CN108331346A - The method for executing indoor pipeline integrated morphology - Google Patents

The method for executing indoor pipeline integrated morphology Download PDF

Info

Publication number
CN108331346A
CN108331346A CN201711407360.3A CN201711407360A CN108331346A CN 108331346 A CN108331346 A CN 108331346A CN 201711407360 A CN201711407360 A CN 201711407360A CN 108331346 A CN108331346 A CN 108331346A
Authority
CN
China
Prior art keywords
pipeline
casing
buried
integrated morphology
space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711407360.3A
Other languages
Chinese (zh)
Inventor
肖俊斌
冯建毅
黄淑芬
陈启斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Times Holding Group Co Ltd
Original Assignee
Guangzhou Times Holding Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Times Holding Group Co Ltd filed Critical Guangzhou Times Holding Group Co Ltd
Priority to CN201711407360.3A priority Critical patent/CN108331346A/en
Publication of CN108331346A publication Critical patent/CN108331346A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/063Re-usable forms
    • E04G15/068Re-usable forms for channels open towards the surface

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The method for executing indoor pipeline integrated morphology, including:In the beam, plate, column of building body, the casing of pre-buried level-one bigger than pipeline;Hydroelectric line is laid among pre-buried good casing;Some larger-size accessories, such as socket box, water supply angle valve, pre-buried plastics back box and foam insert in main structure body are waited for taking out filler after concreting, then accessory are installed into the position vacated;Deck-siding is suitably increased, then groove is reserved in the fringe region of beam, by pipelining in groove;There are the position that packet builds space, such as pelmet in interior, also using the space as pipelining region;The handing-over position of pipeline and building body is covered using dismountable panel, then brushed surface.The present invention can take into account pipeline beauty and be facilitated with maintenance, and combine closely with the agent structure of building, not influence structure safety and interior space utilization rate.

Description

The method for executing indoor pipeline integrated morphology
Technical field
This technology belongs to building engineering field, is related to architectural design and hydroelectric line construction and installation.
Background technology
In traditional architectural design and construction, interior is typically all to be equipped with a large amount of hydroelectric line and accessory, if directly It is exposed indoors, indoor aesthetics can be seriously affected.Many construction units are in order to hidden by hydroelectric line, often by water power Pipeline is embedded in floor bed course, furred ceiling, masonry partition wall etc..Although this traditional hydroelectric line installation method can be by pipe Line secretly applies, but there is also another defects:When being embedded in floor bed course or wall, exist greatly not to maintenance in the future Just, it needs to demolish walls, excavate floor;Although and pipeline is located at convenient to overhaul in furred ceiling, the furred ceiling added can force down again Indoor clear height.To sum up, realize the aesthetics of hydroelectric line installation, shooting convenience, and to the clear height of main building It influences at least, is always the research direction in industry.
Invention content
According to above research direction, new solution below is proposed.The technical solution can take into account pipeline beauty and inspection Facility is repaiied, and is combined closely with the agent structure of building, does not influence structure safety and interior space utilization rate.
To achieve the above object, the present invention adopts the following technical scheme that:
The method for executing indoor pipeline integrated morphology, including:
S1:In the beam, plate, column of building body, the position of the casing of pre-buried level-one bigger than pipeline, casing must binding reinforcement arrangement And the density of reinforcing bar, intensity cannot be influenced;
S2:After main body casting concrete, casing can be fixed in main structure body, and it is pre-buried good that hydroelectric line is laid in later Casing among, some larger-size accessories, such as socket box, water supply angle valve;
S3:Pre-buried plastics back box and foam insert in main structure body;
S4:It waits for taking out filler after concreting, then accessory is installed into the position vacated.
Preferably, the hydroelectric line in the S2 can directly be laid in structural beams, i.e., deck-siding is suitably increased, then existed The fringe region of beam is slotted, by pipelining in groove.
Preferably, include S11 in above-mentioned S1:There are the position that packet builds space, such as pelmet for some interiors, also may be used Using the space as pipelining region.
Preferably, the method further includes S5:By hydroelectric line by service sleeve, reserved texture grooves, utilize interior It is beautiful, smooth to achieve the effect that after packet block space etc. is laid in architecture indoor, it need to also be in the junction of pipeline and building body Position is covered using dismountable panel, then brushed surface, keeps wall, beam face etc. complete in appearance, smooth.
Compared with the prior art, advantageous effect possessed by the present invention is:
Good enough spaces are reserved in main structure body or indoor special component, hydroelectric line can neatly lay wherein, be convenient for Pipeline is installed and maintenance is dismantled, and the beauty and utilization rate for not influencing main structure body safety, not influencing interior decoration.
Description of the drawings
Fig. 1 is the structural schematic diagram of one embodiment of the invention;
Fig. 2 is the structural schematic diagram of another embodiment of the present invention;
Fig. 3 is the structural schematic diagram of further embodiment of this invention.
Specific implementation mode
In the following, in conjunction with attached drawing and specific embodiment, the present invention is described further:
As shown in Figure 1, Figure 2, Figure 3 shows, the method for executing indoor pipeline integrated morphology, including:
S1:In the beam, plate, column of building body, the position of the casing of pre-buried level-one bigger than pipeline, casing must binding reinforcement arrangement And the density of reinforcing bar, intensity cannot be influenced;
S2:After main body casting concrete, casing can be fixed in main structure body, and it is pre-buried good that hydroelectric line is laid in later Casing among, some larger-size accessories, such as socket box, water supply angle valve;
S3:The fillers such as pre-buried plastic foam in main structure body;
S4:It waits for taking out filler after concreting, then accessory is installed into the position vacated.
As a preferred solution, the hydroelectric line in the S2 can directly be laid in structural beams, i.e., deck-siding is fitted Work as increasing, then slots in the fringe region of beam, by pipelining in groove.
As a preferred solution, include S11 in above-mentioned S1:There is the position that packet builds space for some interiors, such as Pelmet etc., also using the space as pipelining region.
As a preferred solution, the method further includes a step S5:Hydroelectric line is passed through into service sleeve, pre- It is beautiful, smooth to achieve the effect that after staying texture grooves, space etc. is built using indoor packet being laid in architecture indoor, it need to also be in pipe The handing-over position of line and building body is covered using dismountable panel, then brushed surface, makes wall, beam face etc. in appearance Completely, smooth.
It will be apparent to those skilled in the art that technical solution that can be as described above and design, make various other Corresponding change and deformation, and all these changes and deformation should all belong to the protection domain of the claims in the present invention Within.

Claims (4)

1. the method for executing indoor pipeline integrated morphology, which is characterized in that include the following steps:
S1:In the beam, plate, column of building body, the position of the casing of pre-buried level-one bigger than pipeline, casing must binding reinforcement arrangement And the density of reinforcing bar, intensity cannot be influenced;
S2:After main body casting concrete, casing can be fixed in main structure body, and it is pre-buried good that hydroelectric line is laid in later Casing among, some larger-size accessories, such as socket box, water supply angle valve;
S3:The fillers such as pre-buried plastic foam in main structure body;
S4:It waits for taking out filler after concreting, then accessory is installed into the position vacated.
2. the method for executing indoor pipeline integrated morphology as described in claim 1, it is characterised in that:Water power pipe in the S2 Line can directly be laid in structural beams, i.e., deck-siding is suitably increased, and then groove be reserved in the fringe region of beam, by pipelining In groove.
3. the method for executing indoor pipeline integrated morphology as described in claim 1, it is characterised in that:Include in above-mentioned S1 S11:There are the position that packet builds space, such as pelmet for some interiors, also using the space as pipelining region.
4. the method for executing indoor pipeline integrated morphology as described in claim 1, it is characterised in that:Further include S5:By water power Pipeline is built by service sleeve, reserved texture grooves, using indoor packet after space etc. is laid in architecture indoor, for reach it is beautiful, Smooth effect need to also be covered at the handing-over position of pipeline and building body using dismountable panel, then brushed surface, make Wall, beam face etc. are complete in appearance, smooth.
CN201711407360.3A 2017-12-22 2017-12-22 The method for executing indoor pipeline integrated morphology Pending CN108331346A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711407360.3A CN108331346A (en) 2017-12-22 2017-12-22 The method for executing indoor pipeline integrated morphology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711407360.3A CN108331346A (en) 2017-12-22 2017-12-22 The method for executing indoor pipeline integrated morphology

Publications (1)

Publication Number Publication Date
CN108331346A true CN108331346A (en) 2018-07-27

Family

ID=62924344

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711407360.3A Pending CN108331346A (en) 2017-12-22 2017-12-22 The method for executing indoor pipeline integrated morphology

Country Status (1)

Country Link
CN (1) CN108331346A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403621A (en) * 2018-12-03 2019-03-01 广州景兴建筑科技有限公司 A kind of readily removable profile aluminum alloy pattern plate of building water power indent
CN110645409A (en) * 2019-08-26 2020-01-03 广东博意建筑设计院有限公司 Pipeline routing method for floating platform with hidden pipeline structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201420396Y (en) * 2009-06-22 2010-03-10 莱西市建筑总公司 Pre-embedded box die of concrete wall
CN102943933A (en) * 2012-11-28 2013-02-27 深圳市鹏城建筑集团有限公司 Method for pre-burying through floor pipeline into floor and sleeve used in method
CN103174289A (en) * 2012-10-20 2013-06-26 中国二十二冶集团有限公司 Construction method for cave entrance reservation of strong and weak electricity distribution box
CN104806025A (en) * 2015-05-26 2015-07-29 中建五局蚌埠建筑工程有限公司 Masonry engineering electromechanical pipeline and wire box direct-buried complete construction process
CN204571289U (en) * 2015-04-24 2015-08-19 中建四局第一建筑工程有限公司 A kind of construction formwork of overhang layer exterior wall preformed hole

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201420396Y (en) * 2009-06-22 2010-03-10 莱西市建筑总公司 Pre-embedded box die of concrete wall
CN103174289A (en) * 2012-10-20 2013-06-26 中国二十二冶集团有限公司 Construction method for cave entrance reservation of strong and weak electricity distribution box
CN102943933A (en) * 2012-11-28 2013-02-27 深圳市鹏城建筑集团有限公司 Method for pre-burying through floor pipeline into floor and sleeve used in method
CN204571289U (en) * 2015-04-24 2015-08-19 中建四局第一建筑工程有限公司 A kind of construction formwork of overhang layer exterior wall preformed hole
CN104806025A (en) * 2015-05-26 2015-07-29 中建五局蚌埠建筑工程有限公司 Masonry engineering electromechanical pipeline and wire box direct-buried complete construction process

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403621A (en) * 2018-12-03 2019-03-01 广州景兴建筑科技有限公司 A kind of readily removable profile aluminum alloy pattern plate of building water power indent
CN110645409A (en) * 2019-08-26 2020-01-03 广东博意建筑设计院有限公司 Pipeline routing method for floating platform with hidden pipeline structure

Similar Documents

Publication Publication Date Title
CN103225362B (en) Assembled light steel keel gypsum plate irregularly-shaped suspended ceiling system
CN204163299U (en) For the indoor integrated finishing assembly of integration
CN104032925A (en) Construction method for CSI residential wall and ground empty space
CN106320521A (en) Pure part plate combined industrialized house assembling structure which can be rapidly erected
CN106121231A (en) A kind of skyscraper interts cross construction method
CN103321327A (en) Unit-assembly-type framework partition wall system and construction method thereof
CN105464309A (en) Integral indoor decorating method and integral indoor decorating component
CN108331346A (en) The method for executing indoor pipeline integrated morphology
CN106958358A (en) The industrialization commercial residential buildings of energy-conserving and environment-protective
CN106894538A (en) Filling wall and agent structure concrete integral shaping method
CN206189685U (en) Integrated floor of modularization and house
CN203394108U (en) Fabricated bathroom
RU92037U1 (en) QUICK BUILDING BUILDING
CN205134527U (en) Three -dimensional building module
CN203230084U (en) Special-shaped suspended ceiling system composed of assembly type light gauge steel keel gypsum boards
KR101041582B1 (en) Prefabricated partition wall for apartment house has a lot of potential for recycling
CN205604546U (en) Link plate system is gone along with sb. to guard him to iteration environmental protection assembled outer wall
CN105040815A (en) Three-dimensional building module and factory building and on-site installing method thereof
CN105369955B (en) A kind of integrated assembled type floor
CN203334476U (en) Unit-assembled framework partition wall system
CN109577523A (en) For spraying the template and construction method of walling body
CN205171752U (en) Prefabricated light steel partition wall and mounting structure thereof
RU2732741C1 (en) Method of erection of multi-storey building with energy-saving multilayer walls
CN207878784U (en) A kind of assembly wall
CN112659354A (en) Machining method of structural electromechanical thermal insulation integrated wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180727

RJ01 Rejection of invention patent application after publication