Invention content
The technical problem to be solved in the present invention is, time-consuming and laborious for above-mentioned electric wiring, and by that may destroy main body
The problem of structure, provides a kind of inside plant assembly system and laying method.
The technical solution that the present invention solves above-mentioned technical problem is to provide a kind of inside plant assembly system, the cable
For forceful electric power line and/or weak electric wire, the inside plant assembly system includes a plurality of floor heating branch that ground is fixed on interval mode
Support keel, multiple floor heating modules being respectively arranged between the floor heating support keel, by between the floor heating support keel and/or
The wire casing and plank screed-coat that gap between floor heating support keel and floor heating module is constituted, and the cable is set to the line
In slot, the plank screed-coat is fixed on the upper surface of the floor heating support keel and covers the floor heating support keel, floor heating
Module and wire casing.
In inside plant assembly system of the present invention, the assembly system further includes being located at the plank screed-coat
The timber floor or floor tile of top.
In inside plant assembly system of the present invention, the floor heating support keel includes the first support keel and the
Two support keels, wherein:First support keel is close to metope setting;Second support keel is in a manner of being mutually parallel
It is arranged at intervals in the ring that first support keel surrounds;The floor heating module is between the second adjacent support keel.
In inside plant assembly system of the present invention, the first side wall of the wire casing is by first support keel
Side constitute, and the second sidewall of the wire casing is made of the side of the side of second support keel and floor heating module.
In inside plant assembly system of the present invention, the inside plant assembly system further includes being located at metope
Socket box and/or switch enclosure;There is fracture, institute on the first support keel of the underface of the socket box and/or switch enclosure
The cable stated in wire casing is connected to the socket box and/or switch enclosure via the fracture.
In inside plant assembly system of the present invention, the cable that is picked out from the wire casing via the metope with it is attached
Cavity between wallboard accesses the socket box and/or switch enclosure, or described in the adiabator layer access via the metope
Socket box and/or switch enclosure, or access the socket box and/or switch enclosure via the spool for being embedded in the metope.
In inside plant assembly system of the present invention, there is Fixing clamp-seat at the wire casing adjacent with the fracture,
And the cable in the wire casing accesses the fracture via the Fixing clamp-seat.
The present invention also provides a kind of inside plant laying method, the cable is forceful electric power line and/or weak electric wire, the method
Include the following steps:
(a) a plurality of floor heating support keel is pressed to the interval mode subscribed respectively and is fixed to ground, the floor heating support keel
Between be reserved with multiple floor heating module installation positions;
(b) multiple floor heating modules are laid on to multiple floor heating module installation positions between floor heating support keel respectively;
(c) cable is laid in by between the floor heating support keel and/or between floor heating support keel and floor heating module
Gap constitute wire casing;
(d) plank screed-coat is fixed on the floor heating support keel, and the plank screed-coat covers the floor heating
Support keel, floor heating module and wire casing.
In inside plant laying method of the present invention, the method further includes:Above the plank screed-coat
It is laid with timber floor or floor tile.
In inside plant laying method of the present invention, the floor heating support keel includes the first support keel and the
Two support keels, wherein:It is close to metope setting in the side of first support keel;Second support keel is to be mutually parallel
Mode be arranged at intervals on the inside of first support keel;The floor heating module be located at the second adjacent support keel it
Between;The method includes:Cable in the wire casing is connected to the socket box of metope via the fracture on the first support keel
And/or switch enclosure, attached wall plate then is installed in metope.
The inside plant assembly system and laying method of the present invention is not necessarily to by the way that cable is combined installation with floor heating module
Electric wiring can be completed in fluting, greatly improves electric wiring efficiency, reduces cost.And the present invention is in combination with attached wall
Cable is arranged in attached wall plate cavity, dry method thermal insulation material, further increases installation effectiveness by plate, dry method internal insulation structure etc..
Specific implementation mode
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
As shown in Figs. 1-3, as shown in Figs. 1-3, it is the schematic diagram of inside plant assembly system embodiment of the present invention, the interior
Cable assembly system can be applied to the power wiring of construction and decoration, including forceful electric power wiring and/or light current wiring, i.e., cable can be
Forceful electric power line and/or weak electric wire.The inside plant assembly system of the present embodiment includes a plurality of floor heating support keel, multiple floor heating modules
14, wire casing 10 and plank screed-coat 15.Above-mentioned a plurality of floor heating support keel is fixed on ground 11, multiple floor heatings with interval mode
Module 14 is respectively arranged on the ground 11 between floor heating support keel.Wire casing 10 by between floor heating support keel and/or floor heating support
Gap between keel and floor heating module 14 is constituted, and the cable 20 of laying is placed in above-mentioned wire casing 10, and the bottom of wire casing 10 can be set
Set insulating layer (between cable 20 and ground 11).Plank screed-coat 15 be fixed on floor heating support keel upper surface (such as
Can be fixed by nailing) and cover floor heating support keel, floor heating module 14 and wire casing 10.
Above-mentioned floor heating module 14 can be existing floor heating module, specifically may include prefabricated fluted thermal insulation board (usually
With elasticity), the heat conduction aluminium flake for being placed in heat preservation plate surface, the heating pipe etc. that is placed in groove.The thickness of floor heating support keel
More than or equal to the thickness of floor heating module 14.Heat accumulation plate specifically can be used in plank screed-coat 15, thereon surfacing, so as to protect
Demonstrate,prove the paving on floor tile or floor.
Above-mentioned inside plant assembly system can be completed by the way that cable 20 is combined installation with floor heating module 14 without fluting
Electric wiring greatly improves electric wiring efficiency, reduces cost.
Particularly, above-mentioned inside plant assembly system may also include timber floor or floor tile above plank screed-coat 15
16, wherein timber floor or floor tile 16 can be fixed on by modes such as gluings on plank screed-coat 15.And it can be on timber floor or ground
Moisture-proof cotton layer 17 can be increased between brick 16 and plank screed-coat 15, to realize moisture-proof isolation.
As described in Figure 3, above-mentioned floor heating support keel specifically may include the first support keel 131 and the second support keel 132,
Wherein the first support keel 131 is close to the setting of metope 12, i.e. the root of metope is the first support keel that a circle is stitched together
131;Second support keel 132 is then arranged at intervals on the inside of the first support keel 131, i.e., second in a manner of being mutually parallel
Support keel 132 are located in the circle that the first support keel 131 is surrounded;Floor heating module 14 is located at the second adjacent support keel 132
Between.
The first side wall of wire casing 10 is made of the side of the first support keel 131, and the second sidewall of wire casing 10 is by second
The side of support keel 132 and the side of floor heating module 14 are constituted.I.e. wire casing 10 is equally arranged around (or partially surrounding) wall.
In this way, convenient for cable 20 is drawn out to metope 12, while being conducive to the heat pipe arrangement of floor heating module 14, avoid cable 20 and floor heating
The heat pipe of module 14 intersects.
Above-mentioned inside plant assembly system further includes the socket box and/or switch enclosure 18 positioned at metope 12, and in socket box
And/or there is fracture (i.e. notch) on the first support keel 131 of the underface of switch enclosure 18, the cable 20 in wire casing 10 is from upper
Fracture extraction is stated, and is connected to socket box and/or switch enclosure 18.
Specifically, when metope 12 is using attached wall plate 22, the cable 20 picked out from wire casing 10 is via metope 12 and attached wall plate
Cavity access socket box between 22 and/or switch enclosure 18;When metope 12 has dry method thermal insulation structure, picked out from wire casing 10
Cable 20 accesses socket box and/or switch enclosure 18 via the adiabator layer of metope 12;When metope uses common cement mortar
Or tile laying, then from the cable 20 that wire casing 10 picks out can be accessed via the spool that is embedded in metope 12 socket box and/
Or switch enclosure 18.
In addition, for protection cable 20, Fixing clamp-seat, and the line in wire casing 10 can be set at the wire casing 10 adjacent with fracture
Cable 20 accesses fracture via Fixing clamp-seat.
At corner, baseboard 21 can be increased, and can have light trough on above-mentioned baseboard 21, the lamp in light trough can directly by
The cable 20 drawn in wire casing 10 is powered.
The present invention also provides a kind of inside plant laying methods, and wherein cable is forceful electric power line and/or weak electric wire, this method packet
Include following steps:
(a) a plurality of floor heating support keel is pressed to the interval mode subscribed respectively and is fixed to ground, above-mentioned floor heating support keel
Between be reserved with multiple floor heating module installation positions.
Above-mentioned floor heating support keel specifically may include the first support keel and the second support keel, wherein the first support keel
It is close to metope setting, i.e. the root of metope is the first support keel that a circle is stitched together;Second support keel is then with mutual
Parallel mode is arranged at intervals on the inside of the first support keel, i.e. the second support keel is located at what the first support keel was surrounded
In circle.
(b) multiple floor heating modules are laid on to multiple floor heating module installation positions between floor heating support keel respectively.It is above-mentioned
Floor heating module specifically may include prefabricated fluted thermal insulation board (usually have elasticity), the heat conduction aluminium flake for being placed in heat preservation plate surface,
The heating pipe etc. being placed in groove.The thickness of floor heating support keel is greater than or equal to the thickness of floor heating module.It is first in the step
Prefabricated fluted thermal insulation board is first laid on floor heating module installation position, is then laid with heat conduction aluminium flake in the upper surface of thermal insulation board,
Then water collecting and diversifying device, heating pipe etc. are placed in the groove of thermal insulation board.
Specifically, above-mentioned floor heating module installation position can be between the second adjacent support keel.
(c) cable is laid in by the sky between floor heating support keel and/or between floor heating support keel and floor heating module
The wire casing that gap is constituted.
Specifically, the first side wall of above-mentioned wire casing can be made of the side of the first support keel, and the second sidewall of wire casing
It is made of the side of the side of the second support keel and floor heating module.I.e. wire casing is equally arranged around (or partially surrounding) wall.
In this way, convenient for cable is drawn out to metope, while being conducive to the heat pipe arrangement of floor heating module, avoid the heat of cable and floor heating module
Pipe intersects.
(d) plank screed-coat is fixed on floor heating support keel, and the plank screed-coat covering floor heating support keel,
Floor heating module and wire casing.
The above method may also include:Timber floor or floor tile are laid with above plank screed-coat.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Any one skilled in the art in the technical scope disclosed by the present invention, the change or replacement that can be readily occurred in,
It should be covered by the protection scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims
Subject to.