CN108316949A - Umbrella arch is without empty lining process - Google Patents

Umbrella arch is without empty lining process Download PDF

Info

Publication number
CN108316949A
CN108316949A CN201810126446.7A CN201810126446A CN108316949A CN 108316949 A CN108316949 A CN 108316949A CN 201810126446 A CN201810126446 A CN 201810126446A CN 108316949 A CN108316949 A CN 108316949A
Authority
CN
China
Prior art keywords
observation
observation tube
grouting pipe
hole
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810126446.7A
Other languages
Chinese (zh)
Other versions
CN108316949B (en
Inventor
陈德斌
冯春田
夏真荣
傅强
罗武装
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201810126446.7A priority Critical patent/CN108316949B/en
Publication of CN108316949A publication Critical patent/CN108316949A/en
Application granted granted Critical
Publication of CN108316949B publication Critical patent/CN108316949B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of umbrella arches without empty lining methods, by the way that observation tube is fanned the air and installed in crown template, when carrying out filling concrete observation perfusion situation, according to the observation to the case where decide whether carry out band be molded into slurry.The present invention is monitored by the way that the lining perfusion of observation tube pair two situation is arranged in trolley crown, filling concrete situation in template from being put in from observation tube using observation probe, it is effectively prevent the generation in cavity, multiple observation tubes can be installed in template, realizes conduct monitoring at all levels.

Description

Umbrella arch is without empty lining process
Technical field
The present invention relates to a kind of tunnel-liner methods, more particularly to a kind of crown lining methods.
Background technology
With lining trolley in Tunnel Second Lining, there is cavity in concrete, prodigious influence can be caused on its intensity, Lining trolley is easy to generate cavity in crown part under normal circumstances, and is not easy to find empty, lining cutting during perfusion Cavity is just found when trolley demoulds;After even demoulding, cavity is not seen, but has had cavity in inside concrete.It is main former Because being:(1)When crown upper part is perfused in lining trolley, due to not having perfusion window, only perfusing hole, personnel are perfused, it is impossible to As in perfusion window, observing the perfusion situation of crown upper part like that, i.e., the perfusion of crown upper part cannot be clearly viewed Situation.(2)At the closeer position of reinforcing bar or reserving hole and built-in fitting, concrete discharging is put, and is not vibrated and is continued to pour Layer concrete on note.(3)When pump concrete, it is too long that centre stops pump time.(4)Concrete flowability is poor.(5)Concrete Isolation, mortar separation, stone is in heaps, serious running pulp, and does not vibrate or the blanking of vertical structure dry concrete Excessively, blocked up, blanking is excessively high, and vibrator vibration is less than forming loose hole.(6)Concrete includes water, soil or other are miscellaneous Object.
In Tunnel Second Lining, just need to remove in case of cavitation to be perfused again, it is time-consuming and laborious, it is of high cost. In order to avoid the above situation occurs, it is common practice to the bulkhead crown highest point of one end finally be perfused in lining trolley, pacify A camera is filled, by perfusion situation of concrete when camera head monitor secondary lining in crown template, or is not taken the photograph As head manually naked eyes directly see, to prevent cavity, but since template is longer(10 meters or more), lining trolley crown is most Eminence is generally evenly distributed with 4 perfusing holes along tunnel longitudinal direction, and each perfusing hole of secondary lining is perfused in filling process Concrete at mouthful is high, high at formation perfusing hole, and the low gradient around perfusing hole, camera can only just be observed close to camera The perfusion situation of this one side has blocked the camera observation subsequent perfusion situation of perfusing hole since the concrete at perfusing hole is high.
Invention content
The technical problem to be solved in the present invention:It cannot be observed for present Observations Means when crown perfusing hole is perfused The problem of situation is perfused behind to crown template perfusing hole, provides a kind of lining cutting for capableing of comprehensive observation crown secondary lining Method.
Technical solution of the present invention:
A kind of umbrella arch includes the following steps without empty lining methods:
One, injected hole and peep hole are opened up in trolley vault template, are welded under injected hole and peep hole and are closed device;
Two, required after keeping trolley formwork in place according to two lining geometry, by Grouting Pipe and observation tube pass through injected hole and peep hole into Row tries measurement on, determines whether the installation length of Grouting Pipe and observation tube meets slip casting, observation and test concrete with Grouting Pipe Whether the full requirement of perfusion;
Three, Grouting Pipe and observation tube are installed, are inserted into after Grouting Pipe withstands splash guard and mark and cut Grouting Pipe, in Grouting Pipe Upper surface opens up cross recess;Grouting Pipe and observation tube are fixed on and closed on device;
Four, crown two serves as a contrast concrete perfusion and observes perfusion situation, when crown concrete being sequentially perfused using perfusing hole, will observe Probe from each observation tube extend into top carry out from, the perfusion situation of monitored concrete, when observe concrete close to see Observation tube is taken out when examining pipe upper end, continues perfusion until next perfusing hole bleeding, replaces perfusing hole and continue to be in the milk.
After step 4, if it is observed that having cavity to generate then carries out the following steps:
Five, prepared by injection slurry and crown band is molded into slurry, and area of being come to nothing between splash guard behind to secondary lining using Grouting Pipe is carried out Slip casting.
Six, pressure gauge and gas vent pulp are observed
Seven, slip casting terminates, and unloads slip casting machine hose, Grouting Pipe is blocked closely knit.
After step 4, the following steps are carried out if cavity is not observed and generates:Grouting Pipe is extracted, slip casting is blocked Hole.
It in step 1, closes device upper surface and offers sliding slot, plate is installed in sliding slot, close device lower end and pass through spiral shell Column connects locating flange.
In step 3, retraction 3-5cm is fixed after observation tube touches splash guard.
In step 4, observation probe is first removed, will be sealed at the top of observation tube, then taken out observation tube, close peep hole.
It is equipped with operating lever in observation tube, observation probe is installed at the top of operating lever.
Operating lever top connects closure plate, and there is sealing terrace in observation tube upper end, pulls down operating lever, seals in terrace and closure plate Side matches.
The operating lever other end connects closure plate by bulb, and the internal face of observation tube upper end has sealing ring, and operating lever is in turn It is inserted into observation tube and pushes up, closure plate upper surface and the cooperation of sealing ring lower surface.
Injected hole and peep hole are between two neighboring perfusing hole and template both ends.
Advantageous effect of the present invention:
This method in crown template by installing observation tube, and concrete fills in template from observation probe is put in from observation tube Situation is noted, the generation in cavity is effectively prevent.Multiple observation tubes can be installed in template, realize conduct monitoring at all levels.
There is closure plate in the upper end of observation tube, seals upper end when for removing observation tube, blocks concrete and is not leaked from observation tube Go out.When observation probe pipe exits crown template, crown mouth is closed using plate and blocks concrete, after observation tube is removed, concrete It will not leak out.
It is popped one's head in by observing, can see the size in cavity, before carrying out empty slip casting, additionally it is possible to which probably estimation is filled out The grouting amount in full cavity, whether observation grouting amount is as filling up empty reference.
Description of the drawings:
Fig. 1 is overall structure of the present invention.
Fig. 2 is the structural schematic diagram of observation tube in embodiment 1.
Fig. 3 is the fixed structure schematic diagram of observation tube in embodiment 2.
Fig. 4 is the sealed structural representation of observation tube in embodiment 2.
Fig. 5 is the sealing of observation tube and mounting structure schematic diagram in embodiment 3.
Fig. 6 is to close apparatus structure schematic diagram.
Fig. 7 is the arrangement schematic diagram of embodiment 4.
Specific implementation mode:
Embodiment 1:Observation tube in the present embodiment is the integrated observation tube of integrated camera.
Peep hole is opened up in the vault template of lining trolley, is welded below peep hole and closes device 4, closes device 4 by solid Determine flange and plate 10 forms, is seen using the locating flange 5 on link bolt connection observation tube 2, easy disassembly on mounting flange Pipe 2 is examined, the mounting flange upper surface for closing device 4 offers sliding slot, and plate 10 is arranged in sliding slot, and plate 10 is close to vault mould Plate, plate 10 is for after taking out observation tube 2, movable flashboard 10 to block peep hole, and concrete will not leak out.5 center of locating flange There is positioning tube 16, pin hole is offered on barrel, observation tube 2 is inserted into positioning tube 16 and is extend into close to tunnel across peep hole The place of splash guard.Note that get out of the way reinforcing bar, otherwise, cause that observation tube 2 and 2 Grouting Pipes 1 cannot be installed.
2 upper end of observation tube seals, and it is the material of annular transparent that one section of observation window 18, observation window 18, which are arranged, at 2 top of observation tube, is seen It examines and camera and headlamp, stepper motor and column 17 is installed in window 18, camera and headlamp are mounted on horizontal stepping electricity On arbor, which is in turn mounted on another vertical step motor axis, realizes camera and the horizontal rotation of 360 ° of headlamp Turn and 15 ° are rotated up and down observation, vertical step motor is connect with column 17, is fixed on observation tube 2 in 2 lower end of observation tube.It sees Examining on 2 hypomere side wall of pipe has location hole, is used for the height of position observation pipe 2.
Concrete construction method is as follows:
(1)Trolley top plate opening installs observation tube 2 and Grouting Pipe 1
Lining trolley crown template highest point builds this side, the distance of 1 lining thickness in perfusing hole 3 close to a upper lining papers (In order to ensure observation tube 2 and Grouting Pipe 1, all in the space of reinforcing bar, which is big probable value), increase peep hole and two Injected hole(Wherein 1 Grouting Pipe 1 is as intermediate exhaust pipe or end parting line venting pipe or spare Grouting Pipe), pay attention to reinforcing bar to be got out of the way, It is no that it will cause cannot install observation tube 2 and 2 Grouting Pipes 1.General lining trolley crown template has 4 perfusing holes, by perfusion Mouth quantity reserves the hole of 5 groups of installation observation tubes 2 and 2 Grouting Pipes 1, the hole position of intermediate 3 groups of installation observation tubes 2 and 2 Grouting Pipes 1 It sets and builds this side, the distance of 1 lining thickness close to a upper lining papers in perfusing hole 3;Each 1 group of installation observation tube 2 and 2 in both ends 20cm or so of the hole site of root Grouting Pipe 1 in lining cutting.4 groups of holes of number since being built a upper lining papers for lining cutting are For one lining papers of the overlap joint block of lining cutting at one end, the other end is used there are no the case where lining cutting, and last 1 group is to be used for lining cutting Trolley both ends all overlap the case where lining cutting and use.Device 4 is closed in welding installation under peep hole and injected hole, in observation tube On bore closure device 4, observation tube 2 is installed.2 slip casting pores are made a call near each observation tube 2(Totally 10 slip casting pores), installation Grouting Pipe bore closure device 4 installs Grouting Pipe 1 and locating flange 5 on the closing device 4 of slip casting pore.When needing slip casting, Filling system is connected in locating flange 5.
(2)It to be sought template in place according to two lining geometry.
After trolley and template, is measured " trying on " is carried out at ready 1 preformed hole of RPC Grouting Pipes, determine Grouting Pipe 1 It detects two thickness of the liner degree and whether meets design requirement, specific standards are subject to Grouting Pipe 1 and withstand splash guard length+2cm.
(3)The length of embedment of Grouting Pipe 1 is recorded on data board
According to(2)Middle operation marks record RPC pipe lengths of embedment after Grouting Pipe 1 withstands splash guard:Label should be item Line, one is the line with two lining template exterior sheathings(For detecting whether two thickness of the liner degree meet the requirements);Another is two lining templates External mold printed line+2cm, i.e. RPC Grouting Pipes(Exhaust pipe)Cutting length.Cross recess is opened up in 1 upper surface of Grouting Pipe.By slip casting Pipe 1 and observation tube 2 are respectively installed in flange, and fixed.Grouting Pipe 1 is fixed using joint steel pipe, after observation tube 2 rises tactile top Determine that suitable location hole, bolt 19 pass through the location hole in perforation and observation tube 2 on locating flange 5, observation tube 2 consolidated It is fixed.
(4)Two lining 3 concrete perfusions of perfusing hole simultaneously observe perfusion situation.
It when vault concrete is perfused, is observed using the observation probe 12 at the top of observation tube 2, observation probe 12 can be with 360 ° rotate horizontally and about 15 ° pitching, the perfusion situation of monitored concrete, until observing concrete close on observation tube 2 Observation tube 2 is taken out at end, closes the plate 10 on device 4, continues perfusion to 3 bleeding of next perfusing hole, replace perfusing hole 3 after Continuous grouting.Successively to 3 concrete perfusion of next perfusing hole, aforesaid operations are repeated, until crown is all filled.If observation tube 2 see the concrete porosity of Tunnel Second Lining, and it is necessary to carry out, prepared by the injection slurry of next step and band is molded into slurry.
(5)Prepared by injection slurry and band is molded into slurry.
Vault slip casting in principle according to since low side toward slip casting high-end.After the completion of two lining filling concretes after 2~3h It carries out, injecting paste material is using filling mortar, the ratio of mud 0.18;Slip casting is operated using dedicated slurrying slip casting all-in-one machine. Slurries require continuous mixing, strictly monitor material utilization amount during mixing, it is ensured that the quality of slurries.Using Grouting Pipe 1 to secondary Lining cutting area of coming to nothing between splash guard behind carries out slip casting, prevents two lining vaults from falling off and concrete leakiness.
(6)Observe pressure gauge and gas vent pulp
Slip casting end mark terminates slip casting with gas vent and end mould outflow underflow.If pulp pressure reaches at trolley formwork 1.0MPa does not go out underflow yet, should replace gas vent slip casting, until stopping note when intermediate row stomata and end parting line venting hole outflow underflow Slurry.
(7)Slip casting terminates, and unloads slip casting machine hose, Grouting Pipe 1 is blocked closely knit.
(8)Removal locating flange 5 after slurries initial set.
Embodiment 2:The case where trolley end mould is removed, lining cutting is all overlapped for lining trolley both ends in the present embodiment It uses, and 2 upper end trepanning of observation tube, by the way of being sealed upwards out of pipe.
(1)Tunnel double-lining lining trolley crown template trepanning
Lining trolley crown template highest point builds this side in perfusing hole 3 close to a upper lining papers, 1 lining thickness away from From increase installation observation tube 2 and 2 Grouting Pipes 1(Wherein 1 Grouting Pipe 1 is as intermediate exhaust pipe or end parting line venting pipe or spare Grouting Pipe).General lining trolley crown template, there is 4 perfusing holes, by perfusing hole quantity, reserves 5 groups of installation observation tubes 2 and 2 The hole site of the hole of Grouting Pipe 1, intermediate 3 groups of installation observation tubes 2 and 2 Grouting Pipes 1 is among two neighboring perfusing hole 3;Both ends The hole site of each 1 group of installation observation tube 2 and 2 Grouting Pipes 1, in the 20cm or so of lining cutting.Lining trolley crown template is opened The hole of 5 installation observation tubes 2 is made a call in hole along the highest point of crown template longitudinal direction, and the closing device 4 of pore is observed in installation, it closes It closes 4 to be welded below crown template, locating flange 5 is by bolt and closes the connection of device 4, opens in the upper surface for closing device 4 Equipped with sliding slot, plate 10 is installed in sliding slot, by sliding plate 10, peep hole can be closed or opened.It is closed in observation pore It closes on device, observation tube 2 is installed.If there is reinforcing bar, observation tube 2 and Grouting Pipe 1 are all in the space of reinforcing bar, by 2 He of observation tube Grouting Pipe 1 is arranged on same cross section, and circumferentially intermediate highest point is observation tube 2, each 1 Grouting Pipe in both sides of observation tube 2 1, intermediate highest point is leaned on as possible.Other 4 groups of observation tubes 2 and Grouting Pipe 1, and same setting.
(2)Require lining trolley in place according to two lining geometry.
Grouting Pipe 1 in the present embodiment is managed using RPC, when lining trolley formwork erection, ensures whole observation tubes 2 and Grouting Pipe 1 Position, all in the space of reinforcing bar, after the completion of formwork erection, installation observation tube 2, Grouting Pipe 1 and locating flange 5.It will be ready RPC Grouting Pipes 1 by Grouting Pipe bore closure device 4 carry out " trying on " measure, determine RPC Grouting Pipes 1 installation length and It detects two thickness of the liner degree and whether meets design requirement, specific standards are subject to RPC Grouting Pipes and withstand splash guard length+2cm.
(3)RPC pipe lengths of embedment are recorded on data board, cut Grouting Pipe 1.
According to(2)Middle operation marks record RPC pipe lengths of embedment after RPC Grouting Pipes 1 withstand splash guard: Label should be a line, and one is the line with two lining template exterior sheathings(For detecting whether two thickness of the liner degree meet the requirements);Another For two lining template external mold printed line+2cm, i.e. RPC Grouting Pipes(Exhaust pipe)Cutting length.Ten are opened up in 1 upper surface of Grouting Pipe Word slot.The locating flange 5 of Grouting Pipe 1 and Grouting Pipe 1 is installed, is inserted into after observation tube 2 and gear is installed on the locating flange 5 of peep hole Plate 6 is fixed baffle 6 by bolt 9, and there is hole in 6 center of baffle.
(4)Two lining 3 concrete perfusions of perfusing hole simultaneously observe perfusion situation.
Two lining concrete are sequentially poured by the sequence of perfusing hole.Observation probe 12 is stretched out of observation tube 2 by operating lever 7 Enter, observation probe is mainly by miniature webcam and lighting lamp group at observation probe 12 is close to splash guard.Observation probe 12 makees 360 ° It rotates horizontally and 15 ° is rotated up and down observation, observation probe level is driven using stepping stepper motor 22 and be rotated up and down, or adopt With manual actuation observation probe level and it is rotated up and down.Concrete completely comes up, and first takes out observation probe 12,7 other end of operating lever By bulb hinged closure plate 8, the inner face of 2 upper end of observation tube has sealing ring, and operating lever 7 is inserted into observation tube 2 in turn, observation Tube top end has the anchor ring of step as sealing ring, 8 upper surface of closure plate and the cooperation of sealing ring lower surface.Closure plate 8 is pressed in close It is sealed in seal ring, further takes out observation tube 2, close the plate 10 on observation tube bore closure device, blocked peep hole and continue perfusion directly To 1 bleeding of Grouting Pipe.Successively to 3 concrete perfusion of next perfusing hole, aforesaid operations are repeated, until crown is all filled.
The perfusion situation that probe 12 is observed according to the observation, decides whether to carry out following several steps, if it is observed that empty The formation in hole must then follow the steps below.
(5)Prepared by injection slurry and band is molded into slurry.
Crown slip casting in principle according to since low side toward slip casting high-end.After the completion of two lining filling concretes after 2~3h It carries out, injecting paste material is using filling mortar, the ratio of mud 0.18;Slip casting is operated using dedicated slurrying slip casting all-in-one machine. Slurries require continuous mixing, strictly monitor material utilization amount during mixing, it is ensured that the quality of slurries.Using Grouting Pipe 1 to secondary Lining cutting area of coming to nothing between splash guard behind carries out slip casting, prevents two lining crowns from falling off and concrete leakiness.
(6)Observe pressure gauge and gas vent pulp.
Slip casting end mark terminates slip casting with gas vent and end mould outflow underflow.If pulp pressure reaches at trolley formwork To 1.0MPa, do not go out underflow yet, gas vent slip casting should be replaced, until stopping when intermediate row stomata and end parting line venting hole outflow underflow Only slip casting.
(7)Slip casting terminates, and unloads slip casting machine hose, Grouting Pipe 1 is blocked closely knit.
(8)Removal locating flange 5 after slurries initial set.
Embodiment 3:The present embodiment is the lining methods for not removing former end die tip observation probe 12, is used for one end lining cutting Overlap a lining papers to build the other end there are no the case where lining cutting to use, and the 2 upper end trepanning of observation tube in the present embodiment, using from Pipe is outer to be pressed downward the mode being sealed.It is as follows:
(1)Lining trolley crown template trepanning
Lining trolley crown template highest point builds this side in each perfusing hole 3 close to a upper lining papers, 1 lining thickness Distance(In order to ensure observation tube 2 and Grouting Pipe 1, all in the space of reinforcing bar, which is big probable value), beat peep hole and note Hole is starched, installation observation tube 2 and 2 Grouting Pipes 1 are increased(Wherein 1 Grouting Pipe 1 is as intermediate exhaust pipe or end parting line venting pipe or standby Use Grouting Pipe), it is noted that reinforcing bar is got out of the way, otherwise, causes that observation tube 2 and 2 Grouting Pipes 1 cannot be installed.General lining trolley top Encircle template, there are 4 perfusing holes, by perfusing hole quantity, reserves the hole of 4 groups of installation observation tubes 2 and 2 Grouting Pipes 1, intermediate 3 groups of peaces This side is built in the hole site for filling observation tube 2 and 2 Grouting Pipes 1 in perfusing hole 3 close to a upper lining papers, 1 lining thickness Distance;20cm or so of the one group of hole at lining cutting end in lining cutting.After determining punch position, longitudinal along crown template Highest point builds this side in perfusing hole close to a upper lining papers, the distance of about 1 lining thickness, makes 4 installation observation tubes 2 Hole(It is identical as perfusing hole quantity to observe hole number), the closing device 4 of observation pore is installed, device 4 is closed and is welded on crown mould Below plate, locating flange 5 is by bolt and closes the connection of device 4, sliding slot is offered in the upper surface for closing device 4, in sliding slot Middle installation plate 10 can close or open peep hole by sliding plate 10.2 Grouting Pipes are made a call near each observation tube 2 Hole(Totally 8 slip casting pores), the closing device 4 of Grouting Pipe is installed, Grouting Pipe 1 and note are installed on Grouting Pipe bore closure device 4 Starch the locating flange of pipe 1.
Observation tube 2 and Grouting Pipe 1, all in the space of reinforcing bar, the one end built in lining trolley without overlapping a upper lining papers, Observation probe is installed outside crown Side Template highest.
(2)Require lining trolley in place according to two lining geometry.
Grouting Pipe 1 in the present embodiment is managed using RPC, and observation tube 2 is steel pipe, when lining trolley formwork erection, ensures all to see The position of pipe 2 and Grouting Pipe 1 is examined all in the space of reinforcing bar, after the completion of formwork erection, installation observation tube 2, Grouting Pipe 1 and closes device 4.Ready Grouting Pipe 1 is carried out " trying on " by Grouting Pipe bore closure device 4 to measure, determines the installation length of Grouting Pipe 1 Whether meet design requirement with two thickness of the liner degree of detection, specific standards are subject to Grouting Pipe 1 and withstand splash guard length+2cm.
(3)1 length of embedment of Grouting Pipe is recorded on data board, cuts Grouting Pipe 1.
According to(2)Middle operation marks record RPC pipe lengths of embedment after RPC Grouting Pipes 1 withstand splash guard: Label should be a line, and one is the line with two lining template exterior sheathings(For detecting whether two thickness of the liner degree meet the requirements);Another For two lining template external mold printed line+2cm, i.e. RPC Grouting Pipes 1(Exhaust pipe)Cutting length.Observation tube 2 is than 1 short 3- of Grouting Pipe 5cm or so.Cross recess is opened up in 1 upper surface of Grouting Pipe, Grouting Pipe 1 and locating flange 5 are installed.
(4)Two lining 3 concrete perfusions of perfusing hole simultaneously observe perfusion situation.
When crown concrete is perfused, the first concrete perfusion since the perfusing hole 3 built close to a upper lining papers, in observation tube 2 Equipped with operating lever 7,7 top of operating lever is equipped with closure plate 8, and 8 lower section of closure plate is equipped with observation probe 12, and observation probe 12 is by miniature Camera and lighting lamp group are at observation probe is close to splash guard.12 rotation of observation probe is driven using stepping stepper motor 22, or Person is using manual actuation observation probe level and is rotated up and down, and 360 ° of observation probe rotates horizontally and 15 ° are rotated up and down observation, mixes When solidifying soil completely comes up, operating lever 7 is pulled down, seals the 8 inside matching of terrace and closure plate.
It exits observation tube 2 and removes observation tube 2, and be installed to next after closing peep hole to observation tube bore closure device 4 On a observation tube bore closure device.Continue perfusion until 3 bleeding of next perfusing hole, is successively perfused next perfusing hole 3 mixed Solidifying soil, repeats aforesaid operations, until crown is all filled.If observation tube 2, see that the concrete of Tunnel Second Lining is empty It is necessary to carry out, prepared by the injection slurry of next step and band is molded into slurry in hole.
(5)Prepared by injection slurry and band is molded into slurry.
Crown slip casting in principle according to since low side toward slip casting high-end.After the completion of two lining filling concretes after 2~3h It carries out, injecting paste material is using filling mortar, the ratio of mud 0.18;Slip casting is operated using dedicated slurrying slip casting all-in-one machine. Slurries require continuous mixing, strictly monitor material utilization amount during mixing, it is ensured that the quality of slurries.Using Grouting Pipe 1 to secondary Lining cutting area of coming to nothing between splash guard behind carries out slip casting, prevents two lining crowns from falling off and concrete leakiness.
(6)Observe pressure gauge and gas vent pulp
Slip casting end mark terminates slip casting with gas vent and end mould outflow underflow.If pulp pressure reaches at trolley formwork 1.0MPa does not go out underflow yet, should replace gas vent slip casting, until stopping note when intermediate row stomata and end parting line venting hole outflow underflow Slurry.
(7)Slip casting terminates, and unloads slip casting machine hose, Grouting Pipe 1 is blocked closely knit.
(8)Removal locating flange 5 after slurries initial set.
Embodiment 4, the peep hole and injected hole in the present embodiment are on the same circumference.
(1)Tunnel double-lining lining trolley crown template trepanning
Lining trolley crown template highest point builds this side in perfusing hole 3 close to a upper lining papers, 1 lining thickness away from From increase installation observation tube 2 and 2 Grouting Pipes 1(Wherein 1 Grouting Pipe 1 is as intermediate exhaust pipe or end parting line venting pipe or spare Grouting Pipe).General lining trolley crown template, there is 4 perfusing holes, by perfusing hole quantity, reserves 5 groups of installation observation tubes 2 and 2 The hole site of the hole of Grouting Pipe 1, intermediate 3 groups of installation observation tubes 2 and 2 Grouting Pipes 1 is among two neighboring perfusing hole 3;Both ends The hole site of each 1 group of installation observation tube 2 and 2 Grouting Pipes 1, in the 20cm or so of lining cutting.Lining trolley crown template is opened The hole of 5 installation observation tubes 2 is made a call in hole along the highest point of crown template longitudinal direction, and installation observation tube bore closure device 4 closes dress The upper surface for setting 4 offers sliding slot, and plate 10 is installed in sliding slot, by sliding plate 10, can close or open peep hole. It closes device 4 to be welded below crown template, locating flange 5 closes device 4 by nut and Stud connection, in locating flange 5 Upper installation observation tube 2.Observation tube 2 and Grouting Pipe 1 are arranged in same cross all in the space of reinforcing bar for observation tube 2 and Grouting Pipe 1 On section, circumferentially intermediate highest point is observation tube 2, and each 1 Grouting Pipe 1 in both sides of observation tube 2 leans on intermediate highest point as possible. It is equally equipped with below injected hole and closes device 4, in addition 4 groups of observation tubes 2 and Grouting Pipe 1, and same setting.Note that wanting Reinforcing bar is got out of the way, otherwise, causes that observation tube 2 and 2 Grouting Pipes 1 cannot be installed.
(2)Grouting Pipe 1 in the present embodiment is managed using RPC, when lining trolley formwork erection, ensures whole observation tubes 2 and slip casting The position of pipe 1, all in the space of reinforcing bar, after the completion of formwork erection, installation observation tube 2, Grouting Pipe 1 and slip casting flange 3.It will be ready to RPC Grouting Pipes 1 by Grouting Pipe bore closure device 4 carry out " trying on " measure, determine that the installation of RPC Grouting Pipes 1 is grown Whether degree and two thickness of the liner degree of detection meet design requirement, and specific standards withstand splash guard length+2cm with RPC Grouting Pipes and are It is accurate.
(3)RPC pipe lengths of embedment are recorded on data board, cut Grouting Pipe 1.
According to(2)Middle operation marks record RPC pipe lengths of embedment after RPC Grouting Pipes 1 withstand splash guard: Label should be a line, and one is the line with two lining template exterior sheathings(For detecting whether two thickness of the liner degree meet the requirements);Another For two lining template external mold printed line+2cm, i.e. RPC Grouting Pipes(Exhaust pipe)Cutting length.Observation tube 2 is than 1 short 5cm of Grouting Pipe Left and right.Cross recess is opened up in 1 upper surface of Grouting Pipe.The locating flange 5 of Grouting Pipe 1 and Grouting Pipe 1 is installed, after being inserted into observation tube 2 Baffle 6 is installed on the locating flange 5 of peep hole, is fixed baffle 6 by bolt 9, there is hole in 6 center of baffle..
(4)Two lining 3 concrete perfusions of perfusing hole simultaneously observe perfusion situation.When crown concrete is perfused, first from close to upper one The perfusing hole 3 that lining papers is built starts concrete perfusion, pops one's head in from being stretched into out of observation tube 2, and observation probe is mainly by miniature video camera Head and lighting lamp group are at observation probe is close to splash guard.It drives observation probe 12 horizontal using stepper motor 22 and is rotated up and down, Or it using manual actuation observation probe level and is rotated up and down.Observation probe 12 can make 360 ° and rotate horizontally and 15 ° of upper backspins Turn observation, concrete completely comes up, and first takes out observation probe, after being loaded on observation tube closure plate, exits observation tube 2 to observation pore and closes Device is closed, after closing observation pore, removes observation tube 2, and be installed on next observation tube bore closure device.Monitored concrete Perfusion situation remove observation probe until observing concrete close to 2 upper end of observation tube, observation tube loaded onto by operating lever 7 The closure plate 8 at top further takes out observation tube 2, closes the plate 10 on observation pore, blocks peep hole and continues perfusion until Grouting Pipe 1 bleeding repeats aforesaid operations, until crown is all filled successively to 3 concrete perfusion of next perfusing hole
(5)If it is observed that the possibility for not having cavity to generate in filling process, then block Grouting Pipe 1 and extract, slip casting is closed Plate 10 below hole above mounting flange 4 closes injected hole.
(6)If it is observed that cavity generates, then carries out band and be molded into slurry, to meet lining quality requirement.

Claims (11)

1. a kind of umbrella arch is without empty lining methods, it is characterised in that include the following steps:
One, injected hole and peep hole are opened up in trolley vault template, are welded under injected hole and peep hole and are closed device(4);
Two, it is required after keeping trolley formwork in place according to two lining geometry, by Grouting Pipe(1)And observation tube(2)Across injected hole and sight It examines hole and tries on measurement, determine Grouting Pipe(1)And observation tube(2)Installation length and detection two thickness of the liner degree whether meet design It is required that;
Three, Grouting Pipe is installed(1)And observation tube(2), it is inserted into Grouting Pipe(1)It is marked after withstanding splash guard and cuts Grouting Pipe (1), in Grouting Pipe(1)Upper surface opens up cross recess;Grouting Pipe 1 and observation tube 2 are fixed on closing device(4)On;
Four, crown two serves as a contrast concrete perfusion and observes perfusion situation, utilizes perfusing hole(3)It, will when crown concrete is sequentially perfused Observation probe(12)From each observation tube(2)It extend into top to be observed, the perfusion situation of monitored concrete is mixed when observing It is solidifying native close to observation tube(2)Observation tube is taken out when upper end(2), continue perfusion until next perfusing hole(3)Bleeding replaces perfusion Mouthful(3)Continue to be in the milk.
2. umbrella arch according to claim 1 is without empty lining methods, it is characterised in that after step 4, carry out following Step:
Five, prepared by injection slurry and crown band is molded into slurry, utilizes Grouting Pipe(1)To secondary lining behind and splash guard between come to nothing area into Row slip casting.
3. observing pressure gauge and gas vent pulp
Seven, slip casting terminates, and unloads slip casting machine hose, by Grouting Pipe(1)It blocks closely knit.
4. the umbrella arch according to right 1 is without empty lining methods, it is characterised in that after step 4, carry out following step Suddenly:Five, Grouting Pipe is extracted(1), block injected hole.
5. according to right 1-3 any one of them umbrella arch without empty lining methods, it is characterised in that in step 1, close Device(4)Upper surface offers sliding slot, and plate is installed in sliding slot(10), close device(4)Lower end passes through Stud connection positioning mode It is blue(5).
6. the umbrella arch according to claim 1-3 is without empty lining methods, it is characterised in that:In step 3, observation Pipe(2)Touch splash guard(11)Retraction 3-5cm is fixed afterwards.
7. the umbrella arch according to claim 1-3 is without empty lining methods, it is characterised in that:In step 4, first take Lower observation probe, by observation tube(2)Top seals, and then takes out observation tube(2), close peep hole.
8. umbrella arch according to claim 6 is without empty lining methods, it is characterised in that:Observation tube(2)It is interior to be equipped with behaviour Make bar(7), operating lever(7)Top installation observation probe(12).
9. umbrella arch according to claim 7 is without empty lining methods, it is characterised in that:Operating lever(7)Top connects Closure plate(8), observation tube(2)There is sealing terrace in upper end, pulls down operating lever(7), seal terrace and closure plate(8)Inside matches.
10. umbrella arch according to claim 7 is without empty lining methods, it is characterised in that:Operating lever(7)The other end is logical Cross bulb connection closure plate(8), observation tube(2)The internal face of upper end has sealing ring, by operating lever(7)It is inserted into observation tube in turn (2)And it pushes up, closure plate(8)Upper surface and the cooperation of sealing ring lower surface.
11. umbrella arch according to claim 7 is without empty lining methods, it is characterised in that:Injected hole and peep hole position In two neighboring perfusing hole(3)Between and template both ends.
CN201810126446.7A 2018-02-08 2018-02-08 Tunnel roof arch hollow-free lining method Active CN108316949B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810126446.7A CN108316949B (en) 2018-02-08 2018-02-08 Tunnel roof arch hollow-free lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810126446.7A CN108316949B (en) 2018-02-08 2018-02-08 Tunnel roof arch hollow-free lining method

Publications (2)

Publication Number Publication Date
CN108316949A true CN108316949A (en) 2018-07-24
CN108316949B CN108316949B (en) 2023-05-26

Family

ID=62903129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810126446.7A Active CN108316949B (en) 2018-02-08 2018-02-08 Tunnel roof arch hollow-free lining method

Country Status (1)

Country Link
CN (1) CN108316949B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109488337A (en) * 2018-11-20 2019-03-19 中铁上海工程局集团有限公司 A kind of anti-come to nothing of tunnel double-lining concrete visualizes casting method
CN109488336A (en) * 2018-11-13 2019-03-19 中铁二局集团有限公司 A kind of tunnel double-lining vault pours observation method
CN110242324A (en) * 2019-05-30 2019-09-17 平顶山平煤机煤矿机械装备有限公司 Tunnel lining trolley secondary grouting device
CN110985041A (en) * 2019-12-31 2020-04-10 中铁隧道局集团有限公司 Construction method for processing sudden surge of separated double-hole tunnel
CN111058864A (en) * 2019-11-29 2020-04-24 中铁九局集团第四工程有限公司 Tunnel vault lining rear cavity high-pressure grouting auxiliary device
CN112502048A (en) * 2020-12-08 2021-03-16 云南省建设投资控股集团有限公司 Highway T roof beam hogging moment slip casting exhaust observation pipe
CN112709322A (en) * 2020-12-26 2021-04-27 杭州均正建筑设计有限公司 Bay window structure and construction method thereof
CN112879037A (en) * 2021-04-22 2021-06-01 黄河交通学院 Safe construction method for mine tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002276293A (en) * 2001-03-19 2002-09-25 Ohbayashi Corp Confirming method of tunnel back-filing grouting material
CN102849092A (en) * 2012-08-30 2013-01-02 中国葛洲坝集团股份有限公司 Visible positioning monitoring system of tunnel trolley
CN104295305A (en) * 2014-02-12 2015-01-21 齐洪军 Process for achieving synchronous implementation of lining vault filling grouting and tunnel lining and equipment
CN204877374U (en) * 2015-08-26 2015-12-16 北京中煤矿山工程有限公司 Empty plugging device of gas vertical wall posterior annulus
JP2016053263A (en) * 2014-09-03 2016-04-14 前田建設工業株式会社 Auxiliary form apparatus for upper surface part in tunnel lining concrete placement
CN105697033A (en) * 2016-04-01 2016-06-22 长安大学 Construction method for treating rock mass cavity without formworks in tunneling
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002276293A (en) * 2001-03-19 2002-09-25 Ohbayashi Corp Confirming method of tunnel back-filing grouting material
CN102849092A (en) * 2012-08-30 2013-01-02 中国葛洲坝集团股份有限公司 Visible positioning monitoring system of tunnel trolley
CN104295305A (en) * 2014-02-12 2015-01-21 齐洪军 Process for achieving synchronous implementation of lining vault filling grouting and tunnel lining and equipment
JP2016053263A (en) * 2014-09-03 2016-04-14 前田建設工業株式会社 Auxiliary form apparatus for upper surface part in tunnel lining concrete placement
CN204877374U (en) * 2015-08-26 2015-12-16 北京中煤矿山工程有限公司 Empty plugging device of gas vertical wall posterior annulus
CN105697033A (en) * 2016-04-01 2016-06-22 长安大学 Construction method for treating rock mass cavity without formworks in tunneling
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109488336A (en) * 2018-11-13 2019-03-19 中铁二局集团有限公司 A kind of tunnel double-lining vault pours observation method
CN109488336B (en) * 2018-11-13 2021-11-23 中铁二局集团有限公司 Tunnel secondary lining vault pouring observation method
CN109488337A (en) * 2018-11-20 2019-03-19 中铁上海工程局集团有限公司 A kind of anti-come to nothing of tunnel double-lining concrete visualizes casting method
CN110242324A (en) * 2019-05-30 2019-09-17 平顶山平煤机煤矿机械装备有限公司 Tunnel lining trolley secondary grouting device
CN111058864A (en) * 2019-11-29 2020-04-24 中铁九局集团第四工程有限公司 Tunnel vault lining rear cavity high-pressure grouting auxiliary device
CN110985041A (en) * 2019-12-31 2020-04-10 中铁隧道局集团有限公司 Construction method for processing sudden surge of separated double-hole tunnel
CN110985041B (en) * 2019-12-31 2021-04-20 中铁隧道局集团有限公司 Construction method for processing sudden surge of separated double-hole tunnel
CN112502048A (en) * 2020-12-08 2021-03-16 云南省建设投资控股集团有限公司 Highway T roof beam hogging moment slip casting exhaust observation pipe
CN112709322A (en) * 2020-12-26 2021-04-27 杭州均正建筑设计有限公司 Bay window structure and construction method thereof
CN112709322B (en) * 2020-12-26 2022-01-11 杭州均正建筑设计有限公司 Bay window structure and construction method thereof
CN112879037A (en) * 2021-04-22 2021-06-01 黄河交通学院 Safe construction method for mine tunnel

Also Published As

Publication number Publication date
CN108316949B (en) 2023-05-26

Similar Documents

Publication Publication Date Title
CN108316949A (en) Umbrella arch is without empty lining process
CN108104843A (en) Tunnel is without empty lining trolley
CN206329346U (en) One kind is based on tunnel lining trolley slip casting pipe fixation structure
CN109707405B (en) Tunnel lining concrete pouring quality control method and device
CN108071406A (en) A kind of tunnel of follow shot is without empty lining trolley
CN109139051A (en) A kind of tunnel grouting structure and construction
CN109057821B (en) Highway soft rock tunnel bilayer arch supporting construction system and its construction method
CN107588243A (en) The construction method of concordant type flexibility wall bushing structure
CN207934912U (en) Tunnel is without empty lining trolley
CN105545003A (en) Concrete hole blocking device
CN115306446A (en) Tunnel secondary lining vault grouting anti-lost grouting pipe with mold and grouting method
CN207829915U (en) A kind of tunnel of follow shot is without empty lining trolley
CN212508343U (en) Tunnel construction is with taking mould slip casting device
CN207829906U (en) Device is observed in crown lining cutting
CN101545259B (en) Device and method for non-underwater concreting by using drilled pile
CN105804403A (en) Rolling ball type concrete pouring structure and method for overground large special-shaped stiff column
CN105821747B (en) The device and its reinforcement of reinforcement after a kind of building road coring
JP2001164589A (en) Construction method for high pressure gas storage facility
CN113279785B (en) Method and device for treating hollow and partial loose part of tunnel secondary lining vault
CN102879553B (en) Testing device for extruding and lining of concrete
CN210509209U (en) Secondary grouting device for tunnel lining trolley
CN109184751A (en) Endoscopic bomb shelter monitoring device and monitoring method for tunnel-liner vault
CN110984153B (en) Construction method for pouring concrete behind hole-penetrating steel pipe
CN210686009U (en) Shield tunnel two-lining concrete structure
CN209761453U (en) TBM tunnel membrane bag cement slurry-stopping body structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant