CN108331342A - Template system of arc beam and construction method thereof - Google Patents
Template system of arc beam and construction method thereof Download PDFInfo
- Publication number
- CN108331342A CN108331342A CN201810459896.8A CN201810459896A CN108331342A CN 108331342 A CN108331342 A CN 108331342A CN 201810459896 A CN201810459896 A CN 201810459896A CN 108331342 A CN108331342 A CN 108331342A
- Authority
- CN
- China
- Prior art keywords
- arc
- formwork
- beam side
- flange
- flute
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/04—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/38—Arched girders or portal frames
- E04C3/44—Arched girders or portal frames of concrete or other stone-like material, e.g. with reinforcements or tensioning members
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种圆弧梁的模板体系及其施工方法,其中,模板体系包括梁底模板结构、梁侧模板结构和第一对拉螺栓;梁底模板结构包括梁底模板面板和梁底次背楞;梁底次背楞的长轴线为圆弧线,且该圆弧线弧度与圆弧梁长轴线弧度相适应;梁底模板面板的长轴线为圆弧线,且该圆弧线弧度与圆弧梁长轴线弧度相适应;梁侧模板结构包括梁侧模板面板、梁侧次背楞和梁侧主背楞;梁侧模板面板的水平切面呈圆弧状,该圆弧的弧度与圆弧梁对应一侧纵向侧面的弧度相适应;梁侧次背楞有一组,每根梁侧次背楞与梁侧模板面板固定连接;在两根相邻的梁侧次背楞之间连接有第二对拉螺栓。本发明解决了传统的施工方法施工圆弧梁时成型效果和施工质量均达不到设计要求的技术问题。
A formwork system for circular arc beams and a construction method thereof, wherein the formwork system includes a beam bottom formwork structure, a beam side formwork structure and a first pair of tension bolts; the beam bottom formwork structure includes a beam bottom formwork panel and a beam bottom back flute; The long axis of the beam bottom back flute is an arc line, and the arc line radian is compatible with the arc beam long axis arc; the long axis of the beam bottom formwork panel is an arc line, and the arc line arc line is in line with the The radian of the long axis of the beam is compatible; the beam side formwork structure includes the beam side formwork panel, the beam side secondary back corrugation and the beam side main back corrugation; the horizontal section of the beam side formwork panel is arc-shaped, and the arc of the arc is the same Corresponding to the curvature of the longitudinal side of one side; there is a set of secondary corrugations on the beam side, and each beam side secondary corrugation is fixedly connected with the beam side formwork panel; there is a second corrugation between two adjacent beam side secondary corrugations. Pull bolts. The invention solves the technical problem that both the forming effect and the construction quality fail to meet the design requirements when the arc beam is constructed by the traditional construction method.
Description
技术领域technical field
本发明属于建筑施工领域,尤其涉及一种圆弧梁的模板体系及其施工方法。The invention belongs to the field of building construction, and in particular relates to a formwork system for circular arc beams and a construction method thereof.
背景技术Background technique
随着建筑业的蓬勃发展,为追求建筑结构形式多样化,圆弧形建筑日益增多,弧线在外侧看来,给人一种优美感;在内侧看来,给人一种向心感。但圆弧建筑在保证美观同时,势必增加了施工的难度。尤其是圆弧处梁的施工,从施工放线到模板支设若用普通方法施工,成型效果和施工质量均达不到设计要求。With the vigorous development of the construction industry, in order to pursue the diversification of architectural structures, there are more and more arc-shaped buildings. Looking from the outside, the arc gives people a sense of elegance; from the inside, it gives people a sense of centripetal. However, while ensuring the beauty of the arc building, it will inevitably increase the difficulty of construction. Especially for the construction of the beam at the arc, if the ordinary method is used for construction from construction setting-out to formwork support, the forming effect and construction quality will not meet the design requirements.
发明内容Contents of the invention
本发明的目的是提供一种圆弧梁的模板体系及其施工方法,要解决传统的施工方法施工圆弧梁的成型效果和施工质量均达不到设计要求的技术问题。The purpose of the present invention is to provide a formwork system and construction method for circular arc beams, and to solve the technical problem that the traditional construction method can not meet the design requirements in terms of the forming effect and construction quality of the circular arc beams.
为实现上述目的,本发明采用如下技术方案。In order to achieve the above object, the present invention adopts the following technical solutions.
一种圆弧梁的模板体系,搭设在圆弧梁下方的脚手架上;该模板体系包括有梁底模板结构、梁侧模板结构以及第一对拉螺栓;所述梁底模板结构包括有梁底模板面板和梁底次背楞;所述梁底次背楞有一组、且沿横向平行间隔布置在脚手架上;其中每根梁底次背楞的长轴线为圆弧线,且该圆弧线的弧度与圆弧梁长轴线的弧度相适应;所述梁底模板面板水平搭设在梁底次背楞上、沿待浇筑圆弧梁的底面通长设置;该梁底模板面板的长轴线为圆弧线,且该圆弧线的弧度与圆弧梁长轴线的弧度相适应;所述梁侧模板结构有两个、分别沿待浇筑圆弧梁两侧的纵向侧面通长设置;其中,每个梁侧模板结构均包括有梁侧模板面板、梁侧次背楞和梁侧主背楞;所述梁侧模板面板的水平切面呈圆弧状,该圆弧的弧度与待浇筑圆弧梁对应一侧纵向侧面的弧度相适应;所述梁侧次背楞有一组、沿梁侧模板面板水平切面的圆弧延伸方向间隔布置,并且每根梁侧次背楞与梁侧模板面板之间固定连接;在每两根相邻的梁侧次背楞之间均沿竖向间隔连接有第二对拉螺栓;所述梁侧主背楞有一组、沿竖向平行间隔连接在梁侧次背楞的外侧,并且每根梁侧主背楞均呈圆弧状;所述第一对拉螺栓连接在圆弧梁两侧、相对应的梁侧主背楞之间。A formwork system of an arc beam, which is erected on a scaffold below the arc beam; the formwork system includes a beam bottom formwork structure, a beam side formwork structure and a first pair of tension bolts; the beam bottom formwork structure includes a beam bottom formwork structure Formwork panel and beam bottom back flute; said beam bottom back flute has a group, and is arranged on the scaffold along the horizontal parallel interval; wherein the long axis of each beam bottom back flute is an arc line, and the arc line The arc of the beam is adapted to the arc of the long axis of the arc beam; the formwork panel at the bottom of the beam is horizontally erected on the back corrugated at the bottom of the beam, and is arranged along the entire length of the bottom surface of the arc beam to be poured; the long axis of the formwork panel at the bottom of the beam is An arc line, and the radian of the arc line is adapted to the arc of the long axis of the arc beam; there are two beam side formwork structures, which are respectively arranged along the longitudinal sides of the two sides of the arc beam to be poured; wherein, Each beam side formwork structure includes a beam side formwork panel, a beam side secondary back corrugation and a beam side main back corrugation; the horizontal section of the beam side formwork panel is arc-shaped, and the arc of the arc is the same as the arc to be poured. The radian of the longitudinal side of the corresponding side of the beam is adapted; there is a group of secondary back corrugations on the beam side, which are arranged at intervals along the arc extension direction of the horizontal section of the beam side formwork panel, and the distance between each beam side secondary back corrugation and the beam side formwork panel There is a fixed connection between each two adjacent beam side secondary back flutes; a second pair of tension bolts is connected along the vertical interval between each two adjacent beam side back flutes; the main back flute on the beam side has a group, which is connected to the beam side at vertical parallel intervals The outer side of the secondary back flute, and the main back flute on each beam side are arc-shaped; the first pair of tension bolts are connected between the two sides of the arc beam and the corresponding main back flute on the beam side.
优选的,所述圆弧梁的横截面呈T形,在圆弧梁两侧翼缘的下方搭设有翼缘底模板结构;所述翼缘底模板结构包括有翼缘底模板面板、翼缘次背楞和翼缘主背楞;所述翼缘底模板面板靠近圆弧梁腹板一侧的侧边为圆弧线,且该侧边紧贴在圆弧梁的腹板上;所述翼缘次背楞沿横向间隔布置,并且每根翼缘次背楞与翼缘底模板面板之间通过第一紧固件连接;所述翼缘主背楞有一组、沿纵向间隔设置在翼缘次背楞的底部,并且每根翼缘主背楞对应搭设在脚手架上;Preferably, the cross-section of the circular arc beam is T-shaped, and a flange bottom formwork structure is set up under the flanges on both sides of the circular arc beam; the flange bottom formwork structure includes a flange bottom formwork panel, a flange secondary The back flute and the main back flute of the flange; the side edge of the flange bottom template panel close to the arc beam web is an arc line, and this side is close to the web of the arc beam; the wing The edge and secondary back flute are arranged at intervals along the transverse direction, and each flange secondary back flute is connected to the flange bottom formwork panel through the first fastener; the flange main back flute has a set of longitudinal intervals arranged on the flange The bottom of the secondary back flute, and the main back flute of each flange is correspondingly erected on the scaffold;
所述圆弧梁其中一侧的翼缘与楼板连接,圆弧梁另一侧的翼缘外侧面上搭设有翼缘侧模板面板;所述翼缘侧模板面板的底部与对应一侧的翼缘次背楞的底部平齐,且通过第二紧固件与翼缘次背楞固定连接。The flange on one side of the circular arc beam is connected to the floor, and the flange side formwork panel is set up on the outer surface of the flange on the other side of the circular arc beam; the bottom of the flange side formwork panel is connected to the wing on the corresponding side. The bottom of the flange secondary back flute is flush, and is fixedly connected with the flange secondary back flute through the second fastener.
优选的,所述梁侧模板结构的顶部支撑在翼缘底模板面板的底部;所述梁侧模板结构的底部超出待浇筑圆弧梁的底面、且支撑在其底部的脚手架的水平杆上,其中,超出部分的长度为100mm~150mm;Preferably, the top of the beam side formwork structure is supported on the bottom of the flange bottom formwork panel; the bottom of the beam side formwork structure exceeds the bottom surface of the circular arc beam to be poured and is supported on the horizontal bar of the scaffold at the bottom, Among them, the length of the excess part is 100mm ~ 150mm;
所述梁底模板结构铺设在其底部脚手架的水平杆上、位于两侧的梁侧模板结构之间。The beam bottom formwork structure is laid on the horizontal bar of the scaffold at the bottom, and is located between the beam side formwork structures on both sides.
优选的,相邻两根梁侧次背楞之间的间距不大于250mm;其中,每根梁侧次背楞通过粘接胶与梁侧模板面板粘接;在梁侧次背楞的侧面上、沿竖向间隔开设有穿过第二对拉螺栓的通孔;竖向相邻的两根第二对拉螺栓之间间距不大于500mm;Preferably, the distance between two adjacent beam side secondary back flutes is not greater than 250mm; wherein, each beam side secondary back flute is bonded to the beam side formwork panel through adhesive glue; on the side of the beam side secondary back flute , There are through holes passing through the second pair of tension bolts spaced apart vertically; the distance between two vertically adjacent second pair of tension bolts is not greater than 500mm;
所述梁侧主背楞为双钢管背楞;所述第一对拉螺栓的两端对应穿设在梁侧主背楞的两根钢管之间的间隙中,并固定。The main back flute on the beam side is a double steel pipe back flute; the two ends of the first pair of pull bolts are respectively inserted in the gap between the two steel pipes on the main back flute on the beam side and fixed.
优选的,所述梁底模板面板为3D打印模板,且梁底模板面板与梁底次背楞之间采用第三紧固件对应连接。Preferably, the beam bottom formwork panel is a 3D printed formwork, and the beam bottom formwork panel and the beam bottom secondary back flute are correspondingly connected by a third fastener.
优选的,所述圆弧梁下方的脚手架的立杆顶部对应设有水平支撑;其中,每根水平支撑均呈圆弧状、且沿圆弧梁的长轴线方向通长设置;所述水平支撑支设在梁侧模板结构和梁底模板结构底部的水平杆的下方;Preferably, the top of the scaffolding pole below the arc beam is correspondingly provided with a horizontal support; wherein, each horizontal support is in the shape of an arc and is arranged along the long axis of the arc beam; the horizontal support Supported under the horizontal bar at the bottom of the beam side formwork structure and the beam bottom formwork structure;
所述脚手架的立杆的底部对应垫设有垫块。The bottom corresponding pad of the pole of described scaffold is provided with spacer.
一种模板体系的施工方法,包括步骤如下。A construction method of a formwork system comprises the following steps.
步骤一,制作梁底模板结构的梁底模板面板和梁底次背楞,同时制作梁侧模板结构的梁侧模板面板、梁侧次背楞和梁侧主背楞。Step 1, making the beam bottom formwork panel and the beam bottom secondary back flute of the beam bottom formwork structure, and simultaneously making the beam side formwork panel, beam side secondary back flute and beam side main back flute of the beam side formwork structure.
步骤二,测量放线:圆弧梁的施工放线采用弦线支距法进行现场放线。Step 2, measuring and setting out: the construction setting out of the circular arc beam adopts the chord distance method to carry out on-site setting out.
步骤三,对梁侧模板结构进行预拼装:将梁侧次背楞粘接在梁侧模板面板的外侧,相邻两根梁侧次背楞之间的间距不大于250mm;将第二对拉螺栓插入相邻梁侧次背楞上对应的通孔中,并拧紧固定。Step 3, pre-assemble the beam side formwork structure: glue the beam side secondary back flute on the outside of the beam side formwork panel, the distance between two adjacent beam side secondary back flutes shall not be greater than 250mm; The bolts are inserted into the corresponding through-holes on the side back of the adjacent beam, and tightened to fix.
步骤四,搭设梁底脚手架:在待浇筑圆弧梁的下方搭设脚手架,并且在圆弧梁下方的立杆顶部对应设置水平支撑。Step 4, set up the scaffolding at the bottom of the beam: set up the scaffolding under the arc beam to be poured, and set the horizontal support on the top of the vertical pole under the arc beam.
步骤五,铺设梁底模板结构:在水平支撑顶部的水平杆上铺设梁底次背楞,两侧的梁底次背楞采用连接件固定,实现梁底次背楞的弧度;然后将梁底模板面板根据图纸放置在设计位置处,对梁底模板面板进行调整并采用第三紧固件与梁底次背楞连接为整体。Step 5, laying the beam bottom formwork structure: Lay the beam bottom secondary corrugation on the horizontal bar at the top of the horizontal support, and the beam bottom secondary corrugations on both sides are fixed with connectors to realize the radian of the beam bottom secondary corrugation; then the beam bottom The formwork panel is placed at the design position according to the drawing, and the formwork panel at the bottom of the beam is adjusted and connected with the secondary back corrugation at the bottom of the beam with the third fastener as a whole.
步骤六,安装圆弧梁内侧纵向侧面位置处的梁侧模板结构;将步骤三中预拼装完毕的梁侧模板结构按照梁的支模方式安装在圆弧梁内侧的纵向侧面上,安装完成后对梁侧模板结构进行固定。Step 6, install the beam side formwork structure at the longitudinal side of the inner side of the arc beam; install the beam side formwork structure pre-assembled in step 3 on the longitudinal side of the inner side of the arc beam according to the way the beam is supported. Fix the beam side formwork structure.
步骤七,圆弧梁的钢筋绑扎。Step seven, binding the steel bars of the arc beams.
步骤八,合圆弧梁外侧纵向侧面上的梁侧模板结构;钢筋绑扎完毕后,将步骤三中预拼装完毕的梁侧模板结构安装在圆弧梁外侧的纵向侧面位置处,待该梁侧模板结构安装完毕后,对两个梁侧模板结构的位置进行复核;然后安装圆弧梁两侧的梁侧主背楞、并连接第一对拉螺栓。Step 8, combine the beam side formwork structure on the outer longitudinal side of the circular arc beam; after the steel bars are bound, install the beam side formwork structure pre-assembled in step 3 on the longitudinal side of the outer side of the circular arc beam, and wait for the beam side After the formwork structure is installed, review the position of the two beam side formwork structures; then install the beam side main back ribs on both sides of the arc beam and connect the first pair of pull bolts.
步骤九,混凝土浇筑。Step nine, concrete pouring.
优选的,步骤一中制作梁侧模板结构的方法具体为:根据圆弧梁的高度制作梁侧次背楞,梁侧次背楞长度超过圆弧梁高100mm~150mm;在梁侧次背楞的两个侧面上、距离两端不小于200mm的位置处开设通孔;Preferably, the method for making the formwork structure on the beam side in step 1 is as follows: according to the height of the arc beam, the secondary back corrugation on the beam side is made, and the length of the secondary back corrugation on the beam side exceeds the height of the arc beam by 100 mm to 150 mm; Through holes are set on the two sides of the container at a position not less than 200mm from both ends;
根据根据圆弧梁的高度和长度制作梁侧模板面板;Make beam side formwork panels according to the height and length of arc beams;
优选的,步骤一中制作梁底模板结构的方法具体为:通过revit软件建立圆弧梁的BIM模型,将圆弧梁的各项参数输入BIM模型,最终通过revit输出端口与3D打印机进行连接,利用3D打印机按照模型参数将梁底模板面板完整打印。Preferably, the method for making the formwork structure at the bottom of the beam in step 1 is as follows: establish the BIM model of the arc beam through revit software, input the parameters of the arc beam into the BIM model, and finally connect with the 3D printer through the revit output port, Use the 3D printer to completely print the beam bottom formwork panel according to the model parameters.
优选的,步骤二中圆弧梁的测量放线的方法具体为:已知设计图纸中圆弧梁的圆弧c1cn,作弦c1cn的平行线a1an和b1bn,将a1an等分成若干段分别为a1a2、a2a3……an-1an,将b1bn等分成若干段分别为b1b2、b2b3……bn-1bn,连接a1b1、a2b2、a3b3......anbn作失高h1、h2、h3......hn,失高h1、h2、h3......hn分别与圆弧c1cn相交于c1、c2、c3......cn;然后将c1、c2、c3......cn的坐标在施工现场进行定位,依次连接形成圆弧曲线,完成放线。Preferably, the method of measuring and setting out the arc beam in step 2 is specifically: the arc c 1 c n of the arc beam in the design drawing is known, and the parallel lines a 1 a n and b 1 of the chord c 1 c n are known b n , divide a 1 a n into several segments as a 1 a 2 , a 2 a 3 ... a n-1 a n , divide b 1 b n into several segments as b 1 b 2 , b 2 b 3 ... b n-1 b n , connect a 1 b 1 , a 2 b 2 , a 3 b 3 ...... a n b n to make height h 1 , h 2 , h 3 ... ...h n , loss of height h 1 , h 2 , h 3 ...h n intersects arc c 1 c n at c 1 , c 2 , c 3 ...c n ; Then locate the coordinates of c 1 , c 2 , c 3 .
优选的,步骤二中圆弧梁的测量放线的方法采用优化失高hn的计算与a1a11、b1b11位置的确定的方法:首先使用电脑作图的方法直接量出失高h1、h2、h3.....hn的尺寸,再在设计图纸中依据轴网进行定位,找出点a1、a2、a3......an与轴网中轴线间的位置关系,同时找出b1、b2、b3......bn与轴网中轴线间的位置关系,然后在施工现场放出a1an、b1bn两条线段,然后根据a1an、b1bn及hn线,定位圆弧梁的圆弧c1cn线。Preferably, the method of measuring and setting out the circular arc beam in step 2 adopts the method of optimizing the calculation of loss height h n and determining the positions of a 1 a 11 and b 1 b 11 : firstly, use the computer drawing method to directly measure the loss height h 1 , h 2 , h 3 .....h n , and then locate the points a 1 , a 2 , a 3 ...a n in the design drawings according to the grid. The positional relationship between the central axis of the grid, find out the positional relationship between b 1 , b 2 , b 3 ... b n and the central axis of the grid at the same time, and then release a 1 a n , b 1 at the construction site b n two line segments, and then according to a 1 a n , b 1 b n and h n lines, locate the arc c 1 c n line of the arc beam.
与现有技术相比本发明具有以下特点和有益效果。Compared with the prior art, the present invention has the following characteristics and beneficial effects.
1、本发明中的模板体系采用圆弧形的梁底模板结构和梁侧模板结构,其中梁底模板结构和梁侧模板结构根据待施工的圆弧梁的结构参数进行设计,大大保证了圆弧梁混凝土浇筑后成型质量。1. The formwork system in the present invention adopts arc-shaped beam bottom formwork structure and beam side formwork structure, wherein the beam bottom formwork structure and beam side formwork structure are designed according to the structural parameters of the arc beam to be constructed, which greatly ensures the circular Forming quality of arc beam concrete after pouring.
2、本发明中的梁侧模板结构中,梁侧次背楞利用粘接胶粘接在梁侧模板面板上,并且在相邻的梁侧次背楞之间连接第二对拉螺栓,梁侧模板结构的这种设计不仅增加了梁侧模板结构的稳定性,而且将梁侧次背楞预先连接在梁侧模板面板上大大的降低了施工难度,尤其适用于大跨度的圆弧梁的施工。2. In the beam side formwork structure in the present invention, the beam side secondary back flute is bonded on the beam side formwork panel with adhesive, and the second pair of pull bolts is connected between adjacent beam side secondary back flutes, and the beam side This design of the side formwork structure not only increases the stability of the beam side formwork structure, but also pre-connects the beam side back flute to the beam side formwork panel, which greatly reduces the construction difficulty, especially for long-span arc beams. construction.
3、本发明的施工方法中通过测量放线,铺底模,加侧模,合模后进行混凝土正常浇筑,最终在强度满足条件要求后,拆除圆弧梁模板,按照先装后拆,后装先拆原则将模板拆除,移至上层循环使用,解决了传统的施工方法中,圆弧梁的成型效果和施工质量均达不到设计要求的技术问题。3. In the construction method of the present invention, set out the line by measuring, lay the bottom formwork, add side forms, and carry out normal pouring of concrete after the formwork is closed. Finally, after the strength meets the condition requirements, the circular arc beam formwork is removed. The principle of dismantling first removes the formwork and moves it to the upper layer for recycling, which solves the technical problem that the forming effect and construction quality of the circular arc beam cannot meet the design requirements in the traditional construction method.
4、本发明的施工方法中,圆弧梁的施工放线采用弦线支距法进行现场放线,并且在确定圆弧c1cn中c1、c2、c3......cn的坐标时,在弦c1cn外侧做平行线a1an和b1bn,利用两条平行线进行坐标的确定,确保坐标的准确度。4. In the construction method of the present invention, the construction setting out of the circular arc beam adopts the chord branch distance method for on-site setting out, and c 1 , c 2 , c 3 ..... in determining the arc c 1 c n For the coordinates of .c n , draw parallel lines a 1 a n and b 1 b n outside the chord c 1 c n , and use the two parallel lines to determine the coordinates to ensure the accuracy of the coordinates.
附图说明Description of drawings
下面结合附图对本发明做进一步详细的说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.
图1是本发明中圆弧梁的布置的结构示意图。Fig. 1 is a structural schematic diagram of the arrangement of circular arc beams in the present invention.
图2是本发明中圆弧梁的横截面示意图。Fig. 2 is a schematic cross-sectional view of an arc beam in the present invention.
图3是本发明中模板体系的结构示意图。Fig. 3 is a schematic structural diagram of the template system in the present invention.
图4是本发明中模板体系的梁底模板结构和梁侧模板结构的细部结构示意图。Fig. 4 is a schematic diagram of the detailed structure of the beam bottom formwork structure and the beam side formwork structure of the formwork system in the present invention.
图5是本发明中梁侧模板面板与梁侧次背楞的连接结构的正面示意图。Fig. 5 is a schematic front view of the connection structure between the formwork panel on the side of the beam and the secondary corrugation on the side of the beam in the present invention.
图6是本发明中梁侧模板面板与梁侧次背楞的连接结构的水平切面示意图。Fig. 6 is a schematic diagram of a horizontal section of the connection structure between the formwork panel on the side of the middle beam and the secondary corrugation on the side of the beam in the present invention.
图7是本发明中梁侧模板面板与梁侧次背楞的连接结构的侧面示意图。Fig. 7 is a schematic side view of the connection structure between the formwork panel on the side of the middle beam and the secondary corrugation on the side of the beam in the present invention.
图8是本发明的施工方法中圆弧梁的测量放线示意图。Fig. 8 is a schematic diagram of measurement and setting-out of arc beams in the construction method of the present invention.
附图标记:1-圆弧梁、2-脚手架、2.1-水平杆、2.2-立杆、3-第一对拉螺栓、4-梁底模板面板、5-梁底次背楞、6-梁侧模板面板、7-梁侧次背楞、8-梁侧主背楞、9-第二对拉螺栓、10-翼缘底模板面板、11-翼缘次背楞、12-翼缘主背楞、13-第一紧固件、14-翼缘侧模板面板、15-第二紧固件、16-通孔、17-第三紧固件、18-水平支撑、19-垫块。Reference signs: 1-arc beam, 2-scaffolding, 2.1-horizontal rod, 2.2-vertical rod, 3-the first pair of pull bolts, 4-beam bottom formwork panel, 5-beam bottom back corrugated, 6-beam Side formwork panel, 7-beam side secondary back flute, 8-beam side main back flute, 9-second pair of tension bolts, 10-flange bottom formwork panel, 11-flange secondary back flute, 12-flange main back Corrugation, 13-first fastener, 14-flange side formwork panel, 15-second fastener, 16-through hole, 17-third fastener, 18-horizontal support, 19-pad.
具体实施方式Detailed ways
如图1-7所示,这种圆弧梁的模板体系,搭设在圆弧梁1下方的脚手架2上;该模板体系包括有梁底模板结构、梁侧模板结构以及第一对拉螺栓3;所述梁底模板结构包括有梁底模板面板4和梁底次背楞5;所述梁底次背楞5有一组、且沿横向平行间隔布置在脚手架2上;其中每根梁底次背楞5的长轴线为圆弧线,且该圆弧线的弧度与圆弧梁1长轴线的弧度相适应;所述梁底模板面板4水平搭设在梁底次背楞5上、沿待浇筑圆弧梁1的底面通长设置;该梁底模板面板4的长轴线为圆弧线,且该圆弧线的弧度与圆弧梁1长轴线的弧度相适应;所述梁侧模板结构有两个、分别沿待浇筑圆弧梁1两侧的纵向侧面通长设置;其中,每个梁侧模板结构均包括有梁侧模板面板6、梁侧次背楞7和梁侧主背楞8;所述梁侧模板面板6的水平切面呈圆弧状,该圆弧的弧度与待浇筑圆弧梁1对应一侧纵向侧面的弧度相适应;所述梁侧次背楞7有一组、沿梁侧模板面板6水平切面的圆弧延伸方向间隔布置,并且每根梁侧次背楞7与梁侧模板面板6之间固定连接;在每两根相邻的梁侧次背楞7之间均沿竖向间隔连接有第二对拉螺栓9;所述梁侧主背楞8有一组、沿竖向平行间隔连接在梁侧次背楞7的外侧,并且每根梁侧主背楞8均呈圆弧状;所述第一对拉螺栓3连接在圆弧梁1两侧、相对应的梁侧主背楞8之间。As shown in Figure 1-7, the formwork system of this arc beam is set up on the scaffold 2 under the arc beam 1; The beam bottom formwork structure includes a beam bottom formwork panel 4 and a beam bottom secondary back corrugation 5; the beam bottom secondary back corrugation 5 has a group and is arranged on the scaffold 2 along the horizontal parallel interval; wherein each beam bottom secondary The long axis of the back flute 5 is an arc line, and the radian of the arc line is adapted to the arc of the long axis of the arc beam 1; The bottom surface of the pouring arc beam 1 is set to be long; the long axis of the beam bottom formwork panel 4 is an arc line, and the arc of the arc line is adapted to the arc of the arc beam 1 long axis; the beam side formwork structure There are two, respectively arranged along the longitudinal sides of both sides of the circular arc beam 1 to be poured; wherein, each beam side formwork structure includes a beam side formwork panel 6, a beam side secondary back flute 7 and a beam side main back flute 8. The horizontal section of the beam side template panel 6 is arc-shaped, and the arc of the arc is adapted to the arc of the longitudinal side of the corresponding side of the arc beam 1 to be poured; the beam side secondary back 7 has a group, Arranged at intervals along the arc extension direction of the horizontal section of the beam side formwork panel 6, and each beam side secondary back flute 7 is fixedly connected to the beam side formwork panel 6; between every two adjacent beam side secondary back flutes 7 The second pair of pull bolts 9 are connected at vertical intervals; the beam side main back flute 8 has a group, which is connected to the outside of the beam side secondary back flute 7 along the vertical parallel interval, and each beam side main back flute 8 are all arc-shaped; the first pair of pull bolts 3 are connected between the two sides of the arc beam 1 and the corresponding main back ribs 8 on the beam side.
本实施例中,模板体系中的各个构件采用定型化加工制作。In this embodiment, each component in the formwork system is manufactured by stereotyped processing.
本实施例中,所述圆弧梁1的横截面呈T形,在圆弧梁1两侧翼缘的下方搭设有翼缘底模板结构;所述翼缘底模板结构包括有翼缘底模板面板10、翼缘次背楞11和翼缘主背楞12;所述翼缘底模板面板10靠近圆弧梁1腹板一侧的侧边为圆弧线,且该侧边紧贴在圆弧梁1的腹板上;所述翼缘次背楞11沿横向间隔布置,并且每根翼缘次背楞11与翼缘底模板面板10之间通过第一紧固件13连接;所述翼缘主背楞12有一组、沿纵向间隔设置在翼缘次背楞11的底部,并且每根翼缘主背楞12对应搭设在脚手架2上In this embodiment, the cross-section of the circular arc beam 1 is T-shaped, and a flange bottom formwork structure is set up under the flanges on both sides of the circular arc beam 1; the flange bottom formwork structure includes a flange bottom formwork panel 10. Flange secondary back flute 11 and flange main back flute 12; the side edge of the flange bottom template panel 10 close to the web side of the arc beam 1 is an arc line, and the side edge is close to the arc line On the web of the beam 1; the flange secondary back flute 11 is arranged at intervals along the transverse direction, and each flange secondary back flute 11 is connected to the flange bottom formwork panel 10 through a first fastener 13; the wing There are one set of main flange back flutes 12 arranged longitudinally at the bottom of the flange secondary back flutes 11, and each flange main back flute 12 is set up on the scaffold 2 correspondingly
所述圆弧梁1其中一侧的翼缘与楼板连接,圆弧梁1另一侧的翼缘外侧面上搭设有翼缘侧模板面板14;所述翼缘侧模板面板14的底部与对应一侧的翼缘次背楞11的底部平齐,且通过第二紧固件15与翼缘次背楞11固定连接。The flange on one side of the circular arc beam 1 is connected to the floor, and the flange side formwork panel 14 is set up on the outer surface of the flange on the other side of the circular arc beam 1; the bottom of the flange side formwork panel 14 is connected to the corresponding The bottom of the flange secondary back flute 11 on one side is flush, and is fixedly connected to the flange secondary back flute 11 through the second fastener 15 .
本实施例中,所述梁侧模板结构的顶部支撑在翼缘底模板面板10的底部;所述梁侧模板结构的底部超出待浇筑圆弧梁1的底面、且支撑在其底部的脚手架2的水平杆2.1上,其中,超出部分的长度为100mm~150mm;In this embodiment, the top of the beam side formwork structure is supported on the bottom of the flange bottom formwork panel 10; the bottom of the beam side formwork structure exceeds the bottom surface of the arc beam 1 to be poured and is supported on the scaffolding 2 at the bottom On the horizontal bar 2.1, the length of the excess part is 100mm-150mm;
所述梁底模板结构铺设在其底部脚手架2的水平杆2.1上、位于两侧的梁侧模板结构之间。The beam bottom formwork structure is laid on the horizontal bar 2.1 of the bottom scaffold 2, between the beam side formwork structures on both sides.
本实施例中,相邻两根梁侧次背楞7之间的间距不大于250mm;其中,每根梁侧次背楞7通过粘接胶与梁侧模板面板6粘接;在梁侧次背楞7的侧面上、沿竖向间隔开设有穿过第二对拉螺栓9的通孔16;竖向相邻的两根第二对拉螺栓9之间间距不大于500mm;In this embodiment, the distance between two adjacent beam side secondary corrugations 7 is not more than 250mm; wherein, each beam side secondary corrugation 7 is bonded to the beam side formwork panel 6 through adhesive glue; On the side of the back flute 7, through holes 16 passing through the second pair of tension bolts 9 are vertically spaced apart; the distance between the vertically adjacent two second pair of tension bolts 9 is not greater than 500mm;
所述梁侧主背楞8为双钢管背楞;所述第一对拉螺栓3的两端对应穿设在梁侧主背楞8的两根钢管之间的间隙中,并固定。The main back flute 8 on the beam side is a double steel pipe back flute; the two ends of the first pair of tension bolts 3 are respectively inserted in the gap between the two steel pipes of the main back flute 8 on the beam side and fixed.
本实施例中,所述第二对拉螺栓9有多组,其中每组第二对拉螺栓9沿竖向平行间隔设置在相邻梁侧次背楞7之间;所述通孔16在梁侧次背楞7的侧面用机械提前打孔,孔宽16mm;为保证第二对拉螺栓9的正常插入,避免同一排螺栓碰撞,相邻两组第二对拉螺栓9的孔位错开布置;根据圆弧梁1的梁高,同一组第二对拉螺栓9的孔位中,上下两排孔位不得超过500mm;相邻两组第二对拉螺栓9的孔位中,横向对应的两个第二对拉螺栓9的孔位竖向间隔50mm。In this embodiment, there are multiple groups of the second pair of tension bolts 9, wherein each group of second pair of tension bolts 9 is vertically parallel and spaced between the secondary back corrugations 7 on the side of adjacent beams; the through holes 16 are The side of the beam side secondary corrugation 7 is mechanically drilled in advance, and the hole width is 16mm; in order to ensure the normal insertion of the second pair of tension bolts 9 and avoid the collision of the same row of bolts, the hole positions of the second pair of tension bolts 9 in two adjacent groups are staggered Arrangement; according to the beam height of the circular arc beam 1, among the holes of the second pair of tie bolts 9 in the same group, the upper and lower rows of holes shall not exceed 500mm; among the holes of the second pair of tie bolts 9 in two adjacent groups, the corresponding The hole positions of the two second pair of pull bolts 9 are vertically spaced by 50mm.
本实施例中,所述梁底模板面板4为3D打印模板,直接将弧度等数据输入3D打印机,通过添加模板材料打印出3D成品;且梁底模板面板4与梁底次背楞5之间采用第三紧固件17对应连接。In this embodiment, the beam bottom formwork panel 4 is a 3D printing template, and data such as radians are directly input into the 3D printer, and the 3D finished product is printed out by adding template materials; Use the third fastener 17 for corresponding connection.
本实施例中,所述圆弧梁1下方的脚手架2的立杆2.2顶部对应设有水平支撑18;其中,每根水平支撑18均呈圆弧状、且沿圆弧梁1的长轴线方向通长设置;所述水平支撑18支设在梁侧模板结构和梁底模板结构底部的水平杆2.1的下方;In this embodiment, the top of the vertical pole 2.2 of the scaffold 2 below the arc beam 1 is correspondingly provided with a horizontal support 18; wherein, each horizontal support 18 is in the shape of an arc and along the long axis direction of the arc beam 1 The overall length is set; the horizontal support 18 is supported under the horizontal bar 2.1 at the bottom of the beam side formwork structure and the beam bottom formwork structure;
所述脚手架2的立杆2.2的底部对应垫设有垫块19。The bottom of the pole 2.2 of the scaffold 2 is provided with a spacer 19 corresponding to the pad.
本实施例中,所述脚手架2采用扣件式钢管,圆弧梁1底支设两根立杆2.2,顶部回顶一根水平支撑18,在梁底模板结构底部的水平杆2.1之间、位于梁底次背楞5的底部沿纵向平行间隔设有梁底主背楞,梁底主背楞采用圆钢管制成。用水准仪对翼缘底模板结构及梁底模板结构测平后,水平杆2.1与立杆2.2连接处均用十字扣件锁紧,拧紧扭力矩不应小于40N·m,且不应大于65N·m。In this embodiment, the scaffold 2 adopts fastener type steel pipes, two vertical poles 2.2 are supported at the bottom of the circular arc beam 1, and a horizontal support 18 is pushed back at the top, between the horizontal poles 2.1 at the bottom of the formwork structure at the beam bottom, The bottom of the beam bottom secondary corrugation 5 is provided with a beam bottom main corrugation along the longitudinal parallel interval, and the beam bottom main corrugation is made of round steel pipe. After measuring the leveling of the flange bottom formwork structure and the beam bottom formwork structure with a level, the joints between the horizontal bar 2.1 and the vertical bar 2.2 are locked with cross fasteners, and the tightening torque should not be less than 40N·m and should not be greater than 65N· m.
本实施例中,梁底模板面板4底部、位于最外侧的两根梁底次背楞5的外边均固定有十字扣件实现梁底次背楞5的弧度,将3D打印的梁底模板面板4按照制作标号,根据图纸放置在规定位置;现场通过吊线坠进行梁底模板面板4位置的微调精准后,在底部的梁底次背楞5上,用木方钉将梁底模板面板4与梁底次背楞5钉为整体。In this embodiment, the bottom of the beam bottom formwork panel 4 and the outer sides of the two outermost beam bottom back corrugations 5 are fixed with cross fasteners to realize the radian of the beam bottom back corrugation 5, and the 3D printed beam bottom formwork panels 4 According to the production label, place it in the specified position according to the drawing; after fine-tuning the position of the beam bottom formwork panel 4 through the hanging wire pendant on site, use wooden square nails to connect the beam bottom formwork panel 4 and The bottom of the beam has 5 nails on the back corrugated as a whole.
本实施例中,所述第一紧固件13、第二紧固件15和第三紧固件17均采用木方钉。In this embodiment, the first fastener 13 , the second fastener 15 and the third fastener 17 are all made of wooden square nails.
当然在其他实施例中,所述第一紧固件13、第二紧固件15和第三紧固件17还可以采用螺钉或者自攻钉等其他类型的钢钉。Of course, in other embodiments, the first fastener 13 , the second fastener 15 and the third fastener 17 may also use other types of steel nails such as screws or self-tapping screws.
这种模板体系的施工方法,包括步骤如下。The construction method of this formwork system includes the following steps.
步骤一,制作梁底模板结构的梁底模板面板4和梁底次背楞5,同时制作梁侧模板结构的梁侧模板面板6、梁侧次背楞7和梁侧主背楞8。Step 1: Make the beam bottom formwork panel 4 and the beam bottom secondary back flute 5 of the beam bottom formwork structure, and simultaneously make the beam side formwork panel 6, the beam side secondary back flute 7 and the beam side main back flute 8 of the beam side formwork structure.
步骤二,测量放线:圆弧梁1的施工放线采用弦线支距法进行现场放线,如图8所示。Step 2, measuring and setting out: the construction setting out of the circular arc beam 1 adopts the chord distance method to carry out on-site setting out, as shown in Figure 8.
步骤三,对梁侧模板结构进行预拼装:将梁侧次背楞7粘接在梁侧模板面板6的外侧,相邻两根梁侧次背楞7之间的间距不大于250mm;将第二对拉螺栓9插入相邻梁侧次背楞7上对应的通孔16中,并拧紧固定。Step 3, pre-assemble the beam side formwork structure: bond the beam side secondary back corrugations 7 to the outside of the beam side formwork panel 6, and the distance between two adjacent beam side secondary back corrugations 7 is not greater than 250mm; Two pairs of pull bolts 9 are inserted into the corresponding through holes 16 on the secondary back corrugated 7 of the adjacent beam side, and are tightened and fixed.
步骤四,搭设梁底脚手架2:在待浇筑圆弧梁1的下方搭设脚手架2,并且在圆弧梁1下方的脚手架2的立杆2.2顶部对应设置水平支撑18。Step 4, setting up the scaffolding 2 at the bottom of the beam: erecting the scaffolding 2 under the circular arc beam 1 to be poured, and setting a horizontal support 18 on the top of the vertical pole 2.2 of the scaffolding 2 under the circular arc beam 1 correspondingly.
步骤五,铺设梁底模板结构:在水平支撑18顶部的水平杆2.1上铺设梁底次背楞5,两侧的梁底次背楞5采用连接件固定,实现梁底次背楞5的弧度;然后将梁底模板面板4根据图纸放置在设计位置处,对梁底模板面板4进行调整并采用第三紧固件17与梁底次背楞5连接为整体。Step 5, laying the beam bottom formwork structure: Lay the beam bottom back flute 5 on the horizontal bar 2.1 on the top of the horizontal support 18, and the beam bottom back flute 5 on both sides are fixed by connectors to realize the radian of the beam bottom back flute 5 Then place the beam bottom formwork panel 4 at the design position according to the drawing, adjust the beam bottom formwork panel 4 and use the third fastener 17 to connect with the beam bottom secondary back flute 5 as a whole.
步骤六,安装圆弧梁1内侧纵向侧面位置处的梁侧模板结构,此处圆弧梁1与楼板连接一侧为内侧;将步骤三中预拼装完毕的梁侧模板结构按照梁的支模方式安装在圆弧梁1内侧的纵向侧面上,安装完成后对梁侧模板结构进行固定。Step 6, install the beam side formwork structure at the longitudinal side of the inner side of the arc beam 1, where the side where the arc beam 1 is connected to the floor is the inner side; the beam side formwork structure pre-assembled in step 3 shall be supported according to the formwork of the beam It is installed on the longitudinal side of the inner side of the arc beam 1 by means of a method, and after the installation is completed, the formwork structure on the side of the beam is fixed.
步骤七,圆弧梁1的钢筋绑扎;钢筋绑扎完毕后,用吹风机或锯末吸尘器将梁侧模板结构内的垃圾清理干净后。Step 7, binding the steel bars of the circular arc beam 1; after the steel bars are bound, use a hair dryer or a sawdust cleaner to clean up the garbage in the formwork structure on the side of the beam.
步骤八,合圆弧梁1外侧纵向侧面上的梁侧模板结构;钢筋绑扎完毕后,将步骤三中预拼装完毕的梁侧模板结构安装在圆弧梁1外侧的纵向侧面位置处,待该梁侧模板结构安装完毕后,对该梁侧模板结构的位置进行吊线复核;然后安装圆弧梁1两侧的梁侧主背楞8、并连接第一对拉螺栓3,有误差时通过调整第一对拉螺栓3进行调节。Step 8, combine the beam side formwork structure on the outer longitudinal side of the circular arc beam 1; After the beam side formwork structure is installed, check the position of the beam side formwork structure with the hanging wire; then install the beam side main back corrugations 8 on both sides of the arc beam 1, and connect the first pair of pull bolts 3, and adjust it if there is an error. The first pair of pull bolts 3 is adjusted.
步骤九,混凝土浇筑。Step nine, concrete pouring.
本实施例中,步骤一中制作梁侧模板结构的方法具体为:根据圆弧梁1的高度制作梁侧次背楞7,梁侧次背楞7长度超过圆弧梁1高100mm~150mm;在梁侧次背楞7的两个侧面上、距离两端不小于200mm的位置处开设通孔16;根据根据圆弧梁1的高度和长度制作梁侧模板面板6;In this embodiment, the method for making the beam side formwork structure in step 1 is as follows: according to the height of the arc beam 1, the beam side secondary corrugation 7 is made, and the length of the beam side secondary corrugation 7 exceeds the height of the arc beam 1 by 100 mm to 150 mm; Open the through hole 16 on the two sides of the beam side back corrugated 7, the distance from the two ends is not less than 200mm; make the beam side formwork panel 6 according to the height and length of the circular arc beam 1;
本实施例中,步骤一中制作梁底模板结构的方法具体为:通过revit软件建立圆弧梁1的BIM模型,将圆弧梁1的各项参数:包括圆弧梁1的截面尺寸、长度、弧度,所处的楼板的厚度,与圆弧梁1相接的竖向承重结构的截面尺寸,圆弧梁1所处的空间定位等输入BIM模型,最终通过revit输出端口与3D打印机进行连接,利用3D打印机按照模型参数将梁底模板面板4完整打印。In this embodiment, the method for making the beam bottom formwork structure in step 1 is specifically: establish the BIM model of the arc beam 1 through the revit software, and set the parameters of the arc beam 1: including the cross-sectional size and length of the arc beam 1 , radian, the thickness of the floor, the cross-sectional size of the vertical load-bearing structure connected to the arc beam 1, and the spatial positioning of the arc beam 1 are input into the BIM model, and finally connected to the 3D printer through the revit output port , use the 3D printer to completely print the beam bottom template panel 4 according to the model parameters.
本实施例中,步骤二中圆弧梁1的测量放线的方法具体为:由于圆弧梁1的弧度、长度及定位(圆弧c1cn)在设计图纸中均是已知的,即已知设计图纸中圆弧梁1的圆弧c1cn,首先在电子设计图中做作弦c1cn的平行线a1an和b1bn,为确保准确度;将a1an等分成若干段分别为a1a2、a2a3……an-1an,将b1bn等分成若干段分别为b1b2、b2b3……bn-1bn,连接a1b1、a2b2、a3b3......anbn作失高h1、h2、h3......hn,失高h1、h2、h3......hn分别与圆弧c1cn相交于c1、c2、c3......cn;然后将c1、c2、c3......cn的坐标在施工现场进行定位,依次连接形成圆弧曲线,完成放线,在图中所取a1~an、b1~bn的点越多,所得到的c1~cn点越多,现场定位的精确度越高。In this embodiment, the method for measuring and setting out the arc beam 1 in step 2 is specifically: since the radian, length and positioning (arc c 1 c n ) of the arc beam 1 are known in the design drawings, That is to say, the arc c 1 c n of the arc beam 1 in the design drawing is known, firstly, the parallel lines a 1 a n and b 1 b n of the chord c 1 c n are made in the electronic design drawing, in order to ensure the accuracy; a 1 a n is divided into several segments, namely a 1 a 2 , a 2 a 3 ... a n-1 a n , and b 1 b n is divided into several segments, respectively b 1 b 2 , b 2 b 3 ... b n-1 b n , connect a 1 b 1 , a 2 b 2 , a 3 b 3 ......a n b n to make height h 1 , h 2 , h 3 ......h n , loss of height h 1 , h 2 , h 3 ... h n intersects arc c 1 c n at c 1 , c 2 , c 3 ... c n respectively; then c 1 , c 2 , c 3 ...... c n coordinates are positioned at the construction site, connected in sequence to form arc curves, and the line is completed . The more points, the more c 1 -c n points obtained, and the higher the accuracy of on-site positioning.
本实施例中,步骤二中圆弧梁1的测量放线的方法还可以用优化失高hn的计算与a1a11、b1b11位置的确定的方法:首先使用电脑作图的方法直接量出失高h1、h2、h3.....hn的尺寸,再在设计图纸中依据轴设计图中的轴网轴线进行定位,找出点a1、a2、a3......an与轴网轴线间的位置关系,同时找出b1、b2、b3......bn与轴网轴线间的位置关系,然后在施工现场放出a1an、b1bn两条线段(轴网根据测绘院所给基准点已放线完成),然后根据a1an、b1bn及hn线,定位圆弧梁1的圆弧c1cn线。In this embodiment, the method of measuring and setting out the circular arc beam 1 in step 2 can also use the method of optimizing the calculation of the lost height h n and the determination of the positions of a 1 a 11 and b 1 b 11 : first, use the method of computer drawing The method directly measures the dimensions of the loss heights h 1 , h 2 , h 3 ..... hn , and then locates the points a 1 , a 2 , The positional relationship between a3...a n and the grid axis, and at the same time find out the positional relationship between b 1 , b 2 , b 3 ...b n and the grid axis, and then at the construction site Release the two line segments a 1 a n and b 1 b n (the axis network has been set out according to the reference point given by the surveying and mapping institute), and then position the arc beam 1 according to the lines a 1 a n , b 1 b n and h n The arc c 1 c n line.
本实施例中,步骤二中进行现场放线的具体方法为:在空余场地根据圆弧梁1的圆弧c1cn线进行放线,将梁侧模板结构置于墨线处,根据弧度通过第一对拉螺栓3上的螺母将圆弧形梁侧模板结构调至墨线部位,保证模板结构的弧度与圆弧梁1的弧度相适应。In this embodiment, the specific method for on-site setting-out in step 2 is: set-out the line according to the arc c 1 c n line of the arc beam 1 in the spare space, place the beam side formwork structure at the ink line, and pass through according to the arc The nuts on the first pair of pull bolts 3 adjust the arc-shaped beam side template structure to the ink line position to ensure that the arc of the template structure is compatible with the arc of the arc beam 1.
上述实施例并非具体实施方式的穷举,还可有其它的实施例,上述实施例目的在于说明本发明,而非限制本发明的保护范围,所有由本发明简单变化而来的应用均落在本发明的保护范围内。Above-mentioned embodiment is not exhaustive of specific implementation, also can have other embodiment, and above-mentioned embodiment purpose is to illustrate the present invention, rather than limit the scope of protection of the present invention, all applications that come from the simple change of the present invention all fall within the scope of this invention. within the scope of protection of the invention.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810459896.8A CN108331342B (en) | 2018-05-15 | 2018-05-15 | Template system of arc beam and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810459896.8A CN108331342B (en) | 2018-05-15 | 2018-05-15 | Template system of arc beam and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108331342A true CN108331342A (en) | 2018-07-27 |
CN108331342B CN108331342B (en) | 2023-03-21 |
Family
ID=62935095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810459896.8A Expired - Fee Related CN108331342B (en) | 2018-05-15 | 2018-05-15 | Template system of arc beam and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108331342B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110397270A (en) * | 2019-06-13 | 2019-11-01 | 中国建筑第四工程局有限公司 | Beam forms and its installation and method for supporting outside a kind of big sectional dimension arc |
CN110453916A (en) * | 2019-08-16 | 2019-11-15 | 杭州昂创科技有限公司 | By the arc beam construction method of adjustable arc beams regularization formwork erecting structure |
CN113338641A (en) * | 2021-06-21 | 2021-09-03 | 中建八局广西建设有限公司 | Arc-shaped sealing beam paying-off method in high-rise building |
CN113482326A (en) * | 2021-06-01 | 2021-10-08 | 上海宝冶集团有限公司 | Method for erecting arc formwork of bare concrete diaphragm wall |
CN116335393A (en) * | 2023-05-31 | 2023-06-27 | 北京市第三建筑工程有限公司 | Construction method of bare concrete hyperboloid beam structure based on wood formwork |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201428240Y (en) * | 2009-04-09 | 2010-03-24 | 温州建设集团公司 | Template with arc steps |
US20140305070A1 (en) * | 2012-06-11 | 2014-10-16 | Zhejiang Construction Engineering Group Co., Ltd. | Constructing method for concrete cylinder of construction steel bar of high-rise steel structure |
CN105971273A (en) * | 2016-06-23 | 2016-09-28 | 杭州江润科技有限公司 | Arc-shaped cast-in-place concrete beam based on set-shaped and quick-disassembling aluminum formworks and construction method |
CN106013787A (en) * | 2016-07-11 | 2016-10-12 | 中国建筑第八工程局有限公司 | Cast-in-place concrete beam formwork tool type reinforcing system and construction technology thereof |
CN106592966A (en) * | 2016-12-28 | 2017-04-26 | 河北建筑工程学院 | Support-beam-plate-free post-cast strip formwork system and construction method thereof |
CN206438769U (en) * | 2016-11-16 | 2017-08-25 | 大连三川建设集团股份有限公司 | It is a kind of to prevent that cast-in-situ concrete beam bottom from rising the structure of mould |
CN208220204U (en) * | 2018-05-15 | 2018-12-11 | 中国建筑第二工程局有限公司 | Template system of circular arc roof beam |
-
2018
- 2018-05-15 CN CN201810459896.8A patent/CN108331342B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201428240Y (en) * | 2009-04-09 | 2010-03-24 | 温州建设集团公司 | Template with arc steps |
US20140305070A1 (en) * | 2012-06-11 | 2014-10-16 | Zhejiang Construction Engineering Group Co., Ltd. | Constructing method for concrete cylinder of construction steel bar of high-rise steel structure |
CN105971273A (en) * | 2016-06-23 | 2016-09-28 | 杭州江润科技有限公司 | Arc-shaped cast-in-place concrete beam based on set-shaped and quick-disassembling aluminum formworks and construction method |
CN106013787A (en) * | 2016-07-11 | 2016-10-12 | 中国建筑第八工程局有限公司 | Cast-in-place concrete beam formwork tool type reinforcing system and construction technology thereof |
CN206438769U (en) * | 2016-11-16 | 2017-08-25 | 大连三川建设集团股份有限公司 | It is a kind of to prevent that cast-in-situ concrete beam bottom from rising the structure of mould |
CN106592966A (en) * | 2016-12-28 | 2017-04-26 | 河北建筑工程学院 | Support-beam-plate-free post-cast strip formwork system and construction method thereof |
CN208220204U (en) * | 2018-05-15 | 2018-12-11 | 中国建筑第二工程局有限公司 | Template system of circular arc roof beam |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110397270A (en) * | 2019-06-13 | 2019-11-01 | 中国建筑第四工程局有限公司 | Beam forms and its installation and method for supporting outside a kind of big sectional dimension arc |
CN110453916A (en) * | 2019-08-16 | 2019-11-15 | 杭州昂创科技有限公司 | By the arc beam construction method of adjustable arc beams regularization formwork erecting structure |
CN113482326A (en) * | 2021-06-01 | 2021-10-08 | 上海宝冶集团有限公司 | Method for erecting arc formwork of bare concrete diaphragm wall |
CN113338641A (en) * | 2021-06-21 | 2021-09-03 | 中建八局广西建设有限公司 | Arc-shaped sealing beam paying-off method in high-rise building |
CN113338641B (en) * | 2021-06-21 | 2023-01-31 | 中建八局广西建设有限公司 | Arc-shaped sealing beam paying-off method in high-rise building |
CN116335393A (en) * | 2023-05-31 | 2023-06-27 | 北京市第三建筑工程有限公司 | Construction method of bare concrete hyperboloid beam structure based on wood formwork |
CN116335393B (en) * | 2023-05-31 | 2023-09-19 | 北京市第三建筑工程有限公司 | Construction method of bare concrete hyperboloid beam structure based on wood formwork |
Also Published As
Publication number | Publication date |
---|---|
CN108331342B (en) | 2023-03-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108331342B (en) | Template system of arc beam and construction method thereof | |
RU2518580C2 (en) | Structure with multiple levels and method of its erection | |
WO2016086480A1 (en) | House structure and construction method therefor | |
US8245469B2 (en) | Deck assembly module for a steel framed building | |
US20170306621A1 (en) | An exterior wall and a method for constructing an exterior wall | |
CN108797847A (en) | A kind of assembled steel frame wall filled with masonry structural system and its construction method | |
US8448387B2 (en) | Wall panel and method | |
CN205604470U (en) | Steel core concrete column - girder steel external diaphragm formula node structure based on rib is indulged in trompil | |
CN105863257A (en) | Slab-beam separation type high-formwork support connected support building method of multilayered/high-rise reinforced concrete structure | |
CN106284988A (en) | Oblique circular cylinder template and construction method thereof | |
CN107859403B (en) | Assembled building structure | |
CN107165316A (en) | It is a kind of be easily installed, the assembling type steel structure out-hung panel node that is molded and its construction technology | |
CN206873673U (en) | A kind of assembling type steel structure out-hung panel node | |
CN206337678U (en) | The assembled steel frame wall filled with masonry system of door shape steel disc connection | |
CN108411763B (en) | Pre-spliced bridge and construction method thereof | |
CN211447349U (en) | Assembled shear force wall with X shaped steel pipe concrete bracing | |
CN112343330A (en) | Cylinder wall construction method and cylinder wall template structure of large-diameter reinforced concrete cylinder | |
CN103485538A (en) | Construction method of energy-saving insulation waterproof wood-trussed roof system | |
CN203603461U (en) | Floor aluminum shuttering splicing formwork structure system | |
CN116657875A (en) | Cantilever steel structure construction platform with formwork system and construction method | |
CN205776981U (en) | A kind of floor and the structure of making floor | |
US20190177975A1 (en) | Structural element | |
CN212175531U (en) | Steel pipe keel structure for super-thick concrete top plate | |
CN110820568B (en) | Method for mounting bailey truss of small-radius curve box girder bridge | |
CN208220204U (en) | Template system of circular arc roof beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230321 |