Each of the tubes 20, 22, 24 is, for example, a double tube having two openings. Therefore, the refrigerant can be supplied from one opening of the double pipe and recovered from another opening, and can be circulated in the double pipe during this time. Underground water around the double pipe may be frozen during the circulation of the refrigerant. As the refrigerant, for example, calcium chloride can be used.
【0015】前記冷媒の供給および回収作業は、両立て
坑12,14内のそれぞれにおいて行うことができる。
この間、両立て坑12,14は鋼板からなる覆工板(図
示せず)で覆っておくことができる。したがって、両立
て坑12,14の開削に要する比較的短い期間を除き、
トンネル構築に要する比較的長い期間にわたり地表面を
一般交通の用に供することができる。The operation of supplying and recovering the refrigerant can be performed in each of the shafts 12 and 14.
During this time, the shafts 12, 14 can be covered with a lining plate (not shown) made of a steel plate. Therefore, except for the relatively short period required for excavation of both shafts 12,14,
The ground surface can be used for general traffic for a relatively long period of time required for tunnel construction.
【0016】前記複数の管の設置に先立ち、前記複数の
管をそれぞれ挿入するための複数の細長い孔を互いに間
隔をおいて地中に設ける。すなわち、浅い立て坑部分1
6から下方へ鉛直に伸びる複数の細長い孔(図示せず)
と、他の立て坑14から下方へ鉛直に伸びる複数の細長
い孔(図示せず)とを設け、さらに、深い立て坑部分1
8から立て坑14の側へ水平に伸びる複数の細長い孔
(図示せず)を設ける。Prior to installation of the plurality of tubes, a plurality of elongated holes for inserting the plurality of tubes are provided in the ground at an interval from each other. That is, shallow shaft part 1
A plurality of elongated holes extending vertically from 6 (not shown)
And a plurality of elongated holes (not shown) extending vertically downward from the other shafts 14, and furthermore, a deep shaft portion 1
A plurality of elongated holes (not shown) extending horizontally from 8 to the side of the shaft 14 are provided.
【0017】前記鉛直な孔および水平な孔は、立て坑1
2,14内にボーリングマシン(図示せず)を運び入
れ、これを前記立て坑内で作動させることにより地盤1
1に穿つことができる。The vertical hole and the horizontal hole correspond to the shaft 1
A boring machine (not shown) is carried into the pits 2 and 14, and is operated in the pit, thereby forming the ground 1.
1 can be drilled.
【0018】その後、各立て坑12,14から各鉛直孔
および各水平孔に管20,22および管24をそれぞれ
挿入し、地中に設置する。Thereafter, the pipes 20, 22 and 24 are inserted into the vertical holes and the horizontal holes from the shafts 12 and 14, respectively, and installed underground.
【0019】浅い立て坑部分16および立て坑14から
それぞれ鉛直に伸びる前記複数の孔は前記立て坑の伸長
方向に関して互いに間隔をおいて設けられている。The plurality of holes extending vertically from the shallow shaft portion 16 and the shaft 14, respectively, are spaced from each other in the direction of extension of the shaft.
【0020】また、深い立て坑部分18から、より詳細
には、立て坑部分18における、浅い立て坑部分16お
よび立て坑14より深い位置から水平に伸びる前記複数
の孔も前記立て坑の伸長方向に関して互いに間隔をおい
て設けられている。しかも、これらの水平な孔は前記鉛
直な孔相互間を伸びており、このため、前記鉛直な孔と
直角に交差している。The plurality of holes extending horizontally from the deep shaft portion 18, more specifically, from a position deeper than the shallow shaft portion 16 and the shaft 14 in the shaft portion 18, also extend in the extending direction of the shaft. Are spaced apart from each other. Moreover, these horizontal holes extend between the vertical holes, and thus intersect at right angles with the vertical holes.
【0021】したがって、前記水平な複数の孔を伸びる
複数の管24は、それぞれ、前記鉛直な複数の孔を伸び
る複数の管20の相互間および複数の管22の相互間を
伸び、複数の管24および管20,22のそれぞれと互
いに直交している。Therefore, the plurality of tubes 24 extending through the plurality of horizontal holes extend between the plurality of tubes 20 extending through the plurality of vertical holes and the plurality of tubes 22 respectively. 24 and each of the tubes 20, 22 are orthogonal to one another.
【0022】このため、前記管における前記冷媒の循環
により、図1に符号26で示すように、前記立て坑の伸
長方向へ連続して伸びる、門形の横断面形状を有する
壁、すなわち、鉛直な複数の管20,22の周囲の凍土
からなる互いに相対する一対の側壁28,30と、水平
な複数の管の周囲の凍土からなる、両側壁28,30に
連なる頂壁32とが地中に形成される。For this reason, by the circulation of the refrigerant in the pipe, as shown by reference numeral 26 in FIG. 1, a wall having a gate-shaped cross-sectional shape that continuously extends in the extending direction of the shaft, ie, a vertical wall A pair of opposing side walls 28 and 30 made of frozen soil around the plurality of tubes 20 and 22 and a top wall 32 connected to both side walls 28 and 30 made of frozen soil around the plurality of horizontal tubes are underground. Formed.
【0023】その後、前記トンネル構築のため、前記門
形の壁26の伸長方向に関する両端に一対の立て坑3
4,36を構築し、一方の立て坑34内から他方の立て
坑36に向けて、凍土からなる門形の壁26で囲まれた
地盤を例えばバックホーのような掘削装置を使用して掘
削する。Thereafter, in order to construct the tunnel, a pair of shafts 3 are provided at both ends of the portal wall 26 in the extending direction.
4, 36, and excavates the ground surrounded by the portal wall 26 made of frozen soil from inside one shaft 34 to the other shaft 36 using a drilling device such as a backhoe. .
【0024】掘削作業は、門形26の壁26で囲まれた
地中において行われるため、これに伴う騒音は地上に漏
れにくい。また、掘削作業の間、各立て坑34,36の
大部分を前記したと同様の覆工板(図示せず)で覆うこ
とができ、これにより、前記騒音の地上への漏れ出しを
低減し、また、地上面における一般交通に対する障害を
少なくすることができる。Since the excavation work is performed in the ground surrounded by the wall 26 of the gate 26, the noise accompanying the excavation hardly leaks to the ground. Also, during excavation work, most of each shaft 34, 36 can be covered with a lining plate (not shown) similar to that described above, thereby reducing leakage of the noise to the ground. In addition, obstacles to general traffic on the ground surface can be reduced.
【0025】掘削は、図2および図3に示すように、逆
巻き工法を用いて行うことができる。但し、図2および
図3においては、掘削状況を明瞭にすべく、凍土からな
る壁28,30,32が省略されている。Excavation can be performed using a reverse winding method, as shown in FIGS. However, in FIGS. 2 and 3, the walls 28, 30, and 32 made of frozen soil are omitted to clarify the excavation situation.
【0026】この工法では、まず、頂壁32下の一部を
該頂壁のほぼ全長にわたって掘削した後、頂壁32の長
手方向に互いに間隔をおいて、例えばH形鋼を用いて門
形に形成してなる複数の鋼製支保工38を掘削壁面に沿
って配置する。In this construction method, first, a part below the top wall 32 is excavated over substantially the entire length of the top wall 32, and then is spaced apart from each other in the longitudinal direction of the top wall 32. Are arranged along the excavated wall surface.
【0027】次に、鋼製支保工38下にこれに沿って湾
曲する移動式型枠40を配置し、鋼製支保工38と型枠
40との間にコンクリートを打設する。これを一方の立
て坑34の側から他方の立て坑36の側へ繰り返し行
い、上床版コンクリート42を形成する。Next, a movable formwork 40 that curves along the steel supporter 38 is disposed below the steel supporter 38, and concrete is cast between the steel supporter 38 and the formwork 40. This is repeated from the side of one shaft 34 to the side of the other shaft 36 to form the upper slab concrete 42.
【0028】次に、上床版コンクリート42下を掘削し
て大背44、土平、中割等を形成し、この間に上床版コ
ンクリート42の両端部下および中央部下にその長手方
向に互いに間隔をおいて打設コンクリートによる複数の
側壁46および中壁48(図1)を構築する。Next, the underside of the upper slab concrete 42 is excavated to form a large back 44, a horizon, a middle split, and the like. Then, a plurality of side walls 46 and a middle wall 48 (FIG. 1) made of cast concrete are constructed.
【0029】前記大背44、土平、中割等の形成、側壁
46および中壁48の構築等の間またはその後に、その
下方の地盤について、凍土からなる両側壁28,30の
下端の高さ位置から上方の高さ位置(例えば数メートル
上方の高さ位置)まで、これらと同様の大背50、土
平、中割等の形成、前記側壁および中壁の構築等を繰り
返し行う。During or after the formation of the large back 44, the horizon, the middle split, etc., the construction of the side walls 46 and the middle wall 48, the height of the lower end of the lower side of the two side walls 28, 30 made of frozen soil, From the height position to the upper height position (for example, a height position several meters above), the formation of the large back 50, the horizon, the middle split, and the like, the construction of the side walls and the middle wall, and the like are repeated.
【0030】こうして、打設コンクリートの成形体から
なる、全体に矩形の横断面形状を有するトンネル10が
構築される。図示のトンネル10は内部空間が4つに仕
切られている。In this way, a tunnel 10 having a rectangular cross-sectional shape as a whole, which is made of a cast concrete compact, is constructed. The illustrated tunnel 10 is divided into four internal spaces.
【図1】本発明に従って構築されたトンネルの横断面図
である。FIG. 1 is a cross-sectional view of a tunnel constructed in accordance with the present invention.
【図2】構築途上にあるトンネルの縦断面図である。FIG. 2 is a longitudinal sectional view of a tunnel under construction.
【図3】構築途上にあるトンネルを上方から見た部分断
面図である。FIG. 3 is a partial cross-sectional view of a tunnel under construction as viewed from above.
10 トンネル 12,14 二条の立て坑 20,22 鉛直な冷媒循環用管 24 水平な冷媒循環用管 28,30 凍土からなる側壁 32 凍土からなる頂壁 DESCRIPTION OF SYMBOLS 10 Tunnel 12,14 Two-row shaft 20,22 Vertical refrigerant circulation pipe 24 Horizontal refrigerant circulation pipe 28,30 Side wall made of frozen soil 32 Top wall made of frozen soil
Claims (2)
と、互いに交差する、各立て坑からその下方に伸びる複
数の冷媒循環用管および両立て坑の一方から水平に伸び
る複数の冷媒循環用管を地盤中に設置すること、前記管
内に冷媒を循環させ、これにより、凍土からなる互いに
相対する一対の側壁および両側壁に連なる頂壁を形成す
ること、これらの壁に囲まれた地盤を掘削することを含
む、トンネルの構築方法。1. Forming two parallel vertical shafts, a plurality of refrigerant circulation tubes crossing each other and extending downward from each vertical shaft, and a plurality of refrigerant circulation tubes extending horizontally from one of the vertical shafts. Installing the pipe in the ground, circulating a refrigerant in the pipe, thereby forming a pair of opposing side walls made of frozen soil and a top wall connected to both side walls, the ground surrounded by these walls A method of constructing a tunnel, including excavating.
工法を用いて行う、請求項1に記載の方法。2. The method according to claim 1, wherein excavation of the ground surrounded by the wall is performed using a reverse winding method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11034014A JP2000230389A (en) | 1999-02-12 | 1999-02-12 | Construction of tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11034014A JP2000230389A (en) | 1999-02-12 | 1999-02-12 | Construction of tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2000230389A true JP2000230389A (en) | 2000-08-22 |
Family
ID=12402559
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11034014A Withdrawn JP2000230389A (en) | 1999-02-12 | 1999-02-12 | Construction of tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2000230389A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105370300A (en) * | 2015-11-17 | 2016-03-02 | 中铁工程装备集团有限公司 | Two-layer or multi-layer underground space construction method |
CN108331584A (en) * | 2017-12-29 | 2018-07-27 | 上海建工集团股份有限公司 | Earthwork digging method under a kind of pipe curtain |
CN108915719A (en) * | 2018-07-05 | 2018-11-30 | 深圳市第建筑工程有限公司 | A kind of method for tunnel construction |
-
1999
- 1999-02-12 JP JP11034014A patent/JP2000230389A/en not_active Withdrawn
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105370300A (en) * | 2015-11-17 | 2016-03-02 | 中铁工程装备集团有限公司 | Two-layer or multi-layer underground space construction method |
CN108331584A (en) * | 2017-12-29 | 2018-07-27 | 上海建工集团股份有限公司 | Earthwork digging method under a kind of pipe curtain |
CN108331584B (en) * | 2017-12-29 | 2019-11-15 | 上海建工集团股份有限公司 | Earthwork digging method under a kind of pipe curtain |
CN108915719A (en) * | 2018-07-05 | 2018-11-30 | 深圳市第建筑工程有限公司 | A kind of method for tunnel construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100406693B1 (en) | A method of construction for the breast wall | |
JP2001115458A (en) | Deep well construction method using earth retaining wall | |
JP2001032673A (en) | Tunnel work execution method | |
JP2000230389A (en) | Construction of tunnel | |
JPH07180154A (en) | Endless chain cutter of underground continuous wall excavator | |
KR200389267Y1 (en) | Box type trench shoring apparatus | |
JPH05280297A (en) | Construction method of underground space body | |
CN212202085U (en) | Close-adhesion type open-and-underground excavation combined subway station structure | |
JP2008063787A (en) | Liquefaction preventing structure | |
KR20000065283A (en) | tubular roof tunnel construction method | |
JPH07331998A (en) | Constructing method of rock cavern | |
JPS6117696A (en) | Construction of underground head | |
JP2004316126A (en) | Work execution method for large section tunnel and deformed section shield boring machine | |
JPH05280278A (en) | Connection method for shield tunnel | |
JPH03250117A (en) | Construction method of bottom enlarged continuous wall | |
JP3616892B2 (en) | Water-sealed underground tank | |
KR102575701B1 (en) | A method of open cut excavation tunnel using a messer plate | |
JP2960316B2 (en) | Soil structure and method of constructing the same | |
JP3710106B2 (en) | How to build a shield start base | |
JPH01121414A (en) | Excavation work of ground | |
JP2002021098A (en) | Cut and cover tunneling method | |
JP2005127042A (en) | Underground water stream maintenance construction method | |
JP2000045313A (en) | Ground water permeation method making use of soil cement column strip earth retaining wall | |
JP3473915B2 (en) | Small diameter pipe burial method | |
JPS5985022A (en) | Underground continuous wall constructing work |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A300 | Withdrawal of application because of no request for examination |
Free format text: JAPANESE INTERMEDIATE CODE: A300 Effective date: 20060509 |