CN105863257A - Slab-beam separation type high-formwork support connected support building method of multilayered/high-rise reinforced concrete structure - Google Patents

Slab-beam separation type high-formwork support connected support building method of multilayered/high-rise reinforced concrete structure Download PDF

Info

Publication number
CN105863257A
CN105863257A CN201610082401.5A CN201610082401A CN105863257A CN 105863257 A CN105863257 A CN 105863257A CN 201610082401 A CN201610082401 A CN 201610082401A CN 105863257 A CN105863257 A CN 105863257A
Authority
CN
China
Prior art keywords
formwork
slab
support
bracket
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610082401.5A
Other languages
Chinese (zh)
Other versions
CN105863257B (en
Inventor
沈安跃
吴焕东
朱仙人
陈永波
王文学
王荣
王慧
陈亮
王露璐
吕沽乾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
UNIJES GROUP CO Ltd
Original Assignee
UNIJES GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by UNIJES GROUP CO Ltd filed Critical UNIJES GROUP CO Ltd
Priority to CN201610082401.5A priority Critical patent/CN105863257B/en
Publication of CN105863257A publication Critical patent/CN105863257A/en
Application granted granted Critical
Publication of CN105863257B publication Critical patent/CN105863257B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明提供一种多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法包括以下步骤:确定支模架参数;建立梁、板分离的支架模型并确立梁板支架的搭设方式;测定下层梁板的强度;搜集下层梁板的设计活荷载;确定梁板连支架的层数;支模架搭设。本发明大大地提高板模板支架周转次数,从而加快了工期。支模架结构计算的模型合理、受力明确,实施的技术先进,安全性和可靠性高。

The present invention provides a method for erecting a slab-beam separated high formwork-connected support of a multi-story and high-rise reinforced concrete structure, which includes the following steps: determining the parameters of the formwork frame; establishing a beam-slab-separated support model and establishing the erection method of the beam-slab support; Measure the strength of the lower beam slab; collect the design live load of the lower beam slab; determine the number of layers of the beam slab and support; erect the formwork. The invention greatly improves the turnover times of the plate formwork support, thereby speeding up the construction period. The calculation model of the formwork frame structure is reasonable, the force is clear, the implementation technology is advanced, and the safety and reliability are high.

Description

多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设 方法Erection of slab-girder separated high-support formwork and support for multi-story and high-rise reinforced concrete structures method

技术领域technical field

本发明涉及多、高层房屋结构上层超重大梁的扣件式、碗扣式以及轮扣式钢管支模架的施工方法。The invention relates to a construction method for fastener-type, bowl-type and wheel-type steel pipe formwork supports for super heavy girders on the upper floors of multi- and high-rise building structures.

背景技术Background technique

梁、板连支架的传统施工方法是将板梁的支模架连接在一起,梁下立杆支在下层的板上或部份梁上,不能辩别梁与板之间的垂直受荷传导途经,也无法建立一种有效的力学模型来精确计算下层连支架的层数,只能以模糊的方法将梁板下的支模架混合连支2层或3层应对上层超重负载,梁板支架交错传荷,不但对板的冲切承载力构成严重的威胁,而且当板梁面积占比很大时,会浪费大量的支模架。The traditional construction method of beams and slabs is to connect the formwork frames of the slab beams together, and the vertical rods under the beams are supported on the slabs or part of the beams on the lower floor, and the vertical load transmission between the beams and the slabs cannot be distinguished However, it is also impossible to establish an effective mechanical model to accurately calculate the number of layers of the lower-level brackets. We can only use a vague method to mix the support formwork under the beam and slab with 2 or 3 layers to cope with the super heavy load on the upper layer. The staggered load transfer of the supports not only poses a serious threat to the punching bearing capacity of the slab, but also wastes a lot of formwork when the area of the slab girder is large.

发明内容Contents of the invention

本发明所要解决的技术问题是提供一种多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,能够克服背景技术中的问题。The technical problem to be solved by the present invention is to provide a method for erecting a slab-beam separated high-support formwork and bracket of a multi-story reinforced concrete structure, which can overcome the problems in the background technology.

本发明解决技术问题所采用的技术方案是:多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,包括以下步骤:The technical scheme that the present invention solves technical problem adopts is: the slab girder separation type high support formwork connecting support erecting method of many, high-rise reinforced concrete structure, comprises the following steps:

(1)根据工程基本情况确定支模架参数;(1) Determine the parameters of the formwork frame according to the basic situation of the project;

(2)建立梁、板分离的支架模型并确立梁板支架的搭设方式;(2) Establish the bracket model of beam and slab separation and establish the erection method of beam and slab bracket;

(3)测定下层梁板的强度;(3) Determination of the strength of the lower beam slab;

(4)搜集下层梁板的设计活荷载;(4) Collect the design live load of the lower beam and slab;

(5)确定梁板连支架的层数;(5) Determine the number of layers of the beam-slab and support;

(6)支模架搭设;(6) Formwork frame erection;

在采用上述技术方案的同时,本发明还可以采用或者组合采用以下进一步的技术方案:While adopting the above-mentioned technical solution, the present invention can also adopt or adopt the following further technical solutions in combination:

所述步骤(1)中的工程基本情况包括建筑面积、建筑高度、基础形式、主体结构、抗震等级、抗震设防烈度、地上层数、地下层数和标准层高度。The basic conditions of the project in the step (1) include building area, building height, foundation form, main structure, seismic grade, seismic fortification intensity, number of floors above ground, number of underground floors and standard floor height.

所述步骤(1)中的支模架参数包括高支模及相关层结构详细情况,具体包括高支模所在层参数、高支模下方层结构参数、立杆基础参数、顶板板模板界面参数和顶梁轴模板界面参数。所述步骤(2)中的支架模型包括横向连杆、纵向连杆、梁底主楞、梁底增强双立杆甚至是多立杆、梁底受力立杆、横向连接杆、板底主楞、板底模板、板底次楞、板底交接断楞、板底断点连接楞、梁底次楞、横向剪刀撑杆、梁侧模板螺栓和板底立杆,The formwork frame parameters in the step (1) include high formwork and relevant layer structure details, specifically including the layer parameters of the high formwork, the layer structure parameters below the high formwork, the pole foundation parameters, and the roof plate formwork interface parameters and top beam axis template interface parameters. The bracket model in the step (2) includes transverse connecting rods, longitudinal connecting rods, beam bottom main corrugations, beam bottom reinforced double uprights or even multi-uprights, beam bottom stressed uprights, transverse connecting rods, slab bottom main flute, slab bottom formwork, slab bottom secondary flute, slab bottom junction broken flute, slab bottom break point connection flute, beam bottom secondary flute, transverse scissors brace, beam side formwork bolts and slab bottom vertical rod,

所述步骤(2)中的搭设方式具体包括以下步骤:The erection method in the described step (2) specifically includes the following steps:

2.1)在梁的横向侧部将板底的模板和主楞在沿梁的纵向方向断开;2.1) On the lateral side of the beam, the formwork at the bottom of the slab and the main flute are disconnected along the longitudinal direction of the beam;

2.2)然后将底板断点连接楞垫在其下再与板的立杆固定;2.2) Then connect the corrugated pad with the broken point of the bottom plate under it and fix it with the vertical pole of the plate;

2.3)取距两端梁底受力杆一定间距的横向连接杆,在其下端与梁底增强立杆以及梁底受力杆连接,同时与所有的纵向连接杆连接固定;2.3) Take the horizontal connecting rod at a certain distance from the beam bottom stress rods at both ends, connect the lower end of the beam bottom reinforced vertical rod and the beam bottom stress rod, and connect and fix all the longitudinal connecting rods at the same time;

2.5)梁底支架沿梁纵向每隔一定距离安装横向剪刀撑。2.5) The beam bottom bracket is installed with horizontal scissors at intervals along the longitudinal direction of the beam.

所述步骤(5)具体包括:Described step (5) specifically comprises:

5.1)根据下一层板的结构配筋状况确定现浇板连支架层数和拆除时间;5.1) Determine the number of layers of cast-in-place slabs and brackets and the removal time according to the structural reinforcement of the next slab;

5.2)楼板受力校验;5.2) Floor force verification;

5.3)根据梁受力计算确定板梁连接方式。5.3) Determine the plate-girder connection method according to the beam force calculation.

所述步骤(5)具体包括:Described step (5) specifically comprises:

5.1)按照模板图纸尺寸拼装成整体,控制模板的偏差在允许范围内;5.1) Assemble into a whole according to the size of the template drawing, and control the deviation of the template within the allowable range;

5.2)逐块检查拼装好的模板的背楞是否符合模板设计要求,模板的编号是否与所用部位一致;5.2) Check piece by piece whether the back flute of the assembled formwork meets the design requirements of the formwork, and whether the number of the formwork is consistent with the part used;

5.3)引测建筑的边柱或者墙轴线,并以该轴线为起点,引出每条轴线,并根据轴线与施工图用墨线弹出模板的内线、边线以及外侧控制线;5.3) Measure the axis of the side column or wall of the building, and use the axis as the starting point to draw out each axis, and pop out the inner line, side line and outer control line of the formwork with ink lines according to the axis and the construction drawing;

5.4)利用水准仪将建筑物水平标高根据实际要求,直接引测到模板的安装位置;5.4) Use the level to measure the horizontal elevation of the building directly to the installation position of the template according to the actual requirements;

5.5)根据模板图在钢筋绑扎验收后合拢梁侧模的支设;5.5) According to the formwork diagram, close up the support of the side formwork of the beam after the steel bar binding acceptance;

5.6)支模前对前一道工序的标高、尺寸预留孔的位置按设计图纸进行技术复核。5.6) Before supporting the formwork, conduct a technical review of the elevation and size of the reserved holes in the previous process according to the design drawings.

所述步骤(6)具体包括:Described step (6) specifically comprises:

6.1)先支梁底支架后支支板支架,再将两者用横向连系杆连接;6.1) First support the beam bottom bracket and then support the support plate bracket, and then connect the two with a horizontal tie rod;

6.2)梁板安装通过钢筋绑扎,在绑扎过程中为钢筋分项工程提供施工面;6.2) The beam and slab are installed through the binding of steel bars, and the construction surface is provided for the sub-projects of steel bars during the binding process;

6.3)在跨度≥4m的梁设置起拱2‰,梁模板上口设有拉紧锁扣杆;6.3) The beam with a span ≥ 4m is set with an arch of 2‰, and the top of the beam formwork is equipped with a tension lock lever;

6.4)用胶带纸封贴≥2mm的板缝;6.4) Use adhesive tape to seal the board seam ≥ 2mm;

6.5)用方木固定梁高>300mm的侧梁模板底部的压条的钢管顶并夹牢;6.5) Use square wood to fix the steel pipe top of the bead at the bottom of the side beam formwork with a beam height > 300mm and clamp it firmly;

6.6)模板搭设后组织验收,填写验收单并数量化验收内容。6.6) After the formwork is set up, organize the acceptance, fill in the acceptance form and quantify the acceptance content.

所述方法在模板搭设后还包括模板拆除的步骤,所述模板拆除必须满足下列要求:The method also includes the step of dismantling the formwork after the formwork is erected, and the dismantling of the formwork must meet the following requirements:

9.1)拆模板前先进行针对性的安全技术交底,并做好记录;9.1) Before removing the formwork, carry out a targeted safety technical disclosure and make a record;

9.2)支拆模板时,2米以上高处作业设置可靠的立足点,并有相应的安全防护措施;9.2) When dismantling the formwork, set a reliable foothold for operations at a height above 2 meters, and have corresponding safety protection measures;

9.3)拆模顺序应遵循先支后拆,后支先拆,从上往下的原则;9.3) The order of formwork removal should follow the principle of support first, then demolition, and last support first, from top to bottom;

9.4)模板拆除前必须有混凝土强度报告,强度达到规定要求后方可拆模。9.4) There must be a concrete strength report before the formwork is removed, and the formwork can only be removed after the strength meets the specified requirements.

本发明的有益效果是:本发明采用了将梁板分离各自支模,后连接的施工方法,并据以建模计算,能精确地找出梁下立杆荷载的作用途征,从而巧妙地解除了多、高层钢筋混凝土大截面梁由于超高超重,需要对大梁下层连续连支数层支模架并同时连带板的支模架连续连支数层的困惑,将受荷较小的板模支架先拆除,并按需要保留梁的下连支层,大大地节约了模板支架的用量,效益十分显著。梁、板模板支架先分离后整连,工艺简单、拆卸方便,充分实现了在保留梁底连支架的同期,板模板支架可先期拆除,大大地提高板模板支架周转次数,从而加快了工期。支模架结构计算的模型合理、受力明确,实施的技术先进,安全性和可靠性高。The beneficial effects of the present invention are: the present invention adopts the construction method of separating the beams and slabs from the formwork and then connecting them, and according to the modeling and calculation, it can accurately find out the functional characteristics of the vertical pole load under the beam, so as to skillfully It solves the confusion that multi- and high-rise reinforced concrete large-section beams need to continuously support several layers of formwork frames at the lower level of the girder due to the super height and weight, and at the same time, the formwork frames with slabs are continuously connected to several layers. The formwork support is removed first, and the lower connecting branch of the beam is retained as required, which greatly saves the amount of formwork support, and the benefits are very significant. The beam and slab formwork brackets are separated first and then connected. The process is simple and easy to disassemble. It fully realizes that the slab formwork support can be removed in advance while retaining the beam bottom connection bracket, which greatly improves the turnover times of the slab formwork support, thus speeding up the construction period. The calculation model of the formwork frame structure is reasonable, the force is clear, the implementation technology is advanced, and the safety and reliability are high.

附图说明Description of drawings

图1是本发明的搭设结构图。Fig. 1 is a construction diagram of the present invention.

图2是本发明的顶板模板搭设平面图。Fig. 2 is a plan view of the roof formwork of the present invention.

图3是本发明的顶板模板搭设立面图。Fig. 3 is the elevation view of the roof formwork of the present invention.

图4是本发明的顶板模板搭设的另一个方向的立面图。Fig. 4 is an elevation view of another direction in which the roof formwork of the present invention is erected.

图5是本发明的高粱模板的搭设立面图。Fig. 5 is a vertical view of sorghum formwork of the present invention.

图中标号:1-横向连接杆,2-纵向连接杆,3-梁底主楞,4-梁底增强立杆,5-梁底受力立杆,6-横向连接断杆,7-板底主楞,8-板底模板,9-板底次楞,10-板底交接断楞,11-板底断点连接楞,12-梁底次楞,13-横向剪力撑杆,14-梁底侧模螺栓,15-板底立杆。Labels in the figure: 1-horizontal connecting rod, 2-longitudinal connecting rod, 3-main corrugation at the bottom of the beam, 4-reinforcing vertical rod at the bottom of the beam, 5-stressed vertical rod at the bottom of the beam, 6-broken horizontal connecting rod, 7-board Bottom main corrugation, 8-slab bottom formwork, 9-slab bottom secondary corrugation, 10-slab bottom junction broken corrugation, 11-slab bottom breakpoint connection corrugation, 12-beam bottom secondary corrugation, 13-transverse shear brace, 14 - side formwork bolts at the bottom of the beam, 15 - uprights at the bottom of the slab.

具体实施方式detailed description

参照附图。Refer to attached picture.

多、高层房屋结构上层超重大梁支模架传统的施工方法是将梁板钢管整体搭设,使得支架的立杆于垂直方向在梁和板之间相互传力生产了模糊效应,不能明确其传力途征,因此也无法采用定量的计算办法来设计下层连支架搭设的层数,传统的做法只能在该浇筑层以下连支三层支架来应对,这对截面高度在1.5米以下的梁或许是安全的,如果梁的截面高度在1.5米以上,就存在严重的安全隐患。本工法基于力学原理,采用梁下支架与板的支架先分离搭设后连接的方法,其关键技术在于梁下横向另加至少两根立杆并按计算要求在梁的纵向加密,梁的横向所加的立杆必须支设在下一层梁上,不再支在下一层板上,使得现浇超重大梁的荷载几乎全部由下层大梁支承,从而严格地区分出梁和板下立杆荷载的各自作用途征,据以建立计算模型精确地计算出各自连支架搭设的层数。充分地实现了梁和板连支层分离的目的。The traditional construction method of super heavy beam support formwork on the upper floor of a multi-story building structure is to erect the beam-slab steel pipe as a whole, so that the vertical rod of the support transmits force between the beam and the slab in the vertical direction, resulting in an ambiguous effect, and the way of force transmission cannot be clearly defined. Therefore, it is impossible to use a quantitative calculation method to design the number of floors to be erected by the lower layer of support. The traditional method can only be used to support the three-layer support below the pouring layer. This may be the case for beams with a section height of less than 1.5 meters. Safe, if the section height of the beam is more than 1.5 meters, there are serious safety hazards. This construction method is based on the principle of mechanics, and adopts the method that the support under the beam and the support of the slab are first separated and erected and then connected. The uprights must be supported on the beams of the next floor instead of the slabs of the next floor, so that the load of the cast-in-place super heavy girders is almost entirely supported by the girders of the lower floor, thereby strictly distinguishing the respective loads of the beams and the vertical poles under the slabs. Functional signs, based on which a calculation model can be established to accurately calculate the number of layers erected by each connecting bracket. Fully realize the purpose of separation of beam and slab connecting branch.

本发明的施工要点:施工流程:根据工程基本情况确定支模架参数,建立梁、板分离的支架模型并进行浇筑层支模架设计计算,测定下层梁板的强度,搜集下层梁板的设计活荷载,分别计算确定梁板连支架的层数,支模架搭设及构造做法,拆模。Construction key points of the present invention: construction process: determine formwork frame parameters according to the basic engineering conditions, establish a beam and slab separated support model and carry out pouring layer formwork design calculations, measure the strength of the lower beam slab, and collect the design of the lower beam slab For the live load, calculate and determine the number of layers of beams and slabs, formwork erection and construction methods, and formwork removal.

本发明具体包括以下步骤:The present invention specifically comprises the following steps:

1、根据工程基本情况确定支模架参数:1. Determine the parameters of the formwork frame according to the basic situation of the project:

表1:工程概况:Table 1: Project overview:

表2:高支模所在层概况:Table 2: Overview of the layer where the high-support formwork is located:

表3:高支模下方层概况:Table 3: Overview of the layer below the high formwork:

表4:立杆基础情况:Table 4: Pole foundation conditions:

表5:顶板板模板(扣件式)界面参数Table 5: Interface parameters of roof plate formwork (fastener type)

表6:顶梁3-8轴模板(扣件式)界面参数:Table 6: Interface parameters of top beam 3-8 axis formwork (fastener type):

2、建立梁、板分离的支架模型并进行浇筑层支模架设计计算,确立梁板支架的搭设方式:现浇板的搭设按照传统方式采用网格式立杆布置,但与梁交接处采用以下方式断开,如图所示:其关键技术在于支架由横向连杆、纵向连杆、梁底主楞、梁底增强双立杆甚至是多立杆、梁底受力立杆、横向连接杆、板底主楞、板底模板、板底次楞、板底交接断楞、板底断点连接楞、梁底次楞、横向剪刀撑杆、梁侧模板螺栓、板底立杆组成,特别要求梁底④号增强双立杆在梁的横向方向间距控制在150毫米至200毫米之间,以确保该立杆能支在下一层梁顶上,不许支立于下一层的板面之上;2. Establish the beam and slab separated bracket model and carry out the design and calculation of the pouring layer support formwork, and establish the erection method of the beam and slab bracket: the erection of the cast-in-place slab adopts the grid-style vertical pole arrangement in the traditional way, but the junction with the beam adopts the following The method is disconnected, as shown in the figure: the key technology is that the support is composed of transverse connecting rods, longitudinal connecting rods, main corrugations at the bottom of the beam, reinforced double vertical rods at the bottom of the beam or even multiple vertical rods, force-bearing vertical rods at the bottom of the beam, and horizontal connecting rods. , slab bottom main corrugation, slab bottom formwork, slab bottom secondary corrugation, slab bottom junction broken corrugation, slab bottom break point connection corrugation, beam bottom secondary corrugation, horizontal scissors braces, beam side formwork bolts, and slab bottom vertical rods, especially It is required that the distance between the reinforced double poles at the bottom of the beam ④ should be controlled between 150mm and 200mm in the transverse direction of the beam, so as to ensure that the poles can be supported on the top of the beam on the next floor, and are not allowed to stand on the surface of the next floor. superior;

在梁的横向侧边须将板底的模板和主楞在沿梁的纵向方向断开,即⑦号板底主楞与⑩号板底交接断楞断开,其间距为100毫米,然后将11号底板断点连接楞垫在其下再与板的立杆固定;On the lateral side of the beam, the formwork and the main flute at the bottom of the slab must be disconnected along the longitudinal direction of the beam, that is, the main flute at the bottom of the slab No. The breakpoint of No. 11 bottom plate is connected to the corrugated pad under it and then fixed with the vertical pole of the plate;

根据⑤号梁底受力杆间距大小,取两端各长出节点200毫米长度的⑥号横向连接杆,在①号横向连接杆的下边与④号的梁底增强立杆以及⑤号的梁底受力杆连接,同时与所有的②号纵向连接杆连接固定;According to the distance between the stress rods at the bottom of No. ⑤ beam, take No. ⑥ horizontal connecting rod with a length of 200 mm at each end of the node, and connect it with No. Bottom force rod connection, and at the same time, it is connected and fixed with all No. ② longitudinal connecting rods;

梁底支架沿梁纵向每隔1.5米安装一付如13号的横向剪刀撑;Install a horizontal scissor brace such as No. 13 every 1.5 meters along the beam bottom bracket along the longitudinal direction of the beam;

建立模型进行设计与计算,具体的计算方法见表7-10。Establish a model for design and calculation, see Table 7-10 for specific calculation methods.

表7:顶板板模(扣件式)计算书Table 7: Calculation sheet for roof formwork (fastener type)

表8:顶板板模(扣件式)验算书Table 8: Roof formwork (fastener type) check book

表9:高梁模板(扣件式)计算书Table 9: Calculation sheet for sorghum formwork (fastener type)

表10:高梁模板(扣件式)验算书Table 10: Sorghum formwork (fastener type) check book

3、测定下层梁板的强度:高层或多层的房屋的上层大跨度梁板浇筑的支模架,受荷一般都很大,所以浇筑层下一层梁板结构未达到设计强度前,不适宜开始在其上搭设支架,所以在搭设浇筑层支架前必须通过回弹仪对下一层梁板结构进行回弹测定,确认其强度达到设计强度后方可开始搭设;3. Determination of the strength of the lower beam and slab: the formwork frame cast by the upper long-span beam and slab of a high-rise or multi-storey building is generally under a large load, so the beam and slab structure of the lower layer of the pouring layer does not reach the design strength. It is suitable to start erecting supports on it, so before setting up the pouring layer supports, the rebound of the beam-slab structure of the next layer must be measured by a rebound tester, and the erection can only be started after confirming that its strength reaches the design strength;

4、搜集下层梁板的设计活荷载:为确保板、梁分离式高支模连支架搭设具备足够的安全性,故必须准确地搜集到梁、板的设计活荷载值,并应与设计单位核实确认无误后进一步进行下连支架搭设与拆除的设计,下各镇中心校综合楼楼面活载分别为1、2楼楼面设计活载取值为3KN/m2,3楼楼面设计活载取值为4KN/m24. Collect the design live loads of the lower beams and slabs: In order to ensure the safety of the erection of the separated high formwork brackets for the slabs and beams, it is necessary to accurately collect the design live load values of the beams and slabs, and contact the design unit After verification and confirmation, the design of the erection and dismantling of the lower connecting brackets will be further carried out. The floor live loads of the comprehensive buildings of the central schools in the lower towns are respectively 3KN/m 2 for the floors of the 1st and 2nd floors, and the floor design for the 3rd floor The value of live load is 4KN/m 2 .

5、分别计算确定梁板连支架的层数:5. Calculate and determine the number of layers of beams and slabs connected with supports:

a.板的设计:由于板的支架面积大,支架所用的材料占比大,所以通过精确的计算,可以在确保安全的前提下,尽量节约钢管材料,因此一般不采用活荷载倒算法验算安全性,要根据下一层板的结构配筋状况计算现浇板连支架层数与拆除的时间要求,力求将设计时结构受力有富余的部分得以充分利用。a. Plate design: due to the large support area of the plate, the proportion of materials used in the support is large, so through accurate calculation, the steel pipe material can be saved as much as possible under the premise of ensuring safety, so the live load inverse algorithm is generally not used to check the safety In order to ensure the stability, the number of layers of cast-in-place slabs and brackets and the time requirements for dismantling should be calculated according to the structural reinforcement of the next layer of slabs, so as to make full use of the parts with surplus structural stress during design.

表8:板的设计参数Table 8: Board Design Parameters

楼板的长边长度(m)The length of the long side of the floor (m) 7.27.2 楼板的短边与长边的比值The ratio of the short side to the long side of the slab 0.620.62 楼板活荷载标准值(kN/m2)Floor live load standard value (kN/m 2 ) 44 钢筋的级别grade of reinforcement HRB400HRB400 混凝土强度等级Concrete Strength Grade C25C25 混凝土设计强度(N/mm2)Design strength of concrete (N/mm 2 ) 11.911.9 楼板支座配筋Floor support reinforcement Φ10Φ10 配筋的间距(mm)Reinforcement Spacing (mm) 200200 浇注层的实测强度(N/mm2)Measured strength of cast layer (N/mm 2 ) 22 下一层的实测强度(N/mm2)The measured strength of the next layer (N/mm 2 ) 2525

各楼层层高、楼面设计荷载、楼板板厚均按相同计。The storey height, floor design load, and floor slab thickness of each floor are calculated on the same basis.

ⅰ.支架所受各类荷载的取值ⅰ. The value of various loads on the support

附加在每根立杆上的楼盖自重荷载为:N板i=1.2×0.12×0.9×0.9×(24+1.1)=2.928kNThe self-weight load of the floor attached to each pole is: N plate i = 1.2×0.12×0.9×0.9×(24+1.1)=2.928kN

模板自重为:N模i=1.2×0.15×0.9×0.9=0.146kNThe self-weight of the template is: N module i = 1.2×0.15×0.9×0.9=0.146kN

支架自重为:N支gi=1.2×0.15×5.6=1.008kNThe self-weight of the bracket is: N gi = 1.2 × 0.15 × 5.6 = 1.008kN

混凝土浇筑施工荷载为:N浇i=1.4×(1+2)×0.9×0.9=3.402kNThe concrete pouring construction load is: N pouring i = 1.4×(1+2)×0.9×0.9=3.402kN

楼盖总的设计荷载为:NQ=1.4×4×0.9×0.9+2.928=7.464kNThe total design load of the floor is: N Q = 1.4×4×0.9×0.9+2.928=7.464kN

ⅱ.下一层楼板承载力验算ⅱ. Calculation of the bearing capacity of the next floor slab

①下一层楼板信息① Next floor information

验算楼板强度时按照最不利情况考虑,楼板承受的荷载按照线荷载均布考虑When checking the strength of the floor slab, the most unfavorable situation is considered, and the load on the floor slab is considered in accordance with the uniform distribution of line loads

宽度范围内配置HRB400,每单位长度(m)楼板截面的钢筋面积As=392.5mm2,fy=360N/mm2 Configure HRB400 within the width range, the reinforcement area per unit length (m) of floor slab section A s = 392.5mm 2 , f y = 360N/mm 2

板的截面尺寸为b×h=4464mm×120mm,楼板的跨度取7.2m,取混凝土保护层厚度20mm,截面有效高度ho=100mmThe section size of the slab is b×h=4464mm×120mm, the span of the floor slab is 7.2m, the thickness of the concrete protective layer is 20mm, and the effective height of the section is h o =100mm

②下一层楼板承载力计算② Calculation of the bearing capacity of the next floor slab

楼板计算长边7.2m,短边为4.464mThe calculation of the long side of the floor is 7.2m, and the short side is 4.464m

q=1.2×((24+1.1)×0.12)+1.4×[(1+2)+0.6×N支i-1/(la×lb)]=7.814kN/m2 q=1.2×((24+1.1)×0.12)+1.4×[(1+2)+0.6×N branch i-1 /(l a ×l b )]=7.814kN/m 2

板带所需承担的最大弯矩按照四边固接双向板计算The maximum bending moment that the plate strip needs to bear is calculated according to the two-way plate fixed on four sides

Mmax=0.078×7.814×4.4642=12.18kN·mM max =0.078×7.814×4.464 2 =12.18kN·m

下一层混凝土强度达到25/11.9×100%=210.1%设计强度The strength of the next layer of concrete reaches 25/11.9×100%=210.1% of the design strength

C25混凝土弯曲抗压强度设计值为fcm=11.9N/mm2 The design value of the flexural compressive strength of C25 concrete is f cm = 11.9N/mm 2

则可以得到矩形截面相对受压区高度Then the height of the rectangular section relative to the compression zone can be obtained

ξ=As×fy/(αl×b×ho×fcm)=392.5×360/(1×4464×100×11.9)=0.027ξ=A s ×f y /(α l ×b×h o ×f cm )=392.5×360/(1×4464×100×11.9)=0.027

计算系数为:αs=ξ(1-0.5ξ)=0.027×(1-0.5×0.027)=0.026The calculation coefficient is: α s =ξ(1-0.5ξ)=0.027×(1-0.5×0.027)=0.026

此时楼板所能承受的最大弯矩为The maximum bending moment that the floor can withstand is

M1=αs×α1×b×ho 2×fcm=0.026×1×4464×1002×11.9×10-6=13.942kN·mM 1s ×α 1 ×b×h o 2 ×f cm =0.026×1×4464×100 2 ×11.9×10 -6 =13.942kN·m

结论:由于∑M1=M1=13.942>Mmax=12.18kN·mConclusion: Since ∑M 1 =M 1 =13.942>M max =12.18kN·m

所以,下一层楼板强度足以承受以上楼层传递下来的荷载,模板支撑可以拆除Therefore, the strength of the next floor slab is sufficient to bear the load transmitted from the upper floor, and the formwork support can be removed

b.梁的设计:本工程分层分别为架空层高2.7米、一层高3.9米、二层高3.6米、三层高5.6米,方案为三层顶结构梁板,根据浇筑层对3层顶现浇板配筋的验算结果,3层现浇板浇筑层的下一层支架可以拆模,现设3、4、5、6、7、8轴梁下一层至下二层支架不予拆除,且双立杆支架自重为0.25KN/m,单立杆支架自重为0.15KN/m,模板自重按0.3KN/m2计:(1-3层结构的梁高0.7米、板厚0.12米,开间4.5米,浇筑层层高5.6米,板下立杆的最大轴力10.1KN,浇筑层梁底立杆最大轴力为9.77KN,板下立杆间距为0.9×0.9,梁底双加立杆纵距为0.45米,1、2楼楼面设计活载取值为3KN/m2,3楼楼面设计活载取值为4KN/m2,).计算如下:板传荷载:由现浇板底支模架立杆轴力计算结果可知,15号板底立杆轴力9.41kN,而大梁底轴力计算结果④号梁底增强立杆轴力Nut=max[R1,R2,R3,R4]=max[3.978,9.768,9.768,3.978]=9.768kN可知,⑤号梁底受力立杆轴力为3.978kN。④号增强立杆轴力为9.768kN,可以看出⑤号梁底受力立杆轴力为3.978kN换算成面荷载为3.978/0.45*0.75=11.79KN/m2,与15号板底立杆轴力9.74kNrqm换算的面荷载9.74/0.9*0.9=12.02KN/m2,此时⑤号梁底受力立杆轴力的面荷载接近,所以以15号立杆轴力作用在板上的效应足以囊括⑤号梁底受力立杆轴力作用在板上的效应,不必考虑因为梁的轴力传递到板上使板结构产生额外的荷载效应,从而可视为梁的荷载全部由④号梁底增强立杆轴力直接作用于下层梁所产生的荷载效应与⑤号梁底受力立杆轴力以及15号板底立杆轴力作用于下层板产生的荷载效应分开,作用途征各自分离,受力传递对象得以明确。b. Beam design: The layers of this project are 2.7 meters high for the overhead floor, 3.9 meters high for the first floor, 3.6 meters high for the second floor, and 5.6 meters high for the third floor. The calculation results of the reinforcement of the cast-in-place slab on the top of the floor, the support of the next floor of the 3-story cast-in-place slab pouring layer can be demolished, and the 3, 4, 5, 6, 7, 8 axle beams are now provided with the supports from the next floor to the second floor It will not be dismantled, and the self-weight of the double pole support is 0.25KN/m, the self-weight of the single pole support is 0.15KN/m, and the self-weight of the formwork is calculated as 0.3KN/ m2 : (the beam height of the 1-3 layer structure is 0.7m, the The thickness is 0.12 meters, the bay is 4.5 meters, the height of the pouring layer is 5.6 meters, the maximum axial force of the vertical rod under the slab is 10.1KN, the maximum axial force of the vertical rod at the bottom of the beam of the pouring layer is 9.77KN, and the distance between the vertical rods under the slab is 0.9×0.9. The vertical distance of the bottom double plus vertical pole is 0.45m, the design live load of the 1st and 2nd floors is 3KN/m 2 , and the design live load of the 3rd floor is 4KN/m 2 , ). The calculation is as follows: Load: From the calculation results of the axial force of the vertical rod of the cast-in-place slab bottom support formwork , it can be known that the axial force of the vertical rod at the bottom of the No. R 1 , R 2 , R 3 , R 4 ] = max[3.978, 9.768, 9.768, 3.978] = 9.768kN. It can be known that the axial force of the vertical bar under the force of No. ⑤ beam is 3.978kN. The axial force of No. ④ enhanced vertical rod is 9.768kN. It can be seen that the axial force of No. ⑤ beam bottom is 3.978kN, which is converted into a surface load of 3.978/0.45*0.75=11.79KN/m2 , which is the same as that of No. 15 slab bottom. The surface load converted from the rod axial force of 9.74kNrqm is 9.74/0.9*0.9=12.02KN/m 2 . At this time, the surface load of the vertical rod axial force on the bottom of No. The effect of ⑤ is enough to include the effect of the axial force of the vertical bar at the bottom of the No. The load effect produced by the axial force of the reinforced vertical rod at the bottom of No. 4 beam directly acting on the lower beam is separated from the axial force of the stressed vertical rod at the bottom of No. 5 beam and the axial force of the vertical rod at the bottom of No. 15 slab acting on the lower layer. The usage signs are separated from each other, and the object of force transmission can be clarified.

ⅰ.板上活载按0.8折减换算成立杆传至4层楼面最大轴力N1=10.4KN÷(0.9×0.9)m2-3×1.4×0.2=11.66KN/m2 ⅰ. The live load on the board is reduced by 0.8 and converted to the maximum axial force N 1 =10.4KN÷(0.9×0.9)m 2 -3×1.4×0.2=11.66KN/m 2

2N板线=11.66×4.5=52.47KN/m 2 N plate line = 11.66 × 4.5 = 52.47KN/m

ⅱ.梁线荷载计算:设梁荷载传至一层立杆止,架空层立杆拆除)ⅱ. Calculation of beam line load: assume that the beam load is transmitted to the vertical pole of the first floor, and the vertical pole of the overhead floor is removed)

N=(9.77÷0.45)×2+0.25×(3.9-0.7)×2÷0.45+(1.68×2+0.4)×0.3×2N Beam =(9.77÷0.45)×2+0.25×(3.9-0.7)×2÷0.45+(1.68×2+0.4)×0.3×2

=43.4+1.6+2.26=43.4+1.6+2.26

=47.3KN/m=47.3KN/m

ⅲ.传递到三层梁和二层梁以及一层梁上的合计线荷载:ⅲ. Total line load transferred to third-story beams, second-story beams, and first-story beams:

N=52.47+47.3=99.77KN/mN combined =52.47+47.3=99.77KN/m

ⅳ.梁的设计线荷载:(设楼面抹面及地砖标准值为1KN/m2)ⅳ. The design line load of the beam: (the standard value of floor plastering and floor tiles is 1KN/m 2 )

(1).对3、4及5交C-D轴梁,设梁底1层、2层支架都不拆除N=[(4+1)+2×(3+1)]×1.4×4.5=81.9KN/m(1). For the 3rd, 4th and 5th intersection CD axle beams, it is assumed that the supports on the first and second floors of the beam bottom are not removed. N = [(4+1)+2×(3+1)]×1.4×4.5= 81.9KN/m

(2).对7、8及5交A-B轴二层有墙梁,设梁底1层、2层支架都不拆除N=[(4+1)+2×(3+1)]×1.4×4.5+(4.6+0.8)×1.2×3.43=104.1KN/m(上梁1.33米上翻)(2). There are wall beams on the second floor of the 7th, 8th and 5th AB axes, and the supports on the first and second floors at the bottom of the beams are not removed. N = [(4+1)+2×(3+1)]× 1.4×4.5+(4.6+0.8)×1.2×3.43=104.1KN/m (the upper beam is turned up at 1.33 meters)

(3).对6轴一、二层均为有墙梁,设梁底1层、2层支架都不拆除N=[(4+1)+2×(3+1)]×1.4×4.5+(4.6+0.8)×1.2×(3.43+2.93)=123KN/m(3). There are wall beams on the 1st and 2nd floors of the 6-axis, and the brackets on the 1st and 2nd floors at the bottom of the beams are not removed. N = [(4+1)+2×(3+1)]×1.4× 4.5+(4.6+0.8)×1.2×(3.43+2.93)=123KN/m

分析:analyze:

根据计算分析:①确定2层板上的支架在浇筑层混凝土达到设计强度前不得拆除;According to the calculation and analysis: ① It is determined that the brackets on the 2nd floor shall not be dismantled before the concrete of the pouring layer reaches the design strength;

②由于对3、4及5交C-D轴梁所设梁底1层、2层支架都不拆除时N=81.9KN/m<N=99.77KN/m,故浇筑层梁立杆支架必须通过架空层连支到地面不能拆除;②Because the supports on the first and second floors of the beams at the cross CD axis beams at intersections 3, 4, and 5 are not removed, N = 81.9KN /m<N = 99.77KN/m, so the vertical pole support of the pouring layer beam must be The connection to the ground through the overhead layer cannot be dismantled;

(③由于对7、8及5交A-B轴二层有墙梁所设梁底1层、2层支架都不拆除N=104.1KN/m>N=99.77KN/m,故7、8及5交A-B轴的梁底支架在架空层可以拆除。(③Because the brackets on the first and second floors of the beams on the second floor of the AB axis at intersections 7, 8 and 5 are not removed, N = 104.1KN /m > N = 99.77KN /m, so 7, 8 And the beam bottom support of the 5th AB axis can be dismantled on the overhead floor.

④由于对6轴一、二层均为有墙梁所设梁底1层、2层支架都不拆除时N=123KN/m>N=99.77KN/m,故6轴的梁底支架在架空层可以拆除。,④Since the first and second floors of the 6-axis are equipped with wall beams, when the first and second floors of the beam are not removed, N = 123KN /m > N = 99.77KN /m, so the 6-axis beam bottom bracket It can be dismantled on the overhead floor. ,

从以上计算结果可以看出,只要浇筑层板下立杆支在下层达到设计强度板结构之上,下一层板结构受荷不大,一般情况下都可以不再连支,可是梁下受荷却很大,如果设计时梁下没有考虑填充墙时,可能需要连支数层才能保证结构安全。分析说明,梁板混合连支2-3层,不仅使大面积板的支架浪费,且由于增加了支架自重,使梁底受荷更大,并且没有对梁的受荷进行确定量的计算,有可能酿成重大安全事故。From the above calculation results, it can be seen that as long as the lower vertical bar of the poured laminate is supported on the lower layer to reach the design strength of the slab structure, the load on the lower layer of the slab structure is not large, and it can be no longer connected under normal circumstances. However, the load is very large. If the infill wall is not considered under the beam in the design, it may be necessary to connect several layers to ensure the safety of the structure. The analysis shows that 2-3 layers of beams and slabs are connected together, which not only wastes the support of large-area slabs, but also increases the load on the bottom of the beam due to the increased self-weight of the support, and does not calculate the definite amount of load on the beam. It may cause a major safety accident.

6、支模架搭设及构造做法6. Formwork erection and construction method

a.根据计算结果,板的支架直接搭设在浇筑层本层已达到设计强度的楼板面结构之上,一般情况的下一层支架可以拆,如果计算结果不宜拆除,最不利的情况下,也只保留下一层支架。而梁的支架须根据计算结果保留数层,其下层所保留的支架搭设形式与构造必须同计算层完全相同。需要进一步明确的是梁底13号横向剪刀撑应沿梁的纵向每隔不超过2米设置一道,立杆的纵向间距和梁底增强杆必须严格遵照设计计算施工,任何有十字交错的杆件必须与第三根杆件相连系,形成空间坐标式的空间杆件结构。a. According to the calculation results, the support of the slab is directly erected on the floor surface structure of the pouring layer that has reached the design strength. In general, the support of the next floor can be removed. If the calculation result is not suitable for removal, in the most unfavorable case, Only the next layer of brackets remains. The support of the beam must retain several floors according to the calculation results, and the erection form and structure of the support reserved on the lower floor must be exactly the same as the calculation floor. It needs to be further clarified that No. 13 transverse scissor braces at the bottom of the beam should be installed at intervals of no more than 2 meters along the longitudinal direction of the beam. It must be connected with the third bar to form a space coordinate space bar structure.

b.梁下连支架必须采用按上述先分离后连接的结构形式,便于下一层板的支架拆除时不影响同层梁的连支架稳定性。b. The lower connecting bracket of the beam must adopt the above-mentioned structural form of separation and then connection, so that the stability of the connecting bracket of the beam on the same floor will not be affected when the bracket of the next floor is removed.

c.按计算结果确定,如果梁的连支层需要一直搭设至底层地面不得拆除,必须对地面以下地基的承载力进行验算并采取加强措施,确保底层承载力满足要求为止。c. According to the calculation results, if the connecting support layer of the beam needs to be erected until the bottom ground cannot be dismantled, the bearing capacity of the foundation below the ground must be checked and strengthening measures must be taken to ensure that the bottom bearing capacity meets the requirements.

Claims (10)

1.多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:包括以下步骤:1. The method for erecting the slab-beam separated high-support formwork and support of many and high-rise reinforced concrete structures is characterized in that: comprise the following steps: (1)根据工程基本情况确定支模架参数;(1) Determine the parameters of the formwork frame according to the basic situation of the project; (2)建立梁、板分离的支架模型并确立梁板支架的搭设方式;(2) Establish a beam-slab separation bracket model and establish the erection method of the beam-slab bracket; (3)测定下层梁板的强度;(3) Determination of the strength of the lower beam slab; (4)搜集下层梁板的设计活荷载;(4) Collect the design live load of the lower beam and slab; (5)建模计算并确定梁板连支架的层数;(5) Modeling calculation and determination of the number of layers of beam-slab and support; (6)支模架搭设。(6) Formwork frame erection. 2.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(1)中的工程基本情况包括建筑面积、建筑高度、基础形式、主体结构、抗震等级、抗震设防烈度、地上层数、地下层数和标准层高度。2. The method for erecting plate-beam separated high-support formwork and brackets of multi- and high-rise reinforced concrete structures as claimed in claim 1, characterized in that: the basic conditions of the project in the step (1) include building area, building height, Foundation form, main structure, seismic grade, seismic fortification intensity, number of floors above ground, number of underground floors and standard story height. 3.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(1)中的支模架参数包括高支模及相关层结构详细情况,具体包括高支模所在层参数、高支模下方层结构参数、立杆基础参数、顶板板模板界面参数和顶梁轴模板界面参数。3. The method for erecting a slab-beam separated high-support formwork with support for multi-story and high-rise reinforced concrete structures as claimed in claim 1, characterized in that: the formwork frame parameters in the step (1) include high formwork and related The details of the layer structure, including the parameters of the layer where the high-support formwork is located, the layer structure parameters below the high-support formwork, the foundation parameters of the pole, the interface parameters of the roof slab formwork, and the interface parameters of the top beam axis formwork. 4.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(2)中的支架模型包括横向连杆、纵向连杆、梁底主楞、梁底增强双立杆甚至是多立杆、梁底受力立杆、横向连接杆、板底主楞、板底模板、板底次楞、板底交接断楞、板底断点连接楞、梁底次楞、横向剪刀撑杆、梁侧模板螺栓和板底立杆。4. The method for erecting a slab-girder separated high-support formwork and bracket of a multi-story and high-rise reinforced concrete structure according to claim 1, wherein the bracket model in the step (2) includes a transverse connecting rod and a longitudinal connecting rod , main flute at the bottom of the beam, reinforced double vertical poles at the bottom of the beam or even multiple vertical poles, force-bearing vertical poles at the bottom of the beam, horizontal connecting rods, main flute at the bottom of the slab, formwork at the bottom of the slab, secondary flute at the bottom of the slab, broken flute at the bottom of the slab, and Bottom break point connection flute, beam bottom secondary flute, transverse scissors brace, beam side formwork bolts and slab bottom vertical rod. 5.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(2)中的搭设方式具体包括以下步骤:5. The method for erecting a slab-beam separated high-support formwork and support for multi-story and high-rise reinforced concrete structures according to claim 1, wherein the erection method in the step (2) specifically includes the following steps: 2.1)在梁的横向侧部将板底的模板和主楞在沿梁的纵向方向断开;2.1) Disconnect the formwork at the bottom of the slab and the main flute along the longitudinal direction of the beam at the lateral side of the beam; 2.2)然后将底板断点连接楞垫在其下再与板的立杆固定;2.2) Then connect the break point of the bottom plate to the corrugated pad and fix it with the vertical pole of the plate; 2.3)取距两端梁底受力杆一定间距的横向连接杆,在其下端与梁底增强立杆以及梁底受力杆连接,同时与所有的纵向连接杆连接固定;2.3) Take the horizontal connecting rod at a certain distance from the beam bottom stress rod at both ends, connect the lower end of the beam bottom reinforced vertical rod and the beam bottom stress rod, and connect and fix all the longitudinal connecting rods at the same time; 2.5)梁底支架沿梁纵向每隔一定距离安装横向剪刀撑。2.5) The beam bottom bracket is installed with horizontal scissors braces at intervals along the longitudinal direction of the beam. 6.如权利要求5所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:在所述步骤2.3)中,梁底增强立杆必须支设在下层梁上,不得支在下层板上,才能够实现梁板分离传荷。6. The method for erecting a slab-girder separated high-support formwork with support for multi-story and high-rise reinforced concrete structures as claimed in claim 5, characterized in that: in the step 2.3), the reinforcement pole at the bottom of the beam must be supported on the lower floor The beam must not be supported on the lower slab, so that the beam-slab separation and load transfer can be realized. 7.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(5)具体包括:7. The method for erecting a slab-beam separated high-support formwork and bracket of a multi-story and high-rise reinforced concrete structure as claimed in claim 1, characterized in that: the step (5) specifically includes: 5.1)根据下一层板的结构配筋状况采用梁板分离式计算模型计算确定现浇板连支架层数和拆除时间;5.1) According to the structural reinforcement status of the next floor slab, the beam-slab separation calculation model is used to calculate and determine the number of layers of the cast-in-place slab and the support and the removal time; 5.2)楼板受力校验;5.2) Floor force verification; 5.3)根据梁受力计算确定板梁连接方式。5.3) Determine the plate-girder connection method according to the beam force calculation. 8.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(5)具体包括:8. The method for erecting a slab-beam separated high-support formwork and bracket of a multi- and high-rise reinforced concrete structure as claimed in claim 1, characterized in that: the step (5) specifically includes: 5.1)按照模板图纸尺寸拼装成整体,控制模板的偏差在允许范围内;5.1) Assemble into a whole according to the size of the template drawing, and control the deviation of the template within the allowable range; 5.2)逐块检查拼装好的模板的背楞是否符合模板设计要求,模板的编号是否与所用部位一致;5.2) Check piece by piece whether the back flute of the assembled formwork meets the design requirements of the formwork, and whether the number of the formwork is consistent with the part used; 5.3)引测建筑的边柱或者墙轴线,并以该轴线为起点,引出每条轴线,并根据轴线与施工图用墨线弹出模板的内线、边线以及外侧控制线;5.3) Measure the axis of the side column or wall of the building, and use the axis as the starting point to draw out each axis, and pop out the inner line, side line and outer control line of the formwork with ink lines according to the axis and the construction drawing; 5.4)利用水准仪将建筑物水平标高根据实际要求,直接引测到模板的安装位置;5.4) Use the level gauge to measure the horizontal elevation of the building directly to the installation position of the formwork according to the actual requirements; 5.5)根据模板图在钢筋绑扎验收后合拢梁侧模的支设;5.5) According to the formwork diagram, close up the support of the side formwork of the beam after the steel bar binding acceptance; 5.6)支模前对前一道工序的标高、尺寸预留孔的位置按设计图纸进行技术复核。5.6) Before setting up the formwork, conduct a technical review of the elevation and size of the reserved holes in the previous process according to the design drawings. 9.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述步骤(6)具体包括:9. The method for erecting a slab-beam separated high-support formwork and bracket of a multi- and high-rise reinforced concrete structure as claimed in claim 1, characterized in that: the step (6) specifically includes: 6.1)先支梁底支架后支支板支架,再将两者用横向连系杆连接;6.1) First support the beam bottom bracket and then support the support plate bracket, and then connect the two with a horizontal tie rod; 6.2)梁板安装通过钢筋绑扎,在绑扎过程中为钢筋分项工程提供施工面;6.2) The beam and slab are installed through the binding of steel bars, and the construction surface is provided for the sub-projects of steel bars during the binding process; 6.3)在跨度≥4m的梁设置起拱2‰,梁模板上口设有拉紧锁扣杆;6.3) Set arching 2‰ for beams with a span ≥ 4m, and set a tension lock bar at the top of the beam formwork; 6.4)用胶带纸封贴≥2mm的板缝;6.4) Use adhesive tape to seal the board seam ≥ 2mm; 6.5)用方木固定梁高>300mm的侧梁模板底部的压条的钢管顶并夹牢;6.5) Use square wood to fix the steel pipe top of the bead at the bottom of the side beam formwork with a beam height > 300mm and clamp it firmly; 6.6)模板搭设后组织验收,填写验收单并数量化验收内容。6.6) After the formwork is set up, organize the acceptance, fill in the acceptance form and quantify the acceptance content. 10.如权利要求1所述的多、高层钢筋混凝土结构的板梁分离式高支模连支架搭设方法,其特征在于:所述方法在模板搭设后还包括模板拆除的步骤,所述模板拆除必须满足下列要求:10. as claimed in claim 1, multi-story reinforced concrete structure plate girder separated high formwork and bracket erection method, it is characterized in that: said method also comprises the step of formwork removal after formwork erection, said formwork removal The following requirements must be met: 9.1)拆模板前先进行针对性的安全技术交底,并做好记录;9.1) Before dismantling the formwork, make a targeted security technical disclosure and make a record; 9.2)支拆模板时,2米以上高处作业设置可靠的立足点,并有相应的安全防护措施;9.2) When dismantling the formwork, set a reliable foothold for operations at a height above 2 meters, and have corresponding safety protection measures; 9.3)拆模顺序应遵循先支后拆,后支先拆,从上往下的原则;9.3) The order of formwork removal should follow the principle of support first and then demolition, and the latter support first, from top to bottom; 9.4)模板拆除前必须有混凝土强度报告,强度达到规定要求后方可拆模。9.4) There must be a concrete strength report before the formwork is removed, and the formwork can only be removed after the strength meets the specified requirements.
CN201610082401.5A 2016-02-05 2016-02-05 The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures Active CN105863257B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610082401.5A CN105863257B (en) 2016-02-05 2016-02-05 The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610082401.5A CN105863257B (en) 2016-02-05 2016-02-05 The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures

Publications (2)

Publication Number Publication Date
CN105863257A true CN105863257A (en) 2016-08-17
CN105863257B CN105863257B (en) 2020-08-21

Family

ID=56624670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610082401.5A Active CN105863257B (en) 2016-02-05 2016-02-05 The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures

Country Status (1)

Country Link
CN (1) CN105863257B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457402A (en) * 2017-02-21 2018-08-28 黄靓 A kind of concrete structure construction method with assembled masonry filler wall
CN109610817A (en) * 2018-11-29 2019-04-12 山东金城建设有限公司 Cross beam falsework and its design and construction method
CN111397786A (en) * 2018-12-29 2020-07-10 中国建筑第八工程局有限公司 Super-thick floor slab support frame axial force monitoring system and method for verifying dismantling condition
CN111663770A (en) * 2020-05-12 2020-09-15 中铁十六局集团城市建设发展有限公司 Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN111877758A (en) * 2020-05-28 2020-11-03 中国化学工程第三建设有限公司 Construction method for understructure overload bearing superstructure
CN111946037A (en) * 2019-05-14 2020-11-17 宏润建设集团股份有限公司 Formwork support and mounting method thereof
CN114033136A (en) * 2021-12-10 2022-02-11 中国十七冶集团有限公司 Construction method for sharing high formwork support and subsequent filling frame
CN115270253A (en) * 2022-07-19 2022-11-01 中国建筑西南设计研究院有限公司 Method, system and medium for judging and displaying plate reinforcing bar compliance
CN117211518A (en) * 2023-09-18 2023-12-12 中建八局第一建设有限公司 A method for dismantling the buckle-type support frame of a large-span open-web sandwich panel structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB142069A (en) * 1919-04-23 1920-04-29 Alfred Chavanne Metal supports of casings or false work for constructions in reinforced concrete
GB762788A (en) * 1954-03-12 1956-12-05 Emile Gustave Louis Girard Improvements in shuttering for ribbed reinforced-concrete floors and in methods of supporting such shuttering
US3650078A (en) * 1970-09-15 1972-03-21 Economy Forms Corp Shore tower assembly
CN102691411A (en) * 2012-06-21 2012-09-26 中国建筑第五工程局有限公司 Beam plate post-cast strip template support system and construction method thereof
CN102900230A (en) * 2012-10-31 2013-01-30 浙江巨星建设集团有限公司 Liftable reinforced concrete post-casting strip construction method
CN103806648A (en) * 2013-12-11 2014-05-21 成都佳美嘉科技有限公司 Reinforcing steel bar formwork frame
CN203846765U (en) * 2014-05-07 2014-09-24 广东信海建筑有限公司 Novel hollow lead screw double-adjustment knocking-down type supporting head
CN104120827A (en) * 2014-07-23 2014-10-29 浙江省一建建设集团有限公司 Ship rail type bare concrete wallboard and construction method thereof

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB142069A (en) * 1919-04-23 1920-04-29 Alfred Chavanne Metal supports of casings or false work for constructions in reinforced concrete
GB762788A (en) * 1954-03-12 1956-12-05 Emile Gustave Louis Girard Improvements in shuttering for ribbed reinforced-concrete floors and in methods of supporting such shuttering
US3650078A (en) * 1970-09-15 1972-03-21 Economy Forms Corp Shore tower assembly
CN102691411A (en) * 2012-06-21 2012-09-26 中国建筑第五工程局有限公司 Beam plate post-cast strip template support system and construction method thereof
CN102900230A (en) * 2012-10-31 2013-01-30 浙江巨星建设集团有限公司 Liftable reinforced concrete post-casting strip construction method
CN103806648A (en) * 2013-12-11 2014-05-21 成都佳美嘉科技有限公司 Reinforcing steel bar formwork frame
CN203846765U (en) * 2014-05-07 2014-09-24 广东信海建筑有限公司 Novel hollow lead screw double-adjustment knocking-down type supporting head
CN104120827A (en) * 2014-07-23 2014-10-29 浙江省一建建设集团有限公司 Ship rail type bare concrete wallboard and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙沛平,张元春: "《钢筋混凝土框架及排架结构施工》", 30 September 1999 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457402A (en) * 2017-02-21 2018-08-28 黄靓 A kind of concrete structure construction method with assembled masonry filler wall
CN109610817A (en) * 2018-11-29 2019-04-12 山东金城建设有限公司 Cross beam falsework and its design and construction method
CN111397786A (en) * 2018-12-29 2020-07-10 中国建筑第八工程局有限公司 Super-thick floor slab support frame axial force monitoring system and method for verifying dismantling condition
CN111946037A (en) * 2019-05-14 2020-11-17 宏润建设集团股份有限公司 Formwork support and mounting method thereof
CN111663770A (en) * 2020-05-12 2020-09-15 中铁十六局集团城市建设发展有限公司 Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN111663770B (en) * 2020-05-12 2021-11-16 中铁十六局集团城市建设发展有限公司 Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN111877758A (en) * 2020-05-28 2020-11-03 中国化学工程第三建设有限公司 Construction method for understructure overload bearing superstructure
CN114033136A (en) * 2021-12-10 2022-02-11 中国十七冶集团有限公司 Construction method for sharing high formwork support and subsequent filling frame
CN115270253A (en) * 2022-07-19 2022-11-01 中国建筑西南设计研究院有限公司 Method, system and medium for judging and displaying plate reinforcing bar compliance
CN117211518A (en) * 2023-09-18 2023-12-12 中建八局第一建设有限公司 A method for dismantling the buckle-type support frame of a large-span open-web sandwich panel structure

Also Published As

Publication number Publication date
CN105863257B (en) 2020-08-21

Similar Documents

Publication Publication Date Title
CN105863257B (en) The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN101851984B (en) Prefabricated steel-concrete composite beam
CN107060275B (en) A modular elevator shaft construction technology
CN204225273U (en) A kind of large-span prestressed groove type plate of upper bands bending steel muscle and frame construction
CN105839823B (en) A kind of hollow superposed floor of close rib of truss-like
CN110409624B (en) Reverse calculation and construction method for large equipment installation and main body structure
CN101200977A (en) Horizontal transport method for roof construction
CN108301531A (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN206428968U (en) A kind of steel bar girder formula is without supporting template system
CN116289608A (en) A construction method of beam-column cast-in-place beam support in narrow area
CN105649249A (en) Bidirectional profiled steel sheet and concrete composite floor slab internally provided with hollow circular steel pipes
CN102322140B (en) Supporting construction method for large-span creasing formwork
CN101694127B (en) Formwork support system for steel frame structure cast-in-place concrete floorslabs
CN205314329U (en) One -way composite floor slab of die mould steel plate concrete of built -in hollow square steel pipe
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN201915631U (en) High-altitude long-span reinforced concrete corridor construction supporting structure
CN104674997A (en) Supporting structure of archaized wood structure building roof and construction method thereof
CN116837889A (en) A kind of basement roof construction elevator foundation construction method
CN101701493B (en) Template support system of box type girder cast-in-place concrete floor plate of steel frame construction
CN100424298C (en) Construction method of making laminated floor slab with upper support frame
CN210002942U (en) transformation structure of old building brick column
CN201826526U (en) Device for supporting template of steel frame structure cast-in-situ concrete floor slab
CN105625619A (en) Profiled steel sheet concrete bilateral composite floor embedded with hollow square steel tubes
CN205776898U (en) Overall assembled reinforced concrete shear wall structure system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Method for erecting slab beam separated high support formwork and connecting brackets for multi story and high-rise reinforced concrete structures

Granted publication date: 20200821

Pledgee: Zhejiang Xianju Rural Commercial Bank Co.,Ltd.

Pledgor: UNIJES GROUP Co.,Ltd.

Registration number: Y2024330001929